1 minute read

Water Projects

Next Article
Public Safety

Public Safety

. North Suffolk Connector

City Council Goal – Transportation

The project will provide for a new two-lane roadway alignment connecting Nansemond Parkway to Shoulders Hill Road using local funding.

FY 23 FY 24 FY 25 FY 26 FY 27 FY 28-32 Total $0 $0 $0 $750,000 $0 $0 $750,000 Operating Costs: The project will not have an operational impact on the City.

Carolina Road Connector

City Council Goal – Transportation

The project will provide for a Carolina Road connector study using local funding.

FY 23 FY 24 FY 25 FY 26 FY 27 FY 28-32 Total $0 $0 $0 $300,000 $0 $0 $300,000

Operating Costs: The project will not have an operational impact on the City.

. Route 460 Improvements

City Council Goal – Transportation

The project will provide for road widening, median construction, sidewalks, and a closed drainage system from Kings Fork Road to the Bypass using state and local funding.

FY 23 FY 24 FY 25 FY 26 FY 27 FY 28-32 Total $0 $0 $0 $900,000 $15,000,000 $0 $15,900,000

Operating Costs: The project will not have an operational impact on the City.

Kings Highway Bridge

City Council Goal – Transportation

The project will provide for design and preliminary engineering of a bridge over the Nansemond River between Chuckatuck and Driver.

FY 23 FY 24 FY 25 FY 26 FY 27 FY 28-32 Total $0 $0 $0 $0 $0 $16,000,000 $16,000,000

Operating Costs: The project will not have an operational impact on the City.

This article is from: