Te Waihorotiu Station / Midtown Community Liaison Group
28 February 2023, 4.00-5.30pm
Caffe Greco
Wyndham Street
1
1. Station construction update
2. Streetscape upgrade plans
3. Te Hā Noa update –Auckland Council / Auckland Transport
4. One-on-one meetings with project leaders
Midtown business and resident support: Natalie & Ben (AC)
Station construction: Matt & Shaun (LA)
Link Alliance streetscapes: Patrick & Nicole (LA)
Loading zones / transport / access: James & Graeme (AT)
Te Hā Noa
Victoria Street construction
Oliver & Philippa (AC)
Station construction update
Sinclair Station Manager
Matt
Welleslely superstructure March 2022 to now
Station passenger concourse and platform levels
June 2022 to now
Victoria/Federal Station entrance mid 2022 to now
Victoria/Elliott Street Station entrance
mid 2022 to now
Station architectural fitout well underway
Escalators
Flooding & response
Streetscape construction overview
Patrick Gibbs – Project Engineer
Nicole Borland – Development Response Manager
Indicative LA programme of works 2023-24
2023
Victoria Street
• Vector enabling works Dec 2022 / Jan 2023 – COMPLETE
• early works - utilities Q1 2023 – IN PROGRESS
• first paver laid Q2 2023
• aim to re-open Victoria St to traffic by approx. end 2023
• phase one of construction works in conjunction with Te Hā Noa Victoria St Project (Federal St to Queen St)
• Kingston Street
above-ground ventilation structure and streetscape early works
• Bluestone wall reconstruction
2023-2024 (detail tbc)
Albert St, from Victoria to Wyndham St
Albert St, from Victoria to Wellesley St
Wellesley Street in conjunction with Wellesley St Bus Improvements Project
Current constraints
- Contractor appointment
- Resource availability
- Utilities provider coordination
- ‘Dig once’ approached is preferred
- Completing underground and above-ground works
Usual Construction Working Hours
Monday – Saturday– 7am - 7pm
Nightworks and early morning works will be required at certain times – we will work with
Stage 1 Utility connections
Stage 2 Base prep
Stage 4 Cutting and laying pavers
Stage 5 Street furniture and tree planting
*Draft plan which is subject to change. This shows the final design features including the station entrance, tree planting, and paver layouts.
*Draft plan which is subject to change. This shows the final design features including the station entrance, tree planting, and paver layouts.
*Draft plan which is subject to change. This shows the final design features including the station entrance, tree planting, and paver layouts.
Pedestrian diversion plan
• We will continue to work with each individual business when we move the works to right up to the property boundary / shop door.
• Access to businesses will be maintained, however several pedestrian diversions / new accessways will be required due to the extremely close proximity of the works to the businesses, and for safety reasons. In some cases small bridges will be used.
• Not all businesses will be diverted simultaneously – we work in a staged approach to minimise pedestrian confusion/overwhelm.
• All of our usual construction effects mitigation measures will be in place and we will continue to work with the shop owners on wayfinding, signage and business support.
• Please bear with us – we are now on the home stretch.
REGENERATING MIDTOWN
Presentation to the CRL Community Liaison Group 28 February 2023
PROJECTS IN MIDTOWN
Te Waihorotiu Station
Te Ha Noa Victoria Street
UPCOMING MAJOR CONSTRUCTION
2022 2023 2024 2025 2026
Federal Street Upgrade
Wai Horotiu Queen Street
Myers Park Underpass
CRL streetscapes
Te Hā Noa Victoria Street
Wellesley Street Bus Improvement Stage 1
Watercare Queen Street Diversion
Symphony Centre Victoria St reopens to traffic
TE HĀ NOA VICTORIA STREET
Block A – City Rail Link
Federal Street to Elliott Street until early 2024
Block B – Auckland Council
Elliott Street to Queen Street March 2023 to early 2024
Block C – Auckland Council
Queen Street to Kitchener St Utilities work 2023
Main works from early 2024
BLOCK B – ELLIOTT STREET TO QUEEN STREET
OUR COMMITMENTS TO YOU
• Coordinating work and minimising disruption
• Keeping you informed
Making sure you can still do what you do
Making sure people can get around
Taking care of the area • Supporting businesses
• Encouraging people to keep coming to the area
•
•
•
FIND OUT MORE • www.ProgressAKL.co.nz/midtown • Sign up for regular construction updates • Individual meetings • On-street team • Contact us at midtown@aucklandcouncil.govt.nz