Karanga-a-Hape CLG December 2023

Page 1

Community Liaison Group Karanga-a-Hape Station 14 December 2023


Meeting Agenda 5:30 – Welcome and community engagement update – Simon Mitchell, Community Manager 5:40 – Station box (below ground) works – Emmanuel Chatoux, Senior Project Engineer 5:50 – Station entrance structures – Michael Coup, Construction Manager 6:00 – Urban Realm – Michael Coup, Construction Manager

6:10 – Vertical Transportation install update – Warwick Sextus, MFH Project Manager 6:20 – Discussion and questions 6:30 – End

2


Community Engagement Simon Mitchell, Community Manager

3


Community Engagement - January to March

4


Community Engagement - April to June

5


Community Engagement – July to September

6


Community Engagement – October to December

7


Community Engagement – year in review figures Compliments • 2023: 156 • 2022: 180 Complaints: • 2023: 26 • 2022: 29 Number of events (presentations, meetings, CLGs, tours, Info Hubs) • 2023: 124 • 2022: 143 Small Business Support Package: • 2023: 100% (15/15) • 2022: 100% (15/15) 8


Station box (below ground) works Emmanuel Chatoux, Senior Project Engineer

9


Beresford Square – B6-B2 escalator shaft readiness

10


Beresford Square - B1 and L0 construction openings closure

11


Mercury lane – Completion of all earthing and bonding connections and terminals

12


Mined tunnels - Completion of civil works

In October, the team completed construction of tunnel structures after three and a half years of work, including:

Mining

Waterpoofing

Permanent lining of concrete.

Civils team on Adit 1 within the temporary access shaft 13


Station entrance structures Michael Coup, Construction Manager

14


Mercury Lane Superstructure View from George Court building - Progress since last update (September):

All precast panels (130 in total) installed.

Precast panel weatherproofing sealants completed.

Stage 3 (left-hand side of picture) concrete complete.

15


Beresford Square structure •

33m long, 15m wide roof installation complete. Water testing underway.

96m of stainless steel gutter installed with 16 expansion joints.

Roof installation for service building (behind the entrance structure) nearing completion.

16


Urban Realm Michael Coup, Construction Manager

17


Urban Realm Begins – Beresford Square Drainage underway – Sewer connection and southern section of pipework completed.

Next step is the north side. Target is January to complete.

18


Station Connections – Beresford Square January – February - Station drainage connections installation

19


Urban realm – Beresford Square Ventilation structure

20


Urban Realm Surface Works – Beresford Square February onwards - Waterproofing, hoarding removals and paving base

21


Vector Future Proofing Works Programme Investigation Works – February Stage 1 – March - April Stage 2 – April - May Stage 3 – July - August

Works consist of: • Open trenching and installation of ducting for Vector • 6x 150mm ducts buried approx. 1200mm.

22


Vector Future Proofing Works

STAGE 1 – KARANGAHAPE ROAD

STAGE 2 – MERCURY LANE

23


Vector Future Proofing Works

STAGE 3 – PITT STREET

24


Vertical Transportation install update Warwick Sextus, MFH Project Manager

25


26


VT Progress Mercury Lane

27


28


VT Beresford Square

29


30


Other stations

31


Discussion and questions

32


Thank you for attending Please email us if you have further questions

Karangahape@linkalliance.co.nz