Construction Communications Gold Medal Edition - Southern California's The Mark

Page 1


A “relationship company” best

each project, according to John

craftmanship. The company provid-

scope of work on the project and

describes Orange County Plastering

Autry, project manager for the com-

ed interior framing, finishing gyp-

performs very well. “OCP is one of

Company Inc. (OCP).

pany. “We find out what our clients’

sum board and exterior framing sub-

Bayley’s key subcontractors,” he

Founded by Robert Smith in 1995

specific needs are on that particular

strate for the panel system and brick

says. “We look forward to future

primarily as a drywall lath and plas-

project, such as schedule concerns,

veneer. With the help of the project

projects with them.”

tering company, OCP has evolved

budget, etc.,” he says. “We then try

and design team, OCP project man-

Maintaining good relationships

and branched out to offer other serv-

to meet their needs. We communi-

ager John Autry says, “The general

with its subcontractors is also very

ices. The Costa Mesa-based compa-

cate with our clients on a regular

contractor maintained a team effort

important to OCP, and plenty of

ny offers drywall, exterior insulation

basis, and if a concern arises, we

throughout the project, and this

one-on-one contact makes that

finish systems (EIFS), exterior wall

address it as soon as possible.

made it a success for the company.”

possible. “We always bring them

systems, fireproofing, glass fiber

“We are a schedule-driven com-

Working through challenging proj-

into our office to go over the

reinforced gypsum, light-gauge steel

pany that can provide quality service

ects is nothing new for the company.

project in detail so both parties are

framing, metal lath/furring, plaster-

at a competitive price,” he contin-

For example, the Del Amo Mall proj-

familiar with critical path activi-

ing, and interior and exterior stucco.

ues. “We are a problem-solving

ect in Torrance presented schedule

ties,” says Autry.

The company has met with success

company that has the ‘do what it

and budget problems. “It required a

The area’s housing market is

that has enabled it to branch out both

takes to get it done’ philosophy from

hands-on approach by all parties

slowing down, he adds, and the

in terms of services and the scope of

the top down.”

working together to resolve the many

commercial side of construction is

its projects for general contractors in

OCP employs a highly experi-

issues that occurred during the course

also feeling the effects. OCP, how-

Southern California. OCP works on

enced office and field staff with crews

of the project to meet the scheduled

ever, is weathering the storm.

projects ranging from condominiums

that work exclusively in their areas of

opening date,” says Autry. The com-

“Our goal is to work closely with

and theaters to hotels and assisted liv-

expertise such as exterior framing or

pany’s longstanding relationship with

our customers, maintaining strong

ing facilities. Its clients extend from

lath and plaster operations. “We also

the project’s general contractor,

relationships so we are their pre-

the San Diego area to Bakersfield.

have special teams that do only fire-

Bayley Construction, proved very

ferred subcontractor.”

Among its more notable jobs are the

proofing,” says Autry. “We also can

valuable on the project.

EIFS it provided to Ocean Villas, the

provide value engineering on many of

Indeed, Bayley and OCP have

establishes with general contractors,

lath and plastering on Woodbury

the scopes we perform to save our

worked together on 10 to 15 projects

subcontractors, owners and more

Town Center, and the drywall for the

clients money.”

ranging in price from $50,000 to

will help ensure a bright future for the company.

Riverside Community Access Center.

OCP’s work on The Mark condo-

$10 million, says Wayne Mathies.

OCP prides itself on providing a

miniums displayed these talents and

According to Mathies, OCP always

high level of craftsmanship throughout

was exercised with a high level of

understands the importance of its

These relationships that OCP

— Corporate Profile

• Metal Stud Framing • Drywall • Fireproofing • Lath & Plaster • • Exterior Insulation Finish Systems (EIFS) • Exterior Wall Systems • Glass Fiber Reinforced Gypsum • • Light-gauge Steel Framing •Interior & Exterior Stucco • Orange County Plastering Company Inc. 3191-B1 Airport Loop Dr. • Costa Mesa, CA 92626 714-957-1971 • fax: 714-957-0958 • www.ocplastering.com


Facts & Figures Owner/Developer: Douglas Wilson Companies Type of Project: A new mixed-use development Size: 360,630 square feet Cost: $90 million (construction costs) Construction Time: September 2004 - May 2007 The Need: A mixed-use complex with upscale residential and retail components as part of the area’s redevelopment The Challenge: Dealing with structural issues associated with the project’s location between two earthquake fault lines, and handling rising materials costs

TEAM MEMBERS

Martinez + Cutri Architects Executive Architect/ Architect of Record Shears Adkins Architects, LLC Design Architect

San Diego, California

The Mark

Hensel Phelps Construction Co. General Contractor

In an area once dominated by vacant lots and warehouses, The

Bergen + Brasier Cabinetry

Mark stands as a shining tower of

Orange County Plastering Company Inc. Lath, Plaster & Drywall Subcontractor

modern architecture that is redefining the skyline in downtown San Diego. The Mark, with its 32-story tower, is the tallest building in the city’s thriving East Village. Encompassing a full city block, the development includes a mix of townhouses, condominiums and retail space. The primary structure in the complex is the gleaming glass tower that consists of 233 condominiums, which range from one-bedroom flats to three-bedroom penthouses and include high-end interior finishes such as European cabinetry, stone counters, stainless steel appliances and custom plumbing fixtures. Connected to the tower is a two-level

Visit our website: www.constructionreviews.com to view additional Gold Medal Award-winning projects.

wing with street-level retail spaces and

single-level

condominiums

above, as well as 11 two-story, brick townhouses. Several levels of belowgrade parking were also included in the project. Photos courtesy of Martinez + Cutri Architects

www.constructionreviews.com

southern california edition

3


The tower’s composition is mod-

Douglas Wilson Companies, the

The architectural expression of

Chris Shears, AIA, president of

ern cubism with the base reminis-

project’s owner/developer, bought

the development accentuates the

Shears Adkins Architects, LLC, the

cent of the neighborhood’s former

the land and built the project from

emerging lifestyle of downtown

project’s design architect, said the

warehouses. Consisting of a rectan-

the ground up, clearing what had

San Diego through the use of

building’s custom-designed, glass-

gular core with angled and curved

once been a city block occupied by

cutting-edge materials such as

and-metal skin is one aspect that

cantilevers extending to multiple

a dilapidated warehouse and a

aluminum, painted metal panels,

distinguishes it from other high-rise

heights, the tower has a modern,

liquor store. The company, which

and glass to give the building’s

structures. “The building is innova-

multifaceted appearance. The struc-

completed an 11-story condomini-

skin residential scale and rich-

tive in that it sets a new standard for

tural concrete spine is exposed in

um loft project called Parkloft just

ness, according to Martinez +

residential design and construction

strategic spots, while the lower

south of The Mark in 2002, sought

Cutri Architects.

in downtown San Diego,” he said.

floors are faced with brick to echo

to diversify its offerings in the neigh-

nearby historic buildings.

borhood with a contemporary,

An open, loft-inspired plan influ-

upscale high-rise development.

ences the townhouses, which feature

“[The Mark’s] sleek design has

street-side entries and roof terraces.

become the architectural bench-

Set back from the street to maintain

mark for the entire redevelopment

the view corridor and minimize shad-

area, second only to the impact of

ows, the complex’s center features a

the three-year-old Petco Park major

common gathering space with a lin-

league baseball park two blocks

ear pool and gently sloping lawn.

south of The Mark,” said Douglas

“This urban oasis is secluded from the

Wilson, CEO of Douglas Wilson

city noise and activity,” said David

Companies. The project adds high-

Priest, AIA, principal for Martinez +

quality design and construction

Cutri Architects, the project’s execu-

value to the for-sale housing market

tive architect/architect of record.

in the urban neighborhood.

continued on page 7

Photos courtesy of Martinez + Cutri Architects

4

southern california edition

gold medal award winner


Photo courtesy of Martinez + Cutri Architects

www.constructionreviews.com

southern california edition

5


The Owner’s Perspective with Douglas Wilson, CEO, Douglas Wilson Companies

Q: Why did you choose to purchase the development? Will the company make any changes to it? DW: Douglas Wilson Companies built the project from the ground up, purchasing and clearing the city block that had been occupied by a dilapidated warehouse building and liquor store. The company had completed a highly successful 11-story condominium loft project, Parkloft, immediately south of The Mark in 2002, and wanted to diversify its offerings in that important urban neighborhood with a contemporary, upscale high-rise product. Q: What is the most unique feature of the facility? DW: Its full-block scale and diversity in design and uses — urban condominiums and two-level penthouse in a glass-and-steel tower, two-story red brick and stucco townhomes, and several commercial-retail spaces surrounding the perimeter of the full city block. Its sleek design has become the architectural benchmark for the entire redevelopment area, second only to the impact of the three-year-old Petco Park major league baseball park two blocks south of The Mark. Q: What else would you like to mention? DW: The Mark is a strong and highly visible component to the emerging contemporary theme of downtown San Diego’s East Village neighborhood, adding high-quality design and construction value to the for-sale housing market in this important urban neighborhood. The Mark is an ultra-modern urban residence that honestly reflects its time and place.

Photo courtesy of Bob Ross Photography

450 B St., #1900 San Diego, CA 92101 619-641-1141


continued from page 4

The building’s look could easily have been corrupted by all the systems competing for expression on the exterior, according to Priest, including the mechanical venting, exterior

maintenance,

elevator

penthouse, waterproofing details and building lighting. “In almost all cases, the team found ways to provide the necessary functions with a corresponding detail that complements the overall design,” he said. For example, mechanical venting for the condominiums is hidden behind an aluminum slab edge cover that incorporates a continuous vent slot. “The detail fits into the aesthetic of the tower while providing flexibility, given [that] the vent duct can be located anywhere along the continuous slot.” The project team faced several challenges during construction, especially with structural issues due to the development’s location between two earthquake fault lines. An internal concrete frame allowed reduced perimeter column locations to accommodate the special situation. Vertically stacking several different types of units throughout the building also presented unique challenges, said Shears. Escalating costs of reinforcing steel posed another dilemma at the project’s start, according to Rod Hammett, project manager for Hensel Phelps Construction Co., the project’s general contractor. “The owner authorized us to pre-purchase the rebar in order to lock Photo courtesy of Martinez + Cutri Architects

the then-current pricing, which required a substantial initial cost

Hammett. “When cost issues came

substrate for the panel system and

of the project. Bergen + Brasier

outlay by them,” he said. “This paid

up in design completion, we looked

brick veneer on The Mark. “The

worked closely with the owner/

off well in the long run as steel

for areas to trade costs from one

general contractor maintained a

developer to ensure the budget was

prices remained unstable for the

budget in order to enhance anoth-

team effort throughout the project,

met, according to Bob White, one

duration of the concrete schedule

er where the owner’s best interests

and this made it a success for the

of the company’s founders. “[We]

on the project.

were represented.”

company,” said John Autry, project

got involved early on in the design

manager for OCP.

process and thereby eliminated

“Hensel Phelps was contracted

Providing a high level of crafts-

prior to design completion, so we

manship on the project was a must

were very involved in design meet-

for

Having been part of The Mark

construction errors and delays,” he

Plastering

was also a highlight for Bergen +

said. “We were directly involved

ings to ensure that the detailing

Company Inc. (OCP), which provid-

Brasier, a kitchen design company

with the project architect in solving

remained

and

ed interior framing, finished gyp-

and supplier of high-end cabinetry

ADA [Americans with Disabilities

schedule constraints,” continued

sum board and exterior framing

that served as a key team member

Act] constraints while maintaining

within

budget

Orange

County

continued on page 11

www.constructionreviews.com

southern california edition

7


The Architects’ Perspective with David Priest, AIA, Principal , Martinez + Cutri Architects and Chris Shears, AIA, President, Shears Adkins Architects, LLC

Q: What were the greatest challenges encountered on this project, either from your firm’s point of view or as a project team? DP: The Mark has a sleek, sophisticated style with large areas of smooth metal panels and aluminum window frames that hold high-performance glass. It would be easy to “corrupt” the look of the building with all of the systems that compete for expression on the exterior; examples would include the mechanical venting, exterior maintenance, elevator penthouse, waterproofing details and building lighting. In almost all cases, the team found ways to provide the necessary functions by creating a detail that complements the overall design.

Martinez + Cutri Architects 750 B St., #1700 • San Diego, CA 92101 • 619-233-4857 • fax: 619-233-7417 • dpriest@mc-architects.com

Q: What were some of the drivers behind the design? What design materials or concepts were used? CS: The Mark is textbook urbanism: a project [that] actively addresses the street and the context of the East Village. The owner’s objective was to develop a building of integrity [that] would endure in terms of quality of design and quality of construction. The building is innovative in that it sets a new standard for residential design and construction in downtown San Diego. The building’s custom-designed skin of metal and glass distinguishes it from other high-rise buildings. Q: What were the greatest challenges encountered on this project, either from your firm’s point of view or as a project team? CS: Challenges included the structural issues associated with a location between two earthquake fault lines and the subsequent internal concrete frame, which allowed reducing perimeter column locations. [There were also] challenges associated with stacking a number of different unit types vertically through the building. [And there were also] the normal challenges in the Center City Development Corporation (CCDC) design review process when you are proposing a contemporary design solution.

Shears Adkins Architects, LLC 1855 Blake St., #150 • Denver, CO 80202 • 303-436-9551 • fax: 303-296-0946 • cshears@shearsadkins.com


Dependability is the cornerstone on

with styles from traditional to contem-

which Bergen + Brasier was founded.

porary. All of Bergen + Brasier’s prod-

The high-end kitchen design company

ucts are “green certified” and also meet

lends its expertise to developers of

design standards set by the Americans

upscale condominium projects in the

with Disabilities Act (ADA).

areas of project design, value engineer-

With multitudes of projects striving for

ing, marketing, project coordination and

green certification these days, Bergen +

supply of high-end cabinetry.

Brasier is poised to deliver. “This has been

“We are dependable because we work

very easy for us to satisfy as our supplying

hard,” says Mary White, one of the

factories have green certification,” says

company’s founders. “We work as a

Mary White. “There are only a handful of

team here at Bergen + Brasier, and we

manufacturers that are currently green, so

are more than willing to put in the time

that gives us an advantage.”

it takes to get a job done well. Giving

The demand for good European

good, solid service to our customers is

design is another recent phenomenon in

what we take the most pride in.”

the industry, and Bergen + Brasier is uniquely suited to answer those

Meeting clients’ every need

demands as well. “The standard, tradi-

Bob and Mary White founded the

tional kitchen layout is not what is

company in a garage in 1988, establishing

being requested,” says Mary White.

it as a custom woodworking business. “By

“Therefore, we are on the forefront in

2001 we had refined our business to pro-

supplying the design sophistication

vide our clientele with the flexibility of a

being called for by the U.S. market.”

Bergen + Brasier 4330 Morena Blvd., Ste. B • San Diego, CA 92117-4324 858-483-1605 • fax: 858-483-8821

small shop while maintaining the quality of a German factory and high-end cabi-

The hallmarks of excellence

netry,” says Mary White. “We also grew

Working closely with a client from

Mary White. “We guarantee that when

one of our projects encountered discrep-

into a company that provides design

the project’s beginning through its com-

we have a delivery on schedule, it will

ancies between plans and build-out of

resources, drawing from an international

pletion is one of Bergen + Brasier’s hall-

arrive as promised.This is uncustomary in

wall lengths. We were quickly and easily

cadre. Because we have the precision of

marks. The first step is having a client

cabinetry supply businesses — they have

able to provide solutions that did not

four substantial manufacturing facilities

meet one on one with the owners or one

typically been known to deliver late.”

incur additional cost or additional time to

behind us, we have gained an excellent

of the full-time design specialists. “We

A project’s budget constraints are

the developer.” Flooding caused extensive

record of dependability.”

desire to be one part of the project team,

also never far from the team’s mind.

damage to another project, but the

Bergen + Brasier is an authorized

and we work well with other primaries

“We’re able to be innovative and, at the

company shipped replacement parts in

dealer of Studio Becker Cabinetry, a line

involved on a project — be they archi-

same time, budget conscious,” says

a timely manner, so the construction

of refined German cabinetry, and Rutt

tects, interior designers or contractors,”

Mary White. “We achieve this by get-

schedule wasn’t affected.

Handcrafted Cabinetry, an American

says Mary White. “Our projects are fully

ting involved early in the design phase

As further proof of its abilities,

line of custom cabinetry. The Studio

documented, which eases communica-

of the project.” The company’s two

Bergen + Brasier’s cabinetry work in the

Becker line strikes an unparalleled bal-

tion with contractors and eliminates

decades of design experience with

sales office of the Seahaus project in La

ance between aesthetics and quality,

surprises. Our office uses advanced

kitchens, bathrooms, wardrobes and

Jolla led to it being named a finalist in

offering made-to-order furniture in

technology to provide the best, quickest

custom built-ins plays a large part in

the Best Sales Office over 1,500 square

styles from traditional to modern. The

and easiest documentation.”

that capability.

feet in the 2004 Sales, Advertising and

Rutt line is built to order and can be

On-time delivery is another crucial

Bergen + Brasier is no stranger to deal-

Marketing (SAM) Awards sponsored

designed for any living space, blending

component of any Bergen + Brasier job.

ing with challenges. “We are extremely

by the San Diego County Building

the ingenuity of modern technology

“To the developer, time is money,” says

flexible,” says Mary White. “For example,

Industry Association. The project was also a finalist in the Best Residential Urban Design category. Bergen + Brasier — dependability you can count on. — Corporate Profile


The General Contractor’s Perspective with Rod Hammett, Project Manager, Hensel Phelps Construction Co. Q: What is the most unique or important feature of the facility (or of the design/construction process)? RH: This building is unique in that the exterior skin of the tower employs custom glazing and metal panels in contrast with typical projects of its nature that use plaster or some other less expensive finish. The tower is also articulated with stepped elevations and projections that make it very architecturally pleasing versus the standard straight box. Q: What is the most innovative aspect of the project (or of the design/construction process)? What could other owners learn from for their future projects? RH: Employ the contractor and key subcontractors early in the design process so that constructability and economy can be discussed before key design elements are set too far in motion. Q: What were the greatest challenges encountered on this project and how, specifically, did you overcome them? RH: Cost escalation on reinforcing steel was a huge risk at the project start. The owner authorized us to pre-purchase the rebar in order to lock the then-current pricing, which required a substantial initial cost outlay by them. This paid off well in the long run as steel prices remained unstable for the duration of the concrete schedule on the project. Q: How did you work with the architect and owner to save time and/or money on the project? How was value engineering applied to your responsibility? RH: Hensel Phelps was contracted prior to design completion, so we were very involved in design meetings to ensure that the detailing remained within budget and schedule constraints. When cost issues came up in design completion, we looked for areas to trade costs from one budget in order to enhance another where the owner’s best interests were represented. Q: What were some of the lessons learned from this project? A: Limit the amount of homebuyer upgrades/options offered. In high-rise condominium construction, the schedule does not allow the contractor and subs to slow in order to accommodate customization of units. Choices of colors and limited upgrade options can enhance the homebuyer experience without making construction flow suffer.

18850 Von Karman Ave., Ste. 100 Irvine, CA 92612 949-852-0111 fax: 949-852-0218 rhammett@henselphelps.com


continued from page 7

excellent design flow. We are extremely flexible, and for this reason we were able to provide solutions to issues [that] did not incur additional cost or additional time [for] the developer.” A high-performance construction team enabled each member to work at peak levels, according to Priest. “We constantly strived to maintain the high level of design clarity and integrity expected by the developer and initiated by the design architect,” he said. Shears concurred, adding that a great project must have a dedicated project team. “In this case,” he said, “the architects had a client who had high standards and demanded excellence.” And the project team delivered. The Mark was completed in May 2007, providing a key component in the neighborhood’s redevelopment. — Andrea Blum Photos courtesy of Martinez + Cutri Architects

www.constructionreviews.com

southern california edition

11


24445 Northwestern Hwy. Ste. 218 • Southfield, MI 48075 • 248-945-4700 • fax: 248-945-4701 • www.constructionreviews.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.