HACKING COVENTRY_FINAL RESOLUTION

Page 1

HACKING // COVENTRY DEVONNE COLL // 08085190



CONTENTS 5.1 [ RE_FLECT, RE_FORM, RE_POSITION ]

RESILIENT COVENTRY 01

1.0 // INTRODUCTION

09

2.0 // LITERATURE REVIEW

23

3.0 // CONNECTIVE CONTENT

33

4.0 // THESIS QUESTION

5.2 FUTURE FUNCTION

HACKING COVENTRY 45

5.0 // PROGRAMMATIC DEVELOPMENT

73

6.0 // THE SITE

93

7.0 // PROGRAMME FIX

109

8.0 // DESIGN DEVELOPMENT

163

9.0 // DEVELOPING RESOLUTION

5.3 RESOLUTION

HACKING COVENTRY 189

10.0 // PROJECT RE_CAP

207

11.0 // DESIGN DEVELOPMENT

225

12.0 // FINAL SCHEME DRAWINGS

263

13.0 // TECHNICAL RESOLUTION

303

14.0 // FINAL RESOLUTION

323

15.0 // BIBLIOGRAPHY

CONTENTS // i


188 // RESOLUTION


10.0 // PROJECT RE_CAP HEADING TEXT

INTRODUCTION // 189


CENTRALISED CONTROL DECREASES RATE OF ADVANCEMENT TRAUMA IS A CATALYST FOR CHANGE + ADVANCEMENT

DECENTRALISED CONTROL INCREASES RATE OF ADVANCEMENT

CREATE SYSTEM WHICH DETECTS WEAKNESSES...

190 // RESOLUTION

+ OVERCOMES THEM TO PRODUCE A MORE RESILIENT CITY


HACKING COVENTRY // SYNOPSIS Hacking Coventry is a civic hub and infrastructural interjection that aims to provide residents of Coventry with a new type of public realm space, which they are able to ‘hack’ and continuously reprogramme to suit their changing needs. Based upon the basic programmes of sports, event and marketplace, the scheme’s strategy employs methods so that these programmes may become interchangeable with each other, and therefore the programme can be chosen by the user. This is achieved through the use of time based grid systems incorporating all programmes, and the strategic use of surfacing, colour and materiality throughout. The scheme is situated upon Junction 6 of the Ring Road a seemingly inappropriate site, yet is the key node separating the inner and outer city centre, separating residents from the city. Challenging this fixture whose only current purpose if for mobility, aims to hack this site and reprogramme what is it used for,, turning this ‘non-place’ into a significant, social, cultural and dynamic place for Coventry’s residents. The notion of a a fluctual programme aims to provide a public space with the movement away from centralised control to decentralised. The underlying concept stems from Coventry’s history of trauma; trauma being seen as a catalyst for change with the rate of advancement increased by decentralised control. For a city used to trauma, a system is needed to detect weaknesses in order to produce a more resilient and adaptive city. Cities are attempting to do this, through the use of ‘smart’ systems; increasingly these are more based upon economics and energy saving controlled by governments rather than citizens. A people-based smart system is needed to respond to the everchanging needs of the citizens. Focusing on social and cultural aspects, the scheme aims to meet this response by creating a tool in which people can create their own environment, creating an more socially and culturally adaptive Coventry.

10.0 PROJECT RE_CAP // 191


COMMUNITY EMPOWERMENT? HYPER-LOCAL CONTENT NORTH WEST “The thing is when you hear them [troublemakers] outside causing trouble you don’t want to go out because you don’t know what will happen.” Female, North West focus group “In Canley they vandalise the buses and also break some of the windows on the buses.” Male, North West focus group

DAIMLER GREEN RESIDENT’S ASSOCIATION

“For me a lot of other issues are related to anti-social behaviour, so it should be quite high on the agenda.” Female, North West focus group

COUNDOUN AGE CONCERN WATCH MIDWEEK 50+

ST CATHERINE’S CHURCH

As an initial starting point, I recorded the organisations that are part of the Coventry Community Empowerment Network. This aims to create projects with specific aims of benefitting specific communities depending on what their most crucial issues are. Although it claims to be community led, it is still a council affiliated network, so any proposals made must be decided by the city council. This demonstrates that communities in Coventry have key ideas of how they could improve the city, are willing to make changes, but at present there is no successful strategy in place through which real community decided changes can be made.

Community development group regarding unemployment and crime “To look outside today and see the difference in people’s confidence, in their ability to walk along a main road without the fear of crime, to see the diverse community that we live in.”

GRAPEVINE

WHITEFRIARS HOUSING

Using information found here and other community projects, helped me to understand the types of community spaces required in the city. Through a process, this was narrowed down to sport, market and event as the key drivers of the scheme.

Non-profit housing and regeneration organisation that owns and manages approximately 17,000 homes across Coventry “Some people want to take pride in the area that they live in, and need to know how to help themselves.”

SOUTH “I think hate crime is on the up. With new people moving into the area there still is the fear of the unknown. The connection between the new communities and the existing communities isn’t that strong.” Male, Southern area focus group “I know [hate crime] does exist in our area and I understand its an increasing problem. So its something that needs to be considered very carefully.” Female, Southern area focus group

FRIENDS OF CANLEY FORD


SANATAN DHARM HINDU TEMPLE SOCIETY

BATRA

EDGWICK PARK SPORTS PROJECT

NORTH EAST “We have a park by us and you do get a congregation who are taking and dealing (drugs)” Female, North-East “There is a lot of illegal parking over the pavements, but that is generally the case across the city.” Female, North-East

BROAD STREET MEETING HALL New community sports facilities

PARADISE RESIDENT’S ASSOCIATION

“I asked the kids why they didn’t play in the park behind our house. It turned out they did play football there sometimes on Sundays, but only in a big group. But at other times they were frightened of the drugs, gangs and boozers. So they played in the street.”

“Where I live there are sixty odd flats and only ten parking spaces.” Male, North-East “You get car crime in spates. They’ll come into an area and vandalise the cars.” Male, North-East

STOKE HEATH COMMUNITY CENTRE

MINORITIES OF EUROPE

OSABA WOMEN’S CENTRE

Support group for minority communities

SINGER RESIDENT’S GROUP

“People often lead parallel lives, living in a street without knowing each other. This can lead to fear fear of the other people you don’t understand.”

HOMELESS SHELTER

SOMALIAN SUPPORT GROUP

TEXT

SKY BLUE RESIDENT’S ASSOCIATION

QUINTON PARK MANSFIELD MEDICAL CENTRE ACTION FOR CHEYLESMORE

PEOPLE’S PLACE STOKE ALDERMOOR RESIDENT’S ASSOCIATION ST. CATHERINES RESIDENT’S ASSOCIATION Young People’s Support Group

“This area is designated as a place the authorities don’t have to worry about – its not one of the deprived areas. But there are pockets of deprivation within Cheylesmore, especially amongst the elderly. You go from the lowest Council Tax band to the second highest, sometimes within a street

“People’s Place never gives up on a youngster. If bad behaviour continues, then People’s Place is doing something wrong. Generally, when the problem is bottomed out, bad behaviour stops.”

WILLENHALL ASSOCIATION

AFRICAN WELFARE ASSOCIATION


SPORT SPACES

EVENT SPACES

MARKET SPACES

SUPPORTING SPACES

FOOTBALL PITCH

STAGE

MARKET STALLS

ENTRANCE

HOCKEY PITCH

AUDITORIUM SEATING

MARKET STORAGE

COMMUNITY HUB

CRICKET

BACKSTAGE

LOADING BAY

RESTAURANT

TENNIS COURTS

LARGE SCALE SCREEN

MANAGEMENT OFFICES

BADMINTON COURTS

DRESSING ROOMS

CAR PARKING

NETBALL COURTS

REHEARSAL STUDIO

INDOOR STREET CIRCULATION

BASKETBALL COURTS

LIGHTING CONTROL

JOINT SERVICE AREAS

9 HOLE GOLF COURSE

SOUND CONTROL

SKI JUMP

BOX OFFICE

FIRST AID

BAR

PHYSIO SUITE

EVENT STORAGE

CHANGING ROOMS FITNESS STUDIO EQUIPMENT STORAGE

FOOTBALL PITCH

TENNIS COURTS

PHYSIO SUITE

EQUIPMENT STORAGE

HOCKEY PITCH

BADMINTON COURTS

CHANGING ROOMS

LIGHTING CONTROL

CRICKET

NETBALL COURTS

FITNESS STUDIO

SOUND CONTROL

TENNIS COURTS

BASKETBALL COURTS

EVENT STORAGE

MARKET STALLS

STAGE

DRESSING ROOMS

LOADING BAY

AUDITORIUM SEATING

REHEARSAL STUDIO

CAR PARKING

BACKSTAGE

EXTERNAL INTERCHANGEABLE ACTIVITY PROGRAMMES

194 // RESOLUTION

INTERNAL INTERCHANGEABLE ACTIVITY PROGRAMMES

INTERCHANGEABLE SUPPORTING PROGRAMMES

JOINT SERVICE AREAS

INTERCHANGEABLE SERVICE PROGRAMMES


FOOTBALL PITCHES

9 HOLE GOLF COURSE

HOCKEY PITCHES

SKI JUMP

CRICKET FOOTBALL PITCHES HOCKEY PITCHES CRICKET MARKET STALLS MARKET STORAGE

LARGE SCALE 9 HOLE GOLF SCREEN COURSE

LOADING BAY

MARKET STORAGE

CAR PARKING

COMMUNITY HUB

BOX OFFICE BAR MANAGEMENT OFFICES

INDOOR COMMUNITY STREET HUB CIRCULATION

LARGE SCALE LOADING BAY SCREEN

MARKET STALLS

MANAGEMENT OFFICES

RESTAURANT ENTRANCE

SKI JUMP

CAR PARKING

ENTRANCE

BOX OFFICE BAR

RESTAURANT

TENNIS COURTS BADMINTON COURTS NETBALL COURTS TENNIS COURTS BASKETBALL BADMINTON COURTS COURTS NETBALL COURTS

STAGE INDOOR STREET CIRCULATION AUDITORIUM SEATING BACKSTAGE STAGE

LIGHTING CONTROL SOUND CONTROL LIGHTING CONTROL JOINT SERVICE AREAS SOUND CONTROL

AUDITORIUM SEATING BACKSTAGE

EVENT STORAGE JOINT SERVICE EQUIPMENT AREAS STORAGE

BASKETBALL COURTS

EVENT STORAGE FIRST AID

CHANGING ROOMS

FITNESS STUDIO

PHYSIO SUITE

DRESSING ROOMS

REHEARSAL STUDIO

FIRST AID

PHYSIO SUITE

TEXT

EQUIPMENT STORAGE

CHANGING ROOMS

FITNESS STUDIO

DRESSING ROOMS

REHEARSAL STUDIO

INITIAL PROGRAMME SPECIFICATION + ORGANISATION To determine the types of spaces the scheme needed, I split the programme specification into four categories: sport, event, market and supporting spaces. I then began to group together the spaces which can become interchangeable, based upon internal and external activities, supporting spaces and servicing, how these could possibly be organised. These groups and organisation have changed as the scheme developed, but this initial process along with site analysis allowed me to produce a strategy for programme organisation across the site.

10.0 PROJECT RE_CAP // 195


RING ROAD, JUNCTION 6

CAR PARK, JUNCTION, GREEN SPACE

THE NON-PLACE, WITHOUT SIGNIFICANCE

THE NON-PLACE TRANSFORMED INTO A PLACE

196 // RESOLUTION


CAR PARK

RING ROAD

GREEN SPACE

THE SITE // RECONNECTION In our group project, Data Dérive, we investigated areas within the city that demonstrated the most flux and stasis of land use throughout history. After mapping a large area of the city, we were able to locate 19 sites that had the most extreme difference between flux and stasis, and so, we considered as points of interest and potential opportunity . The ring road in Coventry acts as a physical barrier separating the city centre from the wider communities, where most of the citizens live. I wanted to find a site along the periphery of the ring road, so that my proposal could act as a bridging point between the inner and outer city centre. The chosen site, includes a derelict car park to the South (due to become offices through the Friargate future development), the ring road junction 6 roundabout, with a pedestrian walkway underneath, leading into Greyfriars Green, a large area of green public space. The ring road junction is normally considered as an unusable building space. However, in order to connect the inner and outer city I will need to infiltrate the entire junction. The ring road could be considered a ‘non-place’, a place of transience that does not hold enough significance for it to be considered a ‘place’. People use the place constantly but only as a route of mobility, there is no other specific activity here. In using this junction as my site, it also relates back to the idea of citizens hacking the city. The scheme will allow the public to constantly reprogramme this non-place, transforming it into a place of significance. 10.0 PROJECT RE_CAP // 197


PUBLIC WALKWAY TO ENTRANCE

LANDSCA

INTERNAL THROUGHWAY EXTENSION OF STREET

CAR PARKING / MARKET / EXTERNAL PITCHES

COMMUNITY HUB

LANDSCAPED ROOF

PUBLIC WALKWAY TO ENTRANCE

S FOR

CAR PARKING / MARKET / EXTERNAL PITCHES


APED ROOF

DESIGN STRATEGY + FORM Using the ideas of linking across the ring road junction and creating an extension of the green space at Greyfriers Green, I essentially wanted to create two large adjoining spaces with ramped landscaped roofs creating a new open public space, with activities located within the building.

ENTRANCE + ORGANISATION

SERVICE AND SUPPORTING AREAS R MIXED USE SPACES

The first ramp extends directly from the green, and will extend over the top of the road still allowing cars to pass underneath it. The second ramp will extend from the car park to the west of the site and the two ramps will meet in the middle of the junction roundabout.

AREAS FOR MIXED SPORT AND EVENT SPACES

This initial form will create a direct and obvious bridging link across the junction, and the ramped landscapes aim to encourage people to use this new public space and cross the boundary between the inner and outer city. From my programme specification and contextual site analysis I constructed a basic site strategy in terms of programme organisation across the site. The car park to the west will consist of mostly external areas for adaptable market stalls, sports pitches and car parking. The landscaped roof will also extend to this space; access into the main building will be via a walkway on the roof that meets stair access when meeting the building, and through an indoor street space that extends throughout the entire scheme. Situated in the main building are sports and event spaces which are interchangeable programmes, with joint service areas, as well as a community hub and management area.

10.0 PROJECT RE_CAP // 199


OVERLAPPING THE ORIGINAL DIMENSIONS DOES NOT WORK

SPACING THE PARKING AND MARKET STALLS SO THAT THEIR OVERALL DISTANCE IS EQUAL

WIDENING THE MARKET STALLS TO FIT A CAR PARKING SPACE OF 2400MM

LENGTHENING THE CAR PARKING SPACE TO FIT THE DEPTH OF TWO MARKET STALLS

200 // RESOLUTION


CAR PARKING + MARKET STALLS WITH OVERALL SAME DIMENSIONS

HOCKEY + FOOTBALL PITCHES, TENNIS COURTS, REQUIRED RUNOFF BOUNDARIES

ADAPTING THE RUNOFF LINES TO THE OVERALL GRID

EXTERNAL FLEXIBLE GRID PARAMETERS // TIME BASED PROGRAMMES The most efficient way to organise the interchangeable programmes was to use a time - based grid system. I began with the simplest, combining the market stalls and car parking spaces. These have different dimensions and cannot just be overlapped - the dimensions of each one must be reworked to create a grid adjusted to suit both market stalls and car parking. A standard market stall measurement is 3m x 2m, whereas a car parking space is 2.4m x 4.8m. Initially I spaced each set of grids out evenly, so that their overall dimensions were equal. Then I widened the 2m width of the market stall to fit a 2.4m car parking space, then lengthened the depth of a carparking space to 6m so that it can fit two market stall spaces. Sports pitch markings were then also applied to the grids, and internal grids for the event and sport spaces were also configured. 10.0 PROJECT RE_CAP // 201


202 // RESOLUTION


SPATIALISING PROGRAMME // BASIC ORGANISATION This shows the development of the basic organisation, with the added arrangement of seating and supporting spaces in the event and sport space, and the cores for circulation as well as the addition of a second floor, which will be used as an outdoor event and sport space. The indoor street needs to be developed much more. This is the main through route for the entire scheme and should be a place of constant activity, and so the programme should be harnessed here as well. Market spaces could be incorporated here, as well as social spaces such as cafes or bars. I think that the programmes within this space could act as plugin spaces or pop-up shops to provide adaptable forms of socialising and entertainment that people can appropriate as they use this link between the outer and inner city. The landscape also needs to be more developed to have the same degree of adaptivity as the rest of the scheme. This could possibly be achieved through the use of surfacing to create different areas for different activities.

10.0 PROJECT RE_CAP // 203


204 // RESOLUTION


HEADING TEXT

1:1000 DEVELOPMENTAL MASSING MODEL

10.0 PROJECT RE_CAP // 205


206 // RESOLUTION


11.0 // DESIGN DEVELOPMENT HEADING TEXT

INTRODUCTION // 207


“ANYONE WHO TAKES AN INTEREST IN THE SECRET WORKINGS OF ANY CLOSED SYSTEM HAS COME TO BE KNOWN AS A ‘HACKER.’ THESE HACKERS OF THE NEW HIVE ANONYMOUSLY CREATE SOCIAL LOCATIONS OR RECLAIM OLD ONES, REBELLING AGAINST AN URBAN LANDSCAPE THAT TILTS THE BALANCE OF EMPOWERMENT FROM THE PRIVATE CITIZEN TO PRIVATE ENTERPRISE. SPACE HACKED AND APPROPRIATED BECOMES AN EXTENSION OF THE PRIVATE AND INTIMATE, A PLAYGROUND...A PLACE FOR SHARING, TRANSCENDING THE INDIVIDUAL, CHALLENGING, MONITORING AND RECOVERING THE CELEBRATION OF THE COLLECTIVE.” [INTERRAININCOGNITA, NO DATE:2]

208 // RESOLUTION


PUBLIC SPACE HACKING // COLLECTIF ETC

SPACE HACKING In order to determine a more dynamic strategic approach to progressing the scheme further, the key notion of space hacking needs to be understood. Space Hacking is the idea of space being reprogrammed and appropriated for various different uses and situations, with the intent that the manipulation of space can alter its regularity and routine. For the urban environment constantly in flux, this is a process which could be employed as a response to the everchanging needs of the users of the space. Within the scheme development so far, the use of a time - based grid system has been configured for visitors to appropriate with the various planned activities as they require. However, elemental configurement of the entire building needs a greater manipulation of space to create a system in which users can truly hack the space. This system will need to consider the notions of surface, circulation and form, and how these elements can be manipulated to interact with each other over a time based period.

11. 0 DESIGN DEVELOPMENT // 209


“THE RELATIONSHIP BETWEEN EACH BUILDING FUNCTION AND INDIVIDUALS ARE ARTICULATED THROUGH THE ACTUALITY OF BUILT FORMS OR THEIR PHYSICAL PRESENCE, THE AGENCY OF ARCHITECTS LIES IN HOW THEY ASSEMBLE THE PHYSICAL ELEMENTS OF THAT BUILT FORM SO AS TO REFRAME THE CONVENTIONAL RELATIONS BETWEEN INDIVIDUALS AND THAT FUNCTION, TO INSPIRE THEM TO ENGAGE WITH IT IN NEW WAYS.” [FARSHID MOUSSAVI ARCHITECTURE, 2013]

210 // RESOLUTION


FOREIGN OFFICE ARCHITECTS // YOKOHAMA PORT TERMINAL Foreign Office Architects are particularly successful at producing schemes which are focused towards the reconstructing of conventional ‘order’ within a building. Their Yokohama Port Terminal project, took the traditional linear idea of the pier, and reconfigured it to create a fluid and multidirectional space which is uninterrupted and based upon a series of specific circulation loops. The terminal acts as an extension from the ground, and aims to be perceived as a series of folded and bifurcated surfaces rather than a built object. The circulation drives the entire scheme in its relation to surface, materiality, connection between the internal and external, and level changes. A strategic approach such as this could be used to reconfigure the connection between the spatial, circulation and surface qualities of my scheme so far, to produce a more dynamic journey through the spaces, and to offer the most potential and opportunity for a fluctual environment open to being hacked.

11. 0 DESIGN DEVELOPMENT // 211


YOKOHAMA PORT TERMINAL STRATEGY

PLAZA

VISITORS DECK

PLAZA

VISITORS DECK

TRANSPORT PLAZA CITY

TRANSPORT PLAZA

CITY

ENTRY / EXIT TO TERMINAL ENTRY / EXIT TO TERMINAL

LOBBY NATIONAL PASSENGERS LOBBY NATIONAL PASSENGERS

ENTRY / EX RESTAURAN ENTRY / EX

RESTAURAN SHOPS/ RESTAURANTS/E SHOPS/

RESTAURANTS/E CHECK IN NATIONAL CHECK IN NATIONAL

APRON APRON

CAR PARK CAR PARK HACKING COVENTRY STRATEGY

OPEN AIR SPORT/EVENT SPACEAIR SPORT/EVENT OPEN

ACTIVITY LAND [UPPER] LAND ACTIVITY

SUPPORTING AREAS [CHANGING/SUITES] SUPPORTING AREAS

INTERNAL SPO SPACE INTERNAL SPO

SPACE

[UPPER]

SPACE

[CHANGING/SUITES]

OUTER RING ROAD OUTER RING ROAD

INDOOR STREET PLAZA STREET INDOOR PLAZA

ACTIVITY LANDSCAPE [LOWER] LANDSCAPE ACTIVITY [LOWER]

EXTERNAL MARKET/SPORT/CAR GRID EXTERNAL MARKET/SPORT/CAR GRID

212 // RESOLUTION

INDOOR STREET COMMUNITY HUB INDOOR STREET COMMUNITY HUB


XIT TO SHOPS / NTSTO SHOPS / XIT

ENTRY / EXIT TO HALL OF CIVIC ENTRY EXCHANGE / EXIT TO HALL OF

CIVIC EXCHANGE HALL OF CIVIC EXHIBITION EXCHANGE HALL OF CIVIC INTERNATIONAL EXHIBITION EXCHANGE PASSENGERS INTERNATIONAL IMMIGRATION LOBBY PASSENGERS

NTS

IMMIGRATION

LOBBY

CRUISE DECK CRUISE DECK

FERRY FERRY

DSCAPE

DSCAPE

ORT / EVENT

ORT / EVENT

MANAGEMENT/ STORAGE/ MANAGEMENT/ LOADING STORAGE/ LOADING

INNER RING ROAD INNER RING ROAD

CIRCULATION STRATEGY The Yokohama Port Terminal circulation strategy is based upon the feedback loop shown opposite. The circulation route aims for fluidity rather than flows of fixed orientation. I have used this construction of the circulation and applied it to my scheme to help with replanning the connections between spaces, and to try and create a strategy that considers the movement between the multiple levels, which I can later connect to how surfaces are manipulated as well.

11. 0 DESIGN DEVELOPMENT // 213


CIRCULATION AS A CONTINUOUS MOVEMENT THROUGHOUT THE SCHEME

SURFACE RESPONSE TO THE PROGRAMMATIC CHANGES AS WELL AS CIRCULATION STRATEGY SURFACE = EVERCHANGING BETWEEN FLOOR / WALL / ROOF

214 // RESOLUTION


CONTINUOUSLY CHANGING FORM

KEY DRIVERS + STRATEGIC PROCESS FOR DEVELOPMENT As well as the circulation strategy being a key driver of the project, surface and form are also particularly significant. Surface treatment has been explored so far, but I also need to consider the spatial qualities of a surface as well - that a surface can be considered as a continuously changing plane perceived not specifically as a floor roof or wall, but all three and can be manipulated between these planes. To develop these circulation and surfacing strategies, the form will need to be considered as well. Similar to the formal quality of Yokohama Port Terminal, developing the scheme extensively in section so that it is continuously changing will allow me to apply these key drivers. I aim to develop every section along every grid line, in order to explore the spatial flux throughout the scheme.

11. 0 DESIGN DEVELOPMENT // 215


GROUND FLOOR PLAN NEEDS STREET DEVELOPMENT

216 // RESOLUTION


DISCONNECTION BETWEEN ROOF AND INTERNAL SPACES

FIRST ITERATIONS The scheme’s plans so far have a couple main flaws which I need to focus on to improve. The first being the main street space. This needs to be a dynamic public space where activities are always taking place, whereas currently it feels more like a corridor than an indoor street. It also needs to connect more with the external grid system, so that the two are not viewed as completely separate environments. Secondly, the roof is a key part of the scheme and currently feels disconnected from the internal building; I need to develop how the circulation strategy can also include the roof space, joining the landscape and the building together.

11. 0 DESIGN DEVELOPMENT // 217


218 // RESOLUTION


The key developments to the entrance of the street include the reconnection between the external grid and main street space. Opening the entrance with ramps that connect to the landscaped roof of the south and a raised walkway on the north, create connective surfaces in areas which were previously just corners of the street. This aims to create a dialogue between the internal and external and a fluidity of movement between the two, whilst also relating to the level changes in this area of the entrance ramps leading to the mezzanine floor. Connecting directly onto the landscape also aims to provide sports users of the landscape such as cyclists runners, skateboarders easier access routes into the street. The shaping of the street has also become less linear with interchangeable social spaces (retail/cafe/bars) and an event / exhibition space aligning the angled edges, and with the addition of light wells emphasising the journey through the space. Having angled edges creates point of interstitial spaces which have provided areas for stepped surfaces and market grids at the further end of the street. The steps provide points of social congregation and act as viewing platforms into the main event areas as well as extensions form the central community hub.

RAMPED EDGES OF THE STREET

STREET TO GRID DEVELOPMENT

11. 0 DESIGN DEVELOPMENT // 219


220 // RESOLUTION


RAMPED INTO LANDSCAPE

EXTERNAL WALKWAYS

CHANGE OF SPATIAL HEIGHTS + POCKETS OF SPACE

EXTERNAL WALKWAYS + POCKETS OF SPACE

The ramped surfaces beginning at edges of the street entrance lead into walkways extending from the main footprint of the building, extending the idea of the landscape, whilst providing circulation routes between floors and balconies providing spectator spots overlooking the external grids.

CONNECTIONS BETWEEN LEVEL CHANGES

Proceeding up the roof landscape, pockets of space are cut into the surface, connecting the landscape with the ground floor and mezzanine level. These provide courtyard-like areas which act as an extension of the event space on the ground floor and a market grid on the mezzanine. The way these spaces are ‘cut’ provides varied sloped surfaces which can be appropriated for other uses such as social sports and urban sports. Throughout the street there are also significant height changes for some spaces (such as the event / exhibition space), which can also be reached via sloped walkways, whilst a major ramp linking the mezzanine into the main event space, can be followed through onto the roof.

STREET TO LANDSCAPE + LEVELS DEVELOPMENT 11. 0 DESIGN DEVELOPMENT // 221


222 // RESOLUTION


SLOPED EXTENSION OF LANDSCAPED ROOF

EXTERNAL ‘BOWL’

SLOPED WALKWAYS CONNECTING INTERNAL SPACES TO VIEWING BALCONY AND ROOF

The main strategies used for connecting the roof to the internal and lower floor spaces, include extending the surface of the roof, and walkways which extend upwards from lower floors. At the northern start of the roof landscape, sloped surfacing is extending from the roof to create and external ‘bowl’ amphitheatre space which can be appropriated for sports or events usage, and houses a covered market grid / public space underneath, leading to an internal market / large screening space used for screening events in Coventry, or within the building itself. The ramp joining the mezzanine with the main event space continues to large viewing area which connects to first floor spaces in the street and onto the main roof space. The height of this also provides raised areas on the roof which can be used for activities such a golf. These highlight the main developmental changes made to circulation and form, with each individual section documented in the final drawings package with spatial hacks.

LANDSCAPE + SURFACE TO INTERNAL DEVELOPMENT 11. 0 DESIGN DEVELOPMENT // 223



12.0 // FINAL SCHEME DRAWINGS


226 // RESOLUTION


DONE

PLANS GF TEXT

INTRODUCTION // 227


228 // RESOLUTION


DONE

PLANS MEZ TEXT

INTRODUCTION // 229


230 // RESOLUTION


DONE

PLANS FF TEXT

INTRODUCTION // 231


232 // RESOLUTION


DONE

PLANS SF TEXT

INTRODUCTION // 233


234 // RESOLUTION


DONE

PLANS ROOF TEXT

INTRODUCTION // 235


236 // [RE_FLECT, RE_FORM, RE_POSITION]


HEADING TEXT

INTRODUCTION // 237


238 // RESOLUTION


SECTIONS SHORT TEXT

12.0 FINAL SCHEME DRAWINGS // 239


240 // RESOLUTION


SECTIONS SHORT TEXT

12.0 FINAL SCHEME DRAWINGS // 241


242 // RESOLUTION


SECTIONS SHORT TEXT

12.0 FINAL SCHEME DRAWINGS // 243


244 // RESOLUTION


SECTIONS SHORT TEXT

12.0 FINAL SCHEME DRAWINGS // 245


246 // RESOLUTION


SECTIONS SHORT TEXT

12.0 FINAL SCHEME DRAWINGS // 247


248 // RESOLUTION


SECTIONS SHORT TEXT

12.0 FINAL SCHEME DRAWINGS // 249


250 // RESOLUTION


DONE

ELEVATION 1 TEXT

12.0 FINAL SCHEME DRAWINGS // 251


252 // RESOLUTION


ELEVATION 2 TEXT

12.0 FINAL SCHEME DRAWINGS // 253


254 // RESOLUTION


SECTION 1 TEXT

12.0 FINAL SCHEME DRAWINGS // 255


256 // RESOLUTION


SECTION 2 TEXT

12.0 FINAL SCHEME DRAWINGS // 257


258 // RESOLUTION


SECTION 1:50 TEXT

INTRODUCTION // 259


260 // RESOLUTION


DONE

SECTION 1:20 TEXT

INTRODUCTION // 261



13.0 // TECHNICAL RESOLUTION HEADING TEXT

INTRODUCTION // 263


GROUND FLOOR STRUCTURAL GRID AND COLUMNS

264 // RESOLUTION


STRUCTURAL RESOLUTION INTEGRATED TECHNOLOGIES MODULE // STRUCTURE As the scale of the building is so large, deals with the site constraints of the ring road, and has varied sectional changes, a strategic structural resolution has been applied to combat these issues. A system was needed that allowed for flexibility of the changing spaces, but also providing great support for large expansive areas. The primary structural system, consists of pile foundations, large plate welded steel columns and prismatic and warren trusses. These elements combined have allowed this flexibility to be achieved. 10M

40M

Foundations: Reinforced concrete pile foundations with a 600mm x 600mm reinforced concrete pile cap have been used to transfer the large building loads into more stable stratum of rock well below the superstructure. The bedrock of the site is mostly weak sandstone, and although this is not the most unstable of ground conditions, given the extremely large building loads that need to be supported, as well as the general slope across the site (which can decrease the shearing strength of a soil), and interaction with the ring road, pile foundations will offer the most stable support for the superstructure. The foundations are applied on a 5m x 5m grid across the footprint of the building. Where the building sits across the road, precast concrete elements will be used to form a tunnel space, with elements either side of the road and through the central reservation. This will house the road underneath the building, whilst allowing the building load to be transferred through these elements to further foundations below. Primary Structure: The foundations support a reinforced concrete ground floor slab, and large columns are needed to allow for the wide spans of the building. These have been formed from large welded steel plates and have varying profiles and sizes throughout the building.

10M

220M

The main structural grid sees columns placed every 10 metres along the perimeter of the footprint. The distance between these columns and columns placed internally varies with the width of the street, but is generally a large span of 20m. The main event space is column free, with a span of 40m. Although the columns are situated on a grid, each column is pushed inwards and outwards of the main gridline and does not always follow a a straight line vertically upwards, due to the design of the building continuously changing in section. This also has a dynamic effect on the facade, which

13. 0 TECHNICAL RESOLUTION // 265


GROUND FLOOR MEZZANINE STRUCTURAL GRID AND COLUMNS

FIRST FLOOR MEZZANINE STRUCTURAL GRID AND COLUMNS

266 // RESOLUTION


SECOND FLOOR MEZZANINE STRUCTURAL GRID AND COLUMNS

then continuously changes angle slightly, as the columns are pushed off the standard grid. To ensure that the correct support is achieved, and building loads are successfully transferred through the columns down to foundations, columns are tapered in profile on each floor, and vertically, with wider columns of 800mm x 800mm on the ground floor, to 300mm x 300mm by the second floor. 1500mm deep prismatic trusses have been used throughout the majority of spaces (excluding the main event space), as they can successfully respond to the changing shapes of the spaces created and external sloped walkways, and provide enough stability without overwhelming the smaller internal spaces - for example the profile of a prismatic truss works well with large spanning internal spaces that do not have a great ceiling height, such as within the street entrances; if warren trusses had been used throughout, ceiling heights would have to have been much greater to accommodate the depth of the truss. However, in th main event space, 2500mm warren trusses have been used to span the larger expanse of 40m, whilst still respecting the height clearances needed for the activities taking place within this space. The trusses run between the columns according to the labelled gridlines shown opposite throughout (in pink), however where the building crosses the road, trusses have to run in the opposite, transverse direction (blue), as columns cannot be situated in the road, so these trusses span between columns either side of the road.

13. 0 TECHNICAL RESOLUTION // 267


SECTION A

SECTION G

SECTION B

SECTION H

SECTION C

SECTION I

SECTION D

SECTION J

SECTION E

SECTION K

SECTION F

SECTION L

268 // RESOLUTION


SEQUENTIAL STRUCTURAL RESOLUTION INTEGRATED TECHNOLOGIES MODULE // STRUCTURE Throughout every section generated, a structural solution has been determined, to demonstrate how the column angles and sizes are changing, is the variation between prismatic and warren trusses depending on the use and size or shape of space created.

13. 0 TECHNICAL RESOLUTION // 269


SECTION M

SECTION R

SECTION N

SECTION S

SECTION O

SECTION T

SECTION P

SECTION U

SECTION Q

270 // RESOLUTION

SECTION V


SECTION 12

SECTION 07

SECTION 06

SECTION 11

SECTION 05

SECTION 10

SECTION 04

SECTION 03

SECTION 09

SECTION 02

SECTION 08

SECTION 01

13. 0 TECHNICAL RESOLUTION // 271


272 // RESOLUTION


LATERAL CONNECTIONS INTEGRATED TECHNOLOGIES MODULE // STRUCTURE

The lateral connections between trusses and columns are also continusly changing throughout, with beams spanning these distances. This diagram aims to demonstrate these connections (pink), whilst also showing the connections of the transverse trusses crossing the roads.

13. 0 TECHNICAL RESOLUTION // 273


BREAKDOWN OF THE PRIMARY STRUCTURE LATERAL CONNECTIONS BETWEEN STRUCTURAL BAYS, CONSISTING OF PRISMATIC TRUSSES ATTACHED TO WELDED STEEL PLATES FORMING ANGLED COLUMNS, WITH BEAMS SPANNING ACROSS THE TRUSSES. [FLOOR CONSTRUCTION SHOWN IN PINK]

274 // RESOLUTION


LATERAL CONNECTIONS INTEGRATED TECHNOLOGIES MODULE // STRUCTURE

TEXT

13. 0 TECHNICAL RESOLUTION // 275


276 // RESOLUTION

05

04

28 10 09 06

29 15

18

21

24

01 // Concrete Pile Foundations (600 x 600mm Pile Cap) 02 // Concrete Slab 03 // Reinforcement Bars 04 // 1500mm deep PrismaticTrusses 05 // Welded Steel Plates (used to form large columns, 800 x 800 at base) 06 //150mm I Section 07 // 150mm C Section 08 // 50mm Floor Insulation 09 // 150mm Steel Deck with Concrete Infill 10 // 20mm Screed 11 // Service Duct 12 // Sprinkler System 13 // Drainage Channel 14 // Internal Double Glazing with openable windows 15 // Rigid Insulation 16 // Suspension Rod 17 // Square Hollow Section 18 // 250mm U Channel Glass with Translucent Insulation 19 // Motorised Blind 20 // Thermally Broken Steel Support Bracket 21 // Aluminium Louvres 22 // Aluminium Ventilation Channel 23 // Airflow Opening 24 // Aluminium Coping 25 // Steel Mesh 26 // Handrailings 27 // Waterproof Capping 28 // Astroturf Surfacing 29 // Paved Surfacing

3D CUT THROUGH FACADE:

INTEGRATED TECHNOLOGIES MODULE // ENVELOPE

3D FACADE STUDY


01

02

03

06

13

14

19 17 20 21 22 16

11

DONE

FACADE 3D TEXT

INTRODUCTION // 277

07

08

09

10

27

26

21


278 // RESOLUTION Service Duct and Sprinkler System 1500mm Prismatic Truss Welded Steel Plates (used to form large columns, 800 x 800 at base) Single Glazed Internal Glazed Screen Double Glazed Internal Skin Motorized Blind Hollow Square Section Insulation Thermally Broken Steel Bracket Aluminium Ventilation Channel Suspension Rods U-Channel Glass Profiles with Translucent Insulation Aluminium Louvres Roof Insulation Damp Proof Course Aluminium Coping

TRANSLUCENT DOUBLE SKIN STRUCTURE

INTEGRATED TECHNOLOGIES MODULE // ENVELOPE

EXPLODED 3D FACADE


FACADE EXPLODED

INTEGRATED TECHNOLOGIES MODULE // ENVELOPE

TEXT

INTRODUCTION // 279

150mm I Beams 50mm Insulation Steel Deck Concrete Infill with Drainage Channel 20mm Screed Steel External Handrail with LED lighting

FLOOR STRUCTURE

Service Duct and Sprinkler System 1500mm Prismatic Truss Welded Steel Plates (used to form large columns, 800 x 800 at base) Double Glazed Internal Skin Motorized Blind Hollow Square Section Insulation Damp Proof Course Thermally Broken Steel Bracket Aluminium Ventilation Channel Suspension Rods Single Glazed External Skin Aluminium Louvres

TRANSPARENT DOUBLE SKIN STRUCTURE


20

19 17 18

08 06 05 07 04 03 13 12 11 10 15

01 02

09 14 16

Roof Junction 1:20 01 // 1500mm Prismatic Truss 02 // Steel Plate Welded Column 03 // 150mm I Beam 04 // 150mm C Section 05 // 50mm Insulation 06 // Steel Deck with Concrete Infil 07 // Damp Proof Course 08 // 20mm Screed 09 // Double Glazed Inner Facade Skin 10 // Motorised Blind 11 // Thermally Broken Steel Support Bracket 12 // Aluminium Ventilation Channel 13 // Aluminium Louvres 14 // Suspension Road 15 // Airflow Opening 16 // U Channel Glass with Transparent Insulation Outer Facade Skin 17 // Rigid Insulation 18 // Aluminium Coping 19 // Steel Handrail 20 // Coloured LED Light

280 // RESOLUTION


JUNCTION 1 TEXT

13. 0 TECHNICAL RESOLUTION // 281


03 18

04

05

07

17

08 06

Facade to Wall Junction 1:20

05 14

01 // 1500mm Prismatic Truss 02 // Steel Plate Welded Column 03 // 150mm I Beam 04 // 50mm Insulation 05 // Steel Deck with Concrete Infill 06 // Damp Proof Course 07 // 20mm Screed 08 // Double Glazed Inner Facade Skin 09 // Motorised Blind 10 // Thermally Broken Steel Support Bracket 11 // Aluminium Ventilation Channel 12 // Aluminum Louvres 13 // Suspension Road 14 // Airflow Opening 15 // U Channel Glass with Transparent Insulation 16 // Rigid Insulation 17 // Service Duct 18 // Sprinkler

282 // RESOLUTION

10

11

12

06 16 01 07

15 13 09 08 02


JUNCTION 2 TEXT

13. 0 TECHNICAL RESOLUTION // 283


17

11

08 12 07 14 09 10 04 13 06

03

02

Facade to Ground Junction 1:20 01 // Concrete Pile Foundations (600 x 600mm Pile Cap) 02 // Concrete Slab 03 // Reinforcement Bars 04 // Steel Plate Welded Column 04 // Insulation (50mm, 200mm) 05 // Damp Proof Course 06 // 20mm Screed 07 // Double Glazed Inner Facade Skin 08 // Motorised Blind 09 // Thermally Broken Steel Support Bracket 10 // Aluminium Louvres 11 // Suspension Road 12 // U Channel Glass with Transparent Insulation 13 // Drainage Channel 14 // LED Lighting

284 // RESOLUTION

01

05


JUNCTION 3

13. 0 TECHNICAL RESOLUTION // 285


RADIANT HEATING SYSTEMS ARE IDEAL FOR HEATING LARGE SPACES, USED HERE AT THE UNIVERSITY OF CAMBRIDGE SPORTS CENTRE AND INDOOR ATHLETICS CENTRE

286 // RESOLUTION


HEATING, COOLING + VENTILATION INTEGRATED TECHNOLOGIES MODULE // ENVIRONMENT A hydronic radiant heating and cooling system will be employed throughout the scheme. Different from a forced air system, radiant systems heat or cool surfaces of objects rather than the air of a space. These surfaces then radiate the warmth or cooling to occupants. This type of system was chosen due to the particularly large spaces of the internal sports/ event space; it would be inefficient to heat and cool the large volumes of air here, so a radiant system would save energy and costs for the building. Radiant systems can be applied though the flooring, ceiling or walls. Initially an under floor application was considered, however the nature of the types of space in the scheme, especially the sport/ event space, may involve heavy equipment or furniture being moving constantly across the floor; so if the floor were to be damaged for any reason, this could impact greatly on an under floor radiant system. Therefore a ceiling application was chosen. Radiant panels in the ceiling and tube heaters in the main event space, will contain tubing carrying water. During winter months when it is cooler, the water is heated, and the heat is radiated into the space, warming occupants. Whereas in the summer, chilled water is circulated through the tubing, absorbing heat radiated in the space, and cooling occupants. A ground source heat pump will be the main energy driver of the scheme. These extract heat from the earth during winter using it as a heat source, and store heat as a heat sink in the summer. A liquid-to-water heat pump will be used to heat and cool the water that is distributed throughout the building. Ventilation will be achieved using a combination of natural ventilation using the double skin facade system, and some areas of mechanical ventilation. A box double skin facade system has been used, with aluminium louvres located at the base and top of ‘box’ unit, which allow external air to circulate within the interstitial space within the inner and outer skin. During warmer months, the openable windows of the inner skin can be opened, allowing air to naturally ventilate spaces, with cool air arriving at the base, and warm air rising and leaving through the top louvres. In winter, the windows are closed the space within the double skin becomes a thermal buffer, reducing radiant losses from the room. Natural ventilation is possible in the majority of spaces throughout the building, taking into account their size - even in the sport/ event spaces as you are able to naturally ventilate a space up to five times its height. However this may not always be practical due to the activities within this space so a mechanical ventilation system will also be used here, as well as in the part of the central street which is not externally open, as well as higher demanding spaces such as the hub kitchen and changing rooms.

13. 0 TECHNICAL RESOLUTION // 287


SUMMER DAY

SUMMER NIGHT

288 // RESOLUTION


WINTER DAY

WINTER NIGHT

13. 0 TECHNICAL RESOLUTION // 289


DAYLIGHTING STRATEGY, DEMONSTRATING THE LIGHT GAINS FROM TRANSLUCENT AND TRANSPARENT FACADES

ELECTRICAL LIGHTING STRATEGY, DEMONSTRATING GENERAL, TASK AND FEATURE LIGHTING.

290 // RESOLUTION


DAYLIGHTING + ELECTRICAL LIGHTING INTEGRATED TECHNOLOGIES MODULE // ENVIRONMENT Daylighting is primarily achieved through the double skin facade, of which the outer skin varies between clear glazing and brightly coloured u-channel glass ( the colours work as zoning throughout the scheme) with transparent insulation, affecting the amount of light let into different types of spaces. More socially driven spaces, such as those located directly onto the street, ramped walkways or the beginning of the roof landscape have clear glazing. Spaces such as the main event space, studios and suites have a transparent facade, so that daylight is not disruptive to the activities taking place. Within the interstitial space of the double skin facade there is a motorised blind which is user controllable to prevent glare and unwanted light entering. There are also lightwells throughout the western part of the street, aiming to channel light through from above, whilst also helping to map the journey through the street. Electrical lighting differs between general, task and feature lighting. The street areas are lit by angled strip lighting to create a dynamic atmosphere and to act as a guide through the street space. Simple downlighters are used within the majority of smaller retail and eating spaces in the street, and spaces on the first floor. Event based spaces such as the main event/ sport space, and the main space on the second floor will be lit using a combination of suspended linear luminaires, to ensure uniform lighting of spaces if that is required (for example, for sporting events), and spot lighting lamps more suited to events. Within the handrails on the roof and ramped walkways, coloured LEDs will be used to create external strips of light, highlighting the building within the ring road.

13. 0 TECHNICAL RESOLUTION // 291


292 // RESOLUTION


ACOUSTICS INTEGRATED TECHNOLOGIES MODULE // ENVIRONMENT Being located on the ring road junction, the primary external noise source will be from the road itself, which can become particularly busy during the daytime, reaching levels of 75+ dB. The use of a double skin facade acts as an insulative barrier around the building perimeter, reducing the amount of noise that reaches the internal spaces; this is exacerbated by the changing angle of the facade - when sound hits a surface some waves are reflected, whilst others penetrate the surface. Having an angled facade rather than a flat plane, will be able to reflect more sound waves, reducing the amount of noise entering the building. The main event/ sport space requires the most acoustic attenuation of all the spaces, to ensure that the acoustic qualities are adaptive to the changing activities of the space, and also to avoid excessive noise travelling into adjacent spaces. This has been achieved by the use of acoustically insulated walls and the movable walls inbetween each space also have acoustic attenuation; again, the space will be helped by the angled nature of the walls surrounding it.

13. 0 TECHNICAL RESOLUTION // 293


FRESH WATER FOUL WATER SERVICE CORES

SC TO

W AL

KW AY

UP

TO

FF

TO

LA

ND

AP

E

TO

W AL

KW AY

UP

TO

SF

TO

W AL

KW AY

UP

TO

SF

STOPCOCKS + METERING EQUIPMENT

294 // [RE_FLECT, RE_FORM, RE_POSITION]


A1

WATER SUPPLY INTEGRATED TECHNOLOGIES MODULE // SERVICES + INTEGRATION

Fresh water is drawn from the main water pipes, and is distributed vertically through the service cores. Stopcocks and metering equipment will be located at these main water pipes, to aim to regulate water usage throughout the building. Part H of the Building Regulations is concerned with drainage and waste and states that a drainage system must be in place for carrying foul water. The site has combined public sewers running through it and across the ring road. Therefore fowl water from the toilets, changing areas and kitchen will be carried through the service cores and then connect to the public sewers. Rainwater harvesting is also used, (as described further on in drainage) with collected water being used to flush toilets, saving cost and energy.

INTRODUCTION // 295


HORIZONTAL + VERTICAL SERVICES CORES VENTILATION DUCTS ELECTRICAL RUNS

SC TO

W AL

KW AY

UP

TO

FF

TO

LA

ND

AP

E

TO

W AL KW AY

UP

TO

SF

TO

W AL

KW AY

UP

TO

SF

HEATING PIPES DISTRIBUTION

296 // RESOLUTION A


A1

SERVICING + DISTRIBUTION INTEGRATED TECHNOLOGIES MODULE // SERVICES + INTEGRATION There are four main vertical service core risers throughout the building, , all of which do not run directly all the way through the building vertically, to allow for the varied sectional changes of the spaces. However, there are also significant horizontal service ducts also running through every floor, for example through each side of the street, ( size) providing a greater servicing space run than a suspended ceiling would. The two main plant rooms are located on the ground floor, to the north of the site adjoining the loading bay, and to the south adjoining the external grid storage space. The northern plant will contian the ground source heat pump distributing heat to the heating pipes. This will be a protected and insulted plant room, that will only be accessed by maintenance staf.f, satisfying Part J of the building regulations, concerning the discharge of the products of combustion. The use of a ground source heat pump also aims to reduce the carbon emissions of the scheme, satisfying Part L2A of the building regulations. The plants connect the horizontal runs, which in turn connect to the vertical. From the horizontal ducts, electrical wiring and heating pipes are distributed into spaces, with electrical circuit runs around the perimeter of each room, and heating pipes for the spaces to be radiantly heated and cooled (showed as shaded, but distributed as shown at the ground floor street entrance). Ventilation ducts are mostly distributed on the ground floor, extending from the northern plant room.

TECHNICAL RESOLUTION: SERVICES + INTEGRATION // 297


FIRE STRATEGY

INTEGRATED TECHNOLOGIES MODULE // SERVICES + INTEGRATION

UP

TO

SF

The fire escape strategy ensures that most horizontal escape distances are complient with Part B of the Building Regulations, with a 45m limit for two-directional escape and 18m for one-directional escape, which are the limits for the this type of programme. The main area different to this is the second floor external area, which only has one protected staircase. However, BS9999 stipulates that this type of building is of lower fire risk (B1) and as there is an alternative route of exit via a ramp down to the first floor which is less than 1:12 gradient, the escape distance can be allowed to increase to 90m. All vertical stair cores are protected using 60 minute fire rated walls and 60 minute fire doors, with every core containing fire hoses and fire extinguishers, and exit into the open air. All stairs are the minimum width of 1100mm, and each core also provides a refuge space of minimum 1400mm x 900mm for wheelchair users, which does not disrupt the escape path of the stair. Sprinkler systems are used extensivly throughout, at no more than 4.5m maximum apart, as are fire alarms, and signage is used to direct people towards all fire exits.

AY

Compartmentation of spaces has been used to prevent the risk of a fire spreading rapidly. Compartmentation of direct escape routes has been employed, as well as between areas of risk such as the hub kitchen, and all doors within compartment walls have the same fire resistnace as the wall. There is also compartmentation between each floor, separating areas of distinct different usage, to prevent the vertical spread of fire.

TO

WA LKW

There are also two main fire fighting shafts (one with a fire fighting lift, one without) as the building is above 18m tall and has a recreational programme, therefore needs these facilities. These shafts run directly through all floors, and open externally onto part of the site where there is sufficient room for fire engines to be situated, and for access to fire equipment.

UP

TO

SF

VERTICAL SERVICE CORES PROTECTED FIRE STAIRS FIRE FIGHTING SHAFTS ESCAPE ROUTES COMPARTMENT WALLS

FIRE EXTINGUISHER

AY

TO

WA LKW

UP

TO

FF

AY

TO

298 // RESOLUTION

DSC

LAN

APE

TO

WA LKW

FIRE HOSE


FIRE STRATEGY INTEGRATED TECHNOLOGIES MODULE // SERVICES + INTEGRATION The fire escape strategy ensures that most horizontal escape distances are compliant with Part B of the Building Regulations, with a 45m limit for two-directional escape and 18m for one-directional escape, which are the limits for the this type of programme. The main area different to this is the second floor external area, which only has one protected staircase. However, BS9999 stipulates that this type of building is of lower fire risk (B1) and as there is an alternative route of exit via a ramp down to the first floor which is less than 1:12 gradient, the escape distance can be allowed to increase to 90m. All vertical stair cores are protected using 60 minute fire rated walls and 60 minute fire doors, with every core containing fire hoses and fire extinguishers, and exit into the open air. All stairs are the minimum width of 1100mm, and each core also provides a refuge space of minimum 1400mm x 900mm for wheelchair users, which does not disrupt the escape path of the stair. Sprinkler systems are used extensively throughout, at no more than 4.5m maximum apart, as are fire alarms, and signage is used to direct people towards all fire exits. There are also two main fire fighting shafts (one with a fire fighting lift, one without) as the building is above 18m tall and has a recreational programme, therefore needs these facilities. These shafts run directly through all floors, and open externally onto part of the site where there is sufficient room for fire engines to be situated, and for access to fire equipment. Compartmentation of spaces has been used to prevent the risk of a fire spreading rapidly. Compartmentation of direct escape routes has been employed, as well as between areas of risk such as the hub kitchen, and all doors within compartment walls have the same fire resistance as the wall. There is also Compartmentation between each floor, separating areas of distinct different usage, to prevent the vertical spread of fire.

INTRODUCTION // 299


NETWORK OF ROOF DRAINAGE CHANNELS

WATER STORAGE TANK

DRAINAGE CHANNELS + UNDERGROUND WATER STORAGE

300 // RESOLUTION


DRAINAGE + WASTE MANAGEMENT INTEGRATED TECHNOLOGIES MODULE // SERVICES + INTEGRATION As the roof of the scheme is fairly expansive, water drainage from here is particularly important. Normally on large roofs a large horizontal drainage zone is preferred rather than distributed, however, due to the many changing levels across the roof, a series of distributed channels has been employed to ensure all surfaces can be drained successfully. Drainage channels are found on each surface, which then feed into the channels of the surfaces of lower levels, essentially travelling down the overall ramped surface of the roof, feeding into downpipes along the way. The drained water is collected, filtered and stored underground, so that a water harvesting system can be used throughout the building. The water collected is then used for the flushing of toilets and... which is a cost-effective decision for the running of water in the building, whilst water reuse is also environmentally friendly. The other main waste management strategy consists of recycling waste from the public visitors. Recycling points will be included primarily throughout the street, as this the most public of all the spaces, and visitors will be encouraged to use these as much as possible.

13. 0 TECHNICAL RESOLUTION // 301


302 // RESOLUTION


14.0 // FINAL RESOLUTION HEADING TEXT

INTRODUCTION // 303


304 // RESOLUTION


1:200 SECTIONAL MODEL WITH ROOF SURFACES

14.0 FINAL RESOLUTION // 305


306 // RESOLUTION


14.0 FINAL RESOLUTION // 307


308 // RESOLUTION


HEADING TEXT

14.0 FINAL RESOLUTION // 309


310 // RESOLUTION


EXTERNAL VISUAL 1 TEXT

EXTERNAL VIEWINTRODUCTION FROM THE EXTERNAL //GRID 311


312 // RESOLUTION


EXTERNAL VISUAL ROAD TEXT

EXTERNAL VIEW APPROACHING THE JUNCTION FROM THE CITY CENTRE INTRODUCTION // 313


314 // RESOLUTION


EXTERNAL DISTANCE TEXT

EXTERNAL VIEW APPROACHING FROM THE RING//ROAD INTRODUCTION 315


316 // [RE_FLECT, RE_FORM, RE_POSITION]


HEADING TEXT

EXTERNAL VIEW APPROACHING FROM THE RING ROAD AT// NIGHT INTRODUCTION 317


318 // RESOLUTION


AERIAL TEXT

EXTERNAL VIEW UNDERNEATH THEINTRODUCTION RING ROAD ROUNDABOUT // 319


320 // RESOLUTION


INTERNAL VISUAL STREET TEXT

INTERNAL VIEW OF THE COMMUNITY HUB, STREETINTRODUCTION AND EVENT/ SPORT// SPACE 321



15.0 9.0 // //BIBLIOGRAPHY BIBLIOGRAPHY HEADING TEXT

INTRODUCTION // 323


BIBLIOGRAPHY LITERATURE: Auge, M. (2008) Non-Places. An Introduction to Supermodernity. London: Verso DCMS (2012) BDUK Broadband Delivery Project. Local Broadband Plan: Coventry, Solihull & Warwickshire Superfast Broadband. Unknown Place of Publication: DCMS. [Online] [Accessed 1st December 2013] Available here: http://www.cswbroadband.org.uk/documents/CSW-LBP-Submitted-20120301REDACTED-20120501.pdf Cabe Space (2013) The Value of Public Space. London: Cabe Space Corner, J. (2000) Taking Measures Across the American Landscape. USA:Yale University Press Haque, U. (2007) ‘The Architectural Relevance of Gordon Pask.’ In, Architectural Design 77.4 (2007) pp. 54-61 Ibelings, H. (2003) Supermodernism. Unknown place of publication: NAi Publishers. Interrainincognita. (no date) Hacking Public Space. [Online][Accessed May 2014] Avaliable here: http://interraincognita.org/wp-content/uploads/2013/02/articleaparienciarevised. pdf Vodanovic, L. (2007) Obsolence and Exchange in Cedric Price’s Dispensable Museum. [Online][Accessed December 2013] Available here: https://www.rochester.edu/in_visible_culture/Issue_11/vodanovic/vodanovic.html Worpole, K. (2000) Here Comes the Sun: Architecture and Public Space in 20th Century European Culture. Unknown place of Publication: Reaktion Books. WEBSITES: Coventry Community Empowerment Network (2013) ‘Members by Location.’ [Online] [Accessed 1st December 2013] Available here: http://www.covcen.org.uk/site/members/wards Coventry Partnership (2013) ‘Communities.’ [Online] [Accessed 1st December 2013] Available here: http://www.coventrypartnership.com/communities

324 // RESOLUTION


Defra Noise Mapping (2013) ‘Maps and Charts.’ [Online] [Accessed 15th December 2013] Available here: http://services.defra.gov.uk/wps/portal/noise Farshid Moussavi Architecture (2014) ‘About FMA’ [Online] [Accessed May 2014] Available here: http://www.farshidmoussavi.com/flash/index.html#/about/profile IMAGES: Archdaily () Rolex Learning Centre. [Online Image] [Accessed February 2014] Avaliable here: http://www.archdaily.com/50235/rolex-learning-center-sanaa/ Archigram () Plug-in City. Notes on the History of Visual Communication Blog. [Online Image] [Accessed 5th December 2013] http://va312ozgunkilic.wordpress.com/2010/12/07/archigram-plug-in-city/ Archinect (2010) Belgrade, Serbia. Congress Center Sava. [Online Image] [Accessed January 2014] Avaliable here: http://archinect.com/blog/article/22227884/belgrade-serbia-_-congress-center-sava Archinect (2006) Renzo Piano. [Online Image] [Accessed February 2014] Avaliable here: http://archinect.com/features/article/31565/renzo-piano Archinect (2008) Wall Supergraphics. [Online Image] [Accessed February 2014] Avaliable here: http://archinect.com/forum/thread/81373/wall-supergraphics Arcspace (2007) Yokohama International Port Termnial [Online Images] [Accessed May 2014] Available here: http://www.arcspace.com/features/foreign-office-architects/yokohamainternational-port-terminal/ Chin, W. (no date) Blur play Olympic Celebration gig at Hyde Park. [Online Image] [Accessed February 2014] Avaliable here: http://www.digitalspy.co.uk/music/i425430-9/blur-performing-at-bt-london-liveblurs-westway-set.html Detail Online (2012) Stadel Museum. [Online Image] [Accessed February 2014] Avaliable here: http://www.detail-online.com/uploads/pics/staedel-museum-17_01.jpg

15.0 BIBLIOGRAPHY // 325


BIBLIOGRAPHY Glass is Green (2012) Stadel Museum Renovated with a Green Roof Dotted with Skylights. [Online Image] [Accessed February 2014] Avaliable here: http://glassisgreen2010.blogspot.co.uk/2012/03/stadel-museum-renovated-withgorgeous.html Inhabitat (2012) Stadel Museum Renovated. [Online Image] [Accessed February 2014] Avaliable here: http://inhabitat.com/stadel-museum-updated-with-a-gorgeous-polka-dotted-greenroof-in-frankfurt/staedel-museum-schneider-schumacher-12/ Inhabitat (2011) TU Delft Library. [Online Image] [Accessed February 2014] Avaliable here: http://assets.inhabitat.com/wp-content/blogs.dir/1/files/2011/03/Tu-DelftLibrary-9.jpg Nieuwenhuys, C. () New Babylon. The Struggle Tumblr. [Online Image] [Accessed 5th December 2013] Available here: http://palethrough.tumblr.com/post/6227217305/new-babylon-by-constantnieuwenhuys-in-1950s Open Buildings (no date) High Museum of Art Extension. [Online Image] [Accessed February 2014] Avaliable here: http://openbuildings.com/buildings/high-museum-of-art-extension-profile-2782 Qubits (2013) Examples. Qubits [Online Image] [Accessed 5th January 2014] Available here: http://www.qubitstoy.com/pages/examples Qubits (2013) Qubits 2.0 Construction Toy – The First Batch. [Online Image] [Accessed 5th January 2014] Available here: http://www.indiegogo.com/projects/qubits-2-0-construction-toy-the-firstbatch?c=gallery Rogers Stirk Harbour + Partners (2014) Centre Pompidou. [Online Image][Accessed February 2014] Available here: ¬http://www.richardrogers.co.uk/work/buildings/centre_pompidou/completed Scalextric (2013) Scalextric Action Track. Scalextric Shop. [Online Image] [Accessed 6th January 2014] Avaliable here: http://www.scalextric.com/shop/track/action-track Snohetta (2012) Oslo Opera House by Snohetta. [Online Image] [Accessed February 2014] Available here: http://thesuperslice.com/2011/11/14/oslo-cooking-spacegroup-jds-snohetta/

326 // RESOLUTION


Space Hacking (2012) Collectif Etc [Online Image] [Accessed May 2014] Available here: http://spacehacking.net/interview-collectif-etc United Editions (2010) Supergraphics. [Online Image][Accessed February 2014] Available here: http://uniteditions.com/resources/798/A505_556_RP_inline%20image_optimised2. jpg Urban Photo (2006) Learning to Love and Elevated Expressway. [Online Image][Accessed February 2014] Available here: http://www.urbanphoto.net/blog/2006/10/28/learning-to-love-an-elevatedexpressway/ West 8 (no date) Schouwburgplein. [Online Image][Accessed January 2014] Available here: http://www.west8.nl/projects/all/schouwburgplein/

15.0 BIBLIOGRAPHY // 327


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.