City Rail Link – C1-C2 Community Liaison Group Meeting MINUTES AND ACTION POINTS Rā: Wā: Wāhi:
18 February 2020 5pm – 6:30pm Level 3, CPO Building, 2 Queen Street, Auckland Central
ATTENDEES CLG Members
CRL staff & contractors
P McLuckie – Resident
Maria HernandezCurry (MHC)
Stakeholder Communications Manager – CRL Ltd
Lucas Nikkel (LN)
C2 Project Manager – CRL Ltd
Nicole Lawton (NL)
Communications Coordinator – CRL Ltd
Andrew Swan (AS)
C1 Construction Manager – CRL Ltd
Simon Lough (SL)
Interface Design Manager– CRL Ltd
Aude Salmon (AS)
Senior Stakeholder Advisor – Connectus Joint Venture
Jhon Aragon (JA)
C1 Delivery Manager – CRL Ltd
Mike Backhurst
Sustainability Advisor – CRL Ltd
T Loveridge – Heart of the City S Greenfield - Resident N Quigley - Tappenden Holdings R Boswell - Resident N Playle – Resident J Mantell – Resident
ITEM
UPDATE/ACTIONS
1
Welcome and introductions
• CLG members in attendance introduced themselves. • MHC welcomed everyone and introduced the meeting agenda.
2
C2 Albert St contract update – Lucas Nikkel
• LN introduces himself. • Explains changes to expected completion times of various stages of Albert Street works. • CLG member asks when that information had been updated and communicated, MHC said it had been updated just recently and communicated with stakeholders in each block. • Picture updates: speaking to photos in the slide show, LN gives updates about stages of work. • Albert Street West – Wyndham to Swanson: Sand will be laid below basalt pavers in the place of normal materials to aid further construction in the area directly in front of planned hotel. • Albert Street East – Wyndham to Swanson: works in front of Mansons development and Icon development reduced to avoid rework. Area in front of NZTC would still be completed for final Page | 1