Memo To:
Maree Drury, Link Alliance
From:
Sarah Macready
CC:
Michelle Chan
Date:
13-Dec-19
Re:
City Rail Link C5 Normanby Road Early Works – Archaeological Management Requirements
Purpose and Project Scope As requested, I provide an assessment of archaeological values within the Normanby Road Early Works project area and the archaeological management procedures that must be followed during the early works. The project area is shown in Figure 1 (shaded area) and I understand the works include: the establishment of a CSA at 14-22 Boston Road, 11 Water Street and partly within 28 Mt Eden Road; utilities diversion including wastewater and stormwater lines; construction of retaining walls at 32 Normanby Road and at the southwest corner of the Normanby Road/ Boston Road roundabout; and construction of a temporary pedestrian and utility bridge across the Normanby Road rail crossing.
Figure 1. Normanby Road Early Works Project Area
⚍ Page 1