Te Waihorotiu Station Presentation 28 February 2023

Page 1

Te Waihorotiu Station / Midtown Community Liaison Group

28 February 2023, 4.00-5.30pm

Caffe Greco

Wyndham Street

1
1. Station construction update 2. Streetscape upgrade plans 3. Te Hā Noa update –Auckland Council / Auckland Transport 4. One-on-one meetings with project leaders

Midtown business and resident support: Natalie & Ben (AC)

Station construction: Matt & Shaun (LA)

Link Alliance streetscapes: Patrick & Nicole (LA)

Loading zones / transport / access:  James & Graeme (AT)

Te Hā Noa

Victoria Street construction

Oliver & Philippa (AC)

Station construction update

Matt
Welleslely superstructure March 2022 to now

Station passenger concourse and platform levels

June 2022 to now

Victoria/Federal Station entrance mid 2022 to now

Victoria/Elliott Street Station entrance

mid 2022 to now

Station architectural fitout well underway

Escalators

Flooding & response

Streetscape construction overview

Patrick Gibbs – Project Engineer Nicole Borland – Development Response Manager

Indicative LA programme of works 2023-24

2023

Victoria Street

• Vector enabling works Dec 2022 / Jan 2023 – COMPLETE

• early works - utilities Q1 2023 – IN PROGRESS

• first paver laid Q2 2023

• aim to re-open Victoria St to traffic by approx. end 2023

• phase one of construction works in conjunction with Te Hā Noa Victoria St Project (Federal St to Queen St)

• Kingston Street

above-ground ventilation structure and streetscape early works

• Bluestone wall reconstruction

2023-2024 (detail tbc)

Albert St, from Victoria to Wyndham St

Albert St, from Victoria to Wellesley St

Wellesley Street in conjunction with Wellesley St Bus Improvements Project

Current constraints

- Contractor appointment

- Resource availability

- Utilities provider coordination

- ‘Dig once’ approached is preferred

- Completing underground and above-ground works

Usual Construction Working Hours

Monday – Saturday– 7am - 7pm

Nightworks and early morning works will be required at certain times – we will work with

Stage 1 Utility connections

Stage 2 Base prep

Stage 4 Cutting and laying pavers

Stage 5 Street furniture and tree planting

*Draft plan which is subject to change. This shows the final design features including the station entrance, tree planting, and paver layouts.

*Draft plan which is subject to change. This shows the final design features including the station entrance, tree planting, and paver layouts.

*Draft plan which is subject to change. This shows the final design features including the station entrance, tree planting, and paver layouts.

Pedestrian diversion plan

• We will continue to work with each individual business when we move the works to right up to the property boundary / shop door.

• Access to businesses will be maintained, however several pedestrian diversions / new accessways will be required due to the extremely close proximity of the works to the businesses, and for safety reasons. In some cases small bridges will be used.

• Not all businesses will be diverted simultaneously – we work in a staged approach to minimise pedestrian confusion/overwhelm.

• All of our usual construction effects mitigation measures will be in place and we will continue to work with the shop owners on wayfinding, signage and business support.

• Please bear with us – we are now on the home stretch.

REGENERATING MIDTOWN

Presentation to the CRL Community Liaison Group 28 February 2023

PROJECTS IN MIDTOWN

Te Waihorotiu Station Te Ha Noa Victoria Street

UPCOMING MAJOR CONSTRUCTION

2022 2023 2024 2025 2026

Federal Street Upgrade

Wai Horotiu Queen Street

Myers Park Underpass

CRL streetscapes

Te Hā Noa Victoria Street

Wellesley Street Bus Improvement Stage 1

Watercare Queen Street Diversion

Symphony Centre Victoria St reopens to traffic

TE HĀ NOA VICTORIA STREET

Block A – City Rail Link

Federal Street to Elliott Street until early 2024

Block B – Auckland Council

Elliott Street to Queen Street March 2023 to early 2024

Block C – Auckland Council

Queen Street to Kitchener St Utilities work 2023

Main works from early 2024

BLOCK B – ELLIOTT STREET TO QUEEN STREET

OUR COMMITMENTS TO YOU

• Coordinating work and minimising disruption

• Keeping you informed

Making sure you can still do what you do

Making sure people can get around

Taking care of the area • Supporting businesses

• Encouraging people to keep coming to the area

FIND OUT MORE • www.ProgressAKL.co.nz/midtown • Sign up for regular construction updates • Individual meetings • On-street team • Contact us at midtown@aucklandcouncil.govt.nz

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.