Karangahape Station CLG Presentation 24 September 2020
CLG Agenda 5:00 – Networking – coffees to order and light snacks 5:30 – Brief welcome – Simon Mitchell, Community Manager 5:35 – Project presentation – Dan Trotman, Construction Manager 5:45 – Break out for table discussions 6:30 – End Table discussions: There will be four tables set up each to address a different topic with subject matter experts on hand to answer questions and provide details on their work. 1. 2. 3. 4.
Beresford Square – Dan Trotman (Construction Manager), Michael Coup (Project Engineer Beresford Square) Mercury Lane – Adam Stilges (Project Engineer) Tunneling update – Cam Butcher (Construction Manager Mined Tunnels) Development Response – Arash Barzin (Development Response Manager) What is Development Response? What business support is available? How do businesses access support?
Project Overview Dan Trotman Construction Manager
3
Beresford Square
Mercury Lane
Mercury Lane January 2020 – September 2020 • Noise enclosure construction (purple) • Installation of diaphragm walls (green), the station’s external walls.
Mercury Lane October 2020 – November 2020 • Installation of plunge columns, providing temporary support for floors and super structure • Mined tunnels started
Mercury Lane November 2020 – January 2022 • Construction of the station’s floors and excavation of the rock beneath
Mercury Lane January 2022 – March 2023 • • • •
Bottom up construction of lower floors Completion of floor columns and walls for station structure Above ground structure Start to station fit-out
Mercury Lane March 2023 – 2024 • Noise enclosure and temporary shaft removal • Station fit-out complete • Urban realm complete
Beresford Square September 2020 – October 2020 • Installation of plunge columns, providing temporary support for floors and super structure
Beresford Square October 2020 – March 2021 • Installation of D-walls (diaphragm walls, shown in green), the stations exterior walls
Beresford Square March 2021 – March 2022 • Construction of station floor and excavation of the rock beneath
Beresford Square March 2022 – March 2023 • Bottom up floor construction • Completion of floor columns and walls for station structure • Start to station fit-out
Beresford Square March 2023 – 2024 • Station fit-out complete • Urban realm complete
Mercury Lane Time lapse camera photo from today @10.45AM
15
Mercury Lane plunge columns
16
Mercury Lane plunge columns
17
Mercury Lane Looking north from above the noise enclosure. Work on the D-wall at Mercury Lane continues with the hydrofraise machine in the foreground.
18 of the 26 panels that make up the station box have now been installed.
18
Mercury Lane Installation of the overhead gantry crane. The gantry crane will lift all plant and spoil via the access shaft.
19
Mercury Lane inside the noise enclosure
20
Mined tunnels Inside the noise enclosure. Looking up from the temporary access shaft.
21
Mined Tunnels Two road header machines will excavate the stations 217-metre platforms and tunnels • TBM breakthrough (northbound): midJuly 2021
• TBM breakthrough (southbound): midJuly 2022
Mined Tunnels Work has begun on the adit tunnel, mining east. Roadheader work will begin in the next few weeks.
23
Canada Street Hoardings Designed and painted by Auckland artist Paul Walsh.
24
Canada Street Hoardings Designed and painted by Auckland Artist Paul Walsh.
25
Beresford Square The crane for the plunge columns has arrived and work will begin next week.
26
Beresford Square Looking west down Beresford Square Guide walls can be seen in the lower centre of the picture, while utility relocation work continues in the centreleft of the picture.
27
Beresford Square Setting up the trench to connect high voltage cables in front of Hopetoun Alpha.
28
Beresford Square Plunge Columns Temporary columns, up to 40-metres deep that support floor slabs during the construction of the various levels of the station.
29
Beresford Square Plunge Columns Plunge columns are removed from within the station once the permanent walls and columns are completed.
30
Beresford Square Plunge Columns Six columns in total Installed sequentially within the road closure Approximate duration 3 – 4 weeks, followed by D-Wall construction Access to private vehicle entrances will be maintained throughout duration.
31
Beresford Square Once the plunge columns are finished work on D-Wall will begin.
32
Questions & Answers
Break out Table Discussion
Thank you