Karanga-a-Hape Station minutes 20 June 2024

Page 1


MINUTES

TIME 5:30-6:30pm

LOCATION The Methodist Church, Pitt Street, Auckland

STAKEHOLDERS Six Community Liaison Group (CLG) members

DATE TE 20 June 2024

Stakeholders Included: Rod Hansen, Reverend Colin Waters, Geanna Littlejohn, Sam (People Being People), Richard Northey, William Keung

ATTENDEES

Auckland Transport (AT): Manoj Nathoo, Siobhan O’Donovan, Brianna Fuller.

Link Alliance staff: Simon Mitchell, Joe Bowles, Kevin Hopkins, Michael Coup, Rachel Blundell.

SUBJECT CLG

Agenda

5:30 – Community engagement – Simon Mitchell, Community Manager

5:35 – Station entrance structures – Michael Coup, Construction Manager

5:45 – Urban Realm – Michael Coup

5:50 – Station fit-out – Kevin Hopkins, Fit-out Manager

6:00 – Station design – Simon Mitchell & Michael Coup

6:10 – Project K – Manoj Nathoo, Auckland Transport

6:20 – Discussion and questions

6:30 – End

Meeting notes

Community engagement – Simon Mitchell

A brief overview of engagement activations and projects undertaken by the communications team since the previous CLG (March), including events at the Pocket Park, around Beresford Square, Pitt Street and along Karangahape Road.

Station entrance structures and Urban Realm – Michael Coup

Michael provided an update on the structure progress since March’s CLG, including roof installation and guttering, steelwork, front of house façade work as well as glazing at both entrances. Michael

also covered the current urban realm works underway and what stakeholders can expect over the coming months.

Station fit-out – Kevin Hopkins

Kevin provided an overview of the fit-out works progress to date, including cable pulling, equipment installation and livening of the station.

Station design – Michael Coup and Simon Mitchell

Simon and Michael covered the Māori creation story, how this is reflected in the station design, and what represents each element.

Project K – Suresh Patel, Auckland Transport

Manoj gave an overview of key team members on the ground, shared the preliminary construction staging and traffic flow post construction.

Questions and Answers

What kind of fencing will there be during Project K’ construction works?

We will use predominantly low-level fencing. We don’t expect it to be for a long period of time. Regarding support, we will be working alongside Werkits to provide support to impacted businesses.