Primary School Facility Assessment

Page 1


FACILITY CONDITIONS

BUILDING ENVELOPE IMPROVEMENTS

Replace Roof on 1999 1st Grade Addition and Multipurpose Room Addition. Replace 1999 and 2001 Built Up Roofs Serving Office Area, Kitchen, and PreK Wing.

The roofs on the 1999 addition to the 1st grade classrooms and the multipurpose/cafeteria room (areas A, H and J) are reaching the end of their useful life and are showing signs of aging such as bridging / stretching at roof perimeters and multiple previous repairs. These roofs should be replaced in the next 3 years.

The roof over the pre-K classrooms, kitchen and boiler room (areas L, O and P) are also reaching the end of their useful life and should be replaced in the next 3 to 5 years. The pre-K classroom wing has a 2001 built up roof, while the kitchen, boiler room and front office are built up roofs done in 1999. The pre-K wing has a solar array that will need to be removed and reinstalled.

Roofing system replacement will improve energy performance by increasing system insulation values, reduce leaks, and will reduce operating and maintenance expenses.

PRIMARY SCHOOL FACILITY CONDITIONS

PRIMARY SCHOOL FACILITY CONDITIONS

BUILDING ENVELOPE IMPROVEMENTS

PS-BE-1 Priority 1 – Replace Roof on 1999 1st Grade Addition and Multipurpose Room Addition

• Removal of old roof systems & wet insulation / deteriorated wood blocking.

• Polyisocyanurate insulation layers. R-30 with a minimum positive slope of 1/8" per foot to ensure proper drainage.

• Recovery insulation board to accept new roof system & provide a stop gap against thermal bridging from insulation fasteners.

• Multiply modified built-up roof system with gravel surfacing. Provides a "severe hail" rating.

• Pre-finished sheet metal copings & counterflashing at all perimeters and projections to protect against damage and UV degradation.

PS-BE-2 Priority 2 – Replace 1999 and 2001 Built Up Roofs Serving Office Area, Kitchen and Pre-K Wing

• Removal of old roof systems & wet insulation / deteriorated wood blocking.

• Polyisocyanurate insulation layers. R-30 with a minimum positive slope of 1/8" per foot to ensure proper drainage.

• Recovery insulation board to accept new roof system & provide a stop gap against thermal bridging from insulation fasteners.

• Multiply modified built-up roof system with gravel surfacing. Provides a "severe hail" rating.

• Pre-finished sheet metal copings & counterflashing at all perimeters and projections to protect against damage and UV degradation.

PS-BE-1&2 Benefits

• Extend life of building

• Reduce energy cost

• Reduce leaks

• Reduce operating and maintenance expenses

BUILDING ENVELOPE IMPROVEMENTS

Install Through-Wall flashing at Steel Lintels, Remove Corrosion From Structural Steel Lintels and Coat with Corrosion Inhibiting Paint, Install Sheet Metal Fashing with Drip Edge Where Necessary Within the Next 3 Years

Through-wall flashing was not originally present at window, door, and other openings. However, drip edge flashing appeared to have been added at a few locations. Exposed steel lintels at many locations are forming pack rust. Through-wall flashings are not present on these lintels. Lintels over and adjacent to window openings in brick cladding are corroded. Pack rust formation can apply pressure on the brick cladding and cause deterioration of the cladding. Corrosion also results in the loss of section of the steel lintels, which reduces strength and stiffness of the steel lintels. This condition warrants repair to prevent further damage to embedded steel and brick cladding, and to prevent water entry into and through the exterior walls.

The exposed steel should be cleaned, corrosion removed and coated with a corrosion inhibiting paint to minimize future corrosion/ deterioration. Install through-wall flashing at existing steel lintels. Install sheet metal flashing with drip edge where necessary.

PRIMARY SCHOOL FACILITY CONDITIONS

BUILDING ENVELOPE IMPROVEMENTS

PS-BE-3 Install Through-Wall Flashing at Steel Lintels, Remove Corrosion from Structural Steel Lintels and Coat with Corrosion Inhibiting Paint, Install Sheet Metal Flashing with Drip Edge Where Necessary Within the Next 3 Years.

• Install through-wall flashing

• Clean and paint steel lintels

• Install sheet metal flashing with drip edge where needed

PS-BE-3 Benefits

• Extend life of building

• Reduce leaks

• Reduce operating and maintenance expenses

BUILDING ENVELOPE IMPROVEMENTS

Repoint Mortar Joints and Replace Cracked/Spalled Brick, Repair Bricks at Steel Bolts and Anchors

In general, the brick masonry façade appears to be in good condition for its age.

Cracked mortar joints between the brick units were noted at several locations and vertical cracking was observed in isolated areas. Cracked, spalled, and broken bricks were also observed. Localized mortar deterioration and isolated brick cracking/spalling is present. These conditions are generally attributable to long term exposure to the elements. Vertical cracks located at corners are likely attributable to a lack of control joints on the façade. Step cracking in the brick facade is likely due to differential settlement.

Mortar is missing at one corner of brick full height. The joint with missing mortar full-height was likely cut for an expansion joint, but no sealant was installed.

General maintenance of brick cladding, including tuckpointing and replacement of damaged brick, is not needed at this time. However, a brick maintenance project to repoint deteriorated mortar joints and replace cracked/spalled brick should be planned in approximately 4 to 6 years.

Steel rods and plates are protruding from the façade at a few locations. The brick surrounding these rods and plates has rust stains and the brick has spalled. The unfinished steel rod and plate corroded due to being exposed to the elements. Although some brick may have broken during the original installation, the majority of the brick damage at lintels is due to moisture intrusion/condensation through the bolt penetrations and the freeze/thaw cycle cracking and spalling the brick.

The purpose of this steel should be investigated further to determine whether they can be removed or if they require protection while repairing the adjacent brick. If abandoned, remove and repair brick masonry. If in use, determine if thermal transfer is occurring and eliminate thermal transfer during the brick repairs.

BUILDING ENVELOPE IMPROVEMENTS

PRIMARY SCHOOL FACILITY CONDITIONS

PS-BE-4 Repoint Mortar Joints and Replace Cracked/Spalled Brick, Repair Bricks at Steel Bolts and Anchors

• Replace brick (approximately 400)

• Repoint 2500 square feet

• Investigate the steel rod and plate to determine if needed

• If abandoned, remove and repair brick

• If in use, eliminate thermal transfer during brick repair

PS-BE-4 Benefits

• Extend life of building

• Reduce operating and maintenance expenses

BUILDING ENVELOPE IMPROVEMENTS

Replace Sealant at Doors, Windows, and Control Joints

Exterior sealant at windows, doors, corners, and other areas of the façade is in poor condition. Weathering, splitting, debonding, and cracking of sealant was observed throughout the façade.

Exterior sealants deteriorate as a result of exposure to UV light, moisture, and temperature cycles. Sealants typically have a lifespan of 8-12 years depending on material, material quality, and application/configuration.

Based on observed conditions, it appears that the sealants on the building have reached or exceeded their useful life.

Sealants are an important component of the exterior building envelope and in many cases are the first line of defense in preventing water entry into and through exterior walls. Deteriorated sealants greatly increase the potential for water entry.

Replace all window and door perimeter, control joint, and penetration sealant at the building façade, as well as any miscellaneous sealants present. These repairs should be completed in the next 0-3 years.

PRIMARY SCHOOL FACILITY CONDITIONS

BUILDING ENVELOPE IMPROVEMENTS

PS-BE-5 Replace Sealant at Doors, Windows, and Control Joints

• Replace sealant (approximately 6,000 LF)

PS-BE-5 Benefits

• Extend life of building

• Reduce operating and maintenance expenses

BUILDING ENVELOPE IMPROVEMENTS

Replace Three (3) Sets of Exterior Double Doors and Nine (9) Single Exterior Doors in the Next Three Years.

PRIMARY SCHOOL FACILITY CONDITIONS

The hollow metal swing doors are corroded at the bottom of the door frames. The door and door frame corrosion are due to water ponding against the building. The weatherstripping has failed at the perimeter of the garage doors. We recommend replacing the indicated exterior doors, including the hardware and locks. Re-key all the door locks to comply with the Districtwide Schlage standard.

PRIMARY

PRIMARY SCHOOL FACILITY CONDITIONS

BUILDING ENVELOPE IMPROVEMENTS

PS-BE-6 Replace Three (3) Exterior Double Doors and Nine (9) Single Doors Including Hardware and Locks. Re-Key all Door Locks to Comply with District Wide Schlage Standard

• Replace exterior doors and frames including hardware and locks

• Replace weatherstripping on garage doors

• Re-key all locks to district wide Schlage standard

PS-BE-6 Benefits

• Increase life of structure

• Prevent further deterioration of building

• Improve safety

PRIMARY SCHOOL FACILITY CONDITIONS

MECHANICAL AND PLUMBING

Update Building Automation System to Include Cooler and Freezer Temperatures and Alarms

The Chisago Lakes Primary School building automation system is in good shape and all hardware and software are current.

However, the existing cooler and freezer do not have temperature monitoring or alarms. Nexus recommends adding temperature monitoring and alarms to the cooler and freezer.

The benefits of this controls improvement include improved equipment control and monitoring.

MECHANICAL AND PLUMBING

PS-ME-1 Update Building Automation System to Include Cooler and Freezer Temperatures and Alarms

• Provide new controls for cooler and freezer

• Integrate new existing controls into platform

• Provide all programming required for this improvement

PS-ME-1 Benefits

• Easy to use, modernized system control updates

• Improved building monitoring and maintenance troubleshooting

• Reduced maintenance

MECHANICAL AND PLUMBING

Replace Seven (7) R-22 RTUs and One (1) 2005 Kitchen MAU

There are several rooftop and make-up air handling units serving the Chisago Lakes Primary School that are becoming maintenance problems for the District. These units are listed below.

• 2003 AAON RTU-3 that serves classrooms. This rooftop air handling unit currently has DX cooling and downstream hot water variable air volume (VAV) boxes.

• 2003 AAON RTU-4 that serves classrooms. This rooftop air handling unit currently has DX cooling and downstream hot water variable air volume (VAV) boxes.

• 2003 AAON RTU-5 that serves classrooms. This rooftop air handling unit currently has DX cooling and downstream hot water variable air volume (VAV) boxes.

• 2003 AAON RTU-6 that serves classrooms. This rooftop air handling unit currently has DX cooling and downstream hot water variable air volume (VAV) boxes.

• 2004 AAON RTU-7 that serves the Media Center. This rooftop air handling unit is a single zone unit with DX cooling and hot water heating coils.

• 2005 AAON RTU-8 that serves classrooms. This rooftop air handling unit currently has DX cooling and downstream hot water variable air volume (VAV) boxes.

• 2005 AAON RTU-9 that serves classrooms. This rooftop air handling unit currently has DX cooling and downstream hot water variable air volume (VAV) boxes.

• 2005 AAON Kitchen make-up air handling unit (MAU). This rooftop makeup air handling unit is a single zone unit with DX cooling and gas heating coils.

Nexus recommends replacing the eight (8) rooftop and make-up air handling units one for one with new double wall rooftop air handling units with hot water heating and DX dehumidification. The new rooftop air handling units would come with code compliant filtration, hot water heating coils, chilled water dehumidification coils, access sections, and supply fans with variable speed drives (VSDs).

The benefits of this HVAC improvement include increased system life expectancy, improved DDC scheduling, improved ventilation, increased energy savings, improved occupant comfort, and an improved learning and working environment.

PRIMARY SCHOOL FACILITY CONDITIONS

MECHANICAL AND PLUMBING

PS-ME-2 Rooftop and Make-Up Air Handling Unit Replacements

• Remove existing rooftop and make-up air handling units, piping, and controls

• Provide new double wall rooftop air handling units with hot water heating and DX dehumidification

• Extended new hot water and refrigerant piping to air handling units as required

• Provide variable speed drives for the supply and relief fans

• Provide all roofing and sealing work as required

• Provide DDC controls, sequencing, and programming

• Provide all associated general construction and electrical work as required

PS-ME-2 Benefits

• Upgraded HVAC infrastructure

• Increased ventilation for improved indoor air quality

• Improved temperature control

• Improved occupant comfort

• Reduced maintenance

• Improved learning/work environment

MECHANICAL AND PLUMBING

Add Dehumidification and Powered Relief to Gym Air Handling Unit

The Primary School Gym is currently being served by a 2021 air handling unit (AHU) with hot water heating but no means of dehumidification.

The lack of dehumidification results in higher humidity levels and occupant discomfort in the gym. The gym is also unable to meet the American Society of Heating and Refrigeration Engineer’s (ASHRAE) Thermal Environmental Conditions for Human Occupancy Standard 55. This ASHRAE design standard specifies the combinations of personal and indoor thermal environmental requirements necessary to achieve an occupant comfort satisfaction rate of 80% or greater. These indoor environmental requirements include temperature, thermal radiation, humidity, and air speed.

Nexus recommends adding a new DX dehumidification coil to the air handling unit to allow for dehumidification of the code required ventilation air to the gym. The coil would be mated with a new air-cooled condensing unit (ACCU) and refrigerant piping would be extended to the air handling unit as required.

Nexus also recommends adding powered relief to the gym in lieu of gravity relief. Powered relief systems provide enhanced control, efficiency, and adaptability compared to traditional gravity relief systems, contributing to better overall performance and operational benefits in air handling units.

The benefits of these upgrades include improved equipment scheduling, improved ventilation, increased energy savings, improved occupant comfort, and an improved learning and working environment.

PRIMARY SCHOOL FACILITY CONDITIONS

MECHANICAL AND PLUMBING

PS-ME-3 Add Dehumidification and Powered Relief to Gym Air Handling Unit

• Provide new DX dehumidification coil with mated air-cooled condensing unit

• Extend new refrigerant piping to air handling unit as required

• Install new powered relief fan for gym

• Provide DDC controls, sequencing, and programming

• Provide all associated general construction and electrical work as required

PS-ME-3 Benefits

• Upgraded HVAC infrastructure

• Improved temperature control

• Improved occupant comfort

• Reduced maintenance

• Improved learning/work environment

MECHANICAL AND PLUMBING

Replace 2005 R-22 ACCU Serving Multi-Purpose Room and Associated Coils and Add Ventilation to Maintenance Office

The existing 2005 condensing unit serving the multi-purpose air handling unit is starting to corrode and deteriorate. This 20-year-old condensing unit is still utilizing R-22 refrigerant which has become obsolete and far less efficient than today’s systems.

Nexus recommends replacing this old inefficient air-cooled condensing unit and the mated DX dehumidification coil with a new air-cooled condensing unit and associated DX dehumidification coil with American Society of Heating and Refrigeration Engineer’s (ASHRAE) code compliant refrigerant that is more energy efficient and environmentally friendly. New refrigerant piping would be installed as required for the new refrigerant.

The Maintenance Office 125 currently has no ventilation, which does not meet the current code for ASHRAE 62.1 Ventilation for Acceptable Indoor Air Quality. This code provides the minimum outside air ventilation rates that are required in the breathing zone for specific spaces.

Nexus recommends adding ventilation to the maintenance office from an adjacent air handling unit to bring in the code required ventilation air.

Benefits of these improvements include reduced maintenance, improved system operation, and increased occupant comfort.

MECHANICAL AND PLUMBING

PS-ME-4 Replace 2005 R-22 ACCU Serving Multi-Purpose Room and Associated Coils and Add Ventilation to Maintenance Office

• Provide new DX dehumidification coil with mated air-cooled condensing unit

• Extend new refrigerant piping to air handling unit as required

• Install new exhaust fan system for boiler room

• Provide DDC controls, sequencing, and programming

• Provide all associated general construction and electrical work as required

PS-ME-4 Benefits

• Upgraded HVAC infrastructure

• Improved temperature control

• Improved occupant comfort

• Reduced maintenance

• Improved learning/work environment

MECHANICAL AND PLUMBING

Replace Eight (8) Exhaust Fans

There are several rooftop exhaust fans serving the building that have exceeded their recommended service life and are in need of replacement.

Nexus recommends replacing some of these fans when major work is taking place so the best pricing can be obtained from the contractors. Nexus has budgeted for the replacement of eight (8) existing exhaust fans for the school. Nexus will work along with the District on the priority of which ones want to be replaced.

Fans will be a direct replacement to the original size/capacity but will have premium efficiency motors installed to increase energy savings. The fan size/capacity may be reduced if engineering can justify where over ventilation is occurring.

The benefits of this HVAC improvement will result in increased energy savings, improved flow and reduced maintenance for exhaust fans, and reduced leaks from seals.

PRIMARY SCHOOL FACILITY CONDITIONS

MECHANICAL AND PLUMBING

PS-ME-5 Replace Eight (8) Exhaust Fans

• Replace rooftop exhaust fans with new exhaust fans with associated ductwork

• Provide all roofing and sealing work as required

• Provide DDC controls, sequencing, and programming

• Provide all associated general construction and electrical work as required

PS-ME-5 Benefits

• Upgraded exhaust system infrastructure

• Improved temperature control

• Improved occupant comfort

• Reduced maintenance

• Improved work environment

MECHANICAL AND PLUMBING

Replace One (1) Non-ADA Wash Fountain, Three (3) Non-ADA Drinking Fountains, Add Domestic Hot Water to Twenty (20) Sinks that are Cold Only, and Replace Ten (10) Flush Valves in Toilet Rooms

There are several plumbing devices that are starting to increase in maintenance/non-ADA compliant and should be replaced. See below for this equipment.

• Non-ADA Wash Fountain (Qty 1)

• Non-ADA Drinking Fountains (Qty 3)

• Flush Valve Replacements in Toilet Rooms (Qty 10)

Nexus recommends replacing these existing plumbing fixtures one for one with new fixtures. Plumbing piping would be modified as required for the new fixtures.

Replacing these plumbing fixtures would provide reduced water consumption, reduced maintenance, and extended life expectancy of the plumbing system.

Nexus also recommends adding hot water to the sinks that are currently cold water only (Qty 20) and adding two (2) demand domestic hot water recirculation pumps for the rooms in the 1965 area of the building that have trouble getting hot water in an appropriate amount of time.

Benefits of this work would be reduced maintenance, improved water quality, and improved domestic hot water system.

MECHANICAL AND PLUMBING

PS-ME-6 Replace One (1) Non-ADA Wash Fountain, Three (3) Non-ADA Drinking Fountains, Add Domestic Hot Water to Twenty (20) Sinks that are Cold Only, and Replace Ten (10) Flush Valves in Toilet Rooms

• Demo existing wash station, drinking fountains, and flush valves

• Provide and install new fixtures one for one

• Modify existing plumbing piping as required for new fixtures

• Provide associated general and electrical construction

• Extend new hot water piping to sinks that are currently cold water only

• Provide and install new demand hot water recirculating pumps and piping for areas with current hot water issues

• Provide associated general and electrical construction work as required

PS-ME-6 Benefits

• Improved occupant comfort

• Improved plumbing fixture operation

• Increased equipment life

• Reduced maintenance

MECHANICAL AND PLUMBING

Fix Domestic Cold-Water Crossover Feeding and Replace Leaky Valves Located in Tunnel (Option 7A)

The existing valves and hangers for the domestic water piping in the tunnel have corroded and are starting to fail. This is causing the pipes to not be properly supported and failed valves are causing cold-water crossover/back feeding issues with the hot water system.

Nexus recommends replacing all the valves and hangers in the tunnel with new valves and hangers to ensure proper piping support and prevent cold and hot water crossover.

Replacing these valves and hangers would provide reduced water consumption, reduced maintenance, and extended life expectancy of the plumbing system.

Demo Domestic Piping in Tunnel Including Valves, Install New Domestic Water Piping (Option 7B)

The existing valves and hangers for the domestic water piping in the tunnel have corroded and are starting to fail. This is causing the pipes to not be properly supported and failed valves are causing cold-water crossover/back feeding issues with the hot water system.

Nexus recommends removing all the domestic water piping in the tunnels and installing a new overhead domestic water system throughout the building.

Replacing these valves and hangers would provide reduced water consumption, reduced maintenance, and extended life expectancy of the plumbing system.

MECHANICAL AND PLUMBING

PS-ME-7A Fix Domestic Cold-Water Crossover Feeding and Replace Leaky Valves Located in Tunnel

• Demo existing valves and hangers in tunnel

• Provide and install new valves and hangers as required

• Modify existing plumbing piping as needed

• Provide associated general construction

PS-ME-7A Benefits

• Improved plumbing fixture operation

• Increased equipment life

• Reduced maintenance

PS-ME-7B Demo Domestic Piping in Tunnel Including Valves, Install New Domestic Water Piping

• Demo existing piping, valves, and hangers in tunnel

• Provide and install new domestic water system overhead

• Modify existing plumbing piping as needed

• Provide associated general construction

PS-ME-7B Benefits

• Improved plumbing fixture operation

• Increased equipment life

• Reduced maintenance

PRIMARY SCHOOL FACILITY CONDITIONS

MECHANICAL AND PLUMBING

Retro-Commissioning of HVAC Equipment

Building retro-commissioning is a systematic process that ensures all buildings perform as efficiently as possible according to the owner’s operational needs as well as adjustment of HVAC equipment’s operational parameters to meet current space use.

The Building Automation System (BAS) plays a crucial role in providing a comfortable, energyefficient environment for students, parents, and staff. Over time, damper and valve controls have gone out of proper adjustment, components fail, and controls sequences are modified and may not be programmed to provide an optimal balance between comfort, indoor air quality, and energy efficiency.

This Nexus Retro-commissioning Team will identify the root cause of HVAC equipment operational issues and will provide adjustments to the sequences and outdoor air setting to improve occupant comfort while reducing energy consumption where possible. The retrocommissioning process will also identify components that require adjustment or replacement.

Retro-commissioning activities include:

HVAC Equipment: Nexus will verify existing HVAC equipment operation and control sequences through observation. We will provide adjustment and tuning services to achieve optimal operation and improved occupant comfort. Documentation of the findings with corrections and recommendations for further improvements will be made.

Services include:

• Ventilation study to assure all spaces are ventilated per the current code requirements and the outdoor air setpoints will be adjusted up or down based on current space occupancy

• Test point commands vs actual controller output at each device for heating, cooling, and mixed air control

• Verify valve/damper operation on reheat coils and air handler coils

• Verify indicated vs actual (duct static, supply and return temperatures)

• Verify mixed-air operation (damper position and economizer operation)

PRIMARY SCHOOL FACILITY CONDITIONS

Valves and Dampers: Nexus will test all existing rooftop (RTU) and indoor air handling unit (AHU) sequences along with the valve and damper operation to ensure control actuators are fully operational. We observe valve/damper/actuator operation and check for any physical signs of valve/damper leakage or binding, which results in operational issues and increased energy consumption. We check discharge temperature with valves in the fully open and closed positions. In addition, we will provide unit pricing to replace any defective valves and/or actuators. Proper RTU and AHU operation provides improved occupant comfort at optimal energy efficiency.

Zone Reheat Valves: Nexus will test existing zone reheat valves for proper operation. We ensure command valves fully open and close and observe valve/actuator operation. We inspect valves for any physical signs of valve leakage or binding, check discharge temperature with valve in the fully open and closed positions and provide unit pricing to replace any defective valves and/or actuators.

Economizer: Nexus will update the control sequence for mixed-air dampers to their setpoints with economizer lockout setpoints.

Heating Water Pump Variable Speed Drives (VSDs): Nexus will lower the pressure setpoint to allow drives to modulate down to the slowest speed required to satisfy the most critical room temperature sensor.

Boilers: Nexus will optimize sequencing and staging of equipment and adjust the water reset schedules based on outside air temperature.

The action steps noted above are part of the Nexus retro-commissioning process. The benefits of this process include improved temperature control and occupant comfort, reduced energy consumption, reduced maintenance, and extended HVAC equipment life.

PRIMARY SCHOOL FACILITY CONDITIONS

MECHANICAL AND PLUMBING

PS-ME-8 Retro-Commissioning of HVAC Equipment

• Provide retro-commissioning of all existing HVAC systems

• Provide adjustments to existing sequences to improve HVAC system operation

• Verify operation of all dampers, actuators, valves, and terminal HVAC devices

PS-ME-8 Benefits

• Improved temperature control and occupant comfort

• Reduced energy consumption

• Reduced maintenance

• Extended HVAC equipment life

ELECTRICAL, TECHNOLOGY, AND SAFETY SYSTEMS

Upgrade Electrical Power Distribution Including the 1965 Switchgear and Panels

The switchboard and panels that are original to the 1965 building are now 60 years old and are at the end of their useful life. The switchboard is manufactured by FPE, which is no longer in existence. Parts for this equipment are no longer available.

It is recommended that the 1965 electrical panels and switchboard be replaced. New panels will provide a safer electrical system since new equipment will be in compliance with current manufacturing standards for electrical equipment and will reduce maintenance costs.

Equipment recommended to be replaced includes one switchboard and 5 panelboards.

ELECTRICAL, TECHNOLOGY, AND SAFETY SYSTEMS

PS-ES-1 Upgrade Electrical Power Distribution Including the 1965 Switchgear and Panels

• Replace One Switchboard

• Replace Five (5) Panelboards

PS-ES-1 Benefits

• Protection of and Improved Reliability of Electrical Infrastructure

• Reduced energy consumption

• Reduced maintenance

• Extended HVAC equipment life

PRIMARY SCHOOL FACILITY CONDITIONS

ELECTRICAL, TECHNOLOGY AND SAFETY SYSTEMS

Install New Generator to Control Primary Systems Such as Boiler, Boiler Pumps, Emergency Lighting, Cooler and Freezer (130 kW)

Currently, there is no backup power generator installed. There are frequent power outages at this location. This poses a risk for building security and life safety. In addition, costs may be incurred due to loss of heat in the building causing it to freeze up and loss of food that is stored in the coolers and freezers.

It is recommended that a generator be installed to provide backup power for these necessary items.

Increase the Size of the Generator from 130 kW to 400 kW to Cover Full Building Load Including Cooling

Alternately, with frequent power outages, installing a generator with full building backup will allow the school to function, even when utility power is lost. Increasing the size of the generator from 130 kW to 400 kW will also allow the building to be cooled.

. ELECTRICAL, TECHNOLOGY, AND SAFETY SYSTEMS

PS-ES-2.1, 2.2 Install New Generator

• Add a backup generator to provide backup power for heating equipment, coolers/freezers, fire alarm/security, and IT network equipment.

• Increase size to also cover cooling of building

PS-ES-2.1, 2.2 Benefits

• Provides better life safety with the IT equipment and life safety systems on the backup power

• Prevents potential financial losses due to power outages

• Option to handle the entire building load to prevent school shutdowns

PRIMARY SCHOOL FACILITY CONDITIONS

ELECTRICAL, TECHNOLOGY AND SAFETY SYSTEMS

LED Lighting Upgrade for Areas with Fluorescent. Retrofit Kits for Fixtures in Good Condition, Replacement for Unique or Outdated Fixtures. Includes 3 Exterior Lights and 54 Emergency Lights

The existing lighting in classrooms, gymnasiums, and common areas is primarily fluorescent lamps throughout. The fixtures appear to be in fair condition; however, LED lamp technology is more energy efficient.

Replacing the light fixtures with LED light fixtures will reduce energy use and maintenance costs. LED light fixtures have a life span of more than 50,000 hours and do not require lamp replacements, which reduces maintenance costs.

It is recommended that the lighting controls be upgraded to include dimming and occupancy sensors.

There is an area outside that is frequently used that is not well lit. It is recommended to add light fixtures as necessary in this area to provide adequate light, which will enhance the safety and security of students and staff.

In addition, emergency batter lights have a useful life of 10-years. It is recommended that emergency lights be replaced to reduce maintenance costs due to fixture or battery replacement. Note – the costs were included in the lighting costs for 54 emergency lights. If the generator is accepted, the cost for these lights would be used to route emergency power throughout to lights so they can be on the generator per our discussion with Kyle.

ELECTRICAL, TECHNOLOGY, AND SAFETY SYSTEMS

PS-ES-3 LED Lighting Upgrade for Areas with Fluorescent. Retrofit Kits for Fixtures in Good Condition, Replacement for Unique or Outdated Fixtures. Includes 3 Exterior Lights and 54 Emergency Lights

• Replace light fixtures throughout the building with LED light fixtures

• Add light fixtures on building exterior

• Controls to provide dimming capabilities

• Automatic shutoff of lighting

PS-ES-3 Benefits

• Reduce energy costs

• Reduce maintenance costs

• Enhance outside security

PRIMARY SCHOOL FACILITY CONDITIONS

ELECTRICAL, TECHNOLOGY AND SAFETY SYSTEMS

Install 5 Additional Security Cameras and 12 Additional Clocks to Existing Systems. Repair Fire Alarm Interface with HVAC System.

Security System Upgrades

Security cameras are approximately 5-6 years old. Although they still have 3-4 years left of their useful life, there are areas that need better camera coverage for better security.

Clock System Upgrades

The existing clock system is a newer system consisting of wireless clocks that synchronize. However, there are 12 locations where older clocks still remain. These clocks should be replaced to match the newer system so all the clocks in the building synchronize together.

Fire Alarm System Upgrades

The existing fire alarm system is a Notifier system with voice evacuation and was recently installed. However, there is an issue with the system as it relates to interface with the HVAC system. This issue needs to be corrected.

ELECTRICAL, TECHNOLOGY, AND SAFETY SYSTEMS

PS-ES-4 Install 5 Additional Security Cameras and 12 Additional Clocks to Existing Systems. Repair Fire Alarm Interface with HVAC Systems

• Correct alarm code issues with fire alarm system

• Add 5 additional security cameras where coverage is lacking

• Add 12 clocks to existing system

PS-ES-4 Benefits

• Protection and improved reliability

• Improved safety

• Enhance security

PRIMARY SCHOOL FACILITY CONDITIONS

ELECTRICAL, TECHNOLOGY AND SAFETY SYSTEMS

Replace Non-Working Sound System in Multi-Purpose Room

The existing sound system in the Multi-Purpose Room is not working and should be replaced. It is recommended that the system be replaced and tied in with the paging system.

ELECTRICAL, TECHNOLOGY, AND SAFETY SYSTEMS

PS-ES-5 Replace Non-Working Sound System in Multi-Purpose Room

• Replace audio system in multi-purpose room

• Add 5 additional security cameras where coverage is lacking

• Add 12 clocks to existing system

PS-ES-5 Benefits

• Protection and improved reliability

• Improved safety

ELECTRICAL, TECHNOLOGY AND SAFETY SYSTEMS

Install New Burglar Alarm Systems with 10 Motion Sensors and Two Keypads.

PRIMARY SCHOOL FACILITY CONDITIONS

A burglar alarm system is also needed to enhance the security of the building. It is recommended that a burglar alarm system be installed.

ELECTRICAL, TECHNOLOGY, AND SAFETY SYSTEMS

PS-ES-6 Install New Burglar Alarm Systems with 10 Motion Sensors and Two Keypads

• Install new burglar alarm

• Install 10 motion sensors

• Install 2 keypads

PS-ES-6 Benefits

• Protection and improved reliability

• Improved safety

INTERIOR FINISHES AND ADA

High Priority Ceilings and Flooring

The Primary school building overall has been maintained very well, however, there are a few high priority interior finishes needs that should be addressed in the next 0-6 years. Replace ACT ceilings and repaint exposed structures as they have reached the end of their useful life and are showing stains and damage. The carpet in a few areas of the building is also showing wear and tear. Replace the old VCT in corridors with new rubber tiles as part of a District wide standardization. The resilient flooring is showing scratches and stains. Replace VCT flooring with a flooring material that requires less maintenance, such as an LVT.

INTERIOR FINISHES AND ADA

PS-IA-1 High Priority Ceiling Upgrades

• Replace ACT ceiling as noted on the plans in 0-6 years

• Repaint rooms with exposed structures

PS-IA-2 High Priority Flooring Upgrades

• Replace carpet in media center with new carpet tiles

• Replace VCT in corridors with rubber tiles

• Replace VCT and resilient flooring with LVT in areas marked on the plans

PS-IA-1 & 2 Benefits

• Improved building aesthetics

• Extending the life of the interior materials

• Reduced maintenance costs

PRIMARY SCHOOL FACILITY CONDITIONS

INTERIOR FINISHES AND ADA

Low Priority Flooring and Ceilings

The low priority needs to be addressed in the next 7-10 years would include. The ceilings in the four 1st grade classrooms and the adjoining corridor should be replaced. The remaining resilient flooring in the classrooms should be updated with a flooring material that requires less maintenance, such as an LVT.

INTERIOR FINISHES AND ADA

PS-IA-5 Low Priority Ceiling Upgrades

• Replace ACT ceiling as noted on the plans in 0-6 years

• Repaint rooms with exposed structures

PS-IA-6 Low Priority Flooring Upgrades

• Replace VCT in corridors with rubber tiles

• Replace VCT and resilient flooring with LVT in areas marked on the plans

PS-IA-5 & 6 Benefits

• Improved building aesthetics

• Extending the life of the interior materials

• Reduced maintenance costs

CEILINGS

FLOORING

PRIMARY SCHOOL FACILITY CONDITIONS

INTERIOR FINISHES AND ADA

Casework needs

The casework in the classrooms is in need of upgrading. It is showing signs of damage and is not meeting the needs of the users. All of the identified casework should be replaced in the next 6 years.

INTERIOR FINISHES AND ADA

PS-IA-3

High Priority Casework

• Replace existing casework with new upgraded casework

PS-IA-3 Benefits

• Improved building aesthetics

• Extending the life of the interior materials

• Reduced maintenance costs

Casework

PRIMARY SCHOOL FACILITY CONDITIONS

INTERIOR FINISHES AND ADA

High Priority Door Replacement, Hardware and Locks. Re-Key All Door Locks to Comply with District-Wide Schlage Standard.

The majority of the interior door hardware needs to be replaced in the next 3 years. There are also a few doors that need replacement including the hardware. All of the door’s locks need to be re-keyed to comply with the District-Wide Schlage standard.

INTERIOR FINISHES AND ADA

PS-IA-4 High Priority Door Replacement, Hardware, and Locks

• Replace hardware on 23 doors

• Replace 21 single doors and hardware

• Replace 2 double doors

PS-IA-4 Benefits

• Improved building aesthetics

• Extending the life of the interior materials

• Improved functionality of building

Doors & Hardware

SITE IMPROVEMENTS

Add New North Parking and Relocate Walkway and Fencing

The ECFE/pre-K wing does not have a way for parents to drop off/pick up the small children. The new parking lot with 16 stalls and a sidewalk directly to the separate entry will improve access. The relocated fence will also improve the safe walking route to school.

SITE IMPROVEMENTS

PS-SI-1 Add New North Parking and Relocate Walkway and Fencing

• New asphalt parking lot with cub and gutter

• New fencing

• Move ECFE entry to door 16

PS-SI-1 Benefits

• Improved building access

• Separate parent loop for ECFE

• Improved walking path for students

SITE IMPROVEMENTS

Remove and Replace Pavement of the Hard Playground on East & West Sides of Building. Improve Drainage with New Catch Basin.

During the site visit it was observed that the asphalt on the east and west hard play areas had a lot of cracking with signs of previous crack sealing. The east hard play area does not drain properly causing safety issues including ice formation. Both the east and west hard play surfaces need to be removed and replaced with new asphalt. A new catch basin should be added to improve drainage of the east area.

SITE IMPROVEMENTS

PS-SI-2 East Playground

• Remove and replace asphalt pavement

• Fine grading/soil correction

• Add catch basin and pipe

• Remove and replace sections of play curb and play mulch for drainage improvement

PS-SI-3 West Playground

• Remove and replace asphalt pavement

• Fine grading/soil correction

PS-SI-2 & 3 Benefits

• Safer play area

• Improved drainage

PRIMARY SCHOOL FACILITY CONDITIONS

East Playground
West Playground
East Playground

SITE IMPROVEMENTS

Remove and Repair North Loop Driveway, Parking Lot, and South Parking

The North parking lot aesthetically is poor because of numerous patches during previous projects, but the pavement is also starting to fail. Lot could benefit from regrading to improve drainage. With storm sewer possibly extended over to the east play area it may now be possible to extend it further to the north parking and add catch basin(s). The south parking lot and drive also had a few areas where pavement was failing. Some areas of curb and sidewalk throughout the site have cracks and large chips.

SITE IMPROVEMENTS

PS-SI-4 North loop driveway and parking lot

• Remove and replace asphalt

• Concrete pavement spot replacements

• Curb and gutter spot replacements

• Minimal fine grading/ soil correction

PS-SI-5 South parking lot

• Remove and replace asphalt pavement

• Concrete pavement spot replacements

• Curb and gutter spot replacements

• Fine grading/soil correction

PS-SI-4 & 5 Benefits

• Increased safety

• Decreased maintenance issues

• Improves facility aesthetics

PRIMARY

SITE IMPROVEMENTS

East and West Playground Equipment, new curbing and top dress wood chips

PRIMARY SCHOOL FACILITY CONDITIONS

The majority of the playground equipment has reached the end of its useful life and should be replaced. The existing arch and tire swings and unity climber on the east playground should remain as they still have some life. On the West playground some of the existing structure, the tire swing and the spin cup should remain. The plastic curbing should be replaced with new concrete curbing. The wood chips should be top dressed, so it is at the designated height for safety. The new equipment would be age appropriate.

SITE IMPROVEMENTS

PS-SI-6 East Playground Upgrade

• Replace aging playground equipment with new 5-12 years equipment

• Replace plastic curbing with concrete curbing

• Top dress wood chips

• Keep arch and tire swings and unity climber

PS-SI-7 East Playground alternate surface

• Replace wood chips with poured in lace rubber safety surfacing

PS-SI-8.1 West Playground Upgrade

• Attach new play structure (5-12 years) to existing structure

• Add new spin cup

• Replace plastic curbing with concrete curbing

• Top dress wood chips

• Keep tire swings and spin cup

PS-SI-8.2 West Playground alternate surface

• Replace wood chips with poured in place rubber safety surfacing

PRIMARY SCHOOL FACILITY CONDITIONS

East Playground

West Playground

PRIMARY SCHOOL FACILITY CONDITIONS

East Playground Equipment

Proposed West Playground

Proposed

SITE IMPROVEMENTS

Softball / Kickball Field Improvements

While onsite it was observed that the east backstop is leaning and should be removed and replaced. Additional fencing to fill gaps to stop balls would make the field more user friendly. The outfield fence is heaving and shifting but still appears to function as an outfield marker that stops balls.

All fields could benefit from weed killing and a top dressing of aglime. Wetlands exist between the north and south fields so no drastic changes can occur without looking at old surveys and possibly requesting a new survey and wetland delineation.

SITE IMPROVEMENTS

• PS-SI-9 Repair and upgrade two softball fields with new fence and backstops

• Remove east backstop as it appears to not be stable

• Install new backstop and additional sideline fencing

• Top dress aglime

• Improve field with installation of benches

• Budget for future removal and replacement of outfield fence

PS-SI-9 Benefits

• Safer play area

PRIMARY SCHOOL EDUCATIONAL ADEQUACY

EDUCATIONAL ADEQUACY

RECONFIGURE

KITCHEN & RELOCATE SERVERY

The kitchen is undersized for the number of students they are serving and creating lines for serving students in a hallway is not ideal. The current average daily participation is 150 breakfast and 290 lunches over 9 lunch periods. Renovations allow expanding of the kitchen by relocating the receiving area to be more centralized within the building and creating a formalized serving area with adjacency into the cafeteria. The new formalized serving area would provide space to utilize equipment that will maintain the proper food temperature during meal service.

DEMOLISH STAGE. RELOCATE RECEIVING AND TSA, PSYCH, PE, AND SPEECH OFFICES. CREATE CHAIR STORAGE ROOM OFF THE GYMNASIUM AND RELOCATE DOUBLE DOORS.

The Primary School was not designed to provide the student services that schools are now required to provide. The school has needs for officing (shared or dedicated) various support team members such as Psychologist, Speech, TSA, as well as providing the “stop and think”, which all support District initiatives. Providing dedicated space for these programs allows the student to engage with the staff or service with dignity. The existing stage space is underutilized as it is being used for storage. The stage would be converted to create these small rooms for officing and student services. A chair storage room would be created on the south end of the gymnasium.

PRIMARY

MEDIA CENTER RENOVATION

Media Centers have evolved over the years and have become a place for many resources beyond just books and research. The desire is to renovate the space to increase flexibility to best serve the versatile needs of media center and large group work.

DIVIDE READING ROOM INTO THREE SEPARATE TEACHING SPACES FOR ACOUSTICAL SEPARATION

Reading Intervention is provided with one staff member and a small group of 4-5 students. The scope includes formalizing the current situation of cubicle partitions into walls and doors with teaching surfaces (marker- and tack- boards) to provide acoustical privacy to allow student focus and enhance hearing/audible connections. Three small group rooms would be created in the current reading intervention space. These group rooms could support other small group activities outside of reading intervention. The space would provide flexibility for the building because it currently lacks small group instructional areas.

INSTALL PERMANENT SHEETROCK WALLS IN KINDERGARTEN AREA

In the Kindergarten classrooms, the walls separating the spaces, and the hallway are demountable wall assemblies. These walls are well past their useful lives. To enhance acoustical separation and increase durability, these demountable walls were requested to be replaced with permanent walls constructed to the underside of the roof. This would require replacement of the casework and teaching surfaces (marker- and tack- boards) that are currently located on the demountable walls.

NEW FLEXIBLE CLASSROOM FURNITURE (50%)

Most classrooms have outdated furniture or do not have sufficient flexible furniture available that will attract students to those areas. Comfortable and inviting furniture has been studied to be as important to the spaces as the lighting, HVAC, and spaces themselves.

PRIMARY