Community Liaison Group Karanga-a-Hape Station 14 December 2023
Meeting Agenda 5:30 – Welcome and community engagement update – Simon Mitchell, Community Manager 5:40 – Station box (below ground) works – Emmanuel Chatoux, Senior Project Engineer 5:50 – Station entrance structures – Michael Coup, Construction Manager 6:00 – Urban Realm – Michael Coup, Construction Manager
6:10 – Vertical Transportation install update – Warwick Sextus, MFH Project Manager 6:20 – Discussion and questions 6:30 – End
2
Community Engagement Simon Mitchell, Community Manager
3
Community Engagement - January to March
4
Community Engagement - April to June
5
Community Engagement – July to September
6
Community Engagement – October to December
7
Community Engagement – year in review figures Compliments • 2023: 156 • 2022: 180 Complaints: • 2023: 26 • 2022: 29 Number of events (presentations, meetings, CLGs, tours, Info Hubs) • 2023: 124 • 2022: 143 Small Business Support Package: • 2023: 100% (15/15) • 2022: 100% (15/15) 8
Station box (below ground) works Emmanuel Chatoux, Senior Project Engineer
9
Beresford Square – B6-B2 escalator shaft readiness
10
Beresford Square - B1 and L0 construction openings closure
11
Mercury lane – Completion of all earthing and bonding connections and terminals
12
Mined tunnels - Completion of civil works
In October, the team completed construction of tunnel structures after three and a half years of work, including:
•
Mining
•
Waterpoofing
•
Permanent lining of concrete.
Civils team on Adit 1 within the temporary access shaft 13
Station entrance structures Michael Coup, Construction Manager
14
Mercury Lane Superstructure View from George Court building - Progress since last update (September):
•
All precast panels (130 in total) installed.
•
Precast panel weatherproofing sealants completed.
•
Stage 3 (left-hand side of picture) concrete complete.
15
Beresford Square structure •
33m long, 15m wide roof installation complete. Water testing underway.
•
96m of stainless steel gutter installed with 16 expansion joints.
•
Roof installation for service building (behind the entrance structure) nearing completion.
16
Urban Realm Michael Coup, Construction Manager
17
Urban Realm Begins – Beresford Square Drainage underway – Sewer connection and southern section of pipework completed.
Next step is the north side. Target is January to complete.
18
Station Connections – Beresford Square January – February - Station drainage connections installation
19
Urban realm – Beresford Square Ventilation structure
20
Urban Realm Surface Works – Beresford Square February onwards - Waterproofing, hoarding removals and paving base
21
Vector Future Proofing Works Programme Investigation Works – February Stage 1 – March - April Stage 2 – April - May Stage 3 – July - August
Works consist of: • Open trenching and installation of ducting for Vector • 6x 150mm ducts buried approx. 1200mm.
22
Vector Future Proofing Works
STAGE 1 – KARANGAHAPE ROAD
STAGE 2 – MERCURY LANE
23
Vector Future Proofing Works
STAGE 3 – PITT STREET
24
Vertical Transportation install update Warwick Sextus, MFH Project Manager
25
26
VT Progress Mercury Lane
27
28
VT Beresford Square
29
30
Other stations
31
Discussion and questions
32
Thank you for attending Please email us if you have further questions