Construction Environmental Management Plan – Addendum

Page 1


Aotea Station Public Realm Reinstatement

Construction Environmental Management Plan – Addendum

CRL-AOT-RME-LKA-RPT-800015

Revision: A01

Date: 29 October 2021

Aotea

Station Public Realm Reinstatement – Construction Environmental Management Plan

CRL-AOT-RME-LKA-RPT-800015

This document is uncontrolled when printed. This document should be printed in colour

Revision Status

Approval Status

1. Introduction

The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the North Auckland Rail Line (NAL) in the vicinity of Mt Eden Station. The CRL also involves the construction of two new underground stations at Aotea and Karangahape and the redevelopment of the station at Mt Eden (refer to Figure 1.1). The design and construction of the CRL infrastructure between the Aotea and Mt Eden Stations is being delivered by the Link Alliance.

In May 2020 Auckland Council confirmed the Outline Plan and associated Construction Environmental Management Plan (CEMP) and Delivery Works Plans (DWPs) for the Aotea Station main construction works (‘Main Works’). This document is an addendum to the Main Works CEMP1 and provides an overarching framework for the management of construction effects associated with the public realm reinstatement (PRR) phase of works.

This addendum has been prepared to detail the construction methodology and address the potential environmental effects associated with the PRR phase of the construction works that were not covered in the Main Works CEMP. Where necessary, this CEMP addendum (the CEMP – PRR addendum) details any further provisions which are required in relation to the PRR works that are not already provided for in the Main Works CEMP. In some instances, it has been appropriate to prepare addendum documents to the respective Main Works DWP also (refer Table 1.1).

Where project details, procedures and protocols are already covered in the Main Works CEMP and are directly applicable to the PRR works, reference is made to the appropriate section of the Main Works CEMP. Accordingly, the CEMP-PRR addendum for Aotea Station should be read in conjunction with the certified Main Works CEMP, and the associated delivery works plans and

1 Aotea Station Main Works Construction Environmental Management Plan, prepared by the Link Alliance, approved by AC, 8 May 2020 (ref.CRL-AOT-RME-LKA-PLN-800025)

Page 5 | Aotea Station – Public Realm Reinstatement

Figure 1 1 CRL Route and Location

management plans Table 1.1 provides an overview of the suite of Main Works DWPs and MPs and additional addendums prepared for these PRR works.

Table 1.1. Overview of CEMP – PRR and sub-plan addendums

Existing Aotea Station Main Works Plans Plan

Construction Environmental Management Plan (CEMP)

Urban Design DWP (Appendix C to the Outline Plan)

Social Impact and Business Disruption

DWP (SIBD DWP) – Appendix F to the CEMP

Communication and Consultation Plan (CCP) - Appendix G to the CEMP

Erosion and Sediment Control Plan (ESCP) – Appendix H to the CEMP

Air Quality DWP / Air Quality Management Plan – Appendix I to the CEMP

Trees and Vegetation DWP – Appendix J to the CEMP

Transport, Access and Parking DWP (TAP DWP) – Appendix K to the CEMP TAP DWP –Addendum (Appendix B)

Construction Noise and Vibration DWP (CNV DWP) – Appendix L to the CEMP

Historic Heritage DWP (HH DWP), Built Heritage - Appendix M to the CEMP

Historic Heritage DWP (HH DWP), Archaeology - Appendix N to the CEMP

Contamination DWP / Contaminated Soils Management Plan – Appendix O to the CEMP

Groundwater and Settlement Monitoring and Contingency Plan (GSMCP) –Appendix P to the CEMP

Industrial and Trade Activities

Environmental Management Plan (ITA EMP) – Appendix Q to the CEMP

Site Specific Construction Noise and Vibration Management Plan – Public Realm Reinstatement (Appendix C)

C 36, 37 and 38

and

2. Aotea Station Public Realm Works

2.1 Overview of Works

This chapter provides a description of the PRR works, which are not included in the Aotea Station Main Works CEMP.

The Aotea Station public realm works extend along Albert Street from Wyndham Street (end of the C2 works site boundary) to the southern end of the Aotea Station Designation 2500-1 located adjacent to 10 Mayoral Drive. This includes sections of intersecting roads including Victoria Street, Wellesley Street, Kingston Street, and Durham Street. The extent of the works area is shown in Figure 2.1 below.

The construction works required to reinstate the permanent aspects of the public space include paving, sealing, tie-in works, stormwater treatment, the installation of street furniture and landscaping. The works will be undertaken in a staged manner (with five main stages), commencing as the current construction works are progressively completed (refer Section 2.2).

A description of each of the key activities relevant to this addendum is provided in Section 2.3

2.2 Construction Staging

The PRR works are divided into five main ‘stages’ as illustrated in Table 2.1. Note that the various phases overlap for some of the works, which is reflected in the total duration of works, being approximately 18 months. An overview of the PRR construction staging is provided in Figure 2.1 and Appendix A.

Table 2.1. Overview of Construction Works and Staging

Stage 1 – Wyndham to Victoria Street

Stage 2 – Victoria Street

Stage 3 – Albert Street

Stage 4 – Wellesley Street

Stage 5 – Mayoral Drive

Albert Street, Durham Street and Kingston Street public realm works

- Public realm works along Victoria and at the intersection with Albert Street.

- Public realm works around the station entrances on Victoria Street.

- Public realm works along Albert Street from Victoria to Wellesley Street.

- Public realm works along lower Albert Street

- Tie ins to Crowne Plaza and Sky City accesses Early 2023

- Public realm works along Wellesley Street and at the intersection with Albert Street.

- Completion of the Aotea Station forecourt

- Public realm works along Mayoral Drive

2023

2023

2023

2024

2.3 Construction Methodology

2.3.1. Overview

Generally, the PRR works will consist of:

• Construction of new stormwater infrastructure

• Installation of utilities

• Construction of tree pits

• Installation of new road pavement

• Installation of new footpath pavements

• Landscaping works

• Installation of road furniture

• Reinstatement of canopies

2.3.2.

Stormwater Infrastructure

New stormwater catchpits, lines and drains are being installed to capture stormwater runoff from the road and footpaths. The new stormwater infrastructure is within the road carriageway and connects into the existing stormwater network.

The stormwater construction works will be staged to construct the main drainage lines, manholes and connections first. Generally, these works start from the downstream connection points and are laid ‘uphill’ to the head of the new drainage line. Once the main drainage lines are completed then the Aco drains, catchpits and leads will be constructed – with the works staged in accordance with the construction phase drawing (Appendix A) and associated traffic management

Figure 2 1: Overview of Construction Staging

Plant used for the stormwater works includes excavators (5T-20T), trucks for spoil disposal and importing backfill materials, concrete trucks, compaction equipment (plate compactors and/or small rollers), trench shields and hand tools. Due to the limited space available on the site, materials will be delivered to site as they are required for the construction works.

2.3.3.

Utilities

A new network of utilities will be required to service the public realm installations and divert main utilities back into permanent alignments. This will include low voltage for lighting and fibre and copper cabling.

Duct installations will be completed using 5 – 14t excavators, trucks for spoil disposal and importing backfill materials, concrete trucks, compaction equipment (plate compactors and/or small rollers), trench shields and hand tools. Due to the limited space available on the site, materials will be delivered to site as they are required for the construction works.

Linked to this utility duct and cable work will be the installation of street lighting and other above ground traffic service installations.

2.3.4.

Tree Pits

Several tree pits will also be constructed for new planting installations. Locations of this are provided in the Urban Design DWP. Many of the tree pits are in close proximity to services and in some cases 25mm steel plates are to be installed to provide an additional root barrier between the tree pits and service trenches. During excavation, as utilities are approached, hydro excavation and pothole techniques will be used to expose them. Excavation around the utility will be undertaken, leaving enough material to support it temporarily. Where required, temporary supports will also be installed around the utilities.

Tree pits will be excavated to depth using excavators (5T-20T) with the excavation battered to provide a safe working zone. The excavations will be around 1-2m deep.

Plant used for the tree pit works includes excavators (10-20T), trucks for spoil disposal and importing backfill materials, compaction equipment (plate compactors and/or small rollers), trench shields and hand tools. Due to the limited space available on the site, materials will be delivered to site as they are required for the construction works.

2.3.5.

Road Pavement

Once the substantial below ground works are completed in each area, the road pavement works will commence. Subsoil drains will be constructed along the edges of the road carriageway, followed by the kerb construction, then subgrade and basecourse layers.

Testing will be undertaken on the subgrade and basecourse layers during construction to confirm the requirements of the civil specifications and drawings have been achieved.

The basecourse material will be placed directly from trucks, and spread and compacted using excavators, graders and plate / roller compactors. The road will be constructed in stages providing the necessary live traffic lanes, vehicle access to properties and maintaining pedestrian and cycle access.

Once the basecourse layers are complete, then the structural asphalt layers will be constructed. Specialist asphalt subcontractors will undertake these works using asphalt paving plant. The final

50mm layer of AC14 will not be placed until the final phase of the works. This is to ensure no damage to the final layer and to provide a consistent finish with fewer visible joints. Line marking works will be completed once the final asphalt layer has been placed.

2.3.6. Footpath Pavements

The footpath pavements will commence in an area once the utilities works, tree pits and kerbing have been completed. Footpath pavements generally consist of basecourse layer, reinforced concrete layer and decorative paving layer.

The footpaths will be constructed in phases, with pedestrian access (1.5m wide) and access to properties maintained. The pedestrian routes will generally be kept close to the building walls, but will be moved within the work zone to allow the works adjacent to the buildings to be completed. At all times the pedestrian access routes and live work zones will be separated by appropriate safety barriers (e.g. fencing).

Testing will be undertaken on the subgrade and basecourse layers during construction to confirm the requirements of the civil specifications and drawings have been achieved.

The basecourse material (cement treated basecourse) will be delivered to the worksite as required by trucks and spread and compacted using small excavators (5-10T), and small roller or plate compactors. Concrete delivery for the structural concrete layer will be by truck, with concrete pumps (Line or boom) used as required. The concrete layer will be constructed in segments to maintain pedestrian movements and suit the constraints of the site. A watering system shall be used to control dust from the placement of fill and bedding material as well as during compaction.

Decorative paving works will involve cutting and placing stone pavers and mixing and placing of Steintec bedding or similar A watering system shall be used to control dust from extraction and any cutting operations. A mobile acoustic enclosure shall be used where practicable for any paver cutting. Materials for these works will be kept on site (in limited quantities as required) and mixed and cut to fit in designated areas of the work zone.

2.3.7. Landscaping

Landscaping works consist of planting, including tree planting in the completed tree pits (refer 2.3.4) This will be one of the final activities and will be completed from the adjacent traffic lane, where they are located in the footpath. Trees will be delivered by truck and planted by hand or using a Hiab crane. Surface tree grilles or permeable covering will be installed once trees have been planted.

2.3.8. Road Furniture

Road furniture includes street lighting and signage, traffic signals, seating, rubbish bins, and bicycle racks. Foundations and utilities supplies for these items will be completed during the previous stages of these works. The installation of road furniture will be one of the final activities undertaken in each area.

Road furniture will generally be delivered to site and installed immediately. Installation will be carried out by specialist installers using hand tools, and Hiab crane for lifting larger items.

Commissioning and testing of the electrical items (e.g., streetlights, traffic signals) will be carried out by specialist electricians in accordance with the specifications and local authority requirements.

2.3.9. Reinstatement of Canopies

Canopies previously removed as part of the early works (Stages 4 and 5) phase will be reinstated as part of the PRR works. These will be reinstated to the same or better standard than existing prior to the works being undertaken.

These works will include builders works, painting and electrical services and will include canopies on 44 Wellesley St, 37 Albert St, and 98 – 102 Albert Street.

2.4 Programme

The PRR works are anticipated to take approximately 18 months to complete and will commence from mid/late – 2022.

2.5 Hours of Work

Construction will be as per those outlined in Section 2.5 of the Main Works CEMP. Works will generally be undertaken Monday to Saturday, 0700 – 1900 hrs. However, certain activities may need to be undertaken outside these hours to minimise traffic impacts or minimise disruption to businesses or residents, such as network utility works where the NUO requires works to be undertaken at night, or the delivery of large plant.

To maintain pedestrian access to business and properties, night works may be required for the installation of pavers. Night works shall be limited to the placing of pre-cut pavers. Cutting of pavers shall be undertaken during daytime construction hours.

2.6 Site layout and management

The Aotea CSA (located at Bledisloe House car park) will service the PRR works, with the area of the CSA reducing as the PRR works proceed until operation of the CSA is no longer required. Once the CSA is no longer required, the area will be stabilised for the future OSD construction. This will be to an agreed state with the OSD developer. Construction of the OSD is programmed to commence August 2024 following the completion of the PRR works.

Key activities within the PRR works areas shall include:

• Liquid waste and solid waste storage and collection (e.g., contaminated water, used chemicals, liquids and slurry from spill clean-up, “slops and slurry” skips) from active work zones

• Asphalt pavement construction equipment

• Fuel storage for pumps, generators etc.

• Use and storage of diesel pumps and compressors

• Use and storage of concrete pumps

• Use and storage of mobile generators

• Concrete breaking

• Storage of construction materials such as steel reinforcing cages, pre-cast concrete elements, geotextiles, formwork (timber and steel), bagged cement, paving materials

• Site offices and construction personnel amenities including portaloo or similar

• Stormwater/groundwater containment and/or treatment facility

• Vehicle movements between active work zones and construction support areas.

The site office, site parking, and compound site security and safety, along with site housekeeping will be as per the Main Works CEMP until no longer practicable, or required, depending on the progress of work and associated constraints.

2.7 Site Security, Safety and Public Viewing

There is no change to the protocols for managing security, safety and public viewing outlined in the Mains Works CEMP.

3. Social and Environmental Management

3.1 Construction Activities and Associated Environmental Receivers

The key construction activities associated with the Aotea Station PRR Works are summarised in Table 3.1 below.

These activities have the potential to generate adverse environmental effects relating to network utility disruption, social and business disruption, transport access and parking, noise and vibration, dust, stormwater discharges, soil contamination, and built heritage.

Table 3.1. Construction activities and associated environmental receivers

Main activities

- Backfilling

- Spoil handling

- Reinstatement

- Installation of utilities

- Planting of trees

- Installation of pavements including concrete cutting

- Installation of street furniture

3.2 Environmental Risk Register

Receiving Environment

- Stormwater (Waitemata Harbour)

- Buildings (vibration/heritage)

- Residents/social and businesses (noise/vibration/dust/odour)

- Traffic network

There is no change to the risk register framework outlined in Section 3.2 of the Main Works CEMP.

It is noted that as the risk register is a ‘living document’ and shall continue to be reviewed monthly as part of the Project Monthly Report and prior to the commencement of new construction activities, such as the PRR works.

3.3 Cumulative Effects

There is no change to the existing approach, whereby sub-plans are relied upon for identification, controls, and monitoring to address cumulative effects. Additional controls are specified in Section 5 of this CEMP.

3.4 Legislative and Other Requirements

There is no change to the identified legislation, polices, plans and consents in Section 3.4 of the Main Works CEMP.

4. Implementation and Operation

The PRR works will be undertaken in accordance with Section 4 of the Main Works CEMP. The following updates to the persons undertaking the roles is detailed in Section 4.1 below.

4.1 Roles and Responsibilities

Table 4.1: Specific Roles and Responsibilities – Link Alliance – updates from Mains Works CEMP

4.2 Training and Induction

There is no change to the environmental and sustainability training and induction procedures outlined in the CEMP.

Aotea
Hutching
Aotea Station Community Manager – Shaun Sutton
Environmental
– Maria Aguiar Environmental Advisor – Jason Haggerty

5. Environmental Management

The Main Works DWPs and Management Plans continue to detail the controls and measure for each of the environmental aspects of the PRR works as specified in Section 5 of the Mains Works CEMP. Furthermore, the following sections identify the environmental aspects associated with the construction of the PRR works with any additional operational controls and mitigation measures specific to the PRR works identified.

5.1 Network Utilities

Consultation and co-ordination with Network Utility Operators will continue to be managed in accordance with the general processes outlined in Section 5.1 of the Main Works CEMP.

5.2 Social Impact and Business Disruption

The PRR works will not change the level of potential adverse social or business disruption effects from the activities identified in the Social Impact Business Disruption (SIBD DWP) In addition, the potential effects of the PRR works don’t extent beyond the ‘affected community’ identified in the Main Works SIBD DWP.

A such, there is no change to the general processes for managing social impacts and business disruption (SIBD) as identified in Section 5.2 of the Main Works CEMP, with additional mitigation to be implemented as outlined in this CEMP Addendum.

5.3 Communication and Consultation

The general processes outlined in the Communication and Consultation Plan2 (CCP) will be used to ensure appropriate communication and consultation with the community, stakeholders, affected parties and affected in-proximity parties occurs during the PRR works as identified in Section 5.3 of the Main Works CEMP.

It is noted that since the Main Works CCP was written a new drop in information hub (Te Pūkaki) has opened beside the Aotea Station site. This is open to the public 11am – 1pm weekdays where people can ask questions and find out more about the City Rail Link, the construction activities occurring at Aotea, and upcoming construction milestones. This will be available for the public during the PRR phase of works.

5.4 Erosion and Sediment Control

There is no change to the general processes for managing erosion and sediment generation as identified in Section 5.4 of the Main Works CEMP.

The Main Works Erosion and Sediment Control Plan (ESCP) follows the principles of Auckland Council GD05. Erosion and sediment control measures will be installed prior to the start of any land

2 It is noted that the Main Works CCP did not reference the building owners identified in Condition 15.4 (xi), (xii), (xiii). The CCP is now being updated to reference these owners specifically through the annual review process as required by Condition 22.1. While these owners were not referenced in earlier CCP documents, engagement and consultation has occurred with parties through the wider Aotea communications process and through specific property and neighbourhood engagement.

disturbance works. The mitigation measures will remain in place until reinstatement of active working areas is complete. General ESC measures include:

• Catchpit/stormwater inlet protection (e.g., covering catchpit grates with geotextile to filter sediment laden runoff);

• Chemical treatment (used to improve the efficiency of sediment retention devices e.g., automated chemical dosing);

• Dewatering devices (devices used to pump out water that collects within open trenches);

• Diversion channel/bund (install to divert runoff from external catchments entering construction areas e.g. hotmix diversion bunds);

• Filter socks (with or without flocculation, to intercept and impound runoff);

• Sand logs/coir logs (use in carriageway to divert clean water from construction site);

• Settlement tanks (for storage of sediment-laden runoff); and

• Stabilised entrance and surface (vehicle movements on sealed surfaces, vehicle accesses to be kept clean, stabilise entrance ways using aggregates).

A Flocculant Treatment Management Plan (FTMP) has been prepared as part of the Mains Works ESCP. PRR works will be undertaken in accordance with the measures identified in the FTMP.

5.5 Air Quality

The main discharges to air that will arise from the PRR works is dust. The following dust generating activities associated with the PRR works have been identified:

• Breaking up and excavating the existing footpath;

• Placement of fill/bedding material;

• Excavation of tree pits;

• Cutting of pavers/kerbstones;

• Concrete cutting; and

• Placement of soil

Apart from the cutting of pavers and concrete as described below, the other activities will be undertaken in accordance with Section 5.5 of the Main Works CEMP and the Air Quality (AQ) Delivery Work Plan

5.5.1.

Mitigation measures

The dust prevention methods outlined in Table 5.1, will be used as applicable to control dust emissions from the cutting of pavers and curb stones, in all areas of the Project. The list is not exhaustive and additional methods which are found to be effective may be used.

Some of the particulate generated by the cutting of pavers and kerbstones has the potential to be respirable quart/crystalline silica which, when uncontrolled, presents some health risks. These risks are controlled through the mitigation proposed in Table 5.1.

Source of Dust Control

Pavement Removal

Placement of Bedding Material

Cutting of Pavers

- Use water as necessary to control dust from extraction and any cutting operations.

- As far as practical excavated material is to be loaded directly into trucks.

- Use water as necessary to control dust from the placement of fill and bedding material as well as during compaction.

- As far as practicable all pavers and curb stones will be cut using equipment fitted with water dust suppression.

- Where it is not possible to use water suppression vacuum extraction systems shall be fitted to the cutting/grinding equipment.

- Solid barriers can also be placed around cutting activities to minimise wind effects.

- Alternatively, enclosures may be required (to mitigate noise).

Monitoring of these dust generating activities will be in accordance with the requirements of the AQ DWP. This includes daily visual inspections.

5.6 Trees and Vegetation

There is no change to the existing processes for managing potential adverse effects on trees and vegetation as identified in Section 5.6 of the Main Works CEMP.

It is noted no further trees are proposed to be removed as part of the PRR works, however protocols are relevant to existing trees to ensure they are appropriately protected during works.

Trees and vegetation are to be installed as described in Section 2.3.4 and 2.3.7. Details of types and location of trees and vegetation is addressed in the Urban Design DWP

5.7 Transport, Access and Parking

A Transport Access and Parking DWP Addendum (Appendix B) has been prepared to specify the methodology during the PRR works. The addendum identifies the transport configurations (including traffic layouts and movements, pedestrian access, property access and parking) for each of the construction configurations of the PRR works.

The five stages of the PRR works have been broken into further sub-stages for the purpose of traffic management planning (refer Section 4) and have been assessed to comply with relevant CRL designation conditions. The relation between the Main Works stages and PRR stages are outlined in the following table.

Table 5.2: Relationship between PRR stages and Main Works stages and respective road network layouts

Table 5 1: Dust management methods for PRR pavement works

Proposed PRR Stage

Stage 1C

Stage 2

Stages 3A, 3B

Traffic Stage 4

Traffic Stages 3 and 4

Traffic Stages 3, 4 and 6

Stages 4A, 4B

Traffic Stage 6

Stage 5

Traffic Stage 6

Network Layout

Albert St / Victoria St West intersection –closed to vehicles

Albert St / Wellesley St West intersection –open to vehicles Mayoral Drive – cul-de-sac

Same as above, but Kingston St is opened

Same as for PRR Stages 1A, 1B, 1C

Same general layout as for previous PRR Stages but either the Albert St / Victoria St West intersection closed to vehicles while Albert St / Wellesley St West intersection is open with two lanes in each direction as per Traffic Stages 3 and 4, or with the Albert St / Victoria St West and Albert St / Wellesley St West intersections both open with one lane in each direction as per Traffic Stage 6.

Albert St / Victoria St West and Albert St / Wellesley St West intersections both open with one lane in each direction.

Same as above.

The effects of the PRR stages on the road network, especially in terms of travel time impacts on inner city bus services are described in Section 5 of the Aotea Main Works TAP DWP. The effects to on-street parking and loading spaces will be as outlined in Section 6 of the Aotea Main Works TAP DWP. The processes and responsibilities in relation to monitoring for the PRR works are consistent with that for the Main Works, as detailed in Section 7 of the Aotea Main Works TAP DWP.

Together with the specific measures to manage the PRR work set out in the TAP DWP - PRR Addendum and the general management measures in the TAP DWP, adverse transport, access and parking effects will be appropriately mitigated.

5.8 Construction Nose and Vibration

Construction noise and vibration will continue to be managed in accordance with the general processes for managing construction noise and vibration as outlined in Section 5.8 of the Main Works CEMP and detailed in the Main Works CNV DWP

Various construction equipment and activities will act as noise and vibration sources during the PRR phase of works, such as excavators, concrete breakers, concrete saws, compactors and trucks. Details of this equipment is provided in Section 4 of the CNV DWP.

General noise and vibration management and mitigation measures are proposed to be implemented throughout construction to avoid, where practicable, exceedances of the noise and vibration criteria.

18 | Aotea Station – Public Realm Reinstatement

These are listed in Section 6 of the CNV DWP and include the use of noise barriers and enclosures where noise limits are predicted to be exceeded. Additional measures for each notable receiver during the PRR phase is provided in a Site-Specific Construction Noise Vibration Management Plan (SSCNVDWP) (Appendix C) The SSCNVMP for the PRR works provides additional detail on the use of mobile acoustic enclosures that may be used to mitigate the effects from stationary plant, such as paver cutting stations

Monitoring of noise and vibration is detailed in Section 8 of the CNV DWP and will be undertaken during construction when noise or vibration has the potential to exceed the limits or in response to noise or vibration complaints.

Engagement with affected parties will continue to be undertaken as detail in Section 7 of the CNVDWP.

5.9 Light Spill and Glare

There is no change to the existing processes for managing construction lighting as identified in Section 5.9 of the CEMP.

5.10 Historic Character

5.10.1.

Built Heritage

The PRR works has the potential to affect historic buildings and historic streetscape elements, as identified in the Aotea Station Main Works Historic Heritage DWP – Built Heritage.

The PRR works will be undertaken in accordance with Section 5.10.1 of the Main Works CEMP and the general management measures outlined in the Historic Heritage DWP – Built Heritage This includes methods to monitor the works (as set out in the CNV DWP, SSCNVMP and GSMCP) and to protect heritage fabric during construction phases. This includes the use of plywood to protect building fabric, use of bracing for parapets, chimneys etc and careful removal of basalt kerbs for reuse.

Protection measures shall be reviewed by the Project Built Heritage Specialist prior to works commencing and periodically during the works.

5.10.2.

Archaeology

The PRR works will be undertaken in accordance with Section 5.10.2 of the Main Works CEMP and the general management measures outlined in the Historic Heritage DWP – Archaeology.

Two recorded archaeological sites are located within the PRR works area, one being along the eastern side of Albert Street between Wyndham Street and Victoria Street (R11/3078; bluestone wall, stairs and toilets). The other is a backfilled or capped off well (R11/1182) within the CSA3

It is noted that the deconstruction and reconstruction of the scheduled Bluestone Wall located on Albert Street (near the Durham Street West intersection) is the subject of a Bluestone Wall Management Plan (confirmed by Auckland Council on 15 October 2020) in accordance with designation condition 45. The wall has now been deconstructed and will be reconstructed 1.5m

3 The Historic Heritage DWP – Archaeology required that the Project Archaeologist monitor the initial earthworks in the station entrance area.

19 | Aotea Station – Public Realm Reinstatement

further to the east once the necessary station construction works are complete (approximately between July and November 2022). The work associated with the Archaeological recording of the wall has been undertaken and is provided for in Section 6 of the HC DWP (Archaeology Section).

The PRR works will result in shallow excavations only and is unlikely that subsurface archaeological remains will be exposed. However, the possibility that subsurface pre-1900 or early 20th century archaeological remains may be exposed during the PRR phase will be mitigated and managed through the implementation of the HCC DWP (Archaeology Section) and an Archaeological Authority (no. 2017/793) granted by Heritage New Zealand Pouhere Taonga (HNZPT) for the wider CRL project (“the HNZPT Authority”).

Measures to mitigate impacts on archaeological remains include:

• Archaeological Discovery Protocols;

• Mana Whenua Protocols;

• Recording of Features and Deposits;

• Artefact Management Plan;

• Stand down periods;

• Post-excavation analysis and archiving; and

• Reporting requirements.

5.11 Urban Design

An Urban Design Delivery Work Plan (Urban Design DWP) has been prepared by the PRR works and the design of the Aotea Station including entrances and associated buildings. The Urban Design DWP is required to ensure that the areas within the designation footprint used during construction are restored and permanent works associated with the CRL are developed in accordance with urban design principles.

5.12 Public Art

The PRR works do not directly affect public art. Accordingly, as stated in Section 5 12 of the Main Works CEMP, a Public Art DWP is not required for these construction works.

5.13 Contaminated Soils

The existing management approach to the disturbance of any contaminated, or potentially contaminated material encountered during the PRR work, and the management of any associated human health or environmental effects will be undertaken in accordance with Section 5.13 of the Main Works CEM and the Main Works Contamination DWP.

5.14 Groundwater and Settlement

Due to the shallow nature of excavations required for the PRR works, groundwater is not expected to be encountered. As stated in the Assessment of Settlement Effects Report4 , a GSMCP is not required for the PRR works.

4 Appendix E of the Aotea Station Main Works Groundwater and Settlement Monitoring and Contingency Plan, prepared by the Link Alliance, dated 22 June 2020

Page 20 | Aotea Station – Public Realm Reinstatement

If groundwater is encountered, groundwater and settlement monitoring will be undertaken in accordance with the Main Works GSMCP.

5.15 Hazardous Substances

Hazards substances will be kept on site within specified hazardous substance storage areas at the site construction compound (within Bledisloe House car park). No additional hazardous substances will be required for the PRR works, from that listed in the Main Works CEMP.

The storage and use of hazardous substances will be managed in managed in accordance with Section 5.15 of the Main Works CEMP and the relevant provisions of the Industrial and Trade Activities Environmental Management Plan (ITA EMP) Any spills on site will be managed in accordance with the General Spill Response Plan provided as Appendix C to the ITA EMP.

5.16 Industrial and Trade Activities

Industrial trade activities will be managed in accordance with Section 5.16 of the Main Works CEMP and the relevant provisions of the Industrial and Trade Activities Environmental Management Plan. This includes activities such as vehicle refuelling, concrete washout, and the management of hazardous substances. Any spills on site will be managed in accordance with the General Spill Response Plan provided as Appendix C to the ITA EMP.

5.17 Building Condition Surveys

Building condition surveys (BCS) were required to be undertaken prior to the Main Works construction phase commencing, in accordance with designation condition 46 and resource consent condition 109. Due to the shallow nature of excavations required, no additional building condition surveys are required prior to the commencement of the PRR phase of works. Post construction condition survey requirements will be undertaken as identified in Section 5.17 of the Main Works CEMP.

5.18 Waste Management

There is no change to the existing processes for waste management as identified in Section 5.18 of the Main Works CEMP.

5.19

Energy Use

There is no change to the existing processes for reducing energy use as identified in Section 5.19 of the Main Works CEMP.

5.20

Water Use

There is no change to the existing processes for reducing water use as identified in Section 5.20 of the Main Works CEMP.

5.21

Material Use

There is no change to the existing processes for reducing material use as identified in Section 5.21 of the Main Works CEMP.

5.22

Emergency and Incident Response

There is no change to the existing processes for incident response as identified within Section 5.22 of the Main Works CEMP.

6. Monitoring and Review

There are no changes to the procedures for environmental monitoring and review requirements as identified within Section 6 of the Main Works CEMP.

7. Conclusion

The existing management approach detailed in the Aotea Station Main Works CEMP, together with the additional measures outlined in this addendum, will appropriately manage any potential adverse effects associated with construction of the PRR works.

Appendix A: Staging Drawings

STAGE2-VICTORIASTREET

·PUBLICREALMCONSTRUCTIONALONG VICTORIAANDATTHEINTERSECTION WITHALBERTST ·COMPLETIONOFTHEPUBLICSPACE AROUNDANDTHESTATIONENTRANCE STRUCTURESONVICTORIA

DURATION:LATE2022TOLATE2023

STAGE3-ALBERTST

ALBERTSTLLA(LV)
ALBERTST(L2LS)
ALBERTSTLLA(LV)

Appendix B: Traffic Access and Parking Delivery Work PlanAddendum

Aotea Station Public Realm Reinstatement

Transport Access and Parking Delivery Work Plan Addendum

CRL-AOT-RME-LKA-RPT-800016

Revision: A01

Date: 4 October 2021

Aotea Station Public Realm Reinstatement – Transport Access and Parking Delivery Work Plan Addendum

CRL-AOT-RME-LKA-RPT-800016

Revision Status

1. Introduction

The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the North Auckland Rail Line (NAL) in the vicinity of Mt Eden Station. The CRL also involves the construction of two new underground stations at Aotea and Karangahape and the redevelopment of the station at Mt Eden (refer to Figure 1.1). The design and construction of the CRL infrastructure between the Aotea and Mt Eden Stations is being delivered by the Link Alliance.

This addendum to the Aotea Station Main Works Transport Access and Parking Delivery Work Plan (TAP DWP)1 has been prepared to address any potential effects associated with the public realm reinstatement works (PRR) phase of construction works.

This addendum should be read in conjunction with the Aotea Station Main Works TAP DWP. Where project details, proposed management and effects are already covered in the Aotea Station Main Works TAP DWP and are directly applicable to the PRR works, reference is made to the appropriate section of the Aotea Station Main Works TAP DWP

2. Project Description

This section presents a summary of the PRR works to provide context to the TAP DWP Addendum. A detailed description of the PRR works is provided in the Aotea Station PRR Construction Environmental Management Plan (CEMP) Addendum. Further detail on the PRR works is also provided in the Aotea Station and Public Realm Reinstatement Urban Design Delivery Work Plan (Urban Design DWP).

1 Aotea Station Main Works Transport Access and Parking Delivery Work Plan, Rev 001, prepared by the Link Alliance, dated 8 May 2020.

Page 4 | Aotea Station Public Realm Reinstatement

Figure 1.1 CRL Route and Location

2.1 Construction Methodology Overview

The PRR works extend along Albert Street from Wyndham Street to the southern end of the Aotea Station Designation 2500-1 located adjacent to 10 Mayoral Drive. This includes sections of intersecting roads including Victoria Street, Wellesley Street, Kingston Street, and Durham Street. The extent of the works area is shown in Figure 2.1 below.

The construction works required to reinstate the permanent aspects of the public space include paving, sealing, tie-in works, stormwater treatment, the installation of street furniture and landscaping. The works will be undertaken in a staged manner (with five main stages), commencing as the current construction works are progressively completed. Refer to the CEMP Addendum for a further detailed description of the works.

2.2 Construction Programme

The PRR works are divided into five ‘phases’ as illustrated in Table 2.1. Note that the various phases overlap for some of the works, which is reflected in the total duration of works, being approximately 18 months.

Stage 2 –

Street - Public realm works along Victoria and at the intersection with Albert Street.

- Public realm works around the station entrances on Victoria Street.

2022 Mid 2023

Late 2022 Late 2023

Figure 2.1: Extent of public realm works
Table 2 1: Overview of Construction Works and Staging
Stage 1 – Wyndham to Victoria Street - Albert Street, Durham Street and Kingston Street public realm works Mid
Victoria

Stage 3 – Albert Street

- Public realm works along Albert Street from Victoria to Wellesley Street.

- Public realm works along lower Albert Street

- Tie ins to Crowne Plaza and Sky City accesses

Stage 4 – Wellesley Street - Public realm works along Wellesley Street and at the intersection with Albert Street.

- Completion of the Aotea Station forecourt

Early 2023 Late 2023

Stage 5 – Mayoral Drive

- Public realm works along Mayoral Drive

Mid 2023 Mid 2024

Mid 2023 Mid 2024

The five stages of the PRR works are equivalent to Traffic Stages 3, 4, 5 and 6 of the Aotea Main Works TAP DWP.

3. Existing Transport Conditions

The traffic volumes of the roads nearest to where the PRR works will be undertaken are shown in Table 3.1. These volumes were obtained from the Auckland Transport (AT) online database on 15 March 2021.

Table 3 1 – Traffic volumes on main roads adjacent PRR works

The surveyed volumes are considered applicable for the 2022 and 2023 years given that the lane capacity for these roads remains the same and that the CBD area is generally operating at capacity during the peak periods

Further details of the existing transport environment are provided in Section 3 of the Aotea Main Works TAP DWP.

4. Proposed Traffic Management

The five stages of the PRR works are divided into further sub-stages for the purposes of construction and traffic management planning. These sub-stages of work are sequenced from north to south along the line of the CRL twin tunnels, starting at Wyndham Street and finishing at Mayoral Drive. The overall traffic management sequencing plan is shown in Figure 4.1

Details for each sub-stage will be included in the Traffic Management Plans (TMP) that will be submitted to AT approximately two to four weeks prior to construction works starting. Traffic Resolution documents will be prepared where changes to legal traffic and parking controls are required to support the approval and implementation of certain TMPs

The indicative traffic management layouts for each sub-stage are provided in the following report sections.

4.1 Albert Street – between Wyndham Street and Victoria Street West (Stages 1A, 1B, 1C)

PRR Stages 1A, 1B and 1C comprise of the reinstatement of the northern Albert Street section that is between Wyndham Street and Victoria Street West.

The indicative traffic management layout for Stage 1A is shown in Figure 4.2.

Figure 4 1 – Sequencing plan for the traffic management of the PRR works

The Stage 1A works are located on the western side of Albert Street. One northbound traffic lane will be provided on Albert Street while southbound traffic movements will be facilitated via the existing slip lane. Pedestrian access to properties on Albert Street and Kingston Street will be maintained at all times via either existing footpaths or protected on-road diversions around work zones.

The indicative plan for Stage 1B is shown in Figure 4.3.

Figure 4 2 – Indicative traffic management layout for Stage 1A

4 3 - Indicative traffic management layout for Stage 1B

Stage 1B comprises of works on the eastern side of Albert Street, Kingston Street and the Albert Street slip lane. Two traffic lanes, one in each direction, will be provided on Albert Street. Access to Albert Street from Durham Street West will be provided at the southern section of the Albert Street slip lane. Pedestrian access to existing properties will be maintained at all times.

The indicative Stage 1C plan is shown in Figure 4.4.

Figure

Figure 4 4 - Indicative traffic management layout for Stage 1C

Stage 1C is the same as Stage 1B for vehicular and pedestrian movements on Albert Street and Kingston Street. However, vehicle access from Durham Street West to Albert Street will be provided on the northern section of the Albert Street slip lane while works are undertaken on the southern section of the slip lane. An existing traffic signal will facilitate vehicles exiting the slip lane at the intersection of Albert Street / Wyndham Street.

4.2 Victoria Street West – between Federal Street and Elliott Street (Stage 2)

The PRR works on Victoria Street West will be undertaken during the long term closure of the Albert Street / Victoria Street West intersection and within the work zone established for the closure. The indicative traffic management layout for Stage 2 is shown in Figure 4.5.

4.5 - Indicative traffic management layout for Stage 2

Vehicle movements through the intersection will not be provided during the closure. Instead a culde-sac layout with a turning head will be provided on both Albert Street approaches to the intersection and the Victoria Street eastern approach. The Victoria Street / Federal Street intersection will operate as a T-junction during this phase.

Pedestrian and cyclist (will be required to dismount) access will be maintained through the intersection and for access to properties interfacing the closure area. During the closure of the Victoria Street West / Albert Street intersection, Wellesley Street West and its intersection with Albert Street will be fully open with two lanes provided in each direction on Wellesley Street West.

4.3 Albert Street – between Victoria Street West and Wellesley Street West (Stages 3A, 3B)

Stages 3A and 3B comprise the reinstatement of the southern Albert Street section that is between Victoria Street West and Wellesley West. This work will be undertaken during the closure of the Victoria Street West / Albert Street intersection. The indicative traffic management layout for Stage 3A is shown in Figure 4.6

Figure

Figure 4 6 - Indicative traffic management layout for Stage 3A

Two vehicle lanes, one in each direction, is provided on Albert Street between Victoria Street West and Wellesley Street West. Vehicle access to the Huawei Centre and Crowne Plaza forecourts will be maintained between the work zones.

The pedestrian footpath on the western side of Albert Street will remain open while a protected onstreet pedestrian path will be provided on the eastern side of Albert Street for pedestrian throughput and access to the Huawei Centre and Crowne Plaza buildings.

The indicative Stage 3B plan is shown in Figure 4.7.

4.7 - Indicative traffic management layout for Stage 3B

Similar to Stage 3A, two traffic lanes are provided on Albert Street, one in each direction with vehicle access to properties on the eastern side of Albert Street, restored to pre-CRL conditions. Pedestrian access to properties on the western side of Albert Street are maintained at all times between work zones.

4.4 Wellesley Street West – between Federal Street and Elliott Street (Stages 4A, 4B)

The reinstatement of Wellesley Street West will be undertaken in two general stages: Stage 4A and 4B. Two vehicle lanes, one in each direction, will be maintained on Wellesley Street West in both stages. Victoria Street West and its intersection with Albert Street will be open with the final configuration of one traffic lane in each direction on Victoria Street West, based on the Te Ha Noa –Victoria Street Linear Park project by Auckland Council

Stage 4A comprises works on the southern side of Wellesley Street West as shown in Figure 4.8.

Figure

Pedestrian access to properties adjacent the work zones will be maintained. Pedestrian through movements between Albert Street and Mayoral Drive will be maintained along the existing western side footpath, crossing Victoria Street West at the intersection traffic signals

Stage 4B comprises works on the northern side of Wellesley Street West as shown in Figure 4.9

Figure 4 8 - Indicative traffic management layout for Stage 4A

4.9 - Indicative traffic management layout for Stage 4B

Pedestrian access to properties on the northern side of Wellesley Street West will be maintained. Pedestrian through movements along Wellesley Street West will be provided on-street, protected from the live traffic by barriers. Pedestrian crossing movements between Albert Street and Mayoral Drive will be maintained at the existing signalised crosswalks.

4.5 Mayoral Drive – between Wellesley Street West and Aotea Centre (Stage 5)

The final stage of the PRR works will utilise the existing work zones on Mayoral Drive and be undertaken concurrently with the reinstatement of Wellesley Street West. The indicative traffic management layout is shown in Figure 4.10.

Figure

Figure 4 10 - Indicative traffic management layout for Stage 5

Mayoral Drive will remain a cul-de-sac road on the eastern approach. Pedestrian access will be maintained to properties on the southern side of Mayoral Drive, provided either on the existing footpath or diverted along the centre of Mayoral Drive between work zones

5. Traffic Modelling Analysis

The scope, methodology and results of the transport modelling assessment for the PRR sub-stages are covered in the Aotea Main Works TAP DWP. The relationship between the Main Works stages and PRR stages are outlined in Table 5.1

Table 5.1 – Relationship between PRR stages and Main Works stages and respective road network layouts

Proposed

Stages 1A, 1B

Traffic Stage 3

Stage 1C Traffic Stage 4

Stage 2 Traffic Stages 3 and 4

Albert St – cul-de-sac, one lane in each direction

Kingston St – closed to vehicles

Albert St / Victoria St West intersection –closed to vehicles

Albert St / Wellesley St West intersection –open to vehicles

Mayoral Drive – cul-de-sac

Same as above, but Kingston St is opened

Same as for PRR Stages 1A, 1B, 1C

Stages 3A, 3B

Traffic Stages 3, 4 and 6

Stages 4A, 4B

Traffic Stage 6

Stage 5

Traffic Stage 6

Same general layout as for previous PRR Stages but either the Albert St / Victoria St West intersection closed to vehicles while Albert St / Wellesley St West intersection is open with two lanes in each direction as per Traffic Stages 3 and 4, or with the Albert St / Victoria St West and Albert St / Wellesley St West intersections both open with one lane in each direction as per Traffic Stage 6

Albert St / Victoria St West and Albert St / Wellesley St West intersections both open with one lane in each direction.

Same as above

As a general requirement of CRL DWPs, the transport modelling of the Aotea Main Works TAP DWP will be reviewed for relevancy in March of each year and updated as necessary It is expected that any specific modelling for the PRR stages would be undertaken outside of the Main Works assessment, should material changes to the PRR traffic management methodology be identified following the submission of the annual TAP DWP update.

6. Assessment of Effects

The scope of the PRR traffic management needs to comply with the relevant CRL designation conditions. Specific conditions for Aotea Station are detailed in Conditions 27.1 and 27.2. By way of summary, the PRR stages described in Section 4 of this report have been assessed to comply with the designation conditions.

Of particular significance, is Condition 27.1(c) which requires two fully operational traffic lanes in each direction at two of the Customs Street, Victoria Street and Wellesley Street intersections with Albert during the period when the third of those intersections is otherwise fully closed.

This will be achieved by undertaking PRR works on Victoria Street West during its established closure at Albert Street from mid-2021 to mid-2023 as part of the Main Works.

The PRR works for Wellesley Street West will be undertaken from mid-2023 onwards, maintaining one lane open in each direction. During this time, the public realm works on Victoria Street West will be mostly completed, with one lane open in each direction as per its final Linear Park configuration. This concurrent arrangement of having both Wellesley Street West and Victoria Street West open with one lane in each direction satisfies Condition 27.1(c), which maintains a combined total of two lanes eastbound and two lanes westbound across the two roads at their intersections with Albert Street.

Pedestrian and cyclist access to properties will be maintained at all times as required by the general condition 25.2(b), which fulfils the specific access requirements of Conditions 27.1 and 27.2.

On-going vehicle access to private property will be maintained to the greatest extent possible as required by the general condition 25.2(c). Specific requirements of Conditions 27.1 and 27.2 will be satisfied.

The effects of the PRR stages on the road network, especially in terms of travel time impacts on inner city bus services are described in Section 5 of the Aotea Main Works TAP DWP. The acceptability of the anticipated delays will be determined by AT prior to the approval of TMPs. Should anticipated delays to any bus services be a concern, then targeted mitigation measures will be discussed and agreed with AT during the development of a specific TMP.

The effects to on-street parking and loading spaces will be as outlined in Section 6 of the Aotea Main Works TAP DWP Changes required to these parking and traffic controls for a duration longer than three weeks will typically be addressed through the Traffic Resolution approval process, which may result in changes to the extent of the parking impacts.

In general, provided that the specific TMPs for the PRR stages comply with the relevant designation conditions captured in the Aotea Main Works TAP DWP, then AT will have sole-discretion over the transport effects of the TMPs to enable its approval.

Where there is conflict between a TMP and designation conditions further discussion will be required with AT and Auckland Council to resolve the appropriate traffic management measures.

Further Transport Specialist inputs may be required occasionally, such as for assessments against relevant designation conditions for specific TMPs, preparation of traffic resolution documents and assessment of effects not covered by either this PRR TAP DWP or the Aotea Main Works TAP DWP These inputs would be made on an as-needed basis.

7. Travel Time / Congestion Monitoring

The travel time and congestion monitoring requirements for CRL are set out in designation condition 26. The processes and responsibilities in relation to monitoring for the PRR works are consistent with that for the Main Works, as detailed in Section 7 of the Aotea Main Works TAP DWP.

8. Consultation and Communication

The scope of the consultation and communication requirements for PRR works are consistent with that established for the Main Works, as detailed in Section 8 of the Aotea Main Works TAP DWP

The Link Alliance communications and engagement team will work with the construction and traffic management teams to ensure that the requirements set out in this TAP DWP are achieved.

Appendix C: Site Specific Construction Noise and Vibration Management Plan

Aotea Station Public Realm Reinstatement

Site Specific Construction Noise and Vibration Management Plan

CRL-AOT-RME-LKA-RPT-800017

Revision: A01 26 October 2021

Site Specific Construction Noise and Vibration Management Plan

CRL-AOT-RME-LKA-RPT-800017

This document is uncontrolled when printed. This document should be printed in colour

Revision Status

Approval Status

Prepared by: Kieran Hill Acoustic Engineer

Approved by: Peter Roan Planning and Approvals Manager

1. Introduction

This is a Site-Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the Aotea Station Main Works

This SSCNVMP provides a specific assessment of construction noise and vibration from the Public Realm Reinstatement (PRR) works within the project designation, that was not previously provided for as part of Aotea Station Main Works CNV DWP.

The PRR works extend along Albert Street from Wyndham Street to the southern end of the Aotea Station Designation 2500-1 located adjacent to 10 Mayoral Drive. This includes sections of intersecting roads including Victoria Street, Wellesley Street, Kingston Street, and Durham Street. PRR works includes the following:

• Paving, sealing, tie in works

• Installation of accessible ramping and stairways

• Installation of furniture

• Landscaping (including installation of tree pits and planters)

• Reinstatement of canopies removed as part of the enabling works

• Stormwater treatment

• Earthworks

The works will be undertaken in a staged manner (with five main stages), commencing as the current construction works are progressively completed (refer Table 1) A detailed description of the PRR works is provided in the Aotea Station PRR Construction Environmental Management Plan (CEMP) Addendum. This SSCNVMP should be read in conjunction with the Aotea Station Main Works Construction Noise and Vibration Delivery Work Plan (CNV DWP) to which this document forms part of Appendix F, as it contains further details of the project, noise criteria, monitoring and general mitigation measures. An overview of the works and details of the construction methodology are contained in Section 3

Stage 2 – Victoria Street

- Public realm works along Victoria and at the intersection with Albert Street.

- Public realm works around the station entrances on Victoria Street. Late 2022

2023

Stage 3 – Albert Street

- Public realm works along Albert Street from Victoria to Wellesley Street.

- Public realm works along lower Albert Street

- Tie ins to Crowne Plaza and Sky City accesses

Early 2023

2023

Table 1 Overview of Construction Works and Staging
Stage 1 – Wyndham to Victoria Street
- Albert Street, Durham Street and Kingston Street public realm works

Stage 4 – Wellesley Street

- Public realm works along Wellesley Street and at the intersection with Albert Street.

- Completion of the Aotea Station forecourt Mid 2023 Mid 2024

Stage 5 – Mayoral Drive - Public realm works along Mayoral Drive Mid 2023 Mid 2024

1.1 Objective

The objective of this SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on sensitive receivers resulting from construction noise and vibration that does not comply with the Project Standards defined in Section 3 of the Aotea Station Main Works CNV DWP.

1.2 Site Plan

The extent of the PRR construction works is shown in Figure 1.

Figure 1 Extent of PRR works

2. Receivers

Receivers where noise and/or vibration levels due to the Public Realm Reinstatement works within the project designation have the potential to exceed project noise or vibration standards, along with the relevant building uses, are listed in Table 1

Table 1 Affected receivers

*This is the Monday to Saturday 07:00 to 22:00 noise criteria. The majority of works will be carried out during this period. For residential receivers the noise limit is reduced to 65 dB LAeq & 80 dB LAFmax on Sundays and Public Holidays between 07:00 to 22:00 and to 60 dB LAeq & 75 dB LAFmax at all other times.

3. Activities

Construction activities for Public Realm Reinstatement works are shown in Table 2.

Table 2 Public Realm Reinstatement construction methodology

Stage

Pavement construction

Footpath construction

Landscaping

Utilities installation

Details of Works

• After completion of ground works - Subsoil drains are constructed along the edges of the road carriageway

• Basecourse material/layer is spread and compacted

• Testing undertaken on the subgrade and basecourse layer during construction

• Structural asphalt layers are constructed and the final 50mm layer of AC14 will be placed at the final phase of the works

• Line markings works are completed after the asphalt layer is laid

• Footpath pavements generally consist of basecourse layer, reinforced concrete layer & decorative layer

• The Basecourse layer (Cemented treated basecourse) is spread and compacted using excavators and small roller/plate compactors

• Structural concrete layer is constructed in segments to maintain pedestrian movements and concrete is delivered via trucks with concrete pumps

• Dust from placement of fill and bedding material is controlled via a watering system

• Decorative paving is constructed by cutting, placing, and mixing of stone pavers with Steintec Bedding

• To maintain pedestrian access to business and properties, night works may be required for the installation of pavers

• A mobile acoustic enclosure is used during all paver cutting

• Duct from extraction and cutting operations is controlled via a watering system

• Landscaping works are completed from the adjacent traffic lane and are one of the final activities completed

• Trees are delivered by truck and planted by hand or using a Hiab Crane

• After the planting of trees, surface tree grilles or permeable coverings will be installed

• To service the urban realm installations& divert main utilities a network is required

• Duct installations are completed using a combination of excavators, trucks (for concrete, and for spoil disposal and importing backfill materials), hand tools, trench shields and compaction equipment

• The installation of street lighting and other above ground traffic service installation is linked to the utility duct and cable work.

Equipment utilised

• Excavators

• Graters

• Plate/Roller compactors

• Asphalt paving plant

• Concrete breaker

• Concrete saw

• Excavators(5-10T)

• Small roller/plate compactors

• Concrete pumps (Line or boom)

• Watering System

• Bedding material

• Stone pavers

• Steintec bedding material

• Mobile acoustic enclosure

• Concrete breaker

• Concrete saw

• Hiab Crane

• 5-14t excavators

• Trucks

• Plate compactors and/or small rollers

• Trench Shields

• Hand Tools

Reinstatement of canopies

Installation of furniture

Details of Works

• Previously removed canopies to be reinstated

• Electrical services, painting and buildings works for the reinstatement of canopies on 44 Wellesley St; 37 Albert St; 98-102 Albert St.

• Road Furniture will be one of the final activities undertaken at each site

• Furniture will be delivered onto site and immediately installed

• Road furniture includes street lighting and signage, seating, rubbish bins, bicycle racks and drinking fountains

• Installation of street lighting signage and traffic signal will be carried out by specialist electricians

Equipment utilised

• Hand tools

• Hiab crane

Construction of new stormwater infrastructure

Construction of tree pits

• Within the road carriageway and connecting into the existing stormwater network is the new infrastructure

• The construction of the main drainage lines, manholes and connections will be completed first

• Works begin from the downstream connection points and laid ‘uphill’ to the head of the new drainage line

• Aco drains, catchpits and leads are constructed after the main drainage lines are completed

• For tree pits that are near services, 25 mm steel plates are to be installed to provide additional barrier between pit and service trenches

• Hydro excavation and pothole techniques will be used to expose tree pits when utilities are approached

• Excavations will be around 1.0-2.0 m

• Temporary supports will be installed around the utilities

• Excavators(5T-20T)

• Trucks (for concrete, spoil disposal and importing backfill materials)

• Plate compactors and/or small rollers

• Trench Shields

• Hand tools

• Excavators(5T-20T)

• Excavators(10T-20T)

• Trucks (for concrete, spoil disposal and importing backfill materials)

• Plate compactors and/or small rollers

• Trench Shields

• Hand tools

Details of the construction equipment that is likely to be used in the above activities and the associated noise levels can be found in Section 4.1 of the CNV DWP. Details of the equipment that is expected to generate high levels of vibration can be found in Section 4.2 of the CNV DWP. The equipment levels detailed are placeholders. All equipment will be measured operating independently and then actual equipment noise/vibration levels and model numbers will be recorded and updated within the table1 .

Construction hours will be as per those outlined in Section 2.5 of the Main Works CEMP. Works will generally be undertaken Monday to Saturday, 0700 – 1900 hrs. However, certain activities may need to be undertaken outside these hours to minimise traffic impacts or minimise disruption to businesses or residents, such as network utility works where the Network Utility Operator (NUO) requires works to be undertaken at night, or the delivery of large plant.

1 The table will be updated as part of the CNV DWP annual review process.

To maintain pedestrian access to business and properties, night works may be required for the installation of pavers. Night works shall be limited to the placing of pre-cut pavers and asphalt paving. Cutting of pavers shall be undertaken during daytime construction hours.

4. Façade performance and internal noise levels

4.1 Noise

The Public Realm Reinstatement works are located close to a number of receivers that internal noise levels will inevitably be high during some activities.

With the mitigation and management measures implemented and barriers installed, the noise levels at the most exposed façade of a number of properties will still exceed the noise criteria by more than 5dB during some construction activities. These properties are detailed in Table 3 along with an estimate of the current façade performance and the worst-case internal noise levels during Public Realm Reinstatement works, e.g. during use of the concrete saw and concrete breaker Noise levels will reduce from those presented in Table 3 during other construction activities.

Predicted noise levels for night works have been included in Table 3 where the building has a residential use or a commercial use that is operational during the night time period.

87-89 Albert Street Ground floor: Vacant (formerly Da Vinci Restaurant)

First floor and above: Offices with multiple tenancies <85 dB

The façade is approximately 90% laminated glazing and the restaurant is mechanically ventilated. The estimated façade performance with the door closed is 30 dB Rw.

<55 dB with the door closed

First floor and above: <75 dB

The façade is approximately 90% single glazing throughout. The windows are openable but wellsealed. The building is mechanically ventilated throughout. The estimated façade performance with the door closed is 30 dB Rw.

Bedrooms are located on Level 1 and above.

Windows are single glazed with trickle vents. Hotel bedrooms have sliding doors opening onto balconies and windows are single glazed laminate. The current façade performance with doors closed is estimated to be 25 dB Rw.

<55 dB with windows closed

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building.

<60 dB with windows/doors closed.

Annoying and disturbing staff or guests. Sleep disruption if undertaken outside the building during night-time/early morning hours.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Notice of noisy works is to be provided at least 24 hours in advance and scheduled outside of sleeping hours where practicable.

The concrete truck and pump to be placed a minimum of 30 meters from the building when concrete pours occur during night-time hours. Alternatively, the most affected rooms

2 This column identifies specific mitigation measures to be applied where practicable. Should it be found that any of the mitigation in this column is not practicable or the requirements of a particular receiver change, alternative mitigation will be provided that results in similar or reduced noise effects. If it is not possible to provide alternative mitigation that results in similar or reduced noise effects, the process detailed in Section 9 of the CNV DWP will be followed.

98-102 Albert Street First floor and above: Surf n Snow <85 dB

Ground floor: Formerly occupied by Rio, currently rented by Stockman’s

<85

/

Shop front is comprised of single glazed bi-folding doors which are usually left completely open. The estimated façade performance with the door closed is 25 dB Rw.

<60 dB when doors are closed.

Annoyance to staff and customers.

Specific Mitigation Measures2

could be booked by the Project when night works occur adjacent to this receiver.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Bi-folding doors on shop front to remain closed during noisy works.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building. Ground floor: 98

The façade is assumed to be 90% single glazing with two doors. The estimated façade performance with the door closed is 20 dB Rw

<65 dB

Annoyance to staff and customers.

Ground Floor: Auckland Print Shop

The façade is masonry with a single glazed door from the street into the store with no mechanical ventilation. The estimated façade performance with the door closed is 25 dB Rw.

<65 dB (with door closed)

Annoyance to staff and customers

Further consultation to take place prior to start of works. Date TBC at time of writing.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building.

(formerly

The façade appears to be masonry and single glazed door from street into store. The entrance to shop is appears to be open during operating hours. The estimated façade performance with the door closed is 20 dB Rw.

Annoyance to staff and customers

Further consultation to take place prior to start of works if occupied. Date TBC at time of writing.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in

the building. Ground Floor: Vacant (formerly Nourish Life)4

The façade is predominantly single glazing. The entrance to shop is appears to be open during operating hours. The estimated façade performance with the door closed is 25 dB Rw.

Annoyance to staff and customers

The façade is masonry with a single glazed door from the street into the store The estimated façade performance with the door closed is 20 dB Rw.

Annoyance to staff and customers.

Further consultation to take place prior to start of works if occupied. Date TBC at time of writing.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building.

Further consultation to take place prior to start of works. Date TBC at time of writing.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building.

3 Business is closed at time of writing

4 Business is closed at time of writing

The façade to Victoria Street west has been assumed to be a rollershutter door that is completely open when the store is open. When works do not directly face towards the entrance, the estimated façade performance with the roller door open is 15 dB Rw. No reduction in noise levels is expected if the works face directly towards the entrance.

The façade is 90% single glazing throughout with a single glazed door. The building has mechanical ventilation but usually the door is kept open. The estimated façade performance with the door closed is 30 dB Rw.

The façade is 90% single glazing throughout openable windows.

The building does not have mechanical ventilation and tenants rely on natural ventilation through windows. Trickle vents are present in certain areas.

Annoyance to staff and customers.

Annoying and disturbing to residents. Sleep disruption if undertaken outside the building during night-time/early morning hours.

Further consultation to take place prior to start of works. Date TBC at time of writing.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building.

Noisy activities must be scheduled for a time outside sleeping hours, with notice given 24 hours in advance.

Manage unnecessary impact sounds. Consultations have identified shift workers who sleep during the daytime within this building.

Mechanical ventilation is required in bedrooms that are located along the facade overlooking the work site if the resident is a

37 Wellesley Street

Ground floor: Reception5 First floor and above: Econolodge Hotel

<90 dB

The estimated façade performance with the windows closed is 25 dB Rw.

5 Business in hibernation at time of writing

The façade on the first floor consists of approximately 90% single glazing with doors onto a balcony space. The estimated façade performance with windows closed is 30 dB Rw

The façade above second floor level is approximately 40% single glazed with openable windows. The façade performance with windows closed is estimated to be 35 dB Rw.

< 60 dB when windows are closed.

Above First Floor: Internal noise level of <55 dB when windows are closed. Potential for NZS 2107 internal noise level criteria (35-40 dB LAeq) for bedrooms to be exceeded during worstcase activities.

Specific Mitigation Measures2

shift worker and needs to sleep during the day.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building.

Notice of noisy works is to be provided at least 24 hours in advance and scheduled outside of sleeping hours.

Further consultation will be required before the commencement of night works to determine if the apartments have bedrooms overlooking the site on Albert Street. If they do it will be necessary to locate the concrete truck and pump a minimum of 30 meters from the building when concrete pours occur during night-time hours.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Notice of noisy works is to be provided at least 24 hours in advance and scheduled outside of sleeping hours where practicable.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used near the building.

The concrete truck and pump will be placed a minimum of 30 meters from the Econolodge

44 - 52 Wellesley Street West

Ground Floor (Mayoral Drive façade): Vacant (formerly Christian Reading Centre)

Ground Floor (Mayoral Drive façade): Crayon Nail & Beauty

<85 dB

Ground Floor (Mayoral Drive façade): NZ Post / Western Union

<85 dB

The façade consists of approximately 95% single glazing. The building is mechanically ventilated with automatic doors onto Mayoral Drive. The estimated façade performance with the door closed is 25 dB Rw.

The façade consists of approximately 80% single glazing with double doors opening onto Albert Street. The building has no mechanical ventilation. The estimated façade performance with the door closed is 25 dB Rw.

<85 dB The façade consists of approximately 90% single glazing. The building is mechanically ventilated with automatic doors onto Mayoral Drive. The estimated façade performance with the door closed is 25 dB Rw.

Ground Floor: Currently vacant (formerly Greedy Guts Café)

<85 dB The façade consists of bifolding doors and is completely open at times when the café is open. The estimated façade reduction is 10 dB.

< 60 dB when doors are closed.

< 60 dB when doors are closed.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used near the building.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used near the building.

< 60 dB when doors are closed.

< 75 dB when doors are open, <60 dB when doors are closed.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used near the building.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when concrete

during

Internal noise level of <40 dB when windows are closed. Unlikely that NZS 2107 internal noise level criteria (35-40 dB LAeq) for bedrooms to be exceeded.

Further consultation to take place prior to start of works. Date TBC at time of writing.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the

Ground floor: Lobby and East Day Spa

Ground Floor: <80

Floor and

<75

Mitigation Measures2

Bedrooms are from approximately 10th floor and upwards, below lobby and bedroom are assumed to be car parking spaces. and concrete trucks are used immediately outside the building.

Notice of noisy works is to be provided at least 24 hours in advance and scheduled outside of sleeping hours.

The concrete truck and pump to be placed a minimum of 30 meters from the building when concrete pours occur during night-time hours.

The façade is predominantly sealed 12.38mm thick laminated glazing. The estimated sound level difference across the façade is 35 dB.

Internal noise level of <45 dB when windows are closed.

Possible that NZS 2107 internal noise level criteria (35-40 dB LAeq) for bedrooms may be exceeded for short periods.

Further consultation to take place prior to start of works. Date TBC at time of writing.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately near the building.

Notice of noisy works is to be provided at least 24 hours in advance and scheduled outside of sleeping hours.

The concrete truck and pump to be placed a minimum of 30 meters from the building when concrete pours occur during night-time hours.

The building façade is 85% glazing with doors opening to the lobby within the Sky City building. The estimated façade performance is 35 dB with windows closed.

Further consultation to take place prior to and during the works.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

83 Albert Street Ground Floor: Little Albert Coffee

First floor and above: Offices <80

The façade is approximately 75% single glazed, 25% masonry wall. The estimated façade performance is 30 dB Rw.

Worst-case noise levels will be intermittent in nature and will occur when concrete breakers are used immediately outside the building.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when the concrete saw is used immediately outside the building. 99 Albert Street (AA Building) Ground floor: Entrance to office building.

<90 dB The façade to the AA store is 90% laminated glazing. The store has two doorways on to Albert Street, opening frequently. The store keeps the doors closed when customers are not entering/departing the store. The store has mechanical ventilation, with an estimated façade performance of 25 dB Rw.

<65 dB with the door closed.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when concrete saw is operating near the building. Levels 1-3:

Levels 4 – 17: Offices

All rooms are mechanically ventilated with single glazed windows. The estimated façade performance is 30 dB Rw.

noise levels will be intermittent in nature and will occur when concrete saw is operating near the building.

Media School – Tower at 92 Albert Street

Ground floor: Building entrance lobby, café area

Ground Floor: <85 dB

Ground floor is the building lift lobby and a small café/coffee shop area. The building is accessed via sliding doors to Albert Street. The estimated façade performance on the ground floor is 25 dB Rw.

< 60 dB when doors are closed.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when concrete saw is operating near the building.

Level 1-4: Vacant

Lollipops Early Childhood Cent (NB: not directly adjacent to site but does have outdoor play area)

Level 5: Design School Lecture Theatre

Lecture theatre façade is 100% glazed. The room is mechanically ventilated. The estimated façade performance is 30 dB Rw. < 35 dB Worst-case noise levels will be intermittent in nature and will occur when concrete saw is used near the building.

Level 6-11: Vacant: N/A N/A N/A

Level 12: Offices

Level 14-20: Media Design School

Office façade is 90% single glazing. Offices are mechanically ventilated. Background noise in the offices is estimated to be 50 - 60 dBA. The estimated façade performance is 30 dB Rw.

The classrooms and learning areas on the Albert Street façade are approximately 90-100% glazed. The rooms are mechanically ventilated. The estimated façade performance is 30 dB Rw. < 35 dB

Worst-case noise levels will be intermittent in nature and will occur when concrete saw is used immediately outside the building.

Worst-case noise levels will be intermittent in nature and will occur when concrete saw is used immediately outside the building.

65 Albert Street (District Court) Ground floor and above: Auckland District Court

Ground: <80 dB

First Floor and above: <90 dB

74 Albert Street Ground floor: Bespoke Café and Printfly Copy Shop

Courtrooms on floors 2 and 3 have facades facing Kingston Street and are approximately 30% single glazing with an estimated façade performance of 35 dB Rw. The courtrooms are mechanically ventilated throughout.

Jury rooms and judicial offices on floors 1, 4 and 1012 on both Albert Street and Kingston Street facades are up to 90% glazing with an estimated façade performance of 35 dB Rw.

Secondary glazing was installed in some of the courtrooms overlooking Albert Street as part of the C2 works.

An internal construction noise limit of 40 dB LAeq is recommended for the court rooms on the Albert Street façade.

Info below taken from C2 consultation:

This building is a hotel and is mechanically ventilated.

< 40 dB in courtrooms without secondary glazing installed. This may result in interference with digital audio recording equipment and court proceedings.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Secondary glazing to be installed in remaining court rooms overlooking Kingston and Albert Street.

Long term noise monitoring to be set up in this building.

<50 dB at ground floor, <45 dB in bedrooms.

Potential for NZS 2107 internal noise level criteria (35-40 dB LAeq) for bedrooms to be

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when concrete

Hotel bedrooms have sliding doors opening onto balconies and windows are single glazed laminate. The estimated façade performance with the door closed is 35 dB Rw.

exceeded during noisy activities.

The façade is a combination of masonry and glass to ancillary rooms. The façade performance is estimated to be at least 45 dB Rw to internal spaces within the Aotea Centre. Performance spaces are located within the building away from external facades facing the works.

Noise from these works is not expected to be audible in Aotea Centre performance spaces.

Specific Mitigation Measures2

sawing takes place immediately outside the building.

Notice of noisy works is to be provided at least 24 hours in advance and scheduled outside of sleeping hours.

The use of noisy equipment outside the property will be kept to a minimum during night-time hours to reduce unnecessary high LMax noise events caused by impact from equipment being dropped, starting up or being moved etc.

The concrete truck and pump to be placed a minimum of 30 meters from the building when concrete pours occur during night-time hours. Additional temporary 1.8m high screening to be provided around pump if closer than 30m.

Alternatively, the most affected rooms could be booked by the Project when night works occur adjacent to this receiver.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

50 Mayoral Drive (Aotea Centre)

All hotel rooms are mechanically ventilated with one openable window. The estimated façade performance is 35 dB R

with windows closed.

< 50 dB in bedrooms with windows closed.

Possible sleep disturbance to guests in bedrooms facing Victoria Street.

Potential for NZS 2107 internal noise level criteria (35-40 dB LAeq) for bedrooms to be exceeded during noisy activities.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when concrete sawing take place immediately outside the building.

The use of noisy equipment outside the property will be kept to a minimum during night-time hours to reduce unnecessary high LMax noise events caused by impact from equipment being dropped, starting up or being moved etc.

Notice of noisy works is to be provided at least 24 hours in advance and scheduled outside of sleeping hours.

The concrete truck and pump to be placed a minimum of 30 meters from the building when concrete pours occur during night-time hours. Alternatively, the most affected rooms could be booked by the Project when night works occur adjacent to this receiver.

Worst-case noise levels will be intermittent in nature and will occur when concrete saw is used immediately outside the

Ground Floor: Fuga Japanese Restaurant

The façade is 80% single glazing with glazed doors.

The estimated façade performance is 25 dB Rw with doors closed.

Worst-case noise levels will be intermittent in nature and will occur when concrete saw is used immediately outside the building.

Ground Floor (Shop 3): Accord Barber

The façade is 80% single glazing with glazed doors.

The estimated façade performance is 25 dB Rw with doors closed.

Worst-case

Ground Floor: EZ Cash

The façade is 80% single glazing with glazed doors.

The estimated façade performance is 25 dB Rw with doors closed.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will occur when concrete breakers are used immediately outside the building.

Ground Floor: Coffee Club

The estimated façade performance is 25 dB Rw with doors closed.

Worst-case noise levels will be intermittent in nature and will occur when concrete breakers are used immediately outside the building.

First floor and

The building is a total of 24 floors, all of which are apartments with openable windows/doors to all four facades of the building. The building is mechanically ventilated throughout. The estimated façade performance is 35 dB RW with windows closed.

Potential for NZS 2107 internal noise level criteria (35-40 dB LAeq) for bedrooms to be exceeded during noisy activities.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Worst-case noise levels will be intermittent in nature and will not take place immediately outside the building.

The concrete truck and pump to be placed a minimum of 30 meters from the building when concrete pours occur during night-time hours. Alternatively, the most affected rooms could be booked by the Project when night works occur adjacent to this receiver.

Notice of noisy works is to be provided at least 24 hours in advance and scheduled outside of sleeping hours.

The façade is 90% glazed with

The estimated façade performance with

Annoyance to staff and customers. Difficulty communicating.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Ground floor: Kebab Time Ground Floor: <90

This building does not have a façade and only has a roller door which is kept open.

Estimated façade performance is 0 dB Rw.

< 90 dB

Annoyance to staff and customers. Difficulty communicating.

Ground floor: Café Midnight Express Ground Floor: <90

Ground floor: Vacant (formerly Taj Mahal) Ground Floor: <90

The Façade is approximately 75% single glazing with a glazed door access. The building has no mechanical ventilation.

Estimated façade performance is 30 dB Rw. < 60 dB

Annoyance to staff and customers. Difficulty communicating.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities

will provide some mitigation but high noise levels will be experienced within the building during some activities due to lack of façade.

Noise monitoring will be conducted at this property when works first commence to check that the barrier is performing as expected and noise levels are as predicted.

Additional screening close to the open area of the façade is required but may not be possible to install without impacting access to the shop or footpath outside. This option will be investigated further.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Ground floor: City Dollar Dealers (Pawn Shop) Ground Floor: <90

The façade is approximately 75% single glazed with no mechanical ventilation. The estimated façade performance is 25 dB R

Annoyance to staff and customers. Difficulty communicating.

Annoyance to staff and customers. Difficulty communicating.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

Screening provided by 1.8m high temporary mobile noise barrier during high noise generating activities.

38 Wyndham Street Ground floor: Hollywood Bakery

Floor:

Mechanical ventilation is available but automatic glazed doors let noise in. The façade at this property is 100% single glazed with an estimated façade performance of 30 dB Rw where there is no door.

The building is mechanically ventilated, and the façade is 100% single glazing on both Albert Street and Wyndham Street frontage. The attenuation provided by the façade is predicted to be 35 dB Rw.

The bakery façade is comprised of 75% laminated single glazing and 25% masonry wall. The Hollywood Bakery plays background music at a low volume. The front doors are open onto Wyndham Street the majority of the time, meaning internal noise levels are elevated due high levels to external noise. The estimated façade performance with the door closed is 30 dB Rw.

with

Notes:

1. Not consulted as CRLL manage this relationship and will be arranging a time for consultation.

2. Not consulted as owner/manager was unavailable.

4.2 Vibration

In addition to the general noise and vibration control measures outlined in Section 5 of the CNV DWP, the specific vibration mitigation measures outlined in Table 4 should be implemented if the initial on-site vibration monitoring demonstrates that the building damage vibration limits will be exceeded.

Table 4 Vibration mitigation measures

Equipment/process

Excavators, bobcats, loaders, roller compactors

Vibration

Grease tracks regularly

Avoid unnecessary revving of engines and banging of buckets on the ground.

Use smaller equipment where possible.

Site-specific vibration mitigation measures are included in Table 5

Table 5 Site-specific mitigation measures

37 Wellesley Street W Mixed Use

83 Albert Street Historic/ Vibration Sensitive

65 Albert Street Historic/ Vibration Sensitive

98-102 Albert Street Historic/ Vibration Sensitive

109-125 Albert Street Mixed Use

128 Albert Street Mixed Use

11 Mayoral Drive

68 Victoria Street W

Historic/ Vibration Sensitive

Vibration may be felt within 37 Wellesley Street W.

Monitoring will be carried out once use of the roller begins within 5 m of the building, to determine the actual levels of vibration from the equipment used.

Vibration may be felt within 83 Albert Street.

Monitoring will be carried out once use of the roller begins within 10 metres of the building, to determine the actual levels of vibration from the equipment used.

Vibration may be felt within 65 Albert Street.

Monitoring will be carried out once use of the roller begins within 10 metres of the building, to determine the actual levels of vibration from the equipment used. Ground-borne noise will also be checked in the court rooms

Long term vibration monitoring to be set up in this building.

Vibration may be felt within 98-102 Albert Street.

Monitoring will be carried out once use of the roller begins within 10 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

Vibration may be felt within 109-125 Albert Street.

Monitoring will be carried out once use of the roller begins within 5 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

Long term vibration monitoring is being conducted in this building.

Vibration may be felt within 128 Albert Street.

Monitoring will be carried out once use of the roller begins within 5 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

Vibration may be felt within 11 Mayoral Drive.

Monitoring will be carried out once use of the roller begins within 10 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

Historic/ Vibration Sensitive Vibration may be felt within 68 Victoria Street W.

Monitoring will be carried out once use of the roller begins within 10 metres of the building to determine the actual levels of vibration from the equipment used.

27-35 Victoria Street W Mixed Use

Specific Mitigation Measures

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

Vibration may be felt within 27-35 Victoria Street W.

Monitoring will be carried out once use of the roller begins within 5 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

54-56 Wellesley Street W Historic/ Vibration Sensitive

182 Federal Street Mixed Use

15-31 Wellesley Street W Mixed Use

75 Victoria Street W Mixed Use

50 Mayoral Drive Historic/ Vibration Sensitive

38 Wyndham Street Mixed Use

103-107 Albert Street Mixed Use

74 Albert Street Mixed Use

291-297 Queen Street Historic/ Vibration Sensitive

Vibration may be felt within 54-56 Wellesley Street W.

Monitoring will be carried out once use of the roller begins within 10 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

Vibration may be felt within 182 Federal Street

Monitoring will be carried out once use of the roller begins within 5 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

Vibration may be felt within 15-31 Wellesley Street W.

Monitoring will be carried out once use of the roller begins within 5 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

Vibration may be felt within 75 Victoria Street W.

Monitoring will be carried out once use of the roller begins within 5 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

Vibration may be felt within 50 Mayoral Drive.

Monitoring will be carried out once use of the roller begins within 10 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

Vibration may be felt within 38 Wyndham Street.

Monitoring will be carried out once rolling begins within 5 metres of the building to determine the actual levels of vibration from the equipment used.

Alternative compaction methodology will be utilised if necessary, to meet the building damage criterion.

Vibration may be felt within 103-107 Albert Street.

Monitoring will be carried out once rolling begins within 5 metres of the building to determine the actual levels of vibration from the equipment used.

Alternative compaction methodology will be utilised if necessary, to meet the building damage criterion.

Alternative piling methodology will be utilised if necessary, to meet the building damage criterion.

Vibration may be felt within 74 Albert Street.

Monitoring will be carried out once rolling begins within 5 metres of the building to determine the actual levels of vibration from the equipment used.

Alternative compaction methodology will be utilised if necessary, to meet the building damage criterion.

Vibration may be felt within 291-297 Queen Street.

Monitoring will be carried out once use of the roller begins within 10 metres of the building to determine the actual levels of vibration from the equipment used.

The Project team will review the construction methodology and select low vibration-emitting equipment where practicable.

5. Communication and Consultation

Section 7 of the CNV DWP details the communication procedures in relation to construction noise and vibration effects. The complaints process is detailed in Section 7.2 of the CNV DWP.

Consultation between the Link Alliance and the stakeholders identified in this SSCNVMP took place from early September 2019 regarding the Main Works phase. Topics that were covered included:

• Sequencing of construction activities

• Likely equipment and associated noise and vibration levels

• Proposed mitigation and management measures

• Construction of their buildings

• Operational hours of their businesses

• Operating environment that is required by the businesses

Further details of the meetings and comments made by the stakeholders are provided in Appendix C of the CNV DWP.

Table 3 has identified where further consultation is required prior to works commencing.

6. Monitoring

Section 8 of the CNV DWP provides details of the methodology for noise and vibration monitoring.

6.1 Noise Monitoring

Noise monitoring will be carried out when excavation begins within 20 metres of the buildings detailed in Table 6. The monitoring will be carried out at first floor level unless access is unable to be arranged.

Table 6 Noise monitoring locations

6.2 Vibration Monitoring

Vibration monitoring will be carried out when works begin on site to determine actual equipment vibration levels and the attenuation provided by local ground conditions. If the initial vibration monitoring demonstrates that the emission radius for the plant is similar to that identified in the CNV DWP addendum, then the monitoring as detailed below will be carried out. If the initial monitoring demonstrates that vibration levels are lower than predicted fewer properties may require monitoring.

Vibration monitoring will be carried out at the following receivers when the roller compactor is operating within 10 metres of the following buildings:

• 291-297 Queen Street

Albert Street

Albert Street

• 98-102 Albert Street

• 50 Mayoral Drive

• 11 Mayoral Drive

• 68 Victoria Street W

• 54-56 Wellesley Street W

Vibration monitoring will be carried out at the following receivers when the roller is operating within 5 metres of the following buildings:

• 182 Federal Street

• 15-31 Wellesley Street W

• 75 Victoria Street W

• 27-35 Victoria Street W

• 109-125 Albert Street

• 128 Albert Street

• 37 Wellesley Street W

• 38 Wyndham Street

• 103-107 Albert Street

• 74 Albert Street

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.