Construction Noise and Vibration Management Plan Addendum

Page 1


Mt Eden Station and Public Realm Reinstatement

Construction Noise and Vibration Management Plan Addendum

CRL-MTE-RME-LKA-RPT-800010

Revision: A02

Date: 08/02/22

Mt Eden Station and Public Realm Reinstatement – Construction Noise and Vibration Management Plan Addendum

CRL-MTE-RME-LKA-RPT-800010

This document is uncontrolled when printed. This document should be printed in colour

Revision Status

Revision

A01 16/11/2021 Final for Council lodgement Micky Yang Craig Fitzgerald

A02 08/02/2022 Updated following Councils review Micky Yang Craig Fitzgerald

Approval Status

Prepared by: Micky Yang Acoustic Consultant 08/02/2022

Reviewed by: Alexandra Scouller Link Alliance - Planner 08/02/2022

Approved by: Peter Roan Link Alliance – Consents Manager 08/02/2022

1. Introduction

The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the North Auckland Rail Line (NAL) in the vicinity of Mt Eden Station. The CRL also involves the construction of two new underground stations at Aotea and Karangahape and the redevelopment of the station at Mt Eden (refer to Figure 1.1). The design and construction of the CRL infrastructure between the Aotea and Mt Eden Stations is being delivered by the Link Alliance.

1.1 CRL Route and Location

This addendum to the Mt Eden Main Works Construction Noise and Vibration Delivery Work Plan (CNV DWP)1 has been prepared to address any potential effects associated with the public realm reinstatement works (PRR) phase of construction works that were not covered in the original Mt Eden CNV DWP.

This addendum should be read in conjunction with the Mt Eden Main Works CNV DWP. Where project details, proposed management and effects are already covered in the Mt Eden Main Works CNV DWP and are directly applicable to the PRR works, reference is made to the appropriate section of the Mt Eden Station Main Works CNV DWP.

2. Project Description

This section presents a summary of the PRR works to provide context to the CNV DWP Addendum. A detailed description of the PRR works is provided in the Mt Eden Station PRR Construction Environmental Management Plan (CEMP) Addendum. Further detail on the PRR works is also provided in the Mt Eden Station Urban Design Delivery Work Plan (Urban Design DWP).

1 Mt Eden Main Works Construction Noise and Vibration Delivery Work Plan, Rev 001C, prepared by the Link Alliance, dated 8 December 2020.

Page 4 | Mt Eden Station and Public Realm Reinstatement

Figure

2.1 Construction Methodology Overview

The extent of the PRR works is shown in Figure 2.1 and includes the Mt Eden Precinct and eastern and western facing connections. An oversite development (OSD) masterplan has been developed for the CRL construction site at Mt Eden which is expected to be delivered by Eke Panuku after the works being undertaken by Link Alliance have been completed. The scope of the works being delivered by the Link Alliance, excludes the OSD area (shaded white in Figure 2.1).

The construction works required to reinstate the permanent aspects of the public space include paving, sealing, tie-in works, stormwater treatment, the installation of street furniture and landscaping. The works will be undertaken in a staged manner as the current construction works are progressively completed. Refer to the CEMP Addendum for a further detailed description of the works.

The PRR works are divided into ‘stages’ (based on activity for the Mt Eden Precinct, and locations for the NAL area) as illustrated in Table 2.1.

Table 2.1. Overview of Construction Works and Staging

Stage/Location

North Auckland Line

Stage 1

Boston Road/Nugent Street/Normanby Road

(East facing connection)

Services installation, road reinstatement and landscaping Jan 2022 120 days

Figure 2 1: Extent of the public realm works

Stage/Location

Stage 2

Fenton Street/Wynyard Street (West facing connection)

Mt Eden Precinct

Stage 3A

Drainage

Stage 3B and 3E

Roading works

Stage 3C Utility works

Footpath/road reinstatement and landscaping

Drainage works along the roads connecting to existing stormwater network

Road pavement, footpath, road furniture and road signals

like LV line for lighting and fiber

Stage 3D Streetscape Landscaping, paving and way finding installation

2.1 Hours of Work

Construction hours will be as per those outlined in Section 2.5 of the Main Works CEMP. Works will generally be undertaken Monday to Saturday, 0700 – 1900 hrs. However, certain activities may need to be undertaken outside these hours to minimise traffic impacts or minimise disruption to businesses or residents, such as network utility works where the Network Utility Operator (NUO) requires works to be undertaken at night, or the delivery of large plant.

To maintain pedestrian access to business and properties, night works may be required for the installation of pavers. Night works shall be limited to the placing of pre-cut pavers. Cutting of pavers shall be undertaken during daytime construction hours.

3. Key Personal

The key personal for the PRR works remain unchanged as the main works. Refer Section 3 of the CNV DWP.

4. Performance Standards

Section 4 of the CNV DWP provides the performance standards.

5. Receivers and Building Types

Section 5 of the CNV DWP provides the key receivers and their associated building types.

6. Risk Assessment – Noise

Section 6.1 of the CNV DWP includes the representative construction plant proposed for the PRR works. However, there are two plants that are not listed in Table 6-1 of the CNV DWP. A grader and asphalt paver has been identified as a potential equipment which is not captured in the CNV DWP These sources have a similar sound power level and noise character to a static/vibratory roller. Both a grader and paver will be used for road forming in the same locations as a drum roller. Therefore, the envelope of effects is unchanged and there is no substantive change required to the CNV DWP. As such, Table 6-1 can be used to predict activity noise levels. Potential noise effects from works are summarised in Section 12.1.

7. Risk Assessment – Vibration

Section 7.1 of the CNV DWP includes the representative vibration sources. There are no new or additional sources. Therefore, Table 7-1 can be used to predict vibration levels. Potential vibration effects from works are summarised in Section 12.2.

8. Blasting

Section 8 of the CNV DWP is not applicable to the PRR works.

9. Mitigation and Management

The mitigation and management measures outlined in Section 9 of the CNV DWP as well as the SSCNVMPs in Appendix C are appropriate and sufficient for the PRR works. No new mitigation or management measures are required at this stage unless the effects, design or construction methodology changes.

However, one new SSCNMP may be required, in accordance with condition 37.2, for:

• 27 Boston Road – Pavement re-instatement works could be up to 75 - 80 dB LAeq for brief times. Therefore, if works are greater than two weeks than an SSCNMP may be required. This has been prepared (reference C85) and is attached in Appendix A.

10. Communication

The same communication procedures as Section 10 of the CNV DWP will be carried out.

11. Monitoring

The same monitoring procedures as Section 11 of the CNV DWP will be carried out.

Appendix A: Site Specific Construction Noise Management Plan

C85 27 Boston Road (BRODIE European) SSCNMP

C85.1 Introduction

This Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) is for 27 Boston Road (BRODIE European). A SSCNMP is required because construction is predicted to exceed the standards in CRL designation conditions 31.

This SSCNVMP has been prepared in accordance with CRL designation condition 37 and is Appendix C85 of the Mt Eden Main Works Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the CNV DWP, and therefore directly references relevant sections of the CNV DWP to avoid repetition. The objective of this SSCNVMP is to detail the best practicable option(s) (BPO) to avoid, remedy or mitigate the identified adverse effects from noise and vibration exceedances at 27 Boston Road.

This SSCNMP has been prepared for the Link Alliance and forms part of the Main Works Construction Environmental Management Plan (CEMP). This SSCNMP is triggered by the Mt Eden public realm reinstatement (PRR) works which are described in the Mt Eden Public Realm Reinstatement CEMP (the CEMP – PRR addendum). The CEMP – PRR addendum is appended to the Main Works CEMP.

C85.2 Engagement

Mt Eden Public Realm Reinstatement Works

Link Alliance representatives Lucy Waite and Micky Yang met with building representative Cameron Brodie on 10 November 2021. The matters discussed included:

• An overview of the project

• General programme, utilities relocation, tree pit excavation, and pavement reinstatement activities

• Overview of the CNV DWP and this SSCNMP, communications triggers, and monitoring

The single level industrial building is used as an automotive repairs workshop. It is not noise sensitive.

The relevant activities which are predicted to exceed the project standards are summarised below and will commence in early 2022. The CNV DWP sets out the BPO measures. Mitigation and management measures are included in Section 9 of the CNV DWP, and referenced in brackets, rather than repeated

• Pavement reinstatement – loudest being plate compactor, up to 75 – 80 dB LAeq for brief periods (noise barriers will be used – refer Section 9.5)

The estimated sound level difference across the façade with the windows and doors closed is 25 decibels. The predicted construction noise effects from Table 12.1 in Section 12.1 are predicted to result in reasonable noise effects Physical receiver mitigation, such as temporary relocation of affected receivers, alternative ventilation and façade sound insulation improvements, have been considered, but are not required as part of the BPO for the Mt Eden Station PRR Works.

Cameron Brodie agreed that prior communication of timeframes for works with the potential to exceed the relevant noise limits was an acceptable means of managing effects. No further activity specific consultation is necessary over and above regular communication (Section 10).

C62.3 Review Process

If affected site representatives request consultation in the future, this SSCNMP will be updated in accordance with CRL designation conditions 37.5, with consideration given to the following:

• The extent to which noise may exceed the designation standards

• The timing and duration of any exceedance

• The type of activity causing any exceedance

• A summary of the communication and consultation with the receiver

• The methods and measures to mitigate effects

• A statement of why they reflect best practicable option

Communications records are contained in the communication and consultation plan (CCP). This SSCNMP will be updated to summarise engagement and any agreed site-specific measures.

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.