PROJECT INVERSION REVITISM 2018 SEMESTER 02 DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
CONTENTS PROJECT INVERSION CONSTRUCTION DOCUMENT DESIGN DEVELOPMENT DOCUMENT MATERIAL RESEARCH - WALL MATERIAL - FLOOR MATERIAL - CEILING MATERIAL - LIGHTING MATERIAL - BIKE EQUIPMENT - TOILET EQUIPMENT - HVAC EQUIPMENT SITE ANALYSIS - AREA STUDY - PHOTO STUDY - SURROUNDING CONDITION - LANDSCAPE ANALYSIS - COUNCIL STUDY - TRAFFIC STUDY - MARKET RESEARCH - SOLAR ANALYSIS BUILDING CODE OF AUSTRALIA STUDY BETTER APARMENTS DESIGN STANDARDS STUDY PRECEDETNS STUDY DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085
FORM FINDING STUDY
TUTOR: DANIEL MAUNDERS
APARTMENT LAYOUT STUDY MID-SEMESTER REVIEW FINAL REVIEW BEFORE SUBMISSION MINUTES
DESIGN DEVELOPMENT DOCUMENTS
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DESIGN DEVELOPMENT 20/08/2018
ARCHITECTURAL DRAWING SHEET LIST
SYSTEM CODES & TAGS
WT
SHEET NAME
REVISION
SCALE
A-000
TITLE SHEET
A
-
A-001
3D VIEWS
A
-
A-101
PROPOSED SITE PLAN
A
1:200
A-102
EXISTING CONDITION / DEMOLITION PLAN
A
1:100
A-103
EXISTING CONDITION / DEMOLITION ELEVATION
A
1:100
A-201
BASEMENT FLOOR PLAN
A
1:50
A-202
GROUND FLOOR PLAN
A
1:50
A-203
TYPICAL LOWER FLOOR PLAN (1/F)
A
1:50
A-204
TYPICAL UPPER FLOOR PLAN (6/F)
A
1:50
A-205
LEVEL 05 COS PLAN
A
1:50
A-205
ROOFTOP PLAN
A
1:50
A-300
BASEMENT RCP
A
1:50
A-301
GROUND RCP
A
1:50
A-302
TYPICAL LOWER FLOOR RCP
A
1:50
A-303
TYPICAL UPPER FLOOR RCP
A
1:50
A-304
LEVEL 05 COS RCP
A
1:50
A-305
ROOFTOP RCP
A
1:50
A-401
ELEVATIONS - NORTH & EAST
A
1:100
A-402
ELEVATIONS - SOUTH & WEST
A
1:100
A-501
SECTIONS A & B
A
1:100
A-502
SECTIONS C & D
A
1:100
A-601
TYPICAL FACADE SECTION 01
A
1:20
A-602
TYPICAL FACADE SECTION 02
A
-
A-651
CONSTRUCTION DETAILS 01
A
1:5
A-652
CONSTRUCTION DETAILS 02
A
1:5
A-701
AREA PLAN TYPICAL LOWER APARTMENTS
A
1:50
A-702
AREA PLAN TYPICAL UPPER APARTMENTS
A
1:50
A-703
TYPICAL STUDIO PLANS & ELEVATIONS
A
-
A-704
TYPICAL 1 BEDROOM PLANS & ELEVATIONS
A
-
A-705
TYPICAL 2 BEDROOM PLANS & ELEVATIONS
A
-
A-706
TYPICAL 3 BEDROOM PLANS & ELEVATIONS
A
-
A-801
TYPICAL DOOR SCHEDULE
A
-
A-802
TYPICAL WINDOW SCHEDULE
A
-
A-803
TYPICAL WALL SCHEDULE
A
-
A-901
SOLAR ANALYSIS DIAGRAM 01
A
1:1000
A-902
SOLAR ANALYSIS DIAGRAM 02
A
1:1000
WALL LEGEND WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
FLOOR LEGEND
DOOR LEGEND
WINDOW LEGEND
LIGHTING LEGEND
FT-01: STONE FLOOR 600x400x10mm BLANCO LIMESTONE
DT-01: DWELLING DOOR DOOR DIMENSION DOOR COMPANY
WI-01: CORRIDOR WINDOW STANEK WINODW WINDOW DIMENSION
LT-01: TRACK LIGHT (SHORT) 135x185x600mm NEVADA 1 LIGHT TRACK SPOT
FT-02: TOILET FLOOR 600x400x10mm PEWTER TRAVERTINE
WT02: FACADE WALL (V)
FT-03: POS FLOOR 600x400x10mm MALI FLAMED BLUESTONE
100mm TIMBER FIN 200mm PRECAST CONCRETE
FINISHING 500mm PRECAST CONCRETE
FT-05: GYM FLOOR 1000x1000x15mm MA1 RUBBER GYM MAT FLOOING
WT04: CORE WALL
RENDERED CONCRETE ON 200mm PRECAST CONCRETE
DT-04: AUTOMATIC DOOR (COS) DOOR DIMENSION DOOR COMPANY
WI-03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION LT-07: ROOFTOP LIGHT (POLE) 1960mm TALL TURIN SINGLE HEAD MEDIUM POST LIGHT
DT-06A: RETAIL DOOR (SINGLE) DOOR DIMENSION DOOR COMPANY
WT06: INTERNAL ROOM DIVIDER GYPSUM BOARD ON 100mm STEEL STUD WALL
CEILING LEGEND CT-01: CORRIDOR CEILING RECESSED CEILING GYPSUM BOARD
WT07: TOILET WALL PEWTER TRAVERTINE 100mm STEEL STUD WALL
CT-02: DWELLING CEILING 3600x250x7.5mm QUICKBOARD CEILING
WT08: EXTERNAL BI-FOLDING
WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION
DT-06B RETAIL DOOR (DOUBLE) DOOR DIMENSION DOOR COMPANY
WI-05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION
DT07: REFUSE DOOR DOOR DIMENSION DOOR COMPANY
LT-10: SUSPENDED TRACK LIGHT 180x165x2000mm DALIS LED SUSPENDED TRACK LIGHT
DT-09 ROOFTOP MECH DOOR DOOR DIMENSION DOOR COMPANY
LT-11: SUSPENDED PRUDENT LIGHT 1180x45mm LEDLUX SPEX 1.2m 2200 LUMEN
BI-FOLDING WINDOW 100mm PRECAST CONCRETE ON TOP
LT-12: STRIP LIGHT 1200x25x25mm FLUX STREAM LED STRIP
CT-05: TIMBER CEILING Lx90x30mm HEMLOCK TIMBER BEAM
WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE BELOW
CT-06: CAFE KITCHEN CEILING 600x300x10mm CLEAN ROOM FL
WT11: RETAIL CURTAIN WALL
CT-07: CAFE CEILING RECESSED CEILING GYPSUM BOARD
GENERAL NOTES
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
TITLE SHEET
SCALE @A1
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
DK&CW DM
As indicated
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
LT-09: CORRIDOR LIGHT 50x50x20mm LED OLYMPIA
CT-04: POS CEILING EXPOSED CONCRETE
WT09: INTERNAL BI-FOLDING
DOUBLE GLAZED CURTAIN WALL WITH ARGON GAS
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
LT-08: RECESSED LIGHT 350x159x2000mm LEDLUX PHAROS PENDANT LIGHT
DT-08 GLASS DOOR (COS) DOOR DIMENSION DOOR COMPANY
CT-03: BATHROOM CEILING 600x400x10mm PEWTER TRAVERTINE
BI-FOLDING WINDOW 100mm PRECAST CONCRETE BELOW
LT-05: POS LIGHT 300x300x100mm KOMBI SQUARE BUNKER LT-06: ROOFTOP LIGHT (BOLLARD) 150x90x600mm OKI BOLLARD BLACK
DT-05B: SERVICE DOOR (DOUBLE) DOOR DIMENSION DOOR COMPANY
FT-07: LOBBY FLOOR 1500x750x15mm SILVER GRANITE FLAMED
WT05: DWELLING DIVIDER
LT-04: WALL MOUNTED LIGHT 500x175x40mm LEDLUS DETA WALL BRACKET
WI-02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION
DT-05A: SERVICE DOOR (SINGLE) DOOR DIMENSION DOOR COMPANY
FT-06: RETAIL FLOOR 900x450x15mm Q STONE MINIMAL
FINISHING 300mm PRECAST CONCRETE
LT-03: DOWN LIGHT 150x88x20mm NEPTUNE ROUNG DOWNLIGHT
DT-03: CAVITY DOOR (STUDIO) DOOR DIMENSION DOOR COMPANY
FT-04: CONCRETE FLOOR CONCRETE FLOOR WITH SMOOTHING SURFACE
WT03: BASEMENT WALL
LT-02: TRACK LIGHT (LONG) 135x185x1200mm NEVADA 1 LIGHT TRACK SPOT
DT-02: ROOM DOOR DOOR DIMENSION DOOR COMPANY
APPROVED
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-000
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
STUDIO POS
1 BEDROOM LIVING ROOM
2 BEDROOM ENTRANCE
3 BEDROOM POS
LEVEL 05 COS
VIEW FROM STREET GENERAL NOTES
GROUND FLOOR LOBBY NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
SCALE @A1
3D VIEWS
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
10/12/18
CHECKED
APPROVED
Checker Approver
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-001
18-214 COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
9
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
2
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
3
NOTES
1
1. 2. 3. 4. 5. 6. 7. 8. 9.
MELBOURNE & METROPOLITAN TRAMWAY BOARD FORMER PRIMARY SCHOOL NO.2363 MELBOURNE UNIVERSITY SCHOOL OF EDUCATION AUSTRALIAN MENUFACTURING WORKER'S UNION FORMER INDEPENDENT MISSION HALL PIXEL 205 SWANSTON SQUARE DEVELOPMENT SHOP (HO99) METROPOLITAN FIRE BRIGADE FIRE STATION NO.3
8
QUEEN SBERR Y STRE ET
1 A
2
3
4
5
6
B
5 4
C D E
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
6
F G H
RMIT DANIEL MAUNDERS
BOUVERIE STREET
PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
PROPOSED SITE PLAN DATE
CHECKED
APPROVED
27/08/18
DK&CW
DM
SCALE
1 : 200
0
1
2
4
6
10.0M
@A1
STATUS
7
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-101
A
COPYRIGHT
1
A-101
PROPOSED SITE PLAN 1 : 200
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
LANDS DOWN E PLAC
E
CLIENT
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
QUEENSBERRY ST
A-103 2
1
2
3
4
5
6
A EXISTING BUILDING 11m (HIDDEN FOREST)
EXISTING BUILDING 10m (SPANISH ACQUISITION)
B
A-103
3
C D
1
A-103
EXISTING BUILDING (BRIDGESTONE TYRES) TO BE REMOVED 436.1m2
E
BOUVERIE ST REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
F
G CLIENT
RMIT DANIEL MAUNDERS
H
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
EXISTING AND DEMOLITION PLAN DATE
CHECKED
APPROVED
27/08/18
DK&CW
DM
LANSDOWNE PL
EXISTING BUILDING 25m (71-79 BOUVERIE ST)
SCALE
1 : 100
0
0.5 1
2
3
5.0M
@A1
STATUS
EXISTING BUILDING 16m (23-37 LANSDOWNE PL)
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-102
A
EXISTING BUILDING 16m (INDEPENDENT DISABILITY SERVICE) COPYRIGHT
1
A-102
LEVEL 00 DEMOLITION PLAN 1 : 100
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
PROJECT
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
EXISTING BUILDING 20m (FORMER PRIMARY SCHOOL)
EXISTING BUILDING 25m (71-79 BOUVERIE ST)
EXISTING BUILDING (BRIDGESTONE TYRES) TO BE REMOVED
QUEENSBERRY ST
NOTES
EXISTING BUILDING 12m (CARLTON TRAM SUBSTATION)
FFL 29.000 GROUND FLOOR
1
A-103
DEMOLITION EAST 1 : 100
EXISITNG BUILDING 11m (HIDDEN FOREST)
EXISTING BUILDING 20m (PIXEL BUILDING)
EXISTING BUILDING (BRIDGESTONE TYRES) TO BE REMOVED
BOUVERIE ST
LANSDOWNE PL
EXISTING BUILDING 10m (THE SPANISH ACQUISITION)
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
FFL 29.000 GROUND FLOOR CLIENT
RMIT DANIEL MAUNDERS 2
A-103
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
DEMOLITION NORTH 1 : 100
DRAWING TITLE
EXISTING CONDITION / DEMOLITION ELEVATION DATE
CHECKED
APPROVED
08/01/18
DK&CW
DM
SCALE
1 : 100
0
0.5 1
2
3
5.0M
@A1
STATUS
18-214
DRAWING NUMBER
REVISION
A-103
EXISTING BUILDING 12m (CARLTON TRAM SUBSTATION)
EXISTING BUILDING (BRIDGESTONE TYRES) TO BE REMOVED
QUEENSBERRY ST
PROJECT #
DD
A
EXISTING BUILDING 25m (71-79 BOUVERIE ST)
FFL 29.000 GROUND FLOOR
COPYRIGHT
3
A-103
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
DEMOLITION WEST 1 : 100
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
PROJECT
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
1
2
3
4
5
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
6
NOTES
500
5440
1
2
A-501
A-501
8177
300
2680
700
1457
700
830
400
800
LIFT FIXING TO REFER MANUFACTURER'S DETAIL 'SCHINDLER 3300NA' BIKE RACK AND FIXING STATION TO REFER MANUFACTURE'S DETAIL 'SECURA BIKECBR10GS'
•
500
WT-03
2000
STUDIO 3 BED
2 BED
2 BED
STUDIO
3000
1 BED
2600
200
1010
A
22657
150
•
STUDIO
2 BED
3 BED
3 BED 1 BED
1 BED
400
2 BED
3 BED
3 BED
STUDIO
6922
1 BED
STORAGE TO BE ALLOCATED TO EACH DWELLING. ALLOCATION TO BE DECIDED BY MANAGING CORPORATION
2 BED
2 BED
2 BED
1 BED
9197
2 BED
STUDIO
WT-04
STUDIO
1 BED
BIKE STORE
4522
1 BED
9572
B
5164
WT-03
STUDIO
STUDIO
FT-04
STUDIO
1 BED
1 BED
1 BED
1 BED
11872
DT-02 STUDIO
WT-11
1758
HYDRALIC ROOM
2
STUDIO
2
STUDIO
FT-04
A-502
A-502
3510
C
STUDIO
STUDIO
FT02 DT-02
BIKE RACK AND FIXING STATION TO REFER MANUFACTURE'S DETAIL 'SECURA BIKECBR10GS'. LAYOUT TO COMPLY AS28090.3
D
STUDIO
DT-04
STUDIO
STORAGE FT-04
STUDIO
DT-04
1700
1398
1000
1100
1000
2645
1700
1057
20372
2167
1 BED
1 BED
STUDIO
LIFT CORE
11122
TOILET
200
1900
2350
1900
2500
2100
2400
CORRIDOR
WT-04
WT-05
DATE
DESCRIPTION
20/08/2018
PROJECT SETUP
1
WT-05
A-502
2100
1 A-502
REV A
FT-04
13767
E
620
DT-01
880
5593
1000
DT-01
500
1700
1017
DT-04
DT-01
300
880
200
1577
WT-05 WT-04
CLIENT
SWITCH EQUIPMENT TO REER MANUFACTURE'S DETAIL
BUILDING FOOTING TO REFER STRUCTURAL ENGINEER'S DETAIL
500
2717
200
2783
2 A-501
300
4650 14367
300
2817
BASEMENT FLOOR PLAN
300 1608
550
5532
400
DATE
CHECKED
APPROVED
27/08/18
DK&CW
DM
SCALE
5450
5500
5500
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
3950
200
1 A-501
400
300
F RAINWATER CAPTURED ON ROOF TO BE RECYLED THROUGH WATER TANK
PROJECT
1 : 50
0 0.2
0.5
1.0
1.5
2.5M
@A1
STATUS
1550
G
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-201
A
H
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
COMMUNICATION EQUIPMENT TO REER MANUFACTURE'S DETAIL
RMIT DANIEL MAUNDERS
2400
SWITCHBOARD ROOM FT-04
FIRE STAIRCASE
300
2700
FIRE STAIRCASE TO COMPLY AS-1657
FT-04
3000
COMMS ROOM
2500
FT-04
FIRE PUMP ROOM
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
1
2
3
4
5
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
6
NOTES
22657 4950
400
A-401
6150
4600
1
200
200
400
200
DT-06B
3007
2
4950
1
A-501
A
5150
6000
3000
200
200
5707
400
A-501
DT-06B
DT-06B
DT-06B
410
200
WT-11
WT-11
REFER TO RETAIL 01 OCCUPANT FOR FURNITURE AND EQUIPMENT LAYOUT/DETAIL
WT-11
REFER TO RETAIL 02 OCCUPANT FOR FURNITURE AND EQUIPMENT LAYOUT/DETAIL
WT-11
REFER TO RETAIL 03 OCCUPANT FOR FURNITURE AND EQUIPMENT LAYOUT/DETAIL
2590
2600
3000
WT-11
REFER TO RETAIL 04 OCCUPANT FOR FURNITURE AND EQUIPMENT LAYOUT/DETAIL
WT-05
FT-06
WT-05
WT-05
RETAIL 01
RETAIL 02
4172
FT-06
RETAIL 03
RETAIL 04
FT-06
FT-06
FT-06
4172
WT-11
4522
7422
7422
7422
7422
400
400
B
WT-11
DT-06B
2
2
A-502
A-502
300
C
2
MAILBOX TO WALL
2750 FIRE CONTROL ROOM 3120
WT-04
1500
1900
A-402
FIRE CONTROL EQUIPMENT TO REFER ENGINEER'S DETAIL
ELECTRICAL SERVICE EQUIPMENT TO REFER ENGINEER'S DETAIL
WT-04
LIFT CORE
WT-11
FT-06
400
D 6051
20372
ELECTRICITY SERVICE ROOM
FURNITURE FOR LOBBY AREA TO BE DECIDED BY CLIENT
LOBBY
WT-04
DT-01
17357
FT-07
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
1
FT-06
A-502
2097
2400
1 A-502
WT-11
DT-06B
WT-09
1800
E
900
300
4650
300
4725
550
5780
11057
WT-04
2700
DT-01
COMM
FIRE STAIRCASE
150
1200
FURNITURE FOR CAFE AREA TO BE DECIDED BY CAFE OCCUPANT
1200 4650
CAFE FT02
550
4750
BI-FOLDING DOORS TO BE USED BY CAFE OWNERS
WT-09
2400
WATER METRE EQUIPMENT TO REFER ENGINEER'S DETAIL 2750
9500
FT-06
CLIENT
RMIT DANIEL MAUNDERS
CAFE FURNITURE TO BE POSITIONED TO ALLOW FREE FLOW MOVEMENT ACROSS SITE
12200
2630
DT-01
WATER METRE ROOM
PROJECT DT-08A
400
300
F
400
WT-11
DRAWING TITLE
REFUSE STORE DT-07
FT-04
GROUND FLOOR PLAN
12987 2500
3600
5900
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
WT-11
WT-11
150
5200
KITCHEN
GAS METRE ROOM
DT-10
KITCHEN EQUIPMENT TO REFER CAFE OCCUPANT
STORAGE
WT-11
FT-04
WT-11
FT02
DT-02
DT-02
DT-02
MALE TOILET FT02
DM
SCALE
1 : 50
0 0.2
0.5
1.0
1.5
2.5M
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-202
DT-01
A
300
300
150
APPROVED
DK&CW
STATUS FT02
DT-10
H
CHECKED
27/08/18
@A1
DT-02
DT-02
FEMALE TOILET DT-10
WT-11
GAS METRE EQUIPMENT TO REFER ENGINEER'S DETAIL
1550
FT02 TO BE WATERPROOFED AND SLOPED FOR DRAINAGE
FT-04
2550
G
DATE
DT-02
5150
DT-02
2700
3950
RUBBISH TO FALL INTO COMPRESSOR WHICH TRANSFERS INTO BINS. REFER TO MANUFACTURER'S DETAIL
FT02 TO BE WATERPROOFED AND SLOPED FOR DRAINAGE
WT-04
FT02 TO BE WATERPROOFED AND 1 DRAINAGE SLOPED FOR
A-402 300
3000
150
2750
150
3030
142
3030
100
3698
200
5957
150 COPYRIGHT
1
2
A-501
A-501
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
DT-01 300
WT-11
1
2
3
4
5
GENERAL NOTES
6
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
22657 200
4950
100 200
1900 100
1283
1600
1000
100
917
2900
200
5150
3575 100
575
3475
1000
100
200
1500
2950
WT-02
WT-01
3000
2207
100
4200
3807
100
WI-03
7
4100
WT-02
WT-02
WT-01
A-501
WT-01
WT-01
WI-03
WI-02
FT-01
FT-03
POS WT-09
2172
KITCHEN
WT-09
3000
BEDROOM BEDROOM (M)
3600
4200
FT-01
WT-01 TIMBER FIN FACADE TO REFER A-601/602 FOR CONSTRUCITON DETAIL
AP-1-0-2
FT-01
BEDROOM (M)
WT-09
3100
BEDRROM (M)
LIVING ROOM
DT-02
100
3050
KITCHEN
2971
2400
2
WT-06
FT-02
FT-01
WT-02 FT-02
TOILET
DT-02
5
TOILET
1000
1900
LIFT CORE
WI-04 WT-02
TOILET
WT-09
FT-02 WT-05
2000
1450
A-703
FT-02 TOILET FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE DT-02
DT-02
6 WT-02
3400
WI-04
DT-01
CORRIDOR
WI-01 FOR NATURAL LIGHT INTO CORRIDOR TO COMPLY BADS ANALYSIS
WT-01
WT-01
WT-02
WT-02
LV01
WI-01
WT-01
FT-01
WT-09 BI-FOLDING WALL TO REFER A-601/602 FOR CONSTRUCTION DETIAL
LIVING ROOM
1400
DT-01
WT-01
AP-1-1-1
9578
WT-09
DT-01
1
2400
A-502 DT-05B
DT-05B
DT-01
DT-01
WATER
ELECTRICAL
4272
DT-05A
DT-01
POS
7079
1
3400
200
FT-03
WI-03
GAS METER
A-602
FT-03 POS FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
E 2017
1828
WT-01
FT-01
BIN CHUTE
WT-05
CLIENT
9007 LIVING ROOM
WI-02
AP-1-2-2
DT-02
100
PROJECT
WT-06
DT-02
WT-06
A-705
8
WT-09
A-705
WT-05
TOILET
3950
LIVING ROOM
2950
WT-09 WT-06
WT-01
1
FT-02
TOILET 4
DT-02
DT-02
FT-02
AP-1-1-2
DRAWING TITLE
A-705
FT-01
5200
3
WT-06
BEDROOM (M)
100 75
FT-01
POS
2600
1000
350
6
A-705
5
1700
1 A-501
FT-02 TOILET FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
Level 01
DM
STATUS
10378
1 A-402
APPROVED
DK&CW
1 : 50
300 10378
CHECKED
27/08/18 0 0.2
0.5
1.0
1.5
2.5M
@A1
300
100
DATE
SCALE
-
150
100
BEDROOM
FT-03 POS FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
A-705
FT-01 WI-04
WI-04
100
1550
1000
350 KITCHEN
3700
WI-04
250
5578
7
200
G
WT-09
FT-03
WT-09
1000
4400
4600
FT-03
1925
TYPICAL LOWER FLOOR PLAN (1/F)
WT-02
POS WT-02
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
100
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-203
A
2 A-501
FT-02 TOILET FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
1 : 50
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
1083
DT-02
2
RMIT DANIEL MAUNDERS
3000
1000
KITCHEN FT-01
WI-03
WT-01
150
PROJECT SETUP
200
4100
FIRE STAIRCASE
4100
4300
2700
WT-06
3000
A-203
DESCRIPTION
20/08/2018
DT05
FT-01
1
DATE
FT-01
COMMS
BEDROOM (M)
F
REV A
KITCHEN
1600
WT-01
H
A-502
WT-01 FT-01
1600
WT-06
2600
1100
FT-02
2
BEDROOM (M)
DT-02
DT-01 WT-01
A-401
WI-03
FT-01
3500
TOILET
2100
2000
3072 1500 5472
WI-02
KITCHEN
WT-05
DT03
1400
WT-01
1907
AP-1-0-1
3600
D
1900
200
1472 4522
DT-02
3
A-703
LIVING ROOM
WT-09 WT-01
2
WT-02
WI-03
AP-1-2-1
4
C
WT-01
LIVING ROOM
3101
4000
4200
WT-09
1
A-703
B
20372
WT-02
FT-03
3000
1
NOTES
WT-09
2 FT-03
A-502
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
WT-02
POS
WT-02
A-402
DO NOT SCALE OFF DRAWINGS.
100
2
WI-05
WT-05
POS
A-502
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
100
1
A-703
2
200
2000
100
2050
A-401
A-501
WT-01
1000
3007
100
200
A
WT-02
1250
2325
1 WT-09 BI-FOLDING WALL TO REFER A-601/602 FOR CONSTRUCTION DETIAL
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
6150
1
2
100
4500
100
2440
4300
100
3
19657
860
1000
200
2000
1280
1000
4
100
5117
800
1500
100
1000
1500
5
3100
1217
1900
1000
1900
100
GENERAL NOTES
6
3000
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
100
1700
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
100
DO NOT SCALE OFF DRAWINGS.
1
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
2
A-501
A-501
A-401
NOTES 1
3000
A
WT-01
B
WT-02
680
75
1060
WT-01
75
WT-02
1070
75
WT-01
1060
WT-01
75 590
1710
WT-01
790
1710
WT-01
1007
1210
WT-02
1720
75
1900 100
75
100
100
4500
100
WT-02
WI-04
WI-04
WI-02
WI-02
WT-01 TIMBER FIN FACADE TO REFER A-601/602 FOR CONSTRUCITON DETAIL
WT-02
WI-03
1600
POS WT-09
DT-02 WT-06
FT-03
POS
FT-02
WT-05
FT-03
3
A-704
2
A-704
6
2788
WT-06
2
DT-03
BEDROOM (M)
A-502
DT-02
KITCHEN
AP-6-0-3
100
75
4
WT-04
WT-01
FT-02 TOILET FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
980
FT-01
800
1000
DT-01 WI-03
200
AP-6-1-3
C
WT-04 DT-01
6 CORRIDOR WI-01 WT-01
FT-01
LV06
DT-05
DT-01
A-706
DT-02
DT-05
DT-05
ELECTRICAL
GAS METER
WT-06
REV
3000
WT-04
DT-05
WI-02
FT-01
LIVING ROOM
COMMS
AP-6-3-1
WT-01
1120
CLIENT
LIVING ROOM
RMIT DANIEL MAUNDERS WT-06
WI-03
WT-09
POS WT-02
DT-02
FT-03
4600
1400
WT-09
WT-09
A-706 7
DRAWING TITLE
A-706 BEDROOM 9
WT-09 BI-FOLDING WALL TO REFER A-601/602 FOR CONSTRUCTION DETIAL
1600
100
BEDROOM
DT-02
FT-01
FT-02 WT-01
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
KITCHEN
4600
DT-03
PROJECT
POS
TOILET
WT-06
WT-06
FT-01
WT-06
TYPICAL UPPER FLOOR PLAN (6/F)
8
A-706
FT-02
FT-03
FT-03 POS FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
WT-02 WI-03
WI-04
WI-03
DATE
CHECKED
APPROVED
27/08/18
DK&CW
DM
100 4950
75 376 75
1060
75
1983
1210
1947
75
1060
75
1557
1210
1053
75
2600
100
100
WI-04
SCALE
1 : 50
0 0.2
0.5
1.0
1.5
2.5M
1500
@A1
WT-02
WT-01
WT-02
WT-01
WT-01
WT-02
WT-01
WT-01
WT-02
STATUS
H 100 100
4700 4900
100 100
606
1000 1700
2193 200
1000 3000
2157 100
1000
1767
3057
100
1000
1233
3700
1 A-501
FT-02 TOILET FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
Level 06
2400 2600
1 A-402
100
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
100 100
A-204
2 A-501
FT-02 TOILET FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
COPYRIGHT
1 : 50
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
AP-0-4
4400
1000
FT-01
100
75
BIN CHUTE
F
1800
1
A-706
WT-01
1200
5797
WT-04
1300
1000
KITCHEN
WT-04
FT-01 WI-05
WT-02
BEDROOM (M)
100
DESCRIPTION
1500
WT-06
WT-06
FIRE STAIRCASE
1
DATE
WT-01
WT-04
A-204
1 A-502
2
DT-01
WATER
KITCHEN
G
1000 WT-01
100
104
3
WI-05
3000
DT-03
WT-01 WT-01
1197
A-706 FT-02
FT-01
1520
WT-01
1310
1
WT-01
WI-01 FOR NATURAL LIGHT INTO CORRIDOR TO COMPLY BADS ANALYSIS
1710
1404 15872
WI-03
DT-01
A-502
E
BEDROOM (M)
5
100200
D
A-706
ENSUITE TOILET
WI-03
WT-01
1210
LIFT SHAFT
2 884
A-402
A-401
BEDROOM 7 (M)
WT-01
4872
2
WT-06
FT-02
2
1
A-704
A-704
4
FT-01
TOILET
WT-09
FT-01
LIVING ROOM
4572
TOILET
4772
WT-06
4772
WT-06
KITCHEN
A-502
FT-03 POS FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
5
WT-09 BI-FOLDING WALL TO REFER A-601/602 FOR CONSTRUCTION DETIAL
100
1800
WT-02
1
1
2
2
3
A-501
100200
4
A-501
5
899
800 75
1103
75
1060
75
637
75
3675
75 395 75
1060
75
2700 1040
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
200100
17157
1900
GENERAL NOTES
6
22057
75
1060
75
1840
75
1560
70
2032
75
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
500
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
4200
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
A-401 FOR PLANTING SCHEME REFER TO LANDSCAPE ARCHITECTURE'S PLAN
WT-02
WT-01
WT-02
WT-01
WT-01
WT-02
WT-01
WT-02
WT-01
WT-02
WT-01
NOTES
WT-02
1
200100
A
WT-02
WT-10
WT-02
GARDEN
WT-10
WT-06 LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06 LT-07
WT-02
COS
WT-09
1850
WT-02
4200
2700
LT-07
WT-11 FT-03
14601 151100 1124
B
5257
OVERHEAD
WT-01
OVERHEAD
WT-01 TIMBER FIN FACADE TO REFER A-601/602 FOR CONSTRUCITON DETAIL WT-02
WT-02
WT-05 WT-11
75
WT-10
WT-01
OVERHEAD
YOGA
1292
FT-05
4322
WT-01
WT-02
GYM AND YOGA EQUIPMENT TO REFER MANUFACTURE'S DETAIL
1560
3892
6321
75
16150
LT-06 WT-02
LT-06
2 A-502
75
WI-01 FOR NATURAL LIGHT INTO CORRIDOR TO COMPLY BADS ANALYSIS
WT-01
WT-01
FT-05
A-502
LT-06
890
C
A-401
2
GYM
WT-05
2
DT-02
1060
LIFT CORE
WT-02
WT-01
WT-09
FT-02
WT-10 LT-06
COS
WT-04
GARDEN
WT-02
FT-03
395 75
200
D
WT-04
DT-01
LT-06
DT-08
1200
1400
20372
9150
1
CORRIDOR
WT-01
A-502
WT-02
WI-01
WT-01 WT-02
FT-01 WT-01
DT-05
DT-01
2212
1912
1
LT-06
DT-05
DT-05
ELECTRICAL
GAS METER
DT-01
A-502
1157
WATER
WT-05
E
WT-11
LV05 WT-09
200
WT-01
1400
2
1305
A-402
WT-05
TOILET
2000
WT-04 WT-05
11822
75
FT-02 TOILET FLOOR TO BE WATERPROOFE D AND SLOBED FOR DRAINAGE
DATE
DESCRIPTION
FT-03 COS FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
4057
1400
WT-05
REV
LT-06
LT-06 WT-04
WT-01
COMMS
DT-05
WT-09 WT-04
4700 FIRE STAIRCASE
WT-01 WT-04
FT-01
BIN CHUTE LT-06
F
CLIENT
RMIT DANIEL MAUNDERS
7250
903
7250
3614
WT-02 DT-08
PROJECT
WT-04
700
RAISED PLANTER TO EDGE OF SITE, REFER TO A-652 FOR DETAIL
WT-09 WT-10
5257 3500
11450 FT-03
COS
4694
DT-08
WT-10
1875
DRAWING TITLE
WT-10 TIMBER FINS TO BE ATTACHED ONTOP OF PLANTER WALL
WT-05
G
DATE
CHECKED
APPROVED
09/20/18
DK&CW
DM
WT-10
OVERHEAD 700
OVERHEAD 1300
WT-05 LT-06
WT-02
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
SCALE
LT-07
1 : 50
LT-06
LT-07
GARDEN
LT-07
9978
200
672
300
728
200
9978
1
WT-04
1 A-501
1
STATUS
22575
300
100200
A-205
0.5
1.0
1.5
2.5M
GARDEN
WT-05 WT-01
0 0.2
@A1
LT-07
H
COS LEVEL 05
WT-02 WT-10
4675
WT-02
WT-01
OVERHEAD
WT-02
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
A-402
200100
18-214
DRAWING NUMBER
REVISION
A-205
WT-04
PROJECT #
DD
2 A-501
Level 05 1 : 50
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
1210
LT-06
WT-04
STUDY
1
2
3
4
5
GENERAL NOTES
6
19657
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
3000
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
100200
899
100
1579
12328
450 100
1900
100
1600
200100
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
1
2
A-501
A-501
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
3000
3000
A
FOR PLANTING SCHEME REFER TO LANDSCAPE ARCHITECTURE'S PLAN
WT-02
WT-01
WT-02
WT-01
WT-02
WT-01
WT-02
WT-01
WT-02
WT-01
WT-02
B
200100
WT-01
200100
WT-02
WT-02 LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
900
LT-06
WT-01 TIMBER FIN FACADE TO REFER A-601/602 FOR CONSTRUCITON DETAIL
GARDEN
100
LT-07
2000
LT-07
WT-10 WT-01
3272
WT-10
LT-06
LT-06
FT-03
2
3701
A-502
2
WT-10
GYM AND YOGA EQUIPMENT TO REFER MANUFACTURE'S DETAIL
4750
1700
2
6207
LT-06
A-502
LT-06 WT-02
ROOF ABOVE LT-06
LT-06
WT-10
DT-01
LT-06
2100
LT-06
A-402
WT-10
2
WT-04
TOILET
WT-04
LIFT CORE
LT-06
FT-02 TOILET FLOOR TO BE WATERPROOFE D AND SLOBED FOR DRAINAGE
WT-04 WT-02
WT-06
2672
C
WT-01 LT-06
LT-07
WT-02
6250 WT-01
FT-03
1
WT-10
FT-03
CORRIDOR
DT-04
1
WT-02
COS
200104
WT-01
DT-04
DT-05
DT-05
A-502
WT-01
DT-05
2700
A-502
1400
WT-02
1604
WT-02
1200
500 100
100200
WT-01
D
DT-01 WT-01
WATER
LT-07
E
A-401
450
6272
LT-06
ELECTRICAL
GAS METER FT-03 COS FLOOR TO BE WATERPROOFED AND SLOBED FOR DRAINAGE
WT-10
6807
3701
LT-06
500 100 500
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
WT-02
FT-03
LT-06
COMMS
DT-05
WT-10
Room WT-04
LT-06
WT-01
WT-04
WT-04
LT-07 FT-03
WT-10
LT-06
BIN CHUTE
CLIENT DT-09
DT-09
LT-06
LT-06
RMIT DANIEL MAUNDERS
LT-06
783
ROOF ABOVE WT-04
MECH PLANT
4250
WT-02
2697
F
7196
LT-06
WT-10 LT-06
WT-01
LT-06
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
RAISED PLANTER TO EDGE OF SITE, REFER TO A-652 FOR DETAIL
HV-01
WT-10
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
HV-01
DRAWING TITLE HV-01
HV-01
HV-01
HV-01
HV-01
ROOFTOP PLAN
LT-06
LT-07
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-07
WT-10 TIMBER FINS TO BE ATTACHED ONTOP OF PLANTER WALL
DATE
CHECKED
APPROVED
27/08/18
DK&CW
DM
100200
WT-02
100200
G
LT-06
903
97
LT-06
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
LT-06
HV-02
LT-06
WT-02
HV-01
PROJECT
SCALE
1500
1 : 50
0 0.2
0.5
1.0
1.5
2.5M
@A1
WT-02
WT-01
WT-01
WT-02
WT-01
WT-02
WT-01
WT-02
WT-01
WT-02
STATUS
H 100200
899
100
16357
100
1
1 A-501
A-402
1600
200100
3000
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-206
A
2 A-501
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
WT-01
100 500
WT-02
3496
3496
LT-06
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
1
2
200
3
4950
500
4
6150 5440
5
5150
150
8177
3007 300
3000
200
7689
1
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
6
NOTES
400
2
A-501
A-501
A-401
A
1
500
200
WT-03
LT-12
3000
LT-12
LT-12
LT-12
LT-12
LT-12 WT-04
WT-03
WT-11 LT-12 LT-12
LT-12
LT-12
LT-12
LT-12
LT-12
LT-12
LT-12
LT-12
LT-12
400
400
B 730
700
6922
LT-12
700
785
LT-12
4522
LT-12
LT-12
LT-12 DT-02
2
A-401
3510
LT-12
LT-12
LT-12
LT-12
2
LT-12
1758
LT-12
2
A-502
A-502
100
WT-11
C
LT-12 LT-03
LT-12
LT-03
STORAGE ROOM TO HAVE EXPOSED CEILING LT-12
2
200
D
LT-12
LT-03
608
LT-03
140
CORRIDOR CEILING TO BE RECESSED FITTED WITH LT-01
CT-01
13767
DESCRIPTION
1 A-502
2100
A-502
DATE
200
E
DT-01
DT-01
300
440 140
2400
1 2100
REV
550
122
830
A-402
2050
1900
2500 CT-03
DT-01 WT-04
550
LT-12
2817 LT-12
CLIENT
WT-04
2500
WT-04
RMIT DANIEL MAUNDERS
WT-05 WT-04 LT-12
WT-04
WT-04
BUILDING FOOTING TO REFER STRUCTURAL ENGINEER'S DETAIL
LT-12
LT-12 WT-04
300
F
PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
BASEMENT RCP
PLANT ROOM TO HAVE EXPOSED CEILING
3950
PLANT ROOM TO HAVE EXPOSED CEILING
DATE
CHECKED
APPROVED
10/12/18
DK&CW
DM
SCALE
5500
1 : 50
0 0.2
0.5
1.0
1.5
2.5M
@A1
STATUS
G
18-214
DRAWING NUMBER
REVISION
1550
A-300
150
H
PROJECT #
DD
1 A-402
1
2
A-501
A-501 COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
2783
2500
2700
2717
2500
WT-05
LT-12
1
2
3
4
1
GENERAL NOTES
6
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
2
A-501
200
5
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
A-501
4950
6150
5150
3007
3000
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
200
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
A-401
NOTES
200
1
DT-06B
DT-06B
1111
1219
578
1151
1219
1261
1219
1150
568
1219
1629
1629 1219
1347
1219
596
827
1219
1641
1219
800
LT-11
LT-11
LT-11
LT-11
LT-11
LT-11
LT-11
LT-11
LT-11
LT-11
1843
305
305
LT-11
CL
1900
2
1395
CL
505
CL
CL
605
623
CL
625
CL
CL
635
CL
655
2
CL
626
CL
595
CL
593
628
CL
505
CL
605
CL
623
CL
625
CL
CL
635
A-502
CL
655
626
CL
CL
595
593
CL
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
933 LT-09 DROP LIGHTS TO HANG FROM EXPOSED CEILING
CL
CL
D
305
305 421
LT-12
1470
A-402
825
CL
1900
LT-12
1200
900
640
725
DT-06B
LT-11
1143
1143
C
1143
LT-11
2 A-502
1143
305
305
4522
1843
LT-11 SUSPENDED LIGHTS TO HANG FROM EXPOSED CEILING
305 LT-11
1843
LT-11
1843
LT-11
LT-11
305
LT-11
LT-11
1843
LT-11
305
B
LT-11
1843
LT-11
1843
LT-11
1843
LT-11
305
305
305
3000
573
DT-06B
1629
DT-06B
1629
A
LT-12
LT-12
825 610
LT-03 DT-01
LT-03
700
LT-03
2000
LT-03
2000
LT-03
2000
CT-05 TIMBER FEATURE CEILING TO BE FIXED TO WALLS
A-502
2100
600
CL
590
1
CT-05
880
2400
A-502
DT-01
1690
1
LT-03
2000
LT-03
2000
LT-03
2000
2000
LT-03
2000
DT-06B
807
CL
LT-12
1200
CL
1000
LT-10
1000
LT-10 LT-12
565
CL
565
2700
PROJECT SETUP
825 CL
725
LT-12
DESCRIPTION
20/08/2018
1031
1031
1185
1535
LT-12
DT-01
DATE
CL
E
REV A
DT-01
1145
600
1055
1125
CL
F
600
LT-12
LT-10
LT-10
LT-12
CLIENT LT-10
RMIT DANIEL MAUNDERS
LT-10 LT-09
950
LT-12
LT-09
LT-09
LT-09
LT-10
LT-03
CL
LT-10
LT-12 DT-02
LT-09
LT-09
LT-09
LT-09
DT-02
512
DT-02 LT-03
LT-03
LT-03
890
LT-03
LT-03 DT-02
DT-10
1040 725
1200
CT-03
LT-03
825
CT-03 DT-02
405
DT-10
LT-03
LT-03
LT-03
LT-03
LT-03
150
650
LT-12
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09
LT-09 DROP LIGHTS TO HANG FROM EXPOSED CEILING
DRAWING TITLE
GROUND RCP DATE
CHECKED
APPROVED
27/08/18
DK&CW
DM
SCALE
1 : 50
0 0.2
0.5
1.0
1.5
2.5M
@A1
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-301
1
1
1006
870
CL
CL DT-01
LT-12 STRIP LIGHTS TO HANG FROM EXPOSED CEILING
A-301
LT-09
LT-10 LT-12
H
1025
LT-09
CL
1200
LT-09
CT-03
DT-02
CL
CL
1040
LT-12
650
1550
775
LT-09
LT-10
CL
860
860
DT-10
DT-02
LT-03 LT-12
LT-09
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
LT-03
LT-03
G
LT-09
994
CT-06
375
LT-03
537
785
LT-12
LT-09
LT-10
972
3950
LT-12
LT-10 LT-10
CL
LT-03
LT-09
LT-09
4169
CL
LT-09
910 1000
1200
CL
910 LT-12
2500
LT-12
915
LT-12
CL
PROJECT CL
DT-07
LT-09
A
A-402
1
2
A-501
A-501
GROUND FLOOR RCP 1 : 50 COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
600
1497
775
DT-08A
CL
950
CL
LT-10
LT-10
1
2
3
4
1
GENERAL NOTES
6
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
2
A-501
200
5
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
A-501
4950
6150
5150
3007
3000
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
200
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
A-401
NOTES
200
1
A
LT-03 LT-05
CT-04
LT-05
3000
LT-03
LT-03
LT-05
LT-03
A-703
LT-03
CT-04
LT-05
LT-05
LT-05 POS LIGHT TO BE FIXED TO EXPOED CEILING
CT-02
2
LT-03
LT-03
CT-02
1 LT-02
LT-02
LT-02
LT-02
CT-04
LT-03 LT-03
B
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
CT-02 LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
CT-02
LT-05
CT-02 LT-03
LT-03
LT-03 LT-01
4
A-703
LT-01
LT-03
3 LT-03
LT-03
LT-03
LT-03
LT-03
LT-01
LT-03 LT-03
LT-01
LT-03
4522
LT-01
2
LT-01 LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
A-401
LT-03
CT-02 CT-03
CT-03
LT-01
2
LT-04
A-502
LT-03
LT-03
LT-03
LT-03
LT-03
LT-04
C
180
DT-01
LT-03
CT-03
1900
A-402
5
LT-03
LT-03
LT-04
LT-03
LT-03
LT-03
LT-03
LT-03
A-502
LT-03 LT-03
LT-03
LT-03 LT-03
LT-03
LT-03
LT-03
CT-03
A-703
LT-03 LT-03
2
2
CT-02
LT-03
LT-03
6
LT-03
LT-03
LT-03
LT-04
D CORRIDOR TO HAVE RECESSED CEILING WITH LT-08
LT-02 CT-01
LT-08
DT-01 LT-03
DT-05A
DT-01
DT-05B
DT-05B
LT-03 LT-03
LT-03
300
1
LT-03
LT-01
DT-01
DT-01
LT-03
LT-03
LT-03
A-502
180140
2400
A-502
E
LT-05
180
760
1400
190
1
DT-01
140180
DT-01
CT-04
LT-02
CT-02
LT-03
DATE
DESCRIPTION
20/08/2018
PROJECT SETUP
LT-03
1000
300
LT-01
LT-02
LT-05 POS LIGHT TO BE FIXED TO EXPOED CEILING
DT05 LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-05
CT-02
2700
REV A
CT-02
F
LT-03
LT-03
CLIENT LT-03
LT-03
2
LT-04 LT-03
LT-03
RMIT DANIEL MAUNDERS
LT-01
LT-03
LT-03
LT-03
LT-03
LT-01
LT-03
LT-01
LT-01
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
A-705
LT-03 CT-03
LT-04
LT-05
1 3950
LT-03 LT-03
CT-02
4
LT-03
LT-03
DRAWING TITLE
A-705 LT-03
CT-04 LT-02
TYPICAL LOWER FLOOR RCP LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-05
LT-03
CT-04
3
LT-03 LT-02
CT-03
LT-02 CT-02 CT-02 LT-03
LT-03
G
7
DATE
CHECKED
APPROVED
27/08/18
DK&CW
DM
A-705 6 1550
CT-02
LT-01
LT-03
LT-03
-
A-705
5
SCALE
1 : 50
LT-03
0 0.2
0.5
1.0
1.5
2.5M
@A1
LT-05
150
LT-05
H
PROJECT
STATUS
18-214
DRAWING NUMBER
REVISION
A-302
1
PROJECT #
DD
A
A-402
1
2
A-501
A-501
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
LT-03
1
2
200
3
4950
4
6150
5
5150
3007
GENERAL NOTES
6 3000
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
200
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
19657
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
3000
DO NOT SCALE OFF DRAWINGS.
1
2
A-501
A-501
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
A-401
NOTES
200
1
3000
A
B LT-05
DT-02
LT-05 CT-04
LT-03 LT-03
LT-03
LT-05
5
LT-05 POS LIGHT TO BE FIXED TO EXPOED CEILING
LT-03 LT-02 CT-03
CT-02
LT-03
LT-02
LT-02
A-704
3
6
A-704
LT-03
LT-03
LT-03 CT-04
2
CT-01 LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
A-704
LT-03
4
LT-04
LT-03
LT-03
7
A-502 CT-02
AP-6-0-3
CT-01
LT-03
DT-03
BEDROOM (M)
LT-05
LT-04
DT-02
A-401
LT-03
LT-01
2
2
LT-03
2 A-502
LT-03
LT-03
LT-03
C
LT-03 DT-01 LT-03
LT-03
LT-03
LT-03
4
CT-02
A-402
LT-03
LT-03
LT-03
DT-01
2
LT-03
LT-03
LT-03
A-706
LT-03
CT-03
D
LT-04
DT-01
LT-03
6
20022
CORRIDOR TO HAVE RECESSED CEILING WITH LT-08
LT-03
A-706
LT-03 LT-03
LT-08
CT-01
1 15872
5
DT-03
1
A-502
A-502
3 DT-01
DT-05
DT-05
2
A-706
DT-02
DT-05
DT-01
REV
DATE
DESCRIPTION
LT-03
E LT-02
LT-02
LT-02
LT-02
LT-02
CT-01
DT-05 LT-03
LT-03
LT-03
LT-03 LT-01
LT-01
CLIENT
F
RMIT DANIEL MAUNDERS
LT-05
LT-03
CT-02
LT-03
LT-04 LT-03
LT-03
LT-03
PROJECT
DT-02
LT-03
LT-03
LT-03
CT-01
LT-03
LT-03
LT-03 LT-03
LT-03
A-706
LT-03
7
A-706
CT-04 CT-02
CT-02
9 LT-03
LT-03
LT-03
DRAWING TITLE
LT-03
TYPICAL UPPER FLOOR RCP
LT-03
8
A-706
LT-04 LT-05
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
DT-02
LT-03
LT-05 CT-04
CT-03
LT-03 LT-03
LT-03
LT-03
LT-03
LT-03
LT-05
LT-05 POS LIGHT TO BE FIXED TO EXPOED CEILING
DATE
CHECKED
APPROVED
08/27/18
DK&CW
DM
G SCALE
1 : 50
1500
STATUS
150
H
0 0.2
0.5
1.0
1.5
2.5M
@A1
1 A-501
A-402
18-214
DRAWING NUMBER
REVISION
A-303
1
PROJECT #
DD
2 A-501
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
LT-03
GENERAL NOTES
1
2
200
3
4950
4
6150
5
5150
6
3007
3000
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
200
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
1
2
A-501
A-501
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
A-401
NOTES
200
1
A
LT-07
LT-07
3000
3100
3050
LT-07 POLE LIGHT, REFER TO PLAN
1999
3001
300
5850
300
4850
300
2707
300
300
B
3050
3100 LT-03
LT-01
TIMBER FEATURE CEILING TO HANG FROM UPPER TOWER
4522
LT-02
LT-02
LT-02
LT-02 LT-03
2
A-401
6122
CT-02
LT-01
2
2
A-502
A-502
LT-03
C DT-02
LT-03
LT-03
1900
LT-03
A-402
LT-03
LT-03
LT-03 LT-01
2
D
300
CT-03
DT-01
CORRIDOR TO HAVE RECESSED CEILING WITH LT-08
LT-03 LT-08
1 2400
WT-06
CT-01
1
A-502
A-502 CT-05 LT-01 DT-01
DT-01
REV
LT-03
DATE
DESCRIPTION
LT-03
4800
E LT-02
LT-03
2700
LT-03 CT-05
CT-05
LT-01
LT-03
CLIENT
RMIT DANIEL MAUNDERS
LT-03
300
F LT-02
LT-03
LT-03
LT-03
LT-03
DRAWING TITLE
3600
LT-03
3950
LT-03
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
CT-05
LEVEL 05 COS RCP
LT-02 LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
LT-03
CHECKED
APPROVED
09/28/18
DK&CW
DM
300
G
DATE
SCALE
LT-07
150
5150
6000
300
4850
300
1
1 A-501
A-402
2707
300
0.5
1.0
1.5
2.5M
LT-07
STATUS
H
0 0.2
@A1
1600
LT-07
1600
1550
1 : 50
LT-07
3050
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-304
2 A-501
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
PROJECT
GENERAL NOTES
1
2
3
4
5
6
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
1
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
A-501
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
2 A-501
A-401
NOTES
1
A
7572
B
LT-07
LT-07
2 5000
6450
A-401
11207
2
2
A-502
A-502
C DT-01 LT-03
LT-03
LT-07
A-402
LT-07
2 LT-07 POLE LIGHTING TO BE PLACE IN RAISED PLANTER, REFER TO PLAN FOR POSITION
D
LT-03
LT-03
CORRIDOR TO HAVE RECESSED CEILING WITH LT-08 LT-08
DT-04
1
CT-01
DT-04
1 A-502
LT-07
7300
A-502 DT-05 DT-01
REV
DATE
DESCRIPTION
E DT-05 LT-07
CLIENT
F
DT-09
RMIT DANIEL MAUNDERS
DT-09
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
ROOFTOP RCP LT-07
5500
LT-07
G
DATE
CHECKED
APPROVED
09/28/18
Checker
DM
SCALE
1 : 50
0 0.2
0.5
1.0
1.5
2.5M
@A1
STATUS
H
1 A-501
A-402
18-214
DRAWING NUMBER
REVISION
A-305
1
PROJECT #
DD
2 A-501
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
PROJECT
6
5
4
3
2
1
H
G
F
E
D
22257 3000
3007
C
B
A
20022
5150
6150
4950
1550
FFL 73.100 ROOF
3950
2700
2400
1900
4522
3000
FFL 73.100 ROOF
LT-07 LT-07
LT-07 LT-07
LT-07
WT-02
WT-02
WT-02
WI-04
WI-04
WT-08
WT-08
WI-02
WI-02
WT-02
WT-02 WT-02
WT-02
1300
WI-02
WT-02
FFL 65.500 Level 10
WT-02
WT-02
WT-02 WT-02
WI-04
WT-02 WT-02 WT-01
WT-01
WI-04
WT-02
WT-02
WI-04
WT-02 WT-02
WI-04
WT-02
WT-02
WI-02 WT-02
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
LT-06
3500 3500
WT-02 WT-02
WT-02 LT-06
WT-02
FFL 51.500 Level 06
WT-02
LT-07 LT-06
WI-02
LT-07 WT-02
LT-06
LT-06
LT-06
WT-02
2500
WT-02
WT-08
WI-03
44100
WI-04
WT-08
1000
WI-02
WT-02
WT-02
WT-02
LT-06
WT-02
WT-02
WI-03
LT-06
WT-02
WT-02
WT-08
LT-06
WT-02
FFL 55.000 Level 07
2200
WT-02
WT-02
WT-02
WT-08
LT-06
2200
2200
WI-02
WI-02
WT-02
LT-06
WT-08 WI-03
1300
WI-02
WT-08
WI-04
1300
3500
1300
WT-02
WT-08
WT-02
WT-02
WT-02
WT-02
WT-02
WT-02
FFL 58.500 Level 08
WT-02
WI-03
FFL 51.500 Level 06
1300
WI-02 WT-02
WT-08
WT-02
WT-08
WI-02
WT-02
FFL 55.000 Level 07
WT-01
WI-03
WT-02
WT-02
WT-01
WI-04
2200
3500
WI-03
WT-01 WT-08
3500
WT-01
WT-08
WI-02
3500
WT-02
WT-01
WT-08
WT-02
WT-02
WT-02
2200
WT-01
WT-02
FFL 62.000 Level 09
WT-02
2200
WT-02 WT-01
1300
WI-02 WT-02
WT-02
FFL 58.500 Level 08
2200
WI-02
WT-02
1200
WT-02
WT-08
WI-03
1300
WI-02
FFL 62.000 Level 09
WT-08
WI-04
2300
3500
WT-08
WI-03
2200
WT-02 WT-08
2
LT-07
A-601
3500
WT-02
WT-02 WT-02
WI-03
1300
3500
WT-08 WI-03
WT-02
FFL 69.000 ROOFTOP
2200
WT-02
2200
WT-02
3500
WT-02 WT-02
WT-08
FFL 65.500 Level 10
1800
WT-02
1800
WT-02
7000
LT-07
DT-04
FFL 69.000 ROOFTOP
44100
4100
LT-07
4100
LT-07
LT-07 WT-10
WT-02
WT-02
1300
FFL 44.500 Level 04
WT-02
WT-01
2200
WT-08
1300
WT-02 WT-01 WT-02
FFL 41.000 Level 03
WT-01
WT-02
WT-01
WT-01
WT-08
WT-02
WT-02
FFL 37.500 Level 02
WT-02
WT-02
WT-08
WT-08
WT-02
WI-03
WI-03
WT-02
WT-02
WT-08
WT-08
WI-02
WT-02
2000
WT-02 WT-02
2000
WT-02
WT-02
FFL 34.000 Level 01
WT-02
WT-02
WT-02
WT-02
WT-04
WT-11 DT-06B
WT-11 DT-06B
DT-06B
5000
WT-11
4000
WT-11
4000
5000
WT-11
WT-11
WT-11 DT-08A
LANDSDOWNE PL
FFL 29.000 GROUND FLOOR
DT-06B
DT-06B
BOUVERIE ST
FFL 29.000 GROUND FLOOR
ELEVATIO NORTH
GENERAL NOTES
WT-02
WT-02
WI-03 WI-05
WT-02
WI-03
3500
2200
2200
WT-08 WI-03
WT-02
WT-08 WI-03
WT-02
WT-02
1
WT-02
WT-01
WT-02
WT-08
WI-02
A-401
WT-02
WT-08
WT-02
BOUVERIE ST
WT-01
WI-02 WT-02
WT-02
DT-06B
WT-02
3500
WT-08 WI-03
1300
WI-02
3500
WT-08
WT-02 WT-01
WI-05
WT-02
WT-11
WI-03
WT-08
WT-02
WT-01
2200
WT-08 WI-03
WT-02
WI-03
WT-02
WT-02
WT-02 WT-08
FFL 34.000 Level 01
WT-02
WT-02
WI-02 WT-02
WT-01
WT-02
WT-08
WI-03
WT-02 WT-02
WI-03
3500
2200
2200 2200
WT-08
1300
3500
WT-02
WI-05
WT-01
WI-03
WT-02
WT-02
WI-03
3500
WT-02
WT-08
WI-02
WT-02
WT-08
WT-02
WT-08
WT-02
WT-08
WT-02
WT-02
WT-02
WI-02 WT-02
WT-02
1300
WI-02
FFL 37.500 Level 02
WT-08 WI-03
2200
3500
WT-08
WT-01
WT-02
FFL 48.000 Level 05
WI-05
WT-02
FFL 41.000 WT-02 Level 03
WT-10
WT-02
WI-03
WT-02
WT-02
WT-02
WT-08
FFL 44.500 Level 04
WT-02
WT-02
WT-10
3500
WT-02
1300
WT-02
1300
WT-02
FFL 48.000 Level 05
1300
WT-10
2
A-401
1 : 100
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
ELEVATION EAST 1 : 100
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
ELEVATIONS - NORTH & EAST
SCALE @A1
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
DK&CW DM
1 : 100
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
APPROVED
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-401
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
1
2
3
4
5
A
6
22257 4950
6150
5150
3007
B
C
3000
3000
4522
D
E
20022
1900
F
2400
LT-07
3950
H 1550
LT-07
WI-04
WI-03
WT-02
WT-02
WT-02
WT-02
WI-04
WI-03
WI-04
WI-03
WT-02
WT-02
WT-02
WT-02
WT-02
WI-04
WI-03
WI-04
WI-03
WT-02
WT-02
WT-02
WT-02
WI-04
WI-03
WI-04
WI-03
WT-02
WI-05
WI-03
WT-02
WT-02
WI-05
WI-03
2110
3500
3500
2110
3500 3500
1390 2110
WT-02
1390
WT-02
WT-02
WT-02 WT-02
WT-08
WT-08 WI-01 WI-03
WT-02
WI-05
WI-03
WT-02 WT-02
FFL 58.500 Level 08
WT-02
WT-08
WT-01 WT-08
WI-03
WT-02 WT-02
FFL 55.000 Level 07
WT-02
WT-02
WT-08
WT-08
3500
WT-08
WT-08 WI-01 WI-03
WT-02
WT-02
WT-02
FFL 51.500 Level 06
44100
2110
WT-02 WT-02
WT-02
WT-02
WT-02 WT-02
WT-10
WT-02
WT-02
WT-02 LT-07
WT-04
WT-09
4890
WT-02
3500
2500
WT-01
2110
WT-02
WT-01
1390
WT-02
WT-02
WT-02
WI-01
3500
WT-02
WT-01
WT-08
WI-03
WT-02
WT-02
WT-02
WT-01 WT-08
WT-02
WT-02
WT-02
WT-02 WT-02
FFL 62.000 Level 09
44100
1300 1000
FFL 51.500 Level 06
WT-02
WT-08
WT-01
WT-08
WT-02
WI-03
WT-02
WI-01
WT-02
WT-02
2200
FFL 55.000 Level 07
WI-05
WT-08
LT-07
WT-02
3500
1300
WT-02
2200
FFL 58.500 Level 08
WT-02
WT-02
WT-01
WI-04
WT-02
WT-02
WI-03
WT-08 WI-03
WI-03
WT-02 WT-02
FFL 65.500 Level 10
WT-02
WI-04
WI-05
WT-02
WT-02
WT-01
WT-08 WI-01
WT-02
WT-08
WT-01
WT-08
WI-03
WT-02
WT-01
WT-02
WT-02
1390
WI-03
3500
2200 1300 2200 1300
WT-08 WI-04
WT-08
WT-02
WT-02
WT-02 WT-02 WT-02
WT-02
2200
FFL 62.000 Level 09
WT-02
FFL 69.000 ROOFTOP
WT-02
LT-07
WT-02
WT-08
WT-02
WT-05
WT-02 WT-02
WT-10
LT-07
1890
WT-02 WT-02
FFL 65.500 Level 10
LT-07
3500
WT-02
LT-07
3500
FFL 69.000 ROOFTOP
WT-04
LT-07
3500
1800
LT-07
4100
FFL 73.100 ROOF
4100
FFL 73.100 ROOF
G
2700
WI-01
WT-10
LT-06
LT-06
WT-02
FFL 48.000 Level 05
WT-02
WT-02
1390
WT-02
FFL 48.000 Level 05
WT-02
WT-02 WT-02
FFL 44.500 Level 04
2110
WT-08
WT-08 WI-03 WI-02
WI-04
WT-02
FFL 44.500 Level 04
WI-01
WI-04
WT-02
1390
WT-04
3500
WT-04
3500
WT-05
WT-02 WT-02
WT-02
WT-02
WT-02
WT-08 WI-03 WI-01
WI-04 WT-01
WT-01
WT-02
FFL 41.000 Level 03
WT-01
WT-01
WT-02
1448
WI-02
WI-04
FFL 41.000 Level 03
2110
WT-08
3500
WT-04
3500
WT-05 WT-04
WT-02 WT-01
WT-01 WT-02
WT-02
WT-02
WT-02
WT-01
WT-01
FFL 37.500 Level 02
2052
WT-08
WT-08 WI-03 WI-02
WI-04
WT-02
FFL 37.500 Level 02
WI-04
WI-01
WT-02
1390
WT-04
3500
20000
WT-04
3500
WT-05
WT-02 WT-02
WT-02
WT-02
WT-02
WT-04
WT-08 WI-03 WI-02
WI-04
FFL 34.000 Level 01
FFL 34.000 Level 01
WT-02
WI-04
WT-02
BOUVERIE ST
1
6000 WT-11
WT-04
DT-07
DT-01
DT-01
BOUVERIE ST
FFL 29.000 GROUND FLOOR
A-402
WT-02 WT-02 WT-02
5000
5000
WT-11
LANDSDOWN ST
WI-01
WT-02 WT-02
WT-04
2110
WT-08
3500
WT-04
3500
WT-05
FFL 29.000 GROUND FLOOR
ELEVATION SOUTH
2
A-402
1 : 100
GENERAL NOTES
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
ELEVATION WEST 1 : 100
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
ELEVATIONS - SOUTH & WEST
SCALE @A1
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
DK&CW DM
1 : 100
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
APPROVED
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-402
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
A
B
C
3000
4522
D
E
1900
F
2400
G
2700
H
3950
A
1550
B
C
3000
FFL 73.100 ROOF
4522
D
E
1900
F
2400
G
2700
H
3950
1550
FFL 73.100 ROOF WT-10
WT-10
WT-10
Room
MECH PLANT
GARDEN
LT-07
GARDEN
ROOFTOP DT-01
LT-07
COS
LT-07
MECH PLANT
1
DT-02
AP-10-1-3
LT-03
CORRIDOR LV10
FIRE STAIRCASE DT-01
LT-03
LT-03
BEDROOM DT-02
BEDROOM (M) WI-03
AP-10-3-1
FFL 65.500 Level 10
LT-03
3500
LT-08
LT-03 DT-02
TOILET AP-9-1-3
LT-03
CORRIDOR LV09
FIRE STAIRCASE DT-01
DT-02
LT-03
DT-02
TOILET
3500
LT-08
LT-03
BEDROOM (M) WI-03
AP-9-3-1
AP-8-1-3
LT-03
CORRIDOR LV08
FIRE STAIRCASE DT-01
LT-03
3500
LT-08
LT-03 DT-02
TOILET AP-7-1-3
LV07
FIRE STAIRCASE DT-01
1
LT-03
3500
LT-08
LT-03 DT-02
AP-6-1-3
LV06
FIRE STAIRCASE DT-01
LT-03
WI-03
AP-7-3-1
LT-03
WI-03
AP-8-3-1
LT-02
LT-03
LT-01
LIVING ROOM WI-02
FFL 55.000 Level 07
LT-03
BEDROOM (M) WI-03
AP-6-3-1
LT-03
BEDROOM WI-03
AP-7-3-1
LT-02
BEDROOM (M)
AP-6-1-3
LT-03
LT-01
LIVING ROOM WI-02
BEDROOM WI-03
AP-6-3-1
WI-03
FFL 51.500 Level 06
44100
FT-01
BEDROOM
WI-03
LT-03
FFL 51.500 Level 06
LT-03
LT-01
LIVING ROOM
BEDROOM (M)
AP-7-1-3
BEDROOM DT-02
WI-03
AP-9-3-1
LT-02
WI-02
BEDROOM (M)
LT-03
CORRIDOR
BEDROOM
WI-03
FFL 58.500 Level 08
FT-01
TOILET
LT-03
BEDROOM (M)
AP-8-1-3
LT-03
FFL 55.000 Level 07
LT-03
WI-03
BEDROOM DT-02
LT-03
LT-01
LIVING ROOM WI-02
BEDROOM (M)
Z-503
AP-8-3-1
LT-03
CORRIDOR
WI-03
WI-03
LT-03
FT-01
BEDROOM
AP-10-3-1
LT-02
AP-9-1-3
LT-03
FFL 58.500 Level 08
LT-03
LT-03
BEDROOM (M)
FFL 62.000 Level 09
BEDROOM DT-02
WI-02
LT-03
LT-03
FT-01
LT-03
LT-03
LT-01
LIVING ROOM
WI-03
BEDROOM
FFL 62.000 Level 09
LT-02
AP-10-1-3
FFL 65.500 Level 10
FT-01
LT-03
LT-03
BEDROOM (M)
3500
3500
LT-08
LT-03
3500
LT-03
TOILET
FFL 69.000 ROOFTOP
3500
LT-03
LT-07
GARDEN
HV-02
A-651 DT-04
FFL 69.000 ROOFTOP
4100
CORRIDOR
3500
COS
3500
4100
LT-08
LT-08
GYM
CORRIDOR LV05
FIRE STAIRCASE
COS
LT-07
GARDEN
GYM
COS
LT-07
GARDEN
3500
3500
GARDEN
LT-06
DT-01
LT-06
1
A-652
FFL 48.000 Level 05
LT-02
LT-01
AP-4-0-2
LIVING ROOM
DT-01
DT-02
DT-02
LV04
WI-04
AP-4-1-2
WI-02
DT-01
FFL 44.500 Level 04
3500
LT-01
TOILET
FIRE STAIRCASE
1
LIVING ROOM
CORRIDOR AP-3-0-2
DT-01
DT-02
DT-02
LV03
2
Z-503
DT-01
FFL 41.000 Level 03
3500
LT-01
TOILET DT-02
FIRE STAIRCASE
CORRIDOR LV02
DT-01
WI-04
AP-2-1-2
WI-02
LT-01
TOILET
FIRE STAIRCASE
DT-02
WI-04 DT-02
LV01
WI-02
AP-1-1-2
LT-11
LT-01
LIVING ROOM KITCHEN
LIVING ROOM
AP-2-1-1
DT-02
BEDROOM
AP-2-2-2
LT-01
KITCHEN
TOILET
LT-01
LIVING ROOM KITCHEN
LIVING ROOM
AP-1-2-1
BEDROOM
LT-11 LT-03
LT-03
AP-1-2-2 WI-02
LT-11 LT-03
AP-1-1-1
DT-02
FFL 34.000 Level 01
FT-01
LT-11
TOILET
LIVING ROOM DT-01
DT-01
FFL 34.000 Level 01
AP-2-2-1
LIVING ROOM
LIFT CORE CORRIDOR AP-1-0-2
BEDROOM
AP-3-2-2
LT-01
KITCHEN
LT-02
LT-01
BEDRROM (M)
AP-3-1-1
WI-02
LT-08 LT-02
POS
LIVING ROOM
FFL 37.500 Level 02
FT-01 LT-05
LT-01
LIVING ROOM KITCHEN
DT-02
LIVING ROOM
DT-01
FFL 37.500 Level 02
AP-3-2-1
TOILET
LT-02
LIVING ROOM DT-02
LT-01
KITCHEN
WI-02
LT-01
BEDRROM (M) AP-2-0-2
3500
WI-02
LT-08 LT-02
POS
BEDROOM
AP-4-2-2
FFL 41.000 Level 03
FT-01 LT-05
LIVING ROOM
AP-4-1-1
DT-02
LIVING ROOM
Z-504
WI-04
AP-3-1-2
LT-01
LIVING ROOM KITCHEN
LT-02
LT-01
BEDRROM (M)
TOILET
WI-02
LT-08 LT-02
POS
AP-4-2-1
KITCHEN
FFL 44.500 Level 04
FT-01 LT-05
LT-01
LIVING ROOM
CORRIDOR
3500
FIRE STAIRCASE TOILET
3500
3500
LT-01
BEDRROM (M)
3500
LT-08 LT-02
POS
3500
FFL 48.000 Level 05
LT-11
LT-11
LT-09 LT-03
LT-03
LT-10 LT-09 LT-03
5000
5000
LT-03 WT-11
RETAIL 02
FIRE STAIRCASE DT-01
DT-02
KITCHEN
5000
FFL 29.000 GROUND FLOOR
5000
FFL 29.000 GROUND FLOOR
STORAGE
HYDRALIC ROOM
CORRIDOR DT-04
FIRE STAIRCASE DT-04
FFL 24.000 BASEMENT FLOOR
1
A-501
FFL 24.000 BASEMENT FLOOR
Section A
2
A-501
1 : 100
GENERAL NOTES
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
Section B 1 : 100
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
SECTION A & B
SCALE @A1
1 : 100
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
DK&CW DM
APPROVED
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-501
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
6
5
4
3000
3
3007
2
5150
1
1
6150
2
3
4950
4950
FFL 73.100 ROOF
4
6150
5
5150
6
3007
3000
FFL 73.100 ROOF WT-10
GARDEN ROOFTOP DT-05
DT-09
DT-05
WT-02
2
Z-505
COS
GARDEN
DT-04 DT-01
DT-05 WT-02
DT-09
DT-04
FFL 69.000 ROOFTOP
WT-10
4100
COS
4100
CORRIDOR
WT-02
FFL 69.000 ROOFTOP WT-02 LT-05
LV10 WI-01
AP-10-0-3
WI-05
DT-05
AP-10-1-3
DT-01
FFL 65.500 Level 10
FFL 65.500 Level 10
AP-10-1-3
BEDROOM (M)
POS
DT-02
DT-02
DT-03
WT-02
LT-03
LT-02
KITCHEN
WI-03
WI-02
WT-02
WT-02
LT-05 LT-03
CORRIDOR
LT-01
LIVING ROOM KITCHEN
LV09 WI-01
AP-9-3-1
DT-02
DT-05
DT-05
DT-01
LT-03
TOILET
AP-9-0-3
WI-05
DT-05
LT-03
TOILET
LT-01
BEDROOM (M)
3500
LT-03
BEDROOM (M)
FFL 62.000 Level 09
LT-03
LT-02
KITCHEN
AP-9-1-3
BEDROOM (M)
POS
DT-02
DT-02
DT-03
WT-02
LT-02
LIVING ROOM
AP-9-1-3
DT-01
FFL 62.000 Level 09
LT-02
WI-03
WI-02
WT-02
WT-02
CORRIDOR
LT-01
LIVING ROOM KITCHEN
WT-01
LT-05
LV08 WI-01
AP-8-3-1
DT-02
DT-05
DT-05
DT-01
LT-03
WT-01
LT-03
TOILET
LIVING ROOM
AP-8-1-3
AP-8-1-3
AP-8-0-3
WI-05
DT-05
LT-03
TOILET
LT-01
BEDROOM (M)
3500
LT-03
BEDROOM (M)
DT-01
FFL 58.500 Level 08
FFL 58.500 Level 08
LT-02
LT-03
LT-02
KITCHEN
BEDROOM (M)
POS
DT-02
DT-02
DT-03
WT-02
LT-02
WI-03
WI-02
WT-02
WT-02
LT-05
CORRIDOR
LT-01
LIVING ROOM KITCHEN
LT-03
LV07 WI-01
AP-7-3-1
DT-02
DT-05
DT-05
DT-01
LT-03
TOILET
LT-02
FFL 55.000 Level 07
BEDROOM (M)
POS
DT-02
DT-02
DT-03
WT-02
LT-03
LT-02
KITCHEN
AP-7-1-3
DT-01
FFL 55.000 Level 07
LT-02
LIVING ROOM
AP-7-0-3
WI-05
DT-05
LT-03
TOILET
LT-01
BEDROOM (M)
3500
LT-03
BEDROOM (M)
WI-03
WI-02
WT-02
WT-02
LT-05 LT-03
CORRIDOR
LT-01
LIVING ROOM KITCHEN
LV06 WI-01
AP-6-3-1
DT-02
DT-05
DT-05
DT-01
LT-03
TOILET
LT-02
FFL 51.500 Level 06
BEDROOM (M)
POS
DT-02
DT-02
DT-03
WT-02
LT-03
LT-02
KITCHEN
AP-6-1-3
DT-01
FFL 51.500 Level 06
LT-02
LIVING ROOM
AP-6-0-3
WI-05
DT-05
LT-03
TOILET
LT-01
BEDROOM (M)
3500
LT-03
BEDROOM (M)
3500
DT-01
LT-02
LIVING ROOM
3500
DT-05
LT-02
3500
DT-05
LT-03
TOILET
3500
AP-10-3-1
DT-02
LT-03
TOILET
LT-01
BEDROOM (M)
3500
LT-03
CORRIDOR
LT-01
LIVING ROOM KITCHEN
3500
LT-03
BEDROOM (M)
WI-03
WI-02
WT-02
WT-01
CORRIDOR COS
GYM
WT-02
LV05
Z-505
WI-01 DT-08
DT-05
DT-05
DT-01
YOGA
GYM
COS
GARDEN
3500
GARDEN
3500
1
DT-05 DT-01
FFL 48.000 Level 05
CORRIDOR
LT-01 WI-03 WI-01
DT-01
DT-01
DT-05
DT-05
DT-01
LT-02
KITCHEN
TOILET
AP-4-0-1
DT-05
AP-4-0-2 DT-02
CORRIDOR
LT-01
LIVING ROOM
LT-01
LV03
WI-03 WI-01
AP-3-1-1
DT-01
DT-01
DT-05
00.461
DT-01
LT-01
LIVING ROOM
LT-02
KITCHEN
TOILET
AP-3-0-1
AP-4-0-2
LT-01
LV02
WI-03 WI-01
AP-2-1-1
DT-01
DT-01
DT-05
DT-05
DT-01
LT-01
LIVING ROOM
LT-02
KITCHEN
TOILET
AP-2-0-1
AP-2-0-2
LT-01 WI-03 WI-01
AP-1-1-1
DT-01
DT-01
DT-05B
DT-05B
DT-01
LT-01
LIVING ROOM
3500
LV01
LT-02
KITCHEN
TOILET
DT-05A
BEDROOM (M)
KITCHEN
TOILET
BEDROOM (M)
LT-01
AP-1-0-2
LIVING ROOM AP-1-2-1
DT-02
DT-02
FFL 34.000 Level 01
WT-02
LT-11
LT-11
LT-11
LT-11
LT-11
LT-11
LT-11
LT-11
LT-10
DT-02
DT-01
ELECTRICITY SERVICE ROOM
DT-01
5000
FIRE CONTROL ROOM
LOBBY
5000
LT-10
TOILET
DT-02
LIVING ROOM
DT-01
LT-09
KITCHEN
WI-02
AP-1-0-1
FFL 34.000 Level 01
LIVING ROOM AP-2-2-1
DT-02
CORRIDOR
LT-01
LIVING ROOM
LT-01
FFL 37.500 Level 02
WT-02
LT-02
BEDROOM (M)
DT-02
LIVING ROOM
DT-01
POS
TOILET
WI-02
DT-05
FFL 37.500 Level 02
KITCHEN
AP-3-2-1
WT-01
CORRIDOR
LT-01
LIVING ROOM
LIVING ROOM
WT-01
3500
LT-02
POS
LT-01
DT-02
FFL 41.000 Level 03
WT-02
1
DT-02
LIVING ROOM
DT-01
A-601
BEDROOM (M)
WI-02
DT-05
FFL 41.000 Level 03
TOILET
WT-02
3500
LT-02
POS
KITCHEN
FFL 44.500 Level 04
WT-02
2
LIVING ROOM AP-4-2-1
DT-01
FFL 44.500 Level 04
Z-504
LT-01
LIVING ROOM
3500
AP-4-1-1
LT-01
LIVING ROOM WI-02
3500
LV04
3500
LT-01
LIVING ROOM
3500
LT-02
POS
3500
FFL 48.000 Level 05
WT-11
RETAIL 01
RETAIL 03
RETAIL 02
RETAIL 04
DT-01
FFL 29.000 GROUND FLOOR
FFL 29.000 GROUND FLOOR LT-12
LT-12
LT-12
LT-12
LT-12
5000
5000
LT-12
CORRIDOR DT-04
DT-01
BIKE STORE DT-01
FFL 24.000 BASEMENT FLOOR
1
A-502
STORAGE
FFL 24.000 BASEMENT FLOOR
Section C
2
A-502
1 : 100
GENERAL NOTES
HYDRALIC ROOM
DT-01
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
Section D 1 : 100
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
SECTION C & D
SCALE @A1
1 : 100
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
DK&CW DM
APPROVED
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-502
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
DATE DESCRIPTION CLIENT DRAWING TITLE
20/08/2018 PROJECT SETUP
RMIT DANIEL MAUNDERS TYPICAL FACADE WALL SECTION 01
PROJECT DATE CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 27/08/18 DK&CW DM
APPROVED
SCALE @A1
1 : 20
STATUS
DD 18-214
DRAWING NUMBER REVISION
A-601
0 0.2 0.5 1.0 1.5
A
2.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
PROJECT #
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
A-601
1
200mm CONCRETE SANDWICH WALL
WT-02 VERTICAL TIMBER FINS TO BE SPACED 74mm APART
WT-01 HORIZONTAL TIMBER FINS TO BE SPACED 74mm APART
100mm CONCRETE WALL FOR TIMBER FINS TO FIX AND ACT AS BALLUSTRADE FOR POS
WT-02 VERTICAL TIMBER FINS TO BE SPACED 74mm APART
WT-01 HORIZONTAL TIMBER FINS TO BE SPACED 74mm APART
180mm HOLLOW CORE CONCRTE FLOOR SLAB CONNECTED TO STRUCTAL WALL
FT-03 MALI FLAMED BLUESTONE TO BE WATERPROOFED AND SLOPED FOR DRAINAGE
WT-02 VERTICAL TIMBER FINS TO BE SPACED 74mm APART
WT-01 HORIZONTAL TIMBER FINS TO BE SPACED 74mm APART
60mm STAINLESS STEEL T BRACKET TO BE CASTED INTO WT-05 PRIOR TO FIXING TIMBER FINS. CENTRE T BRACKET AND TIMBER FIN TO HIDE BRACKET FROM OUTSIDE
WT-02 VERTICAL TIMBER FINS TO BE SPACED 74mm APART
EXTERIOR BI-FOLIDNG WINDOW TO BE INSTALLED 1000mm FROM FFL
WT-08 EXTERIOR BI-FOLDING WINDOW. REFER TO A-602 FOR DETAIL
WT-01 HORIZONTAL TIMBER FINS TO BE SPACED 74mm APART
WT-02 VERTICAL TIMBER FINS TO BE SPACED 74mm APART
SECTION TYPICAL FACADE 1 : 20
FFL 34.000 Level 01
FFL 37.500 Level 02
FFL 41.000 Level 03
FFL 44.500 Level 04
FFL 48.000 Level 05
180mm HOLLOW CORE CONCRETE FLOOR SLAB CONNECTED TO STRUCTAL WALL
RAISED PLANTER ON SLAB. REFER TO A-651 FOR DETAIL
100 900
TRANSFER PLAT ON LVL 05. REFER TO A-652 FOR DETAIL
500 75 74 75 74 75
2
A-601
WT-01
75 90
75 75 75 75
818
ELEVATION TYPICAL FACADE 1 : 20
FFL 34.000 Level 01
FFL 37.500 Level 02
FFL 41.000 Level 03
FFL 44.500 Level 04
FFL 48.000 Level 05
LT-06
2200
WT-05 200mm PRECAST SANDWICH WALL TO BE CAPPED OFF AND WATERPROOFED
6 LT-06
E
818
LT-06
100 100 90 1790
390 200 1790 120 1000 180 20 190 2110 1000
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt 180 20
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
3300
DO NOT SCALE OFF DRAWINGS.
180 20
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
REV
A
3300
NOTES 180 20
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
120
GENERAL NOTES WT-02
WT-08
WT-02
WT-08
WT-02
4272
818
WT-08
WT-02
WT-08
WT-02
1
1 A-502
LT-06
A-502
818
WT-10
LT-06
D
818
90 75
75 75 75 75 75
LT-06
WT-01
75 74 75
74 75 74 75 74 75
130
A-602
100
60
30
180
50
31
75
98
CL
36
CL
32
200
860
100
75
CT-04 EXPOSED CEILING TO POS
WT-09 INTERIOR BI-FOLIDNG WINDOW TO BE INSTALLED, OPENING AWAY FROM POS
CEILING CAVITY
WT-08 BI-FOLDING WINDOW TO BE FIXED TON FACADE WALL
74
WT-08 BI-FOLDING WINDOW TO BE FIXED TO 100mm CONCRETE WALL
D 75
75mm TIMBER FINS TO BE COATED WITH WATERPROOFING SEALENT
29
CL
36
CL
CEILING CAVITY
35
12 6 12 6 14 CT-02
80
16
DOUBLE GLAZING WINDOW WITH ARGON GAS FILLING
5
74
284
A-602
58
A-602
75
100
75
4
WT-05 200mm PRECAST SANDWICH WALL TO WRAP AROUND CORNER
75
4
20
20 60
820
75
820
FFL 37.500 Level 02
75
30
30
180mm HOLLOW CORE CONCRETE FLOOR SLAB CONNECTED TO STRUCTURAL WALL
FFL 37.500 Level 02
75
5 90 5
FFL 37.500 Level 02
100
180mm HOLLOW CORE CONCRETE FLOOR SLAB CONNECTED TO STRUCTURAL WALL
20
A-602
100
2
WT-05
180
2
WT-09
6 180mm HOLLOW CORE CONCRETE FLOOR SLAB CONNECTED TO STRUCTURAL WALL
180
WT-08 TO BE FIXED ONTO 100mm ALUMINIUMPOST
100
WT-06
6
6
CT-04
60
WT-01 HORIZONTAL TIMBER FINS TO BE SPACE 74mm APART
WT-01 HORIZONTAL TIMBER FINS TO BE SPACE 74mm APART
74
74
100
A-602
200mm CONCRETE SANDWICH WALL
DOUBLE GLAZING WINDOW WITH ARGON GAS FILLING
129
WT-02 VERTICAL TIMBER FINS TO BE SPACE 74mm APART
100
60
60
BI-FOLIDNG WINDOW. REFER TO MANUFACTURE'S DETAIL FOR INSTALLATION GUIDE
WT-02 VERTICAL TIMBER FINS TO BE SPACE 74mm APART
100
CL CL 16 28 16
130
30
A-602
200mm CONCRETE SANDWICH WALL
54
3 54
3
75
75
4300
FT-03 MALI FLAMED BLUESTONE TO BE WATERPROOFED AND SLOPED FOR DRAINAGE
860
FT-03
6 6 35 12 12 14 15
40
75
1 A-502
75
1 A-502
50
2270
3000
32 10 33
75
74
860
10
60mm STAINLESS STEEL T BRACKET TO BE CASTED INTO WT-05 PRIOR TO FIXING TIMBER FINS. CENTRE T BRACKET AND TIMBER FIN TO HIDE BRACKET FROM OUTSIDE
STAINLESS STEEL NUT AND BOLT TO BE HIDDEN INTO THE TIMBER FINS AS MUCH AS POSSIBLE
3000
60mm STAINLESS STEEL T BRACKET TO BE CASTED INTO WT-05 PRIOR TO FIXING TIMBER FINS. CENTRE T BRACKET AND TIMBER FIN TO HIDE BRACKET FROM OUTSIDE
60
75
WT-08 EXTERIOR BI-FOLIDNG WINDOW TO BE INSTALLED CENTRE HUNG
10
FT-01
60
40 10
90
250
250
860
1800
E
WT-08
100
60
200
60mm STAINLESS STEEL T BRACKET TO BE CASTED INTO WT-05 PRIOR TO FIXING TIMBER FINS. CENTRE T BRACKET AND TIMBER FIN TO HIDE BRACKET FROM OUTSIDE
180mm HOLLOW CORE CONCRETE FLOOR SLAB CONNECTED TO STRUCTURAL WALL
180mm HOLLOW CORE CONCRETE FLOOR SLAB CONNECTED TO STRUCTURAL WALL
100
75
TIMBER FINS TO BE FASTENED WITH SCREW AND BOLT
60
180mm HOLLOW CORE CONCRETE FLOOR SLAB CONNECTED TO STRUCTURAL WALL
60
WT-09
860
60mm STAINLESS STEEL T BRACKET TO BE CASTED INTO WT-05 PRIOR TO FIXING TIMBER FINS. CENTRE T BRACKET AND TIMBER FIN TO HIDE BRACKET FROM OUTSIDE
250
100
1000
WT-02
60mm STAINLESS STEEL T BRACKET TO BE CASTED INTO WT-05 PRIOR TO FIXING TIMBER FINS. CENTRE T BRACKET AND TIMBER FIN TO HIDE BRACKET FROM OUTSIDE
250
60
60mm STAINLESS STEEL T BRACKET TO BE CASTED INTO WT-05 PRIOR TO FIXING TIMBER FINS. CENTRE T BRACKET AND TIMBER FIN TO HIDE BRACKET FROM OUTSIDE
75
WT-08 TO BE FIXED ONTO WT-05
130
FT-03 MALI FLAMED BLUESTONE TO BE WATERPROOFED AND SLOPED FOR DRAINAGE
250
250
75
FT-03 MALI FLAMED BLUESTONE TO BE WATERPROOFED AND SLOPED FOR DRAINAGE
75
30
WT-05
FFL 34.000 Level 01
FFL 34.000 Level 01
FT-03
FT-01
60
20
FFL 34.000 Level 01
FT-03 MALI FLAMED BLUESTONE TO BE WATERPROOFED AND SLOPED FOR DRAINAGE
1
A-602
2
TYPICAL FACADE DETAIL 01 1 : 10
GENERAL NOTES
A-602
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
TYPICAL FACADE DETAIL 02 1:5
3
A-602
TYPICAL FACADE DETAIL 03 1:5
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
TYPICAL FACADE WALL SECTIONS 02
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
4
A-602
TYPICAL FACADE DETAIL 04 1:5
SCALE @A1
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
DK&CW DM
APPROVED
As indicated
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-602
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
G
LT-07 DOMUS 'SINGLE HEAD' LIGHTING TO BE PLACED THE GARDEN ZONE. REFER TO MANUFACTURE'S DETAIL FOR FIXING. REFER TO ROOFTOP PLAN FOR QUANTITY AND PLACEMENT LT06 SECRUA POST 'URBAN SQUARE LIGHT' BOLLARD LIGHT TO BE PLACED IN THE GARDEN ZONE. REFER TO MANUFACTURER'S DETAIL FOR FIXING. REFER TO ROOFTOP PLAN FOR QUANTITY AND PLACEMENT SPECIFIED PLANTING - REFER LANDSCAPE PLAN FOR PLANTING LAYOUT, SPECIES, POTSIZES AND QUANTITIES
WT-10 TIMBER FINS TO BE INSTALLED ON PLANTER WALLS. REFER TO ROOFTOP PLAN FOR PLACEMENT AND QUANTITIES
LT-06
75mm DEPTH DECORATIVE PEBBLE MULCH
100mm WIDE INSITUE CONCRETE PLANTER WALL TO ENGINEER'S DETAILS. CLASS 1 APPROVED EXPOSED AGGREGATE CONCRETE
200mm WIDE INSULATED CONCRETE SANDWICH PANEL PLANTER WALL WRAPED ON EXTERIOR TO ENGINEER'S DETAILS. CLASS 1 APPROVED EXPOSED AGGREGATE CONCRETE
HVAC UNIT PLACEMENT AND FIXING TO REFER TO MANUFACTURE'S DETAIL
APPLY WELDED WATERPROOF MEMBRANE TO WALLS AND BASE OF ALL PLANTERS. CORE FLUTE OR PROTECTION BOARD TO BE INSTALLED OVER WATERPROOF LINER
APPROVED 50mm DRAINAGE CELL TO WALLS AND BASE
FT-03 'MALI FLAMED BLUESTONE' TO BE INSTALLED ON 200mm HOLLOWCORE PRECAST CONCRETE FLOOR WITH THIN SET MORTAR AND WATERPROOFING MEMBRANE. REFER TO MANUFACTURE'S DETAIL FOR CONSTRUCTION
PROVIDE FILTER FABRIC OVER DRAINAGE CELL
FT-03
CEMENT SCREED TO BASE OF ALL PLANTERS TO PROVIDE MIN 2% FALL TO DRAINAGE POINTS AS PER HYDRAULIC ENGINEER'S DETAILS
FFL 69.000 ROOFTOP
DRAINAGE PITS AND LAYOUT TO BE NOMINATED BY HYDRAULIC ENGINEER TO WORK WITH PAIVNG DESIGN AND LANDSCAPE. STRUCURAL WATERPROOFING DETAILS TO BE PROVIDED BY ENGINEER
1
A-651
CONSTRUCTION DETAIL 01 1:5
GENERAL NOTES
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
CONSTRUCTION DETAILS
SCALE @A1
1:5
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
DK&CW DM
APPROVED
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-651
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
A
B
WT-10
WT-06
C01
FT-03 'MALI FLAMED BLUESTONE' TO BE INSTALLED ON 200mm HOLLOWCORE PRECAST CONCRETE FLOOR WITH THIN SET MORTAR AND WATERPROOFING MEMBRANE. REFER TO MANUFACTURE'S DETAIL FOR CONSTRUCTION
WT-11
TIMBER BENCH WT-02
GROUT VOIDS OF HOLLOW CORE UNITS AT ENDS TO TIE INTO CONCRETE SUPPORT
EXTEND STEEL DOWELS INTO REINFORCEDCONCRETE TOPPING FOR STRUCTRAL CONTINUITY
CAST-IN-SITU CONCRETE SCREED, REINFORCED WITH WIRE MESH, BONDS TO PRECAST SLABS TO FORM A COMPOSITE STRUCTURAL UNIT FFL 48.000 Level 05
VOID TRANSFER BEAM WT-01
HIGH-DENSITY PLASTIC BEARING STRIP
STIRRUPS IN CONCRETE BEAM TO TIE INTO TOPPING
CT02
LT-02
WT-09
1
A-652
CONSTRUCTION DETAIL 02 1:5
GENERAL NOTES
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
CONSTRUCTION DETAILS
SCALE @A1
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
DK&CW DM
1:5
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 181012 Week 13.rvt
APPROVED
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-652
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
1
2
3
200
4
5
22257 4950
GENERAL NOTES
6
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
200
6150
5150
3007
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
3000
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
1
2
A-401
A-501
A-501
NOTES
200
1
A
BEDROOM (M) POS KITCHEN
8 m²
3000
5 m²
3000
3000
1875
2
A-703
3400
BEDROOM POS
3000
8 m²
2000
POS 10 m²
11 m²
1
8 m²
3400
LIVING ROOM
BEDROOM (M)
3000
B
31 m²
3400 BEDRROM (M)
13 m² LIVING ROOM
3000
11 m²
12 m²
4
A-703
14 m²
4522
STUDIO TYPE 01
KITCHEN 3
5092
LIVING ROOM
6857
5 m²
2 BEDROOM TYPE 01
45 m²
77 m² KITCHEN
STUDIO TYPE 02
TOILET
4050
2
45 m²
7 m²
BEDROOM (M) TOILET
2
12 m²
C TOILET
8 m²
A-703 6 m²
1900
A-502
3000
TOILET
5
2 3400
7 m²
A-502
A-402
A-401
5 m²
LIFT CORE
2 6
20022
D CORRIDOR
1
1
16 m²
2400
LIVING ROOM 24 m²
1 BEDROOM TYPE 01 WATER
ELECTRICAL
GAS METER
POS
4272
A-502
8 m²
56 m²
E
A-502
REV
DATE
DESCRIPTION
KITCHEN 4 m²
3000
2700
3400
COMMS
FIRE STAIRCASE
BEDROOM (M) BIN CHUTE
12 m²
9007
CLIENT
F
RMIT DANIEL MAUNDERS 2
2 BEDROOM TYPE 02
LIVING ROOM
80 m²
31 m²
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
7 m²
1 4
1 BEDROOM TYPE 02
TOILET
69 m²
DRAWING TITLE
9 m² A-705
3912
9 m²
3
BEDROOM
BEDROOM (M)
12 m²
12 m²
G
POS
DATE
CHECKED
APPROVED
9 m²
10/12/18
Checker
Approver
A-705
LIVING ROOM
6
36 m²
1550
KITCHEN
A-705
5
SCALE
1 : 50
-
STATUS
A-501
0.5 1
2
3
5.0M
A-402
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-701
1
1
0
@A1
4 m²
150
H
3000
7 3000
3000
AREA PLAN TYPICAL LOWER FLOOR (1/F)
3000
3950
2000 POS
2 A-501
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
A-705
TOILET
PROJECT
1
2
3
200
4
5
19257 4950
100
6150
5150
3007
GENERAL NOTES
6 2900
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
200
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
3000
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
1
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
2
A-501
A-501
A-401
NOTES 1
2925
3000
A
B 1900 1800
POS 8 m²
TOILET
TOILET
7 m²
9 m²
5 3
A-704
3000
4522
LIVING ROOM
6
KITCHEN
20 m²
2
A-704
A-704
4
3400
1 BEDROOM TYPE 02 6647
56 m²
2
14 m²
A-502
KITCHEN 3 m²
3000
C
A-401
BEDROOM (M)
39 m²
A-502
2
7
STUDIO TYPE 03
2
POS 9 m²
3 m²
BEDROOM (M)
A-402
4
3400
LIFT SHAFT
2
ENSUITE TOILET
A-706
4 m²
5
D 1400
20022
6
13 m²
3400
A-706
CORRIDOR
1
1
13 m²
A-502
2400
BEDROOM (M)
3000
1900
20 m²
A-502
3 WATER
ELECTRICAL
A-706
2
GAS METER
REV
DATE
DESCRIPTION
E STUDIO TYPE 04 KITCHEN
42 m²
LIVING ROOM KITCHEN
COMMS
33 m² LIVING ROOM
4 m²
2700
8 m²
33 m²
FIRE STAIRCASE
3 BEDROOM TYPE 01
BIN CHUTE
101 m²
2599 CLIENT
RMIT DANIEL MAUNDERS
BEDROOM (M)
5 m² PROJECT
3000
7600
LIVING ROOM
12 m²
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
3400 KITCHEN
BEDROOM
6 m²
13 m²
11 m²
9 TOILET
12 m²
8
A-706
8 m²
POS
1800
POS
3000
A-706 BEDROOM 3000
7
3000
3950
A-706
8 m²
3000
DRAWING TITLE
AREA PLAN TYPICAL UPPER FLOOR (6/F) DATE
CHECKED
APPROVED
10/12/18
Checker
Approver
G 1 : 50
1450
1550
SCALE
0
0.5 1
2
3
5.0M
@A1
STATUS
H
1 A-501
A-402
18-214
DRAWING NUMBER
REVISION
A-702
1
PROJECT #
DD
2 A-501
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
F
100 LT-03
925
800
800
800
448
LT-03
720
1142
CUSTOM MADE WARDROBE TO BE PLACE IN EACH BEDROOM
LT-03
BIRCH FINISHING TO CABINET DOORS
1574
BI-FOLDING WINDOW TO CONNECT POS AND BEDROOM (M)
605
733
90
817
733
LT-03
597
DOUBLE GLAZING BI-FOLDING WINDOW. REFER TO A-651 FOR DETAIL
560 1027
40
OVEN
RENDERED CONCRETE WALL
320
EXPOSED WORDROBE
1000
1374
40
1858
120
RENDERED CONCRETE FINISHING
3000
60 KITCHEN WASH BASIN TO REFER CAROMA 'AURA SINK MIXER' IS 1632
LT-04 WALL MOUNTED LIGHT TO BE PLACED ABOVE BED
MICROWAVE
450
910
LT-04
52
LT-04
LT-03 TO BE INSTALLED ON TOP SIDE OF COOKING ZONE
1240
2100
1780
WT-08 WT-09
FT-01 TO BE WATERPROOFED
DISHWASHER
500
600
REFRIGERATOR
FT-01
1
A-703
STUDIO BEDROOM (M) EAST 1 : 20
2
A-703
STUDIO BEDROOM (M) SOUTH 1 : 20
3
A-703
STUDIO LIVING ROOM EAST 1 : 20
2
CT-03
LT-03
LT-03
1845
40
980
LT-01
1171
1160
40
8 m² LT-01
40
TOILET WALL TO BE CLADDED WITH TILE 100x100mm WATERPROFFED
LT-04 TO BE INTALLED ON TOP OF MIRROR CABINET
40
WI-04 TOILET WINDOW TO BE TINTED TO PROVIDE PRIVACY
1
POS
TOILET TILE TO BE INSTALLED FROM FLOOR TO CEILING HEIGHT WATER PROOFED
LT-03 DOWN LIGHT TO FIXED TO CEILING
620
LT-03
A-703
30
40
CT-03 LT-03
1420
40
SHOWER CURTAIN TO BE INSTALLED ONTO BATH 'CAROMA CU6WFW'
BEDROOM (M)
LT-01
10 m²
LT-01 TRACK LIGHTING TO BE ADJUSTABLE FOR OCCUPANT'S NEEDS
WI-02 FULL HIGHT WINDOW TO MAXIMISE ON SOLAR ACCESS TO DWELLING
LIVING ROOM
4
A-703
3 KITCHEN
14 m²
5 m²
STUDIO TOILET DOOR TO BE SLIDE INTO WALL CAVITY SPACE
2860
LT-04
WT-09 BI-FOLDING WINDOW TO CONNECT LIVING ROOM TO POS
WI-02
940
WI-04
WI-04
1000
WT-09
2340
1829
DT03
5
TOILET
5
A-703
1060
STUDIO TOILET NORTH 1 : 20
GENERAL NOTES
6
A-703
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
6
824615W 'CUBE WALL FACED TOILET' BY CAROMA
FT-01
STUDIO TOILET SOUTH 1 : 20
4
A-703
30
FT-02
40
920
6 m²
A-703 631710W 'OPAL SOLE WALL BASIN' BY CAROMA
7
STUDIO LIVING ROOM WEST 1 : 20
A-703
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
1 : 50
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
TYPICAL STUDIO PLANS & ELEVATIONS
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
DK&CW DM
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
STUDIO PLAN
SCALE @A1
APPROVED
As indicated
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-703
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
LT-03
LT-03
CT-03
CT-02
LT-03
CT-03
LT-03
LT-02
CL
CL
745
448
605
817
CL
WI-02 WINDOW TO MAXIMISE ON SOLAR ACCESS TO DWELLING
40
40
920
600
CL
410
40
WI-04 TOILET WINDOW TO BE TINTED TO PROVIDE PRIVACY
635
TOILET TILE TO BE INSTALLED FROM FLOOR TO CEILING HEIGHT WATER PROOFED
LT-03
1049
TOILET TILE TO BE INSTALLED FROM FLOOR TO CEILING HEIGHT WATER PROOFED
LT-03 TO BE INSTALLED ON TOP SIDE OF COOKING ZONE
951 CL
824615W 'CUBE WALL FACED TOILET' BY CAROMA
SHOWER CURTAIN TO BE INSTALLED ONTO 'CAROMA DOLPHIN SHOWER BASE'
DT-02
40
MICROWAVE
LT-03 DOWN LIGHT TO FIXED TO CEILING
1049
1160
857
658 1142
1975
BIRCH FINISHING TO CABINET DOORS 1235
733
LT-02
1975
LT-03
951
1020
LT-02
509
LT-03
1171
LT-03 CT-02
LT-01 TRACK LIGHTING TO BE ADJUSTABLE FOR OCCUPANT'S NEEDS
40
1420
WI-02
40
917
WI-02
500
KITCHEN WASH BASIN TO REFER CAROMA 'AURA SINK MIXER' IS 1632
DT-02
DT-01
920
40
500
LT-04
LT-04 TO BE INTALLED ON TOP OF MIRROR CABINET
WI-04
40
1858
27
1870
OVEN
631710W 'OPAL SOLE WALL BASIN' BY CAROMA
850
DINING TABLE TO BE DECIDED BY OCCUPANT
290
TV SET AND COUCH TO BE DECIDED BY OCCUPANT
40
1829
1000
860
40
2400
1420
1240
200 40
FREESTANDING BATH AND FILLER REFER CAROMA 'NOIR 1700' AND 'EPIC BATH FILLER' FOR DETAIL
DISHWASHER
610
REFRIGERATOR
3
A-704
150
3040
FT-01
4
1 BED LIVING ROOM NORTH 1 : 20
A-704
FT-02 TILE TO BE WATERPROOFED AND SLOPED
FT-02 TILE TO BE WATER PROOFED AND SLOPED FT-01
FT-02
1 BED LIVING ROOM SOUTH 1 : 20
5
A-704
FT-02
6
1 BED TOILET NORTH
1 BED TOILET SOUTH
A-704
1 : 20
1 : 20
190
100 100 90 100
100 100
LT-03
CT-02
LT-03
450
2400
250
CL
CL
850
1774
POS
BEDROOM (M)
CL
WT-09
3000
3300
3300
3000
WT-01 TIMBER FINS TO BE ATTACHED TO CONCRETE WALL
WT-09
14 m²
LT-04 WALL MOUNTED LIGHT TO BE PLACED ABOVE BED
52
WI-03
120
120
100
40
WT-01 TIMBER FINS TO BE ATTACHED TO CONCRETE WALL
500
9 m²
FT-03 MALI FLAMED BLUESTONE TO BE WATER PROOFED AND SLOPED
FT-01
FT-03
FT-03
1 BED BEDROOM NORTH 1 : 20
580
7
A-704
1 BED BEDROOM SOUTH 1 : 20
1
A-704
GENERAL NOTES
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
RMIT DANIEL MAUNDERS
TYPICAL 1 BEDROOM PLANS & ELEVATIONS
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
09/29/18
Checker Approver
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
POS
2
A-704
500
1800
FT-03 MALI FLAMED BLUESTONE TO BE WATER PROOFED AND SLOPED
FT-01
500
1174
1510
440
40
EXPOSED WORDROBE
425
1000
525
1000
40
560
320
50
500
2
760
LT-04
7
200 40
1020
A-704
LT-04
1800
BEDROOM (M)
DT-02
850
1790
2100
100
1790
4
WT-09 BI-FOLDING WINDOW TO CONNECT POS AND BEDROOM (M)
WT-08
20 m²
WT-09 BI-FOLDING WINDOW TO CONNECT POS AND BEDROOM (M)
WT-08
LIVING ROOM
WT-08 BI-FOLDING WINDOW TO BE INSTALLED 1000mm FROM FFL
WT-08 BI-FOLDING WINDOW TO BE INSTALLED 1000mm FROM FFL
5
750
100
CUSTOM MADE WARDROBE TO BE PLACE IN EACH BEDROOM
3
1800
A-704
LT-03
TOILET
9 m²
LT-03
300
3 m²
CT-02
LT-05
750
KITCHEN
LT-03
CT-04
A-704
LT-05
6
CT-04
1 BEDROOM PLAN 1 : 50
SCALE @A1
APPROVED
As indicated
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-704
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
LT-01
TOILET TILE TO BE INSTALLED FROM FLOOR TO CEILING HEIGHT WATER PROOFED
LT-01
1171
LT-01
2207
100
2309
76
991
248
76
915
76
1909
137 76
915
SHOWER CURTAIN TO BE INSTALLED ONTO BATH 'CAROMA CU6WFW'
76
LT-03
LT-03 DOWN LIGHT TO FIXED TO CEILING
TOILET TILE TO BE INSTALLED FROM FLOOR TO CEILING HEIGHT WATER PROOFED
WI-04 TOILET WINDOW TO BE TINTED TO PROVIDE PRIVACY
794
76
915
40
100
LT-01 TRACK LIGHTING TO BE ADJUSTABLE FOR OCCUPANT'S NEEDS
76
WT-09 BI-FOLDING WINDOW TO CONNECT LIVING SPACE AND POS
CT-03
LT-03
LT-03
1160
790
LT-01
CT-03
LT-03
1337
CT-02
40
920
40
LT-04
LT-04 TO BE INTALLED ON TOP OF MIRROR CABINET WI-04
DT-02
DT-02
40
1829
DT-02
151
DT-02
2134
TV SET TO BE DECIDED BY OCCUPANT.
598
860
3000
WT-09
49
509
865
FREESTANDING BATH AND FILLER REFER CAROMA 'NOIR 1700' AND 'EPIC BATH FILLER' FOR DETAIL
FT-01 BLANCO LIMESTONE TO BE INSTALLED ONTOP OF 200mm CONCRETE SLAB WITH 5mm THIN SET MORTAR
FT-01
900
631710W 'OPAL SOLE WALL BASIN' BY CAROMA
824615W 'CUBE WALL FACED TOILET' BY CAROMA FT-02
FT-02
2 BED LIVING ROOM SOUTH 1 : 20 LT-03
3
A-705
1000
464 LT-01
1072
150 40
920
40
LT-01
LT-01
2336
A-705
1 : 20
2 BED TOILET NORTH 1 : 20
LT-01
2336
CL
678
4
2 BED TOILET SOUTH
LT-01 TRACK LIGHTING TO BE ADJUSTABLE FOR OCCUPANT'S NEEDS
CT-02
LT-03
364
733
1
A-705
2336
CL
CL
1000 CL
4929
BIRCH FINISHING TO CABINET DOORS
LT-03 TO BE INSTALLED ON TOP SIDE OF COOKING ZONE
3000
2850
1240
MICROWAVE
TV SET AND COUCH TO BE DECIDED BY OCCUPANT
POS
30
DINING TABLE TO BE DECIDED BY OCCUPANT
9 m²
KITCHEN WASH BASIN TO REFER CAROMA 'AURA SINK MIXER' IS 1632 DT-01
847
OVEN
REFRIGERATOR
FT-01
100
CT-02
LT-03
LT-03
LT-03
LT-03
CT-02
LT-03 CT-02
950
LT-03
LT-03
500
LT-04 WALL MOUNTED LIGHT TO BE PLACED ABOVE BED
WI-04
120
RENDERED CONCRETE FINISHING
600
DT-02
-
A-705
2100
GENERAL NOTES
6
A-705
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
2 BED BEDROOM (M) WEST 1 : 20
7
A-705
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
8
2 BED BEDROOM NORTH 1 : 20
A-705
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
TYPICAL 2 BEDROOM PLANS & INTERNAL ELEVATIONS
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
DK&CW DM
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
3
A-705
500 FT-01
FT-01
NOTES
4
QUEEN SIZE BED TO BE DECIDED BY OCCUPANT
500 FT-01
2 BED BEDROOM (M) EAST 1 : 20
TOILET
40
320
400
EXPOSED WORDROBE
900
1000
EXPOSED WORDROBE
1374
320
WT-09 INTERIOR BI-FOLDING WINDOW TO CONNECT POS AND BEDROOM (M)
9 m²
40
40
850
50
CUSTOM MADE WARDROBE TO BE PLACE IN EACH BEDROOM
12 m²
BEDROOM
1
7
31 m²
7624
A-705
915
LIVING ROOM
159 76
4 m²
350
KITCHEN
10
2134
LT-04
940
3000 52 LT-04
500
40
515
90 110
WT-09
5
10
2
CUSTOM MADE WARDROBE TO BE PLACE IN EACH BEDROOM
2950
EXPOSED WORDROBE
A-705
415
76 RENDERED CONCRETE FINISHING
LT-04 WALL MOUNTED LIGHT TO BE PLACED ABOVE BED
50
10
2100
WT-08 EXTERIOR BIFOLDING WINDOW TO EDGE OF POS
CUSTOM MADE WARDROBE TO BE PLACE IN EACH BEDROOM
500
440
2100
2100
1780
WT-08
972
1574
1160
790
950
A-705
5
LT-03
600
6
2 BED LIVING ROOM NORTH 1 : 20
12 m²
BEDROOM (M)
2
A-705
FT-01 IN KITCHEN ZONE TO BE WATERPROOFED
150
150
DISHWASHER
2 BEDROOM PLAN 1 : 50 SCALE @A1
APPROVED
As indicated
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-705
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
76
1525
CL
453
453
LT-01
453
453
453
1003
CL
675
98
CL
750
3000
LT-01
492
395
CL
CL
450
1003
855
453
453
LT-03
CT-02
LT-02
675
453
453
453
LT-03
1525
1100
740
CL
1000
395
CL
239
650
730
448
605
812
890
CL
1187
40
920
40
240
76
2350
LT-03
40
1100
LT-02
1020
740
CT-02
600
LT-03
LT-03
790
LT-03
LT-03 TO BE INSTALLED ON TOP SIDE OF COOKING ZONE
40
200 40
1420
40
1200
100
1700
KITCHEN WASH BASIN TO REFER CAROMA 'AURA SINK MIXER' IS 1632
TV SET AND COUCH TO BE DECIDED BY OCCUPANT
DT-01 DT-02
2134
1940
DT-02
3000
DT-06
WT-09
2260
3000
WI-02
3000
MICROWAVE
WT-09 BI-FOLDING WINDOW TO CONNECT POS AND BEDROOM (M)
OVEN BIRCH FINISHING TO CABINET DOORS
DINING TABLE TO BE DECIDED BY OCCUPANT
3
3 BED LIVING ROOM EAST 1 : 20 LT-03
900
2580
LT-03
363
LT-03
CT-02
CL
CL WT-02 TIMBER FIN TO BE FIXED TO CONCRETE WALL
LT-03
CT-02
363
WT-02
LT-03
CL
425
525
CT-03
LT-03
2580
440
900 CL
560
100
3 BED LIVING ROOM WEST 1 : 20
CL
2450
LT-03
TOILET TILE TO BE INSTALLED FROM FLOOR TO CEILING HEIGHT WATER PROOFED
LT-03 DOWN LIGHT TO FIXED TO CEILING
558
1334
40
CL
FT-01
790
558
A-706
520
2
FT-01 IN KITCHEN ZONE TO BE WATERPROOFED
150
FT-01
A-706
REFRIGERATOR
DISHWASHER
CUSTOM MADE WARDROBE TO BE PLACE IN EACH BEDROOM
2100
WT-01
WI-03 FULL HEIGHT WINDOW TO ALLOW MAXIMUM SOLAR ACCESS INTO DWELLING
76
915
7624
52 3000
52
487
890
DT-02
40
149
500
2134
4
40
320
EXPOSED WORDROBE
345
487 524
2036
824615W 'CUBE WALL FACED TOILET' BY CAROMA
1829
LT-04
600
WI-03
LT-04
SHOWER CURTAIN TO BE INSTALLED ONTO 'CAROMA DOLPHIN SHOWER BASE'
LT-04
RENDERED CONCRETE FINISHING
2370
3020
LT-04 WALL MOUNTED LIGHT TO BE PLACED ABOVE BED
LT-04 TO BE INTALLED ON TOP OF MIRROR CABINET
76
1774
WT-01 TIMBER FIN TO BE FIXED TO CONCRETE WALL
3 BED BEDROOM (M) NORTH 1 : 20
5
A-706
CT-02
610
880
500
3
A-706
13 m²
A-706
2
LT-03
LT-03
LT-03
880
LT-03
920
767
KITCHEN
CL
LT-03 DOWN LIGHT TO FIXED TO CEILING
DOUBLE GLAZING BI-FOLDING WINDOW. REFER TO A-651 FOR DETAIL
200
4 m²
CL
LIVING ROOM 33 m²
1000
1857
WT-09
40
1780
2100
2100
6
FT-02
3 BED ENSUITE WEST 1 : 20
100
WT-08
RENDERED CONCRETE FINISHING
5
BEDROOM (M)
880 CL
50
4 m²
1334
3050
600
1160
CL CUSTOM MADE WARDROBE TO BE PLACE IN EACH BEDROOM
LT-03
490
1005
CL
A-706
A-706
CT-02 LT-03
LT-03
2425
6
3 BED BEDROOM (M) SOUTH 1 : 20
1774
LT-03
270
FT-02 TILE TO BE WATERPROOFED AND SLOPED
FT-01
100
4
520
500 30 40
FT-01
A-706
631710W 'OPAL SOLE WALL BASIN' BY CAROMA
QUEEN SIZE BED TO BE DECIDED BY OCCUPANT
650
RENDERED CONCRETE FINISHING
ENSUITE TOILET
WI-04 SHOWER CURTAIN TO BE INSTALLED ONTO BATH 'CAROMA CU6WFW'
LT-04
494
770
40
506
40
494
RENDERED CONCRETE WALL
1000
LT-04 WALL MOUNTED LIGHT TO BE PLACED ABOVE BED
52
7
A-706 BEDROOM 9
11 m²
EXPOSED WORDROBE
FREESTANDING BATH AND FILLER REFER CAROMA 'NOIR 1700' AND 'EPIC BATH FILLER' FOR DETAIL
696
500
500
POS 12 m²
A-706
824615W 'CUBE WALL FACED TOILET' BY CAROMA
900
400
320 40
EXPOSED WORDROBE
TOILET TILE TO BE INSTALLED FROM FLOOR TO CEILING HEIGHT WATER PROOFED
1174
LT-04
836
120
52
LT-04
LT-04
LT-04 TO BE INTALLED ON TOP OF MIRROR CABINET
1614
BI-FOLDING WINDOW TO CONNECT POS AND BEDROOM (M)
860
3000
WI-04 TOILET WINDOW TO BE TINTED TO PROVIDE PRIVACY
CUSTOM MADE WARDROBE TO BE PLACE IN EACH BEDROOM
LT-04 WALL MOUNTED LIGHT TO BE PLACED ABOVE BED
TOILET
BEDROOM
8 m²
13 m²
A-706
8
631710W 'OPAL SOLE WALL BASIN' BY CAROMA
FT-01 FT-01
7
A-706
3 BED BEDROOM WEST 1 : 20
GENERAL NOTES
8
A-706
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
3 BED BEDROOM EAST 1 : 20
9
A-706 REV
DATE
DESCRIPTION
3 BED TOILET SOUTH
1
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
3 BEDROOM PLAN 1 : 50
CLIENT
DRAWING TITLE
RMIT DANIEL MAUNDERS
TYPICAL 3 BEDROOM PLANS & ELEVATIONS 01
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
09/29/18
Checker Approver
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
A-706
1 : 20
SCALE @A1
APPROVED
As indicated
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-706
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
1000 40
920
1060
40 40
915
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
40
76
NOTES
100
950
2420
2380
2210
990
2134
2280
2420
76
76
980
40
40
1067
Level 01 Level 01 Level 01 Level 01 Level 01 Level 01 Level 02 Level 02 Level 02 Level 02 Level 02 Level 02 Level 03 Level 03 Level 03 Level 03 Level 03 Level 03 Level 04 Level 04 Level 04 Level 04 Level 04 Level 04 Level 06 Level 06 Level 06 Level 06 Level 07 Level 07 Level 07 Level 07 Level 08 Level 08 Level 08 Level 08 Level 09 Level 09 Level 09 Level 09 Level 10 Level 10 Level 10 Level 10 BASEMENT FLOOR GROUND FLOOR GROUND FLOOR GROUND FLOOR BASEMENT FLOOR GROUND FLOOR Level 05 BASEMENT FLOOR GROUND FLOOR GROUND FLOOR GROUND FLOOR Level 05 GROUND FLOOR GROUND FLOOR
Count 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Height 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210
Width 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067
DT-02 Location
AP-1-0-2_Toilet AP-1-1-1_Living Room AP-1-1-1_Toilet AP-1-1-2_Bedroom (M) AP-1-1-2_Toilet AP-1-2-1_Bedroom AP-1-2-1_Bedroom (M) AP-1-2-1_Toilet AP-1-2-2_Bedroom AP-1-2-2_Bedroom (M) AP-1-2-2_Toilet AP-2-0-2_Toilet AP-2-1-1_Living Room AP-2-1-1_Toilet AP-2-1-2_Bedroom (M) AP-2-1-2_Toilet AP-2-2-1_Bedroom AP-2-2-1_Bedroom (M) AP-2-2-1_Toilet AP-2-2-2_Bedroom AP-2-2-2_Bedroom (M) AP-2-2-2_Toilet AP-3-0-2_Toilet AP-3-1-1_Living Room AP-3-1-1_Toilet AP-3-1-2_Bedroom (M) AP-3-1-2_Toilet AP-3-2-1_Bedroom AP-3-2-1_Bedroom AP-3-2-1_Bedroom (M) AP-3-2-1_Bedroom (M) AP-3-2-1_Toilet AP-3-2-2_Bedroom AP-3-2-2_Bedroom (M) AP-3-2-2_Toilet AP-4-0-2_Toilet AP-4-1-1_Living Room AP-4-1-1_Toilet AP-4-1-2_Bedroom (M)
Level Level 01 Level 01 Level 01 Level 01 Level 01 Level 01 Level 01 Level 01 Level 01 Level 01 Level 01 Level 02 Level 02 Level 02 Level 02 Level 02 Level 02 Level 02 Level 02 Level 02 Level 02 Level 02 Level 03 Level 03 Level 03 Level 03 Level 03 Level 03 Level 04 Level 03 Level 04 Level 03 Level 03 Level 03 Level 03 Level 04 Level 04 Level 04 Level 04
Count 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 76
Height 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210 2210
Width 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067 1067
DT-03 Location
AP-4-1-2_Toilet AP-4-2-1_Toilet AP-4-2-2_Bedroom AP-4-2-2_Bedroom (M) AP-4-2-2_Toilet AP-6-1-3_Bedroom (M) AP-6-1-3_Toilet AP-6-3-1_Bedroom AP-6-3-1_Bedroom AP-6-3-1_Bedroom (M) AP-6-3-1_Toilet AP-7-1-3_Bedroom (M) AP-7-1-3_Toilet AP-7-3-1_Bedroom AP-7-3-1_Bedroom AP-7-3-1_Bedroom (M) AP-7-3-1_Toilet AP-8-1-3_Bedroom (M) AP-8-1-3_Toilet AP-8-3-1_Bedroom AP-8-3-1_Bedroom AP-8-3-1_Bedroom (M) AP-8-3-1_Toilet AP-9-1-3_Bedroom (M) AP-9-1-3_Toilet AP-9-3-1_Bedroom AP-9-3-1_Bedroom AP-9-3-1_Bedroom (M) AP-9-3-1_Toilet AP-10-1-3_Bedroom (M) AP-10-1-3_Toilet AP-10-3-1_Bedroom AP-10-3-1_Bedroom AP-10-3-1_Bedroom (M) AP-10-3-1_Toilet Toilet Toilet
Level Level 04 Level 04 Level 04 Level 04 Level 04 Level 06 Level 06 Level 06 Level 06 Level 06 Level 06 Level 07 Level 07 Level 07 Level 07 Level 07 Level 07 Level 08 Level 08 Level 08 Level 08 Level 08 Level 08 Level 09 Level 09 Level 09 Level 09 Level 09 Level 09 Level 10 Level 10 Level 10 Level 10 Level 10 Level 10 Level 05 BASEMENT FLOOR
Count 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 19
Height 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420
Width
Location
1060 1060 1060 1060 1060 1060 1060 1060 1060 1060 1060 1060 1060 1060 1060 1060 1060 1060 1060
Level
AP-1-0-1_Toilet AP-2-0-1_Toilet AP-3-0-1_Toilet AP-4-0-1_Toilet AP-6-0-3_Bedroom (M) AP-6-0-4_Kitchen AP-6-3-1_Toilet AP-7-0-3_Bedroom (M) AP-7-0-4_Kitchen AP-7-3-1_Toilet AP-8-0-3_Bedroom (M) AP-8-0-4_Kitchen AP-8-3-1_Toilet AP-9-0-3_Bedroom (M) AP-9-0-4_Kitchen AP-9-3-1_Toilet AP-10-0-3_Bedroom (M) AP-10-0-4_Kitchen AP-10-3-1_Toilet
Level 01 Level 02 Level 03 Level 04 Level 06 Level 06 Level 06 Level 07 Level 07 Level 07 Level 08 Level 08 Level 08 Level 09 Level 09 Level 09 Level 10 Level 10 Level 10
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
CLIENT
RMIT DANIEL MAUNDERS 1700 PROJECT
850 100
850
650
100 100
650
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
100
DRAWING TITLE
TYPICAL DOOR SCHEDULE DATE
CHECKED
08/01/18
DK&CW
APPROVED
DM
SCALE
1 : 20
0
0.5 1
2
3
5.0M
@A1
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-801
A
DT-04 Count
Height
Width
1
2000
1700
2 1
2000 2000
1700 1700
1
2000
1700
5
Location
Level
Bike Store
BASEMENT FLOOR Corridor ROOFTOP Store Room BASEMENT FLOOR Switchboard Room BASEMENT FLOOR
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 181012 Week 13.rvt
AP-1-0-1_Living Room AP-1-0-2_Living Room AP-1-1-1_Living Room AP-1-1-2_Living Room AP-1-2-1_Living Room AP-1-2-2_Living Room AP-2-0-1_Living Room AP-2-0-2_Living Room AP-2-1-1_Living Room AP-2-1-2_Living Room AP-2-2-1_Living Room AP-2-2-2_Living Room AP-3-0-1_Living Room AP-3-0-2_Living Room AP-3-1-1_Living Room AP-3-1-2_Living Room AP-3-2-1_Living Room AP-3-2-2_Living Room AP-4-0-1_Living Room AP-4-0-2_Living Room AP-4-1-1_Living Room AP-4-1-2_Living Room AP-4-2-1_Living Room AP-4-2-2_Living Room AP-6-0-3_Living Room AP-6-0-4_Living Room AP-6-1-3_Living Room AP-6-3-1_Living Room AP-7-0-3_Living Room AP-7-0-4_Living Room AP-7-1-3_Living Room AP-7-3-1_Living Room AP-8-0-3_Living Room AP-8-0-4_Living Room AP-8-1-3_Living Room AP-8-3-1_Living Room AP-9-0-3_Living Room AP-9-0-4_Living Room AP-9-1-3_Living Room AP-9-3-1_Living Room AP-10-0-3_Living Room AP-10-0-4_Living Room AP-10-1-3_Living Room AP-10-3-1_Living Room Comms Electricity Service Room Female Toilet Fire Control Room Fire Pump Room Fire Staircase Gas Meter Room Gym Hyralic Room Kitchen Kitchen Storage Male Toilet Study Toilet Water Meter Room
Level
100
1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000
DT-02 Location
1750
2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420 2420
Width
2000
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 13 1 1 1 2 1 1 1 1 1 72
Height
150
DT-01 Count
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
1000 920
NOTES 40 40
40
1000 920
40 40
40
1500 40
1420
1000
40
920
40
40
40
40
1000 920
40
560 1810
640
940
1 1 1 1 1 1 1 1 1 1 10
Width (mm) 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000
WI-02
Height (mm) 2950 2950 2950 2950 2950 2950 2950 2950 2950 2950
Location LV01 LV02 LV03 LV04 LV05 LV06 LV07 LV08 LV09 LV10
Count 1 1 1 1 1 1 1 1 1 1 1 1 2 1 2 1 2 1 2 1 2 1 27
Width (mm) 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 1500
Height (mm) 2940 1950 1950 2940 1950 1950 2940 1950 1950 2940 1950 1950 1950 1950 1950 1950 1950 1950 1950 1950 1950 1950
WI-03 Location AP-1-0-1_Living Room AP-1-2-1_Living Room AP-1-2-2_Living Room AP-2-0-1_Living Room AP-2-2-1_Living Room AP-2-2-2_Living Room AP-3-0-1_Living Room AP-3-2-1_Living Room AP-3-2-2_Living Room AP-4-0-1_Living Room AP-4-2-1_Living Room AP-4-2-2_Living Room AP-6-1-3_Living Room AP-6-3-1_Living Room AP-7-1-3_Living Room AP-7-3-1_Living Room AP-8-1-3_Living Room AP-8-3-1_Living Room AP-9-1-3_Living Room AP-9-3-1_Living Room AP-10-1-3_Living Room AP-10-3-1_Living Room
Count 1 1 2 1 1 1 1 2 2 1 1 2 1 1 1 1 2 1 1 2 1 1 2 1 2 1 1 2 1 2 1 1 2 1 2 1 1 2 1 2 1 1 2 1 59
Width (mm) 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000
Height (mm) 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450 2450
870
WI-04 Location AP-1-0-1_Bedroom (M) AP-1-1-1_Bedroom (M) AP-1-1-2_Bedroom (M) AP-1-2-1_Bedroom AP-1-2-1_Bedroom (M) AP-2-0-1_Bedroom (M) AP-2-1-1_Bedroom (M) AP-2-1-2_Bedroom (M) AP-2-2-1_Bedroom AP-3-0-1_Bedroom (M) AP-3-1-1_Bedroom (M) AP-3-1-2_Bedroom (M) AP-3-2-1_Bedroom AP-3-2-1_Bedroom (M) AP-4-0-1_Bedroom (M) AP-4-1-1_Bedroom (M) AP-4-1-2_Bedroom (M) AP-4-2-1_Bedroom AP-4-2-1_Bedroom (M) AP-6-0-3_Bedroom (M) AP-6-0-4_Bedroom (M) AP-6-1-3_Bedroom (M) AP-6-3-1_Bedroom AP-6-3-1_Bedroom (M) AP-7-0-3_Bedroom (M) AP-7-0-4_Bedroom (M) AP-7-1-3_Bedroom (M) AP-7-3-1_Bedroom AP-7-3-1_Bedroom (M) AP-8-0-3_Bedroom (M) AP-8-0-4_Bedroom (M) AP-8-1-3_Bedroom (M) AP-8-3-1_Bedroom AP-8-3-1_Bedroom (M) AP-9-0-3_Bedroom (M) AP-9-0-4_Bedroom (M) AP-9-1-3_Bedroom (M) AP-9-3-1_Bedroom AP-9-3-1_Bedroom (M) AP-10-0-3_Bedroom (M) AP-10-0-4_Bedroom (M) AP-10-1-3_Bedroom (M) AP-10-3-1_Bedroom AP-10-3-1_Bedroom (M)
Count 2 1 1 1 2 1 1 1 2 1 1 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 40
Width (mm) 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000
Height (mm) 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940
WI-05 Location AP-1-0-1_Toilet AP-1-1-2_Living Room AP-1-2-2_Bedroom AP-1-2-2_Toilet AP-2-0-1_Toilet AP-2-1-2_Living Room AP-2-2-2_Bedroom AP-2-2-2_Toilet AP-3-0-1_Toilet AP-3-1-2_Living Room AP-3-2-2_Bedroom AP-3-2-2_Toilet AP-4-0-1_Toilet AP-4-1-2_Living Room AP-4-2-2_Bedroom AP-4-2-2_Toilet AP-6-0-3_Toilet AP-6-0-4_Toilet AP-6-1-3_Toilet AP-6-3-1_Toilet AP-7-0-3_Toilet AP-7-0-4_Toilet AP-7-1-3_Toilet AP-7-3-1_Toilet AP-8-0-3_Toilet AP-8-0-4_Toilet AP-8-1-3_Toilet AP-8-3-1_Toilet AP-9-0-3_Toilet AP-9-0-4_Toilet AP-9-1-3_Toilet AP-9-3-1_Toilet AP-10-0-3_Toilet AP-10-0-4_Toilet AP-10-1-3_Toilet AP-10-3-1_Toilet
Count 1 1 1 1 2 2 2 2 2 14
Width (mm) 1000 1000 1000 1000 1000 1000 1000 1000 1000
Height (mm) 640 640 640 640 640 640 640 640 640
Location AP-1-0-2_Kichen AP-2-0-2_Kitchen AP-3-0-2_Kitchen AP-4-0-2_Kitchen AP-6-0-4_Kitchen AP-7-0-4_Kitchen AP-8-0-4_Kitchen AP-9-0-4_Kitchen AP-10-0-4_Kitchen
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
CLIENT
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
TYPICAL WINDOW SCHEDULE DATE
CHECKED
08/01/18 SCALE
1 : 20
DK&CW 0
0.5 1
2
APPROVED
DM 3
5.0M
@A1
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-803
A
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 181012 Week 13.rvt
WI-01 Count
40
40
FFL
40
870
1510
40
40
2370 1950
1870
2450
860
40
2950
2870
40
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
125
40 40
670
125
750 40
NOTES
1925
1175
1280
2175 1260
2120 2120 2120 2120
Width 750 750 750 750
DT-05B Location
Level
Count
Comms_Core Female Toilet GROUND FLOOR Toilet ROOFTOP Water Meter Room_Core
11 11 22
Height 1280 1280
DT-06A
Width 1280 1280
Location
Count
Electrical Room_Core Gas Meter Room_Core
1 1
Height
Width
2425
DT-06B
Location
1175
Level
Lobby
Count
GROUND FLOOR
1 1 1 1 1 1 6
Height 2425 2425 2425 2425 2425 2425
Width
Location
1925 1925 1925 1925 1925 1925
Retail 1 Retail 4 Retail 4 Retail 3 Retail 2 Lobby
Level GROUND FLOOR GROUND FLOOR GROUND FLOOR GROUND FLOOR GROUND FLOOR GROUND FLOOR
REV
DATE
DESCRIPTION
3150 75
3000
75
750 925
40
40
920
CLIENT
670
RMIT DANIEL MAUNDERS
40
40
PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
700
40
125
250
1000
DRAWING TITLE
2020
2120
2000
1860
600
1905
2000
2155
2250
TYPICAL DOOR SCHEDULE 2 DATE
CHECKED
10/12/18 875
SCALE
1 : 20
100
100
700 100
125
DT-07
1 1
Height 2250
Width 3150
DT-08 Location
Refuse Storage
Level GROUND FLOOR
Count 1 1 1 3
Height 925 925 925
Width 2155 2155 2155
DT-09 Location Corridor Gym Study
Level Level 05 Level 05 Level 05
Count 2 2
Height 2000
Width 1000
0
0.5 1
2
APPROVED
Approver 3
5.0M
@A1
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-802 Count
Checker
DT-10 Location
Mech Plant
Level ROOFTOP
Type Mark DT-10 DT-10 3
Count 2 1
Height 2120 2120
Width 750 750
Location Female Toilet Male Toilet
Level GROUND FLOOR GROUND FLOOR
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 181012 Week 13.rvt
11 1 1 11 24
Height
125
125
990
1220
1980
2120
990 100
DT-05A Count
2425
40
2175
600
2425
600
40
40
N
N
N
12:00 PM
3:00 PM 9:00 AM
W
1
A-901
6:10 AM
6:15 PM
22 September E W
S
SOLAR STUDY SPRING EQUINOX 9AM
6:10 AM
6:15 PM
2
A-901
22 September E W
S
SOLAR STUDY SPRING EQUINOX 12PM
3
A-901
N
6:10 AM
6:15 PM
22 September E
S
SOLAR STUDY SPRING EQUINOX 3PM
N
N
12:00 PM
3:00 PM 9:00 AM
E
W
E
W
4:56 AM
7:40 PM
4:56 AM
7:40 PM
21 December
4
A-901
SOLAR STUDY SUMMER SOLSTICE 9AM
GENERAL NOTES
S
NOTES
4:56 AM
7:40 PM
21 December
5
A-901
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
E
W
SOLAR STUDY SUMMER SOLSTICE 12PM
21 December
6
S
A-901
SOLAR STUDY SUMMER SOLSTICE 3PM
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
SOLAR ANALYSIS DIAGRAMS
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
DK&CW DM
S
SCALE @A1
1:1000
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
APPROVED
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-901
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
N
N
N
12:00 PM
3:00 PM 9:00 AM
W
6:23 AM
6:31 PM
1
A-902
SOLAR STUDY AUTUMN EQUINOX 9AM
E 20 March
W
S
6:23 AM
6:31 PM
2
A-902
E 20 March
W
S
SOLAR STUDY AUTUMN EQUINOX 12PM
3
A-902
N
6:23 AM
6:31 PM
SOLAR STUDY AUTUMN EQUINOX 3PM
N
E 20 March
S N
12:00 PM
3:00 PM 9:00 AM
21 June
21 June
7:37 AM
5:06 PM
E
W
4
A-902
SOLAR STUDY WINTER SOLSTICE 9AM
GENERAL NOTES
S
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
21 June
7:37 AM
5:06 PM
E
W
5
A-902
SOLAR STUDY WINTER SOLSTICE 12PM
7:37 AM
5:06 PM
E
W
6
S
A-902
SOLAR STUDY WINTER SOLSTICE 3PM
REV
DATE
DESCRIPTION
CLIENT
DRAWING TITLE
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS
SOLAR ANALYSIS DIAGRAMS
PROJECT
DATE
CHECKED
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
DK&CW DM
S
SCALE @A1
1:1000
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 181012 Week 13.rvt
APPROVED
STATUS
PROJECT #
DD
18-214
DRAWING NUMBER
REVISION
A-902
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
MATERIAL RESEARCH
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
Concrete Wall
Curtain wall
Timber Stud Wall
Timber Feature
Exposed Concrete with trowel finish filling tie rod with mortar
U-Max 150 Front Double Glazed - 34mm Pocket
90mm Timber stud frame 5mm Gypsum plaster board
Vertical open-joint timber cladding
Wall Materials
300mm Concrete
150mm Concrete
Toilet Tile
Cafe Tile
Hollowcore: 300mm Precast
Hollowcore: 150mm Precast
Novoceram: OZ Froid 60x60mm
Novoceram: Petitot Sepia 60x120mm
Floor Material
Plaster Panel
Cafe Ceiling
Exposed Floor
Armstrong: Ultima +OP 60x120mm
Innowood: Innoceil
Exposed Concrete with trowel finish filling tie rod with mortar
Ceiling Material
Recessed Light
Pendant Light
Sconce Lamp
Lights2you: 12w DL5530 316 Stainless Steel LED Downlight
Mica Lighting: Jet100 LED Pendant Light
Weplight: Lupe 60 Wall
Lighting Material 01
WAll Lamp
Troffer Light
Louver Light
Cult Design: BL7 Wall Lamp
Pierlite: Unilux Profile Surface Mount
Lug Light Factory: Office+ LB LED 600x600 P/T ED 37W
Unilux Profile Surface Mount Low profile, surface mounted T8 troffer module.
Specification Body manufactured in steel with durable white powder coat finish Body is fixed to the ceiling by hidden screw fixings through back of body Electrical components located under side mounted metal gear cover for electrical safety Single piece, non-discolouring, high impact, injection moulded acrylic diffuser (except 18W versions) Diffuser is held by internal tensile steel spring easy to remove for re-lamping Body and diffuser fit closely together and have no horizontal surfaces, thereby preventing the ingress of dust and dirt Terminal block accepts 2 x 2.5mm cable termination Lamps excluded to allow for a choice of colours at time of ordering Integral electronic control gear
Product Codes
Quick Specification
Code
Version
Dim (mm)
Mass (kg)
SEP218EL
2 x 18W T8 EL
615 x 277 x 100
3.0
SEP236EL
2 x 36W T8 EL
1265 x 277 x 100
6.2
SEP336EL
3 x 36W T8 EL
1265 x 277 x 100
6.4
Pierlite surface mounted maximum glare control T8/T5 low profile system, robust polycarbonate hinges, injection moulded acrylic diffuser.
Design Application Food preparation areas, schools, TAFE, universities, libraries, retail stores, hospitals, general office areas and utility rooms.
9.4kg
Max Dim (mm) 1650 x 277 x 100 PDF Prepared: 19.05.2018 14:05pm, Last page update: Nov 2017
Lighting Material 02
Bike Rack
Bike Pump
Bike Workstand
Secura Bike: Dual Height 10 Bike Parking CBR10GS
Secura Bike: Bicycle Pumping Station BPS01
Secura Bike: Bicycle Repair Station BBRS02
Bike Furnitures
Toilet Bowl
Male Urinal
Hand Basin
Handrail
Caroma: Liano Easy Height Invisi ii
Caroma: Integra Urina
Caroma: Moon 500 Wall Basin 1TH White
RBA: 90LH +450 Straight Grab Set
Toilet Materials
HVAC 01
HVAC 02
Johnson Controls: Series 100
Johnson Controls: Series 40
HVAC Units
SITE ANALYSIS
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
Site Condition
QUEENSBERRY ST
R BE
NS
E UE
Q
3D view of the site: corner of Queensberry St and Bouverie St
Site address: 81/89 Bouverie St, Carlton VIC 3053 Area: 460m2 Perimeter: 85m
Immediate site surrounding
BOUVERY ST
ST
LANSDOWNE PL
IE
ER
UV
BO RY
ST
Photo Study Street and context views of site. The city provides a backdrop for the site, while the proposed building may function as a welcome sign to RMIT from the North. Yellow massing suggests how building sits within site.
Heritage buildings run along Queensbury street. The brickwork links neighbouring building creating a continuous flow of texture and colour along the street scape. Brickwork is characteristic of many Melbourne inner suburbs building, creating a record of a point in time. Does brickwork form part of the facade in order to integrate it into the street front?
Surrounding Condition
View to the east
View to the south
View to the north
View to the west
Given site positioning on the border of Carlton and the CBD’s northern edge, their is ample opportunity to capture views along various faces of the building. These views can also be exploited across different floor levels. Above views are taken from a hypothetical top floor or roof top. Due to heritage of neighbouring buildings, there is little risk of immediate high rises. Views best from North, East and West
ST RY BAR
Tree Study
25
Ulmus x hollandica: ELM 24
Platanus x acerifolia: LONDON PLANES QUEENS
Angophora costata: SMOOTHBARKED APPLE
ST
TER ST
Corymbia ficifolia: RED FLOWERING GUM ON ST
BOUVER
IE ST
LEICES
K BER
ELE
T Y S
BERRY
SWANST
Quercus rubra: RED OAK
Eucalyptus leucoxylon: YELLOW GUM
Melia Azedarach: WHITE CEDAR 29
30
AB LEZ
ETH
ST
28
26
Celtis australis: EUROPEAN NETTLE TREE
27
E
25
24
Flindersia australis: AUSTRALIAN TEAK
23
Site location in broader context
22
Ulmus x hollandica
Platanus x acerifolia
Angophora costata
Corymbia ficifolia
Quercus rubra
Eucalyptus leucoxylon
Melia Azedarach
Celtis australis
Flindersia australis
ST
GARTON DR
ST
il City Yarra LYGON
ST
ST
DRUMMOND
ST
ST
ST
ST
ST
ST CHARLES
STATION PL
DAVID
SUTTON
LA
POWELL
Counc
il
PL
COCHRANE
WATSON JIMMY LA LA
TESORIERO
ST
ST
PL
PL
UNION
ELGIN
City
BARRUP ST
CANNING
Yarra
ST
ST
LA
PL
HYAM
PL
LYGON
PL
RATHDOWNE
RATHDOWNE
DRUMMOND
LYGON
LYGON
DORRIT
PL
ST
ST
GRATTAN
ST
ST
LA
PL
LA MAMA
CARDIGAN
SWANSTON
PL
ST
ST
MALVINA
ORMOND CARDIGAN
PL
RODNEY
PL
ST
MISSION
LITTLE PL
NICHOLSON
RATHDOWNE
ELM TREE
HUDSON PL
PL
DRUMMOND
LYGON
ST
ST
CARDIGAN ST
DESHALL PL
CARDIGAN
TCE
CARDIGAN
OWNE ST
UMMOND ST
ORR
GON
SWANSTON ST
TCE
CARDIGAN
WANSTON
ST
LIT. QUEENSBERRY LA QUEENSBURY
PL
RUSH
PL
PL
BARKLY
PL
BOUVERIE
LEICESTER
ST
Design and Development Zone - Design and Development Schedule 61 Area 4.1+4.2
Pond
MAP No 5HO
OWNE ST
ORR
GON
* A complete list of zones and other overlays is in the written part of this scheme. M
Yarra Pond
NICHOLSON
GARDENS
ST
PL
HUDSON PL
ELM TREE
CARLTON
AMENDMENT C198
N BUILDING
Printed: 8/10/2015 RATHDOWNE
DRUMMOND
LYGON
DESHALL PL
ST
ST
il Counc City
BARRUP ST
CANNING
ST
ST
LA PL
RODNEY
MISSION
MELBOURNE EXHIBITIO
STATION DAVID
PL
RATHDOWNE
DRUMMOND
RATHDOWNE
PL
LA MAMA
LYGON
ST
PL
ORMOND PL
GROSVENOR PL
PL
ST
ST
ST
ST
ST
PL
LA
PL
PL
ST
PL
WATSON JIMMY LA
COCHRANE
LA
SUTTON
UNION
PL
LA
POWELL
ST DORRIT
LYGON
PL
ST
LYGON
PL
ST
CARDIGAN LITTLE
YOUNG
IEVERS
EARL
11
PL
ST
CARDIGAN ST
DRUMMOND
* This map should be read in conjunction with additional Planning Overlay Maps (if applicable) as indicated on the INDEX TO MAPS.
TCE
CARDIGAN
ST
WANSTON
ST
ST
10
9
D
8
ST
ST
ST
ST
ST
7
VICTORIA
6
PL
EAST
PL
MAGENTA PL
ST
TCE
CARDIGAN
PL
5
WI
Y
HYAM
GRATTAN
PL
BOUVERIE
LEICESTER
IE
ESSEX
4
PL
BOUVER
PL
ALLISON LA State of Victoria
3
ALMA
2
c
S
State School
SAN MAR L
EADE
S
St. Mary's
Church except This publication is copyright. No part may be reproduced by any processR.C. West provisions of the Copyright Act. in accordance with the Melbourne
ARGYLE PL
FINLAY
PL
Heritage Buildings surrounding the site - VHR H2325: Carlton Tram Substation - VHR H0970: Former Primary School - VHR H2138: Cast Iron Urinal - H7822-0973: Former Carlton & United Brewery Site ST
LL
PL
LIT. QUEENSBERRY LA QUEENSBURY
ST
LANSDOWNE
CORNELL
ST
COBDEN
GIBBONS PL LA
MONAHA N
PL
ST LT. COBDEN PRINCESS
ST
ST
CARLTON
ST
LA
CAPEL
GRACIE LA
PL
PL
RRY
ST
KIN G
PL
PEEL
VICTORIA
QUEENSBE
PL
ST HOWARD
SWANSTON
ST
ST
MOSS
CAPEL
LT HOWARD ST
HOWARD
BLAIRS PL
PL
CHETWYND
LEVESON
LT. LEVESO N
ST
ERROL
TRAFALGAR
GARDINER
ARGYLE PL SOUTH
TCE
RUSH
PL
PL
IEVERS
1
LITTLE CURZON
ST
WARWICK
L
ST
PL
INDEX TO ADJOINING MAPS
ST
KELVIN
LINCOLN
CARDIGAN
ST
BARKLY
LA
LINCOLN SQ SOUTH
ST
ST.GEORGES R.C. SCHOOL
PELHAM
CANADA
ST
CURZON
ST
ST
LT.ERRO
RAGLAN ERROL
O'CONNE
ST
PL
ST UNION
ST
ST D FO R BE D
PELHAM
LEICESTER
OWEN
PL
ST
CUMBERLAND
PL
ARGYLE PL NORTH
PELHAM
ST
SARTORI
LA
ELM PL
CARDIGAN
SWANSTON
PL
ST
ST
MALVINA
ST
ST BERKLEY
BARRY
O
ST
LA
ST
ELIZABETH
ST
PL D R FO
O D
BE D
EC R W
KW BL AC
ST
LA
JACOBYS PL
PEARSON
PELHAM
RRY
ATKIN
st
SQ NORTH
ST
UMMOND ST
ST E SID K
ST
PA R
LA
S H
LE
IG
C
H
N BU
KY N
TH H
O
ST
PL
COOKS
CHETWYND
PL
LANCASHIRE
PL
PL
PL AM
LA
WYLIES LA LA
QUEENS BERRY
MATTINGLYS
ST
S R VIL LIE
T R O U C AR H
CO UR TN PL EY
ST LA
FALSHAMS
CALLAHANS
LA
ISAAC'S
ABBOTSFO RD
LOTHIAN ST ST
ST NTH
ST NTH LIT LOTHIAN
LITTLE LOTHIAN
GH ST NTH
ST
ST
ST
ST
TEMPER ANCE HALL LA
CURZON
ST
LINCOLN
Y KL
CARLTON
ST
MURCHISO N
ABBOTSFOR D
PL
R BA
PL
ST
ST
ST. STH
FO PL R D
SCOTTS
VICTORIA
PL Y RKL BA
LE
LIT LOTHIAN
D
PL
BEARD
TCE
PL
ST
ABBOTSFORD
BE
ST
TT
MAP No 5PO
Pond
QUEENSBE
ST
LI
LOTHIAN
LI NG
GRATTAN LA
LT GRATTA N CHURCH
ST BANBRIDGE
PL REGISTR Y LA
ST
AMENDMENT C196
RYANS LA
LA
CHURCH
ON
PL
M
ST
JONES
Victoria Bowling Club
KET
LA
NAUGHT PL
UNIVERSITY
Pond
* This map should be read in conjunction with additional Planning Overlay Maps (if applicable) as indicated on the INDEX TO MAPS.
BENDIGO
ST
HAYMAR
UNIVERSITY PL
YORK
CARLOW
ST
POST OFFICE
Printed: 12/10/2015
GARDENS
* A complete list of zones and other overlays is in the written part of this scheme.
LITTLE DRYBUR
ST
RD
ST
PL UNIVERSITY
STH
W RE PL CK YN IG H TS ID E PL
R D LA W S
E
ST
ST
LA N
Y
H
O
BARR
DRYBURG
PL
R
LEY
st
BR O XFO LA ID TY
STATE COLLEGE OF VICTORIA
ELL NN
LOTHIAN
BYRON
ST
G KIN
ST
ST
DO W
ST
LA
GRATTAN
O'CO
ST
VICTORIA
MILLER
CE R
EY
ST ARDEN LA
ROYAL DENTAL HOSPITAL
BERK
ST
ST
PL ELGIN
ROYAL
PREPARED BY: Planning Mapping Services
ST
H ABET
T
RRY
ST
MILLER
EN
TN
VA LE
GRATTAN
ST
CULLENS
SOUTH
MOTON
ROYAL MELBOURNE HOSPITAL
ELIZ
ELM
R
M AR K LA ET
UR
GLASS
ST
QUEENSBE
CO
ST
PURCELL
200 m
U M
ST
ST
ST
LA
CHARLES
ST
ST
G E
N BUILDING
CARLTON
Yarra LYGON ST
DRUMMOND
ST
ST
PH Y
ST R
ST
EARL
BEATONS
ST
NORTH
0
R
HAINES LA
G EO
Y
SCOTIA
PROVOST
PLACE
PLACE
BALLIE
ST
SP
ST
HUR
HUR
200
BAILLIE
MACART
MACART
PL
LT
ARDEN
ST
WELCH
ST
PL
Housing Commission of Victoria
Court House MAHONE S PL
GOLDHAR
ST
LT PROVOS
ST
Y
O'SHANASS
ARDEN
TESORIERO
K PA R ST
KE R
H
W
AR
EIR S
AR LA TS
STE
UNIVERSITY HIGH SCHOOL
ST
ST
LT
M AR
ST
DRYBURGH
MILLER LA LITTLE ELGIN
PL
ST
PL
RD
ARDEN
ASTOR
ALPIN
FARADAY
ST
O'SHANASS Y ST
ST
TYNE
ST
HARRIS
HAINES
ST
LT PALMER STON
PL
ST UNIVERSITY OF MELBOURNE SCHOOL OF VET SCIENCE
ON
St.Judes Church
HOLMWOOD
PL
PITT
ELGIN
ES
LA
D O M R KE
ST
S KE SY LA
HAINES ST
W
HARDWICK
LA
LS AE H IC cM M
PALMERST PAINSDALE
MELBOURNE EXHIBITIO
ST
PL
WOOD ST
ST
ST
LA
R TH
STORY
FITZGIBBON
H AP M C
O
POST OFFICE
ST
ST
ST
ST
BENJAMIN
SE AT EH O U
Y
A LA N
G
R
PA R GR K
S
SW
ST
HOMEBUSH
LE
YO U LA NG
LA
LA
DONOVANS
LA
O
WIMBLE
LA
O
PL
M
LA
LA
ST G
ERSKINE
LE E PL MIN
IS AV
LA
ST LA
CARROLS
ST
K
GROSVENOR
City
PRINCES PARK
ST
ST
CO LL EG E
DR
LA
G
R
U DE C H YS
LA LANGFORDS LA MUGG
LA
CARRS
R
R
PL
CARROL
PA
G
PL
9
11
YOUNG
CANNING LA
AN
E
PALMERSTON
MELBOURNE UNIVERSITY
MORRAH
PL
MAGENTA PL
M
ST ILL NE
8
10
AP
ST
7
CH
OO
LA
KAY
5
6
PL
WATERL
BUTLER
PL
4
DRUMMOND
ST
EAST
IEVERS
ST
ST
ARGYLE PL
FINLAY
BAYLES
ESSEX
2
3
Housing Commission of Victoria
1
LL
ERSKINE
ST
ST
INDEX TO ADJOINING MAPS
MILE
way Tram
SHANDS
Queen Elizabeth Hospital
ST
ST
KERRS
LYTTON
EL
ST
WOOD ST
HAINES ST
CE
PL
ST
ST
VICTORIA
RD
PP
LA
DRYBURGH
TERY
College Square Student Accommodation
KE
ST
CE
ST
AH R
ERSKINE
RR IS
SP EN ST
ES
ST
R O M
ST KES
FEU ST
YL
HOSPITAL
DEGRAVES
IE
OWEN
ST.GEORGES R.C. SCHOOL
CHILDRENS
BROUGHAM
PL
ES
CEME
ST EA
LA
PRINCES
Y KL
CARLTON
200 m
ST
MELBOURNE GENERAL CEMETERY
0
ST
MURCHISO N
UE
SCHOOL
AIN
BA
ROYAL
PL
D
EN
ST. MICHAELS
ST
NO
ST
ALMA
BOUVER
R
AV
COLLEGE
N
LANSDOWNE
ST COBDEN
COLLEGE
CR
GIBBONS PL LA
MONAHA N
PL
CORNELL
RY TE ME
200
ST
ST
SARTORI
PL
CE
THE
PL
Y RKL BA LE
R BA
PL
O'CONNE
ARGYLE PL SOUTH
TCE
PL
PL
TT
LI
CARLOW
ST
CEMETERY
ES T
VICTORIA
S EN BR DR
DR
TO
IEVERS
VICTORIA
il Counc
Heritage Overlay
ST
NORTH
SOUTH
ST
KELVIN
LINCOLN
ST
IO
BARRY
BERKLEY ST
D
PL
PL
PELHAM
LINCOLN SQ SOUTH
CARLTON
Y
PL
PL
BEARD
PL REGISTR Y LA
ST
LA
RRY
ST
ST
c
State School
ST
ST
ST
Parking Zone - Parking Precinct 12 This publication is copyright. No part may be reproduced by any West provisions of the Copyright Act. in accordance with the Melbourne
UNIVERSITY
UNIVERSITY
ON
TCE
CANADA
PL
ALLISON LA State of Victoria
YORK
GRATTAN LA
ST
PL
ST
S EN GENERAL
CR
SOUTH
G
PELHAM
LEICESTER
ST LT. COBDEN PRINCESS
ST St. Mary's processR.C. except Church
PL ST
POST OFFICE
ARGYLE PL NORTH
PELHAM
ST
LA
CAPEL
GRACIE LA
AVENUE
BR IN
SQ NORTH
ST
WARWICK
PL
ST HOWARD
PL
PEEL
VICTORIA
ST
ll
EN S DR
ELL
ST
ST
PL D R
O D
D FO R BE D
ST ST
PL
CAPEL
LT HOWARD ST
MOSS
HOWARD
GARDINER
BLAIRS PL
ST
ST
QUEENSBE
ST
LEVESON
ST
TRAFALGAR
LT. LEVESO N
ST
LITTLE CURZON
CURZON
L
ST RAGLAN
ERROL
ELM PL
UNION
st
ST
DR
HO
PLACE
PLACE
MOTON
UNIVERSITY
PL
ST
COLLEGE
ST
LINCOLN
PL
Club
ROYAL PARK
SCOTTS
ST
LT.ERRO
PL
ST
HUR
HUR
PL
ST
TEMPER ANCE HALL LA
CURZON
ST
MACART
PL
NAUGHT
PL
MELBOURNE
UNIVERSITY
ST
PELHAM
RRY
MACARTHUR RD
FL EM
ST
ELIZABETH
ST O KW
D
FO PL R D
BL AC
ST
LA
JACOBYS
BE
CRAWFORD OVAL
D
CHURCH
CUMBERLAND
KIN G
ST MACART
WELCH
PL
LT GRATTA N ST
CHURCH
ST
E
LI NG
UNIVERSITY
STATE COLLEGE OF VICTORIA
Victoria Bowling Club
KET
ST BANBRIDGE
AN
HAYMAR
LA
PL
PEARSON
RD
FO
R EC
N
W RE PL CK YN IG H TS ID E PL
R D LA W S
BE D
O H
W
O
LA
PL
CHETWYND
LA
RYANS LA
LA
QUEENSBE
PL
ST
Housing Commission of Victoria
ST
GOLDHAR
ROYAL
ST E SID K
ST
PA R
LA
S H
LE
IG
C
H
PL
PL AM TH
KY N
C COOKS
JONES
PL
LANCASHIRE
ST
GRATTAN
ROYAL DENTAL HOSPITAL
N BU
S R VIL LIE
ST
R
PARK
W
PRINCES PARK
ST
PH U M O U
R
T
ST
CO UR TN PL EY
AR H LA
ST
BENDIGO
LA
PL
QUEENS BERRY
DO W PL
ATKIN
ERROL
PL
Court House MAHONE S PL
R
HAINES LA LA CALLAHANS
LA
FALSHAMS
WYLIES LA LA
ST
MATTINGLYS
BR O XFO LA ID TY
ST
ST
ST
ST
DR
ST
GARTON
ROY
ST
BENJAMIN
ST Y
EIR LA S
W
H
ST ISAAC'S
ST
ABBOTSFOR D
ST. STH
LIT LOTHIAN ABBOTSFORD
LOTHIAN
ST
ALPIN
ST
PREPARED BY: Planning Mapping Services
ST
LEONARD
CO LL EG E
ST ST
POST OFFICE
WIMBLE ST
PA R
K
ST
FITZGIBBON
SE AT EH O U G
A LA N
C H AP M
S
AR
KE R
YO U LA NG
LA AR LA TS W
STE
LA
LA
ST
HOMEBUSH
HARDWICK
ABBOTSFO RD
LOTHIAN ST ST
ST NTH
ST NTH
LITTLE LOTHIAN
LIT LOTHIAN
LITTLE DRYBUR STH ST
H DRYBURG
LOTHIAN
st
DRYBURGH
LA
LA
ST
ERSKINE
LE E PL MIN G
LA IS
CARROLS
AV
LA
ST CARROL
LA CARRS LA
DONOVANS
DRYBURGH
CE
ST GH ST NTH
Yarra
NICHOLSON ST
T
RRY
ST
GARTON
THE
MILE
DR
LA
ERSKINE
MUGG LA SHANDS
CANNING LA KERRS
cil Coun City
BARRUP ST
CANN ING
EY
GRATTAN
Oval
Counc
TT IO ELL
LA
ST
U DE C H YS LA
G
R
LANGFORDS
ST
ST STATION
DAVID PL
NE RATHDOW
RATHD OWNE
ST
ST
LA HUDSON PL
ELM TREE PL
RATHD OWNE OWNE ST
ORR
TN
ST
ST
PL
TT
UR
ST ARDEN LA
ST
GARTON
ROY PDE
LA
AVENUE
CULLENS
ASTOR
ROYAL MELBOURNE HOSPITAL
THE
Cou rts
M AR K LA ET
VA LE
D
BR
ST
R
ba
G E
ST
ST
CE R
ay
Net
QUEENSBE
ST
MILLER LA LITTLE ELGIN
UNIVERSITY HIGH SCHOOL
R LA
Tramw
BR EN S
R
Y
BYRON
PURCELL
Hill
PRINCES
ELLIOT
N
ST
EN
CO
GLASS
MILLER
Overlays Whitley College
Pavilion
R
LA
LT PALMER STON
PL
TYNE
ST
ST
PROVOST
ST ON
St.Judes Church
HOLMWOOD
FARADAY
G EO
SCOTIA
BEATONS
PITT
ELGIN
Pavilion
RR
ST
BALLIE
ST
ILL NE
ST
Brens Oval
ST
LT
M AR
ARDEN
S
State Hockey Centre
PL
ST
PALMERST PL
MACPHERS ON
Tennis
RD
STORY
UNIVERSITY OF MELBOURNE SCHOOL OF VET SCIENCE
PU
ST
Princes
MACARTHU R
ST
OO
PL
PAINSDALE
PO
WALKER
TREACY
TO
BAILLIE
VICTORIA
ST
HERITAGE OVERLAY
ST
VICTORIA
Housing Commission of Victoria
KAY
PALMERSTON
MELBOURNE UNIVERSITY
ST
ES
Y
ST
Pond
Ground
G.Smith
D O RM KE
ST
MILLER
SP
Carlton
COLLEGE
AV
ST ELS HA IC cM M
ST
O'SHANASS
ELM
R
* A complete list of zones and other overlays is in the written part of this scheme. M
R TH
HAINES
LT
ST
SP EN ST CE
ST
LA
COLLEGE
AV
G
LA
PL
ST
ST
PL
DRUMMOND
LYGON ST
PL
ORMOND RODNEY
PL MISSION
DRUMMOND DESHALL PL
UMMON D ST
MAP No 5
Cricket
IN
way
ST
ST
ST COCHR ANE
LA MAMA PL
ST
LA
LYGON
PL
LYGON
ST
ST
Pond
RIDLEY
MELBOURNE ZOOLOGICAL GARDENS
FL EM
Tram
ST
DRUMMO ND
ST WATSON JIMMY LA LA
SUTTON
UNION
PL
LA DORRIT
LYGON HYAM PL
ST
CARDIGAN LITTLE
LA
CARD IGAN
TCE
CARDIGAN ST
ST
ST
* This map should be read in conjunction with additional Planning Overlay Maps (if applicable) as indicated on the INDEX TO MAPS.
TCE
CARDIGA N
WANSTON
ST
CARDIGAN
SWAN STON
BOUVERIE
LEICESTER
COBDEN MILE
THE
PL
QUEENSBURY
LIT. QUEENS BERRY
PL
LANSDO WNE
ST
LT. COBDEN ST
CAPEL
PEEL ST
ST
RUSH
PL
PL
BARKLY
ST
WARWICK
ST
EARL
CARLTON GARDENS
K
R
WI
D
AMENDMENT C173 & C196
ST
GON
ST HOWARD
CHET WYND
ST
ST
PL
ST
ST
GRATTA N
BERKLEY
BARRY
ST BE D FO RD
ST ST
ST N
LEVESON
ERROL
LT. LEVESO
ST LITTLE CURZON
CURZON
CARD IGAN
SWAN STON
PL
ST
ST
MALVINA
ST
ST
ST
ST
L P D R O ED F
D
KW O O
B
W R EC
BL AC
ST
LA
JACOBYS PL
PL
LA
ELIZABETH
ST
P
L P
KY N
AM TH H
O
ST
CHETWYND PEARSO N
COOKS
PL
LANCAS HIRE
ST
ELM PL
UNION
ST
PL
Printed: 8/10/2015
G
R
RY
SAN MAR L
PL
ESSEX
N BUILDIN
G
O
S
ay
PL
EXHIBITIO
O
ST
PL
ST E S ID
S
T
AR K
P
LA
S H
LE
IG
C
H
UN B
RS VIL LIE
LA
ST
LA
PL
BERRY QUEENS
MATTIN GLYS
L
EY TN PL
R U CO
HA R C
O UR
T
ST LA CALLAHANS
LA
FALSHAM S
WYLIES LA
ST
ABBOTSFORD
ST. STH
LIT LOTHIAN
POWELL
ROYAL
M
ST ISAAC'S
ABBOTSFO RD
LOTHIAN ST ST
LIT LOTHIAN
LITTLE LOTHIAN
ST NTH
ST NTH
ST LITTLE DRYBUR GHST NTH
st
GROSVE NOR
MELBOU RNE
ST
EADE
mw
PL
YOUNG
IEVERS PL
11
PL
LYTTON
WATERL
BUTLER
MORRAH SP IT AL
PA R GR K
ARDEN
9
DRUMM OND
PL
O
ST
BOUVE RIE
MAGENT A PL
SW
l
Tra
PL
ST
ST
10
H
ST
PL
ALMA
S
EAST
PL
S
ST
ST
VICTORIA
COURSE
GOLF
CORNEL L
ARGYL E PL
FINLAY
EN
PA
LE
nci
MELBOURNE ZOOLOGICAL GARDENS
ARGYLE PL SOUTH
TCE
GIBBON PL LA
MONAH AN
8
ST R
ST
ST
PL
PL
7
D
G KIN
L
WI
SAN MAR
DES
c
Y
N
6
IL
ST
ABBOTSF ORD
IEVERS
FEU ST
5
H
ST
2
4
O
LT PROVOS
ST.GEO RGES R.C. SCHOO L
PELHAM
KELVIN
CARLTO
ST
ALLISON LA State of Victoria
1
C
HARRIS
ARDEN
INDEX TO ADJOINING MAPS
3
LA
LINCO LN
ES
ST
O'CONNELL
ST
CANAD A
LINCOLN SQ SOUT H
RRY
Planning Zone - CCZ5: Capital City Zone 5 - Surrounding Zones: CDZ2 & RDZ1 State School
G
T
PELHAM
PL
PL
ST
St. Mary's
LA
O YA L
AN
E
M
HAINES ST
O'SHANASS Y ST
ST
M
Y
PRINCE SS
ST
This publication is copyright. No part may be reproduced by any process R.C.except Church West in accordance with theMelbourne provisions of the Copyright Act.
OWEN
AP
LEY
LA
G
LY
SARTOR I
CH
BARR
GRACIELA
RK
CARLT ON
ST
ST
ST
BERK
QUEENSBE
PL
ST
HOWAR D PL
BA
PL
ST
ARGYLE PL NORTH
PELHAM
VICTOR IA
MURCHISON
R
ST
ST AIN
Y
College Square Student Accommodation
RD
BAYLES
WOOD ST
HAINES ST
ST
ST KL
LE TT
ST
H ABET
VICTORIA
CAPEL LT HOWARD
ST
MOSS
PL
TCE
PL
BAR LI
DEGRAVES
ES
ELIZ
PL
PL
PL
BEARD
GRATT AN LA
CARLOW
ITY ST
PRINCES
ST EA TERY
Queen Elizabeth Hospital
ELL NN
GARDINE R
BLAIRS
aw Field
T
WOOD ST
200 m
PREPARED BY: Planning Mapping Services
PL UNIVERS
UNIVER SITY PL REGIST RY LA
NAUGH TON YORK
ST LEICES TER
ST
TRAFAL GAR PL
ST
0
PL
ST
ST ST
SQ
NORTH
ST
ST
PL
200 ST
NORTH
SOUTH
YL
O'CO
STH
LINCOL N
PL
Y
ST
SCOTTS
RR BA
ST
RAGLAN ERROL
KIN
N
ST
PELHAM
Y RKLE BE
TEMPE RANCE HALL LA
LT.ERR OL
PL
PLACE
PLACE
MOTON ITY ST
POST OFFICE PL
PL
H
H
D
ABET
DRYBURG
BE D FO PL R
ELIZ
LOTHIAN
CHURC H
LL
st
G
NE
LOTHIAN
LI N
LT GRATTA ST
CHURC H
ST BANBR IDGE
CUMBER LAND
CURZO N
ST MACAR THUR
MACAR THUR
PL
RR IS LA
PL
WELCH
AR
PL
NO
RD
W
STATE COLLEG E OF VICTORIA
Victoria Bowling Club
HAYMA RKET LA
RRY
ST
MILLER
ST
RYANS LA
LA
QUEENSBE
ST
R
O
PL
ATKIN
KIN
CE
JONES
EA
EN
ST
ROYAL DENTAL HOSPITAL
W R E BR P L CK YN IG H O TS XFO ID E RD LA PL ID LA LA WS ST N E
ON O'C
ELM
MILLER
D
TY RO
ST
ST
BENDIG O
GRAT TAN
D
ST
RRY
VICTORIA
SP EN ST CER
SP
ST
ST ST
Municipal Boundary
ST
GOLDH
ERSKINE
ST
ST
Housing Commission of Victoria
Court House MAHON ES
UNIVERS
ST
R
QUEENSBE
LA
PURCEL L
GRAT TAN
ST
BYRON
GLASS
LT PROVO ST
ST
ROYAL MELBOURNE HOSPITAL
ST
ST
ST CULLEN S
VA LE
ST
ST
S LA
PROVOST
ST
T
ARDEN LA
SCOTIA
BEATON
ST
ST
M AR LA KE
Y
ST
BALLIE
CHARLE S
ST ELGIN PL
ST
U R
HAINES LA
E ST
E
BAILLIE
TESORIERO
PA
RK
ST
ST PH Y
E IR W
LA
S
HA R
S
RG
ST
TN
LT
ARDEN
ST
E
DR
ST ST WIMBLE
ST
H C S
A LARTS
TE
W
HARDWICK
DRYBURGH
UNIVERSITY HIGH SCHOOL
FARADAY EO
Y
R U
ST
O
SY
C
O'SHANAS
PL
ALPIN PL
TYNE
M AR
ST ARDE N
ASTOR
LT G
BA ST
S KE SY LA
S KE SY LA
HAIN ES
STON
ST
MILLER LA
LITTLE ELGIN
ES
ST
RD CE
D
ST
ARDEN
DRYBURGH
O M
HARRIS
O'SHANAS SY ST
PL
ELGIN
ST UNIVERSITY OF MELBOURNE SCHOOL OF VET SCIENCE
LT PALMER
ST
ST
R KE
ST
KE R
O U LA NG
LS AE
LA
H
STORY
PA R GR K
ST
Y
TH
LA
R
BENJAMIN
AP M A LA N
ST
FITZGIBBON
O U SE G AT EH
CARROL S
ST
HOMEBUSH LA
LA DONOVA NS
KERRS
LA
O
IC cM M
HAINES ST
ST
FEU ST
POST OFFICE
G
LA
R
St.Jude s Church
HOLMW OOD
CEME
ST
SW
WOOD ST
HAIN ES ST
ES
LE
ON
ST
ST
WOOD ST
O
LA
LA
ST
ERSKINE
LE E P M L IN
LA
ST CARR OL
CARRS
AV IS
ERSKINE
MUGG
LA
LA
CANNIN G
SHANDS
LA
G
M
ST. MICHAELS
BROUGHAM
KES
PITT ST
LE
PL
N
PL
ST IL L NE
PL
PALMERST PAINSDA
TO
EL
Y
STON
MELBOURNE GENERAL CEMETERY
CR ST
SOUTH
G
PP
R
KAY
PALMER
ST
COLLEGE
CR
ROYAL PARK
IN
KE
E
O
Housing Commission of Victoria
ST
LA
MELBOURNE UNIVERSITY
EM
SCHOOL
WATER LOO
BUTLER
MORR AH
ST
FL
ST
ST
ES T
COLLEGE
ST
ST
CEMETERY
COLLEGE
UNIVERSITY
AH R
ST
AN
ST
UNIVERSITY
RD
ST
R O
M
K R
LA
ST
W
AN
M
AP
LYTTON
EL
AH
H
PL
RD
Queen Elizabet h Hospita l
RR
ST
VICTOR IA
PP
R
C
College Square Student Accommod ation
KE
R
ST
PA
ST
IS
ST EA TE RY
BAYLES
O
ERSKINE
ST
M
ST KES
RR
LL EG CO
LA
ST
UC DE H YS LA
G
R
LANGFO RDS LA
HOSPITAL
ST
PDE
ll ba Net
LYGON
CDZ2
PRINC ES
N
UE
CHILDRENS
BROUGHAM
DEGRAVES
BA YL ES
ROYAL
SCHOOL
ST
CEME
TO
EN
UE
ST. MICHAELS
PL
NO
ST
N
G
AV
EN AV
TO
IN
GENERAL
CRAWFORD OVAL
MACARTHUR RD
Pavilion
FL EM
Capital City Zone - Schedule 5 Capital City Zone - Schedule 6 Comprehensive Development Zone Schedule 2
CCZ6
MELBOURNE GENERAL CEMETERY
CR
SOUTH
G
DR
BR
Mixed Use Zone Residential Growth Zone Schedule 1
RGZ1
Special Purpose CCZ5
COLLEGE CR
ROYAL PARK
IN
BR EN S
cil Coun Yarra
PRINCES PARK
w ay Tram
General Residential Zone Schedule 4
MUZ
MELBOURNE
ELLIOT
AV
D
D
GRZ4
T
R
R
General Residential Zone Schedule 2
RY TE ME
Y
General Residential Zone Schedule 1
GRZ2
THE
R TE ME
GRZ1
COLLEGE
EM
RD
Parking Overlay - Precinct 1 Parking Overlay - Precinct 12
PO1 PO12
PARK
CE
CE
THE
ES T
UNIVERSITY COLLEGE
UNIVERSITY
ST
DR
Public Use Zone - Transport Road Zone - Category 1
ST
S EN BR DR
City
Public Use Zone - Other Public Use
PUZ4
DR
CRAWFORD OVAL
D FL
EN S
ST
IO T T
S BR EN
ELL
MILE
Public Use Zone - Local Government
PUZ7
PRINCES
S EN
S EN BR DR
DR
PUZ6
RDZ1
MACARTHUR RD
W
R
CEMETERY
LEONARD
MACARTHU R
Residential
ELLIOT
N
ST
GENERAL
Whitley College
G.Smith Oval
BR
S EN MELBOURNE
AN
AIN
ST
DR
Cou rts
Cou rts ba ll Net
BR EN S
DR
DR
PUZ3
Overlays
Brens Oval
Public Use Zone - Education Public Use Zone - Health And Community
PUZ2
Club
Pavilion
Public Park And Recreation Zone Public Use Zone Cemetery/crematorium
PUZ5
AVENUE
AVENUE
BR
RR
TO
THE
PARK
Pavilion
G
ay
ay
RD
IN
State
Commercial 1 Zone
PPRZ
PRINCES
ST
ST Hill
re ey Cent Hock
Public Land Whitley College
MACPHERS ON
Princes
Tennis
Commercial C1Z
AV
Tramw
THE
Tramw
Club
Pavilion
LEONARD
ST
TREACY
Brens Oval
MACARTHU R
WALKER
COLLEGE
State Hockey Centre
EM
MILE
AVENUE
THE AV
ST Hill
Tennis
Oval
COLLEGE
MACPHERS ON
Princes
CHETWYND
THE
GARTON
ST
TREACY
G.Smith
D
WALKER
Ground
R
D
MELBOURNE ZOOLOGICAL GARDENS
COLLEGE
T
RIDLEY
aw Field
COLLEGE
AV
PARKING OVERLAY
Carlton Cricket
Ground
R
MELBOURNE ZOOLOGICAL GARDENS
FL
LA
Tra
THE
ay mw
ST
Cricket RIDLEY
aw Field
ST
R
R LA
LA
Carlton
PU
PDE
ST
MILE
COURSE
GOLF
PU
AVENUE
MELBOURNE ZOOLOGICAL GARDENS
ZONES
PO
PO
LA
Tra
MELBOURNE PLANNING SCHEME - LOCAL PROVISION
l
GARTON
COURSE
GOLF
ROY
THE
MELBOURNE ZOOLOGICAL GARDENS
nci
mw a
y
Council Study
Traffic Study 25
25
24
24
28
25
26
29
30
27
25
24
28
29
30
28
29
30
27
26
24 23
23
22
22
0900: Showing busy inner city morning traffic
1500: Showing more traffic free across the site compared to morning
25
25
24
24
28
25
26
29
30
27
25
24
24
23
23
22
1200: Showing Bouverie St and Queensberry St’s traffic lower than morning
27
26
22
1900: Showing bussy inner city afternoon traffic
Heavy
Medium
Light
Buildings
Site
Summer 0900
Summer 1200
Summer 1500
Winter 0900
Winter 1200
Winter 1500
Target Audience Age: 10
20
30
40
50
60
70
80
Occupation: University Student + Urban Professional Status: Private =
P
Couple =
C
Sharing =
S
Early Family =
E
Re
Room Typology Studio
1 Bed
Re
FFL: 3.5m
2 Bed
2.5 Bed
sid
Re
3 Bed
CO S
l
sid
Re
6m
en tia
en tia
l
sid
Re
en tia
l
sid
en tia
sid
en tia
Se
tb ac
k
(G ym
l l
el 1 Lev
0
el 0 Lev
8
el 0 Lev
6
el 0 Lev
9
el 0 Lev
7
6m
,P
FFL: 3.5m FFL: 5m
FFL: 5m
P
P
P C
E
S
oo Re l, BB s id Q) en t ia Re l s id en t ia Re l s id en t ia Re l sid en t Re ia l ta il, Lo bb Ca y, rp Re ar fu k, se Su bs ta tio n
Set
Vertical: 17.5m
bac
k
l 05
e Lev
l 04
e Lev
Vertical: 22.5m
l 03
e Lev
l 02
e Lev
l 01
e Lev
und Gro B
or Flo
nt me ase
-01
Ground Floor: Item or Eating or Convenience Store
Car Park + Bike Park + Substation Common Open Space: Swimming Pool + Gym + BBQ
Market Research
Basement:
BUILDING CODES OF AUSTRALIA STUDY
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
BETTER APARTMENTS DESIGN STANDARDS Building Setback Functional Layout
Ͳ Adequate daylight into room windows Ͳ Avoid direct views into room & POS Ͳ Outlook from dwellings to outside Ͳ All bedrooms to have additional area to add a wardrobe Type Width Depth Main 3m 3.4m Other 3m 3m Ͳ All dwellings to have a living area (exclude dining & kitchen) Type Width Area Studio & 1 Bed 3.3m 10m2 2 or more Bed 3.6m 12m2
Storage Noise Impact
Energy Efficiency Solar Access to COS
Room Depth
Ͳ Insure rooms for adequate daylight Ͳ Room depth < 2.5 times ceiling height Ͳ Open plan room depth < 9m Open plan room: living + dining + kitchen (located furthest from window) + ceiling ht > 2.7m from ffl to fcl (excluding kitchen service) Ͳ Room depth: from external surface of room window to rear wall
Natural Ventilation
Private Open Space
Windows
Ͳ Insure adequate daylight into room Ͳ to be located in external wall Ͳ min 1.2m (w) max (d): 1.5 x (w) measured from outside face Ͳ Clear to sky
Communal Open Space
Ͳ Insure adequate facility Ͳ convenient access to storage space Type Min volume (total) Studio 8m3 1 bed 10m3 2 bed 14m3 3 or more 18m3
Min volume (in dwelling) 5m3 6m3 9m3 12m3
Ͳ Contain noise Ͳ Location of (living area & bedroom & POS) + (service & lift & COS & car park) Ͳ Bedroom < 35db(A) LAeq 8h Ͳ Living area < 40dB(A) LAeq 16h Ͳ Measured unfurnished & window closed Ͳ Orient to use solar energy Ͳ Living area & POS: north side if practicable Ͳ Solar access to north to be optimised Ͳ Melbourne Central (zone 21) < 30 MJ/M2 per annum Ͳ COS to be located on north side if appropriate Ͳ 50% or 125m2 of primary COS > 2hrs of sunlight 9amͲ3pm on 21 June
Ͳ Dwellings to maximise on openable equipment Ͳ 40% of dwellings to achieve effective cross ventilation Ͳ Max breeze path through dwellings 18m Ͳ Min breeze path through dwellings 5m Ͳ Ventilation openings have approx. the same area Ͳ Breeze path measured between ventilation openings on different orientations of the dwelling Ͳ Min 25m2 + 3m @ natural ground level (convenient access from living room) Ͳ Min 15m2 + 3m @ podium (convenient access from living room) Ͳ Balcony: Type Min area Min dimension Studio or 1 bed 8m2 1.8m 2 bed 8m2 2m 3 or more bed 12m2 2.4m Ͳ Rooftop: 10m2 with min 2m (convenient access from living room) Ͳ Service on balcony = Balcony + 1.5m2
Ͳ Development > 40 dwellings = min 2.5m2 (per dwelling) or 250m2 COS to be located Ͳ Provide passive surveillance Ͳ Provide outlook for as many dwellings as practicable Ͳ Avoid overlooking into rooms and POS of new dwellings Ͳ Minimise noise to dwellings Ͳ Designed to protect any natural features on site Ͳ Maximise landscape opportunities Ͳ Accessibility and usability
BETTER APARMENTS DESIGN STANDARDS STUDY
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
BCA STUDY Section A General Provisions
A1.1: Climate zone 6 (Melbourne) A3.2: Class 2 (apartment) + Class 6 (retail) + Class 7a (carpark)
Section C Fire Resistance
C1.1: Type A Construction (most fire-resistant) C1.1: Table 3 Type A Construction: FRL of building elements (P.120) C1.1: Table 3.9 Requirement for car parks (P.124-125)
Section D Access and Egress
Service and Equipment Section F Health and Amenity
E1.5: fire sprinkler system [AS 2118.4] E1.8: Fire control centre located egress from any part of its floor E3.6b: Lift [AS1735.12] F1.4: Waterproofing membrane [AS 4654] F1.5: Roof coverings [AS 2049, AS 2908.1, AS 1562.1, AS 4256, AS1562.3] F2.1: Sanitary facility
F2.4: Unisex sanitary compartments + showers = more than 1 in COS F3.1: Room height
DP1: road entrance DP3: Falling distance in m D1.2: Exit within each building + basement + each floor D1.3: Fire isolated stairway = 3 consecutive floors + 1 for car park D1.3: Exit travel distance < 6m from 2 exit & <20m single exit D1.5: 45m < Distance between alternative exit > 9m + min 2 exit per floor D1.6: Exit dimension < 2m(ht) + < 1m(d) D1.7: Door must open away from stairway, passageway, ramp D2.13: Riser and going dimensions Section J Energy Efficiency
F4.1: Natural light provided in all habitable rooms J1.3: Roof and ceiling R-Value
J1.5a: External Wall
Section E
D2.14: Landings < 1:50 gradient + < 750mm long or 500mm for L shape [AS 4586] D2.16: barriers to roof, stair, ramp, bridge height on BCA D2.17: Handrails D3.1: Disable access on COS D3.5: Disable car park 1 space every 50 car parking D3.10: swimming pools E1.3: 1 x Fire hydrants on total floor area > 500m2 [AS2419.1]
MELBOURNE PLANNING SCHEME ORDINANCE STUDY
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
MELBOURNE PLANNING SCHEME ORDINANCE
Table 2: Design Requirements for all DDO Areas
Classification: City North
Design Objective Building Heights, Scale and Setbacks To ensure that the height of new buildings reinforces the built form character of specific areas as defined in Table 1 in this Schedule. To ensure appropriate building scale, height and setbacks at interfaces with established residential areas having regard to existing character, context and amenity. To ensure appropriate building scale on the side and rear boundaries of new buildings and works that respects the scale of existing adjoining buildings. To avoid to exposed blank walls To assist in limiting visual impact and adverse amenity on adjacent development sites. To promote articulated rooflines with architectural interest and variation. To establish a generally consistent built form to the street edge that creates a strong sense of definition and place. To ensure that the scale of built form provides an urban environment that is comfortable for pedestrians. To ensure equitable and good access to sunlight / daylight for occupants of buildings and in public places. To ensure that new development is adaptable over the long term to a range of alternate uses. To ensure that new buildings and works adjoining individually significant heritage buildings or buildings within a heritage precinct respects the character, form, massing and scale of the heritage buildings.
Schedule 61 to the design and development overlay Planning Scheme map: DDO61 Design objectives To encourage City North to develop as a central city precinct characterised by university, research and medical buildings. To establish a midͲrise scale of buildings (6 to 15 storeys) that is distinct from the tall built form in the Hoddle Grid area to the south, which steps down at the interface to the lower scale surrounding established neighbourhoods in North and West Melbourne. To support increased density and diversity of uses along the Victoria Street, Flemington Road, Elizabeth Street and Swanston Street tram corridors and around the proposed Grattan and CBD North Metro Rail stations. To establish built form that creates a strong sense of street definition by adopting a building height at the street edge determined by a 1:1 (building height to street width) ratio. To ensure development responds appropriately with suitable building scale, heights and setbacks to the existing character, context, and interfaces with established residential areas, and immediate amenity. To ensure that new buildings respect the rich heritage fabric of the area and that new buildings that adjoin the heritage buildings respect their height, scale, character and proportions. To develop a fine grain urban form by encouraging buildings with a wide street to be broken into smaller vertical sections, To develop the Haymarket area as a central city gateway precinct and public transport interchange. To ensure university, research and medical buildings are actively integrated with the surrounding public realm. To ensure university, research and medical buildings are actively integrated with the surrounding public realm. To design buildings to provide passive surveillance and activation of ground floors addressing the streets. To ensure development allows good levels of daylight and sunlight to penetrate to the streets and to lower storeys of buildings by providing adequate separation between buildings. To deliver a scale of development that provides a high level of pedestrian amenity having regard to sunlight, sky views and wind conditions. To improve the walkability of the precinct by encouraging new laneways and pedestrian connections. To encourage the ground floor of buildings to be designed so that they can be converted to a range of alternative active uses over time.
Table 1: Preferred Built Form Outcomes for Specific Areas DDO Area
Building Height
4.1
40 m (ht)
Street edge height and upper level setback Buildings fronting Queensberry, Bouverie, Ͳ 24 metre street edge height. Ͳ Any part of the building above 24 metres setback 6 metres from the street.
Built form outcome � Reinforces Elizabeth Street as a civic spine and facilitates the enhancement of its landscape character. � Creates stronger definition to the streetscape. � Complements the existing character established by the university, research and medical buildings. � Ensures sunlight reaches the lower floors of new developments. � Facilitates an integrated built form on both sides of the Swanston Street. � Delivers a scale of development that provides street definition and a high level of pedestrian amenity, having regard to access to sunlight, sky views and a pedestrian friendly scale. � Provides a street edge height that integrates new development with lower scale heritage buildings.
Building Facades and Street Frontages To ensure that buildings are well designed and enhance the amenity of City North. To deliver a fine grain built form with architectural variety and interest. To encourage high quality facade and architectural detailing.
Design Requirement Deliver a scale of development at the street edge in accordance with Table 1 in this Schedule. Buildings should be constructed to the street boundary of the site. Upper levels above the maximum street wall heights should be visually recessive and more diminutive than the building’s base. On corner sites where two different street edge heights are nominated, buildings should “turn the corner” and apply the higher street edge and transition to the lower nominated street edge height. Buildings should have a minimum ground floor to floor height of 4 metres at ground floor and a minimum floor to floor height of 3.2 metres in levels above the ground floor.
The design of new buildings should respect the character, height, scale, rhythm and proportions of the heritage buildings. New buildings should step down in height to adjoining lower scale heritage buildings. New buildings should consider retaining the traditional heritage street wall (as opposed to defining a new higher street wall) where appropriate. Addressing the Street The articulation of building facades should express a fine grain. Expressing the vertical elements is encouraged to minimise the dominance of wide building frontages. Multiple doors/entrances to buildings and windows should be provided off the street to improve activation of the street. The facades of buildings should maintain the continuity, and traditional characteristic vertical rhythm of streetscapes. All visible sides of a building should be fully designed and
PRECEDENTS STUDY
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
Citylife Apartment
Salk Institute
Urban Tower Retro 67
Mode-Gakuen Spiral Towers - Nikken Sekkei - Nakamura-ku, Nagoya, Japan
The building employs an inner truss tube system that acts as a central pillar supporting the three anshaped wing sections. The truss tube is constructed of concrete-filled, steel tubular columns with structural braces affixed around the base.
The truss systems helps achieve high seismic capacity, with two vibration damping systems that self-adjust and sway against the movement of the building
FACADE: UNIT CURTAIN WALL
Triangular gridded dual-layer glass curtain wall incorporating an energy saving ventilation system and reduced heat loads. Each floor rotates 3 degrees with a 1 percent reduction to the floor.
Twisting shape would promote an environment for fostering creativity within the schools
This air flow system significantly reduces heating and cooling loads by passing indoor/outdoor air (exhaust air/return air) between two panes of glass. The cavity between the panes typically includes blinds which can be shut according to heating/cooling requirements.
The design was planned to optimize the pedestrian network and spaces with green spaces and restaurants.
DOUBLE SKIN AIR FLOW WIDOW SYSTEM
Central Canteen of Tsinghua University
FORM FINDING STUDY
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
Borrowing the idea of â&#x20AC;&#x153;spiraling motion towards the skyâ&#x20AC;? in order to make use of the offset space for a stepping terrace.
Outline the surrounding urban fabric in a continuous line and applied as the form of building by extrusion.
Interloacking and stacking various volumes of flats/units
APARTMENT LAYOUT STUDY
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
MID SEMESTER REVIEW
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DESIGN DEVELOPMENT 20/08/2018
ARCHITECTURAL DRAWING SHEET LIST
SYSTEM CODES & TAGS
SCHEDULES/ SPECIFICATIONS/ REPORTS
WT
SHEET NAME
REVISION
SCALE
A-000
TITLE SHEET
A
-
A-101
EXISTING SITE PLAN
A
1:200 1:100
A-102
EXISTING AND DEMOLITION PLAN
A
A-201
BASEMENT FLOOR PLAN
A
1:50
A-202
GROUND FLOOR PLAN
A
1:50
A-203
TYPICAL LOWER FLOOR PLAN (1/F)
A
1:50
A-204
TYPICAL UPPER FLOOR PLAN (6/F)
A
1:50
A-205
ROOF PLAN
A
1:50
A-301
GROUND RCP
A
1:50
A-302
TYPICAL LOWER FLOOR RCP
A
1:50
A-303
TYPICAL UPPER FLOOR RCP
A
1:50
A-401
ELEVATIONS - NORTH & EAST
A
1:100
A-402
ELEVATIONS - SOUTH & WEST
A
1:100
A-501
SECTIONS
A
1:100
A-601
TYPICAL FACADE SECTION
A
1:20
GENERAL NOTES
REV
DATE
DESCRIPTION
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
A
20/08/2018
PROJECT SETUP
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
SCALE @A1
TITLE SHEET
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-000
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
QUEEN SBERR Y STRE ET
2
A-103
1 A 3
2 3
1
A-401
4
5
6
B 2
2
A-402
C
A-401
D E
DATE
DESCRIPTION
20/08/2018
PROJECT SETUP
1
A-103
UP
F
CLIENT
RMIT DANIEL MAUNDERS PROJECT
BOUVERIE STREET
1
A-402
LANDS DOWN E PLAC E
REV A
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
DRAWING TITLE
EXISTING SITE PLAN DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 200
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-101
18-214
A
COPYRIGHT
1
A-101
EXISTING SITE PLAN
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
1 : 200
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
A-103
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
QUEENSBERRY ST
2
A-103
1
2
3
4
5
6
A EXISTING BUILDING 11m (HIDDEN FOREST)
EXISTING BUILDING 10m (SPANISH ACQUISITION)
3
B
A-103
1
A-103
C D
BOUVERIE ST REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
E
RMIT DANIEL MAUNDERS
F
PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
DRAWING TITLE
EXISTING AND DEMOLITION PLAN DATE
27/08/18
LANSDOWNE PL EXISTING BUILDING 25m (71-79 BOUVERIE ST)
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 100
@A1
EXISTING BUILDING 16m (23-37 LANSDOWNE PL)
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-102
18-214
A
EXISTING BUILDING 16m (INDEPENDENT DISABILITY SERVICE) COPYRIGHT
1
A-102
LEVEL 00 DEMOLITION PLAN
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
1 : 100
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
CLIENT
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
1
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
A-501
1
2
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
3
4
5
DO NOT SCALE OFF DRAWINGS.
6
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
9272
B
9272
7272
A
STORAGE
BIKE STORE 9300
4450
C 2
2
A-501
2100
A-501
10950
DATE
DESCRIPTION
20/08/2018
PROJECT SETUP
4800
D
REV A
FIRE PUMP ROOM 2850
COMMS
2500
SWITCHBOARD ROOM
2850
2750
RMIT DANIEL MAUNDERS
E
PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
DRAWING TITLE
BASEMENT FLOOR PLAN DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 50
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
F
A-201
18-214
A
COPYRIGHT
1
A-201
BASEMENT FLOOR
1 : 50
1
A-501
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
CLIENT
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
1
2
3
1
4
1
5
6
A-401
A-501
7272
A
RETAIL 2
RETAIL 1
B
RETAIL 3
RETAIL 4 2
A-401
4700
4450
2050
2750
3120
CL
GAS METER ROOM
C ELECTRICITY SERVICE ROOM
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
2
2100
5901
2
A-501
6153
A-501
LOBBY
D 2630
WATER METER ROOM
COMM
CLIENT
RMIT DANIEL MAUNDERS PROJECT
E
10300
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
5900 3600
5878
KITCHEN
CL
CAFE
GROUND FLOOR PLAN
2500
REFUSE STORAGE
DRAWING TITLE
DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 50
3030
@A1
2550
1050
3000
FEMALE TOILET
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
3698
1400
FIRE CONTROL ROOM
MALE TOILET
9978
A-202
18-214
A
F
1
A-202
GROUND FLOOR PLAN
1
1
A-402
A-501
1 : 50 COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
2
A-402
6303
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
1
2
3
4
1
5
22660
A-401
6
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
5000
1500
4950
5100
6110
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
1
A-501
NOTES
A BEDROOM
POS POS
LIVING ROOM
4772
3600
BEDROOM
POS
BEDROOM BEDROOM
STUDIO 90 40.2 m²
2 BED
LIVING ROOM
B
91 76.4 m²
2
A-401
3000
92 60.6 m²
LIVING ROOM
3300
2
TOILET
BEDROOM
2900
5000
TOILET
2000
TOILET
1 BED
A-402
2000
C
89
20372 A-501
POS
56.0 m²
2
A-501
2100
2
1 BED
LIVING ROOM
WATER METER
3212
D TOILET
GAS METER REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
UP
3000
COMM
ELE
BIN
E 1 BED
LIVING ROOM
87
TOILET
LIVING ROOM
60.7 m²
2 BED
4000
2300
88 79.3 m²
BEDROOM
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
DRAWING TITLE
TYPICAL LOWER FLOOR PLAN (1/F)
5500
BEDROOM
RMIT DANIEL MAUNDERS PROJECT
BEDROOM
DATE
27/08/18
DK&CW
APPROVED
Approver
TOILET 1200
1600
POS
CHECKED
SCALE
1 : 50
@A1
F 1100
1
A-501
1
A-402
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-203
18-214
A
COPYRIGHT
1
A-203
Level 01
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
1 : 50
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
CLIENT
POS
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
1
2
3
1
4
5
6
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
A-401
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
1
NOTES
A-501
A
B
1 BED 94
2
A-401
58.4 m² 4500
STUDIO 93 40.9 m²
2
A-402
C 2
2
A-501
A-501
D
KITCHEN
ELE
GAS METER REV
DATE
DESCRIPTION
1601
WATER METER
COMM 600
1300
3 BED 2000
95 BIN
100.2 m²
STUDIO
CLIENT
RMIT DANIEL MAUNDERS
1000
97 41.1 m²
PROJECT
BATHROOM
POS 3700
BEDROOM
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
DRAWING TITLE
3057
TYPICAL UPPER FLOOR PLAN (6/F) POS DATE
27/08/18
CHECKED
Checker
APPROVED
Approver
SCALE
1 : 50
@A1
F A-501
1
A-402
1
Level 06
PROJECT #
DRAWING NUMBER
REVISION
DD 1
A-204
STATUS
A-204
18-214
COPYRIGHT
1 : 50
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
E
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
1
2
3
1
4
5
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
6
DO NOT SCALE OFF DRAWINGS.
A-401
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
1
A-501
A
B 2
A-401
2
A-402
C 2
2
A-501
A-501
D
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
DRAWING TITLE
ROOF PLAN DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 50
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
F 1
A-501
1
A-205
18-214
A
A-402
1
A-205
ROOFTOP
COPYRIGHT
1 : 50
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
CLIENT
E
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
1
A-501
1
2
3
1
4
5
6
A-401
A
1
B
3
1
A-601
A-601
2
A-103
A-401
2
A-402
C 2
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
2
A-501
A-501
D RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
E
DRAWING TITLE
GROUND RCP DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 50
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-301
18-214
A
F
1
A-402
1
A-501
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
1
A-301
GROUND FLOOR RCP
1 : 50
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
CLIENT
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
1
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
A-501
1
2
3
1
4
5
6
NOTES
A-401
A
1
B
1
A-601
A-601
2
180
A-401
2
A-402
760
180
C 2
2
A-501
A-501
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
D
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
E
DRAWING TITLE
TYPICAL LOWER FLOOR RCP DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 50
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-302
F
18-214
A
1
A-402
1
A-501
COPYRIGHT
1
A-302
Level 01
1 : 50
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
CLIENT
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
1
2
3
4
1
5
DO NOT SCALE OFF DRAWINGS.
6
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
A-401
NOTES
1
A-501
A
B
1 BED 94
STUDIO
2
A-401
58.4 m²
93
180
40.9 m²
2
180
760
180
2
1400
C
180
A-402
2
A-501
A-501
REV
DATE
DESCRIPTION
D 3 BED 95 100.2 m²
E
RMIT DANIEL MAUNDERS
STUDIO
PROJECT
97
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
41.1 m²
DRAWING TITLE
TYPICAL UPPER FLOOR RCP DATE
08/27/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 50
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
F
A-303
1
A-501
18-214
1
A-402
COPYRIGHT
1
A-303
Level 06
1 : 50
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
CLIENT
6
5
4
3
2
F
1
LIVING ROOM
FFL 65.500 Level 10
FFL 62.000 Level 09
FFL 62.000 Level 09
FFL 58.500 Level 08
FFL 58.500 Level 08
B
A
BATHROOM
FFL 55.000 Level 07
FFL 55.000 Level 07
LIVING ROOM
BATHROOM
FFL 51.500 Level 06
FFL 51.500 Level 06
FFL 48.000 Level 05
FFL 48.000 Level 05
FFL 44.500 Level 04
FFL 44.500 Level 04
FFL 41.000 Level 03
FFL 41.000 Level 03
FFL 37.500 Level 02
FFL 37.500 Level 02
FFL 34.000 Level 01
FFL 34.000 Level 01
FFL 29.000 00 GROUND FLOOR FFL
FFL 29.000 00 GROUND FLOOR FFL
ELEVATIO NORTH
GENERAL NOTES
C
BATHROOM
FFL 65.500 Level 10
LIVING ROOM
1
D
FFL 69.000 ROOFTOP
FFL 69.000 ROOFTOP
A-401
E
2
A-401
1 : 100
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
ELEVATION EAST
1 : 100
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
ELEVATIONS - NORTH & EAST
SCALE @A1
1 : 100
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-401
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
1
2
3
4
5
A
6
FFL 69.000 ROOFTOP
FFL 69.000 ROOFTOP
FFL 65.500 Level 10
FFL 65.500 Level 10
FFL 62.000 Level 09
FFL 62.000 Level 09
FFL 58.500 Level 08
FFL 58.500 Level 08
FFL 55.000 Level 07
FFL 55.000 Level 07
FFL 51.500 Level 06
FFL 51.500 Level 06
FFL 48.000 Level 05
FFL 48.000 Level 05
FFL 44.500 Level 04
FFL 44.500 Level 04
FFL 41.000 Level 03
FFL 41.000 Level 03
FFL 37.500 Level 02
FFL 37.500 Level 02
FFL 34.000 Level 01
FFL 34.000 Level 01
FFL 29.000 00 GROUND FLOOR FFL
FFL 29.000 00 GROUND FLOOR FFL
1
A-402
ELEVATION SOUTH
GENERAL NOTES
2
A-402
1 : 100
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
C
ELEVATION WEST
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
B
D
E
F
1 : 100
ELEVATIONS - SOUTH & WEST
SCALE @A1
1 : 100
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-402
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
A
1
A-501 GENERAL NOTES
B
C
D
E
F
6
FFL 69.000 ROOFTOP
FFL 69.000 ROOFTOP
FFL 65.500 Level 10
FFL 65.500 Level 10
FFL 62.000 Level 09
FFL 62.000 Level 09
FFL 58.500 Level 08
FFL 58.500 Level 08
FFL 55.000 Level 07
FFL 55.000 Level 07
FFL 51.500 Level 06
FFL 51.500 Level 06
FFL 48.000 Level 05
FFL 48.000 Level 05
FFL 44.500 Level 04
FFL 44.500 Level 04
FFL 41.000 Level 03
FFL 41.000 Level 03
FFL 37.500 Level 02
FFL 37.500 Level 02
FFL 34.000 Level 01
FFL 34.000 Level 01
FFL 29.000 00 GROUND FLOOR FFL
FFL 29.000 00 GROUND FLOOR FFL
FFL 24.000 BASEMENT FLOOR
FFL 24.000 BASEMENT FLOOR
Section A-A
2
A-501
1 : 100
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
5
Section B-B
4
2
1
1 : 100
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
3
SCALE @A1
1 : 100
SECTION
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-501
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
6
FFL 44.500 Level 04
BEDROOM
FFL 41.000 Level 03
FFL 37.500 Level 02
1
A-601
GENERAL NOTES
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
TYPICAL FACADE SECTIONS
1 : 20
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
TYPICAL FACADE SECTION
SCALE @A1
1 : 20
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
D:\2018\180716 Master Semester 2\Design Elective_Revitism_Daniel Maunders\Revitism 180826.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
CHECKED
APPROVED
Checker DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-601
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
FINAL REVIEW BEFORE SUBMISSION
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DESIGN DEVELOPMENT 20/08/2018
ARCHITECTURAL DRAWING SHEET LIST
SYSTEM CODES & TAGS
SCHEDULES/ SPECIFICATIONS/ REPORTS
WT
SHEET NAME
REVISION
SCALE
A-000
TITLE SHEET
A
-
A-101
EXISTING SITE PLAN
A
1:200
A-102
EXISTING AND DEMOLITION PLAN
A
1:100
A-201
BASEMENT FLOOR PLAN
A
1:50
A-202
GROUND FLOOR PLAN
A
1:50
A-203
TYPICAL LOWER FLOOR PLAN (1/F)
A
1:50
A-204
TYPICAL UPPER FLOOR PLAN (6/F)
A
1:50
A-205
ROOF PLAN
A
1:50
A-301
GROUND RCP
A
1:50
A-302
TYPICAL LOWER FLOOR RCP
A
1:50
A-303
TYPICAL UPPER FLOOR RCP
A
1:50
A-401
ELEVATIONS - NORTH & EAST
A
1:100
A-402
ELEVATIONS - SOUTH & WEST
A
1:100
A-501
SECTIONS
A
1:100
A-601
TYPICAL FACADE SECTION
A
1:20
WINDOW LEGEND
DOOR LEGEND
WALL LEGEND
WI01: CORRIDOR WINDOW WINDOW NAME WINDOW DIMENSION
DT01: DWELLING DOOR DOOR DIMENSION DOOR COMPANY
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WI02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION
DT02: ROOM DOOR DOOR DIMENSION DOOR COMPANY
WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WI03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION
DT03: CAVITY DOOR (STUDIO) DOOR DIMENSION DOOR COMPANY
WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION
DT04: AUTOMATIC DOOR (COS) DOOR DIMENSION DOOR COMPANY
WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE
WI05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION
DT05: SERVICE DOOR DOOR DIMENSION DOOR COMPANY
WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE
DT06 RETAIL DOOR DOOR DIMENSION DOOR COMPANY
WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE
DT07: REFUSE DOOR DOOR DIMENSION DOOR COMPANY
WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE
LIGHTING LEGEND
WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
LT01: TRACK LIGHT (SHORT) DIMENSION AND BULB NO. LIGHT COMPANY NAME
WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
LT02: TRACK LIGHT (LONG) DIMENSION AND BULB NO. LIGHT COMPANY NAME
WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE
LT03: DOWN LIGHT BULB DIMENSION LIGHT COMPANY NAME
WT11: RETAIL CURTAIN WALL CURTAIN WALL
LT04: WALL MOUNTED LIGHT BULB DIMENSION LIGHT COMPANY NAME LT05: POS LIGHT BULB DIMENSION LIGHT COMPANY NAME LT06: ROOFTOP LIGHT (BOLLARD) LIGHT DIMENSION LIGHT COMPANY NAME LT07: ROOFTOP LIGHT (POLE) LIGHT DIMENSION LIGHT COMPANY NAME LT08: RECESSED LIGHT BULB DIMENSION LIGHT COMPANY NAME
GENERAL NOTES
REV
DATE
DESCRIPTION
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
A
20/08/2018
PROJECT SETUP
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
SCALE @A1
As indicated
TITLE SHEET
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-000
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
QUEEN SBERR Y STRE ET
1
2 3
REF.
B
4
5
6
REF.
A
REF. REF. REF.
D
REF.
E
F
REF.
C
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
REF. REF.
REF.
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
SITE PLAN DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 200
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-101
18-214
A
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
BOUVER IE STREE T
LANDS DOWN E PLAC E
CLIENT
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
QUEENSBERRY ST
2
A-103
1
2
3
4
5
6
A EXISTING BUILDING 10m (SPANISH ACQUISITION)
B 3
1
A-103
C
EXISTING BUILDING (BRIDGESTONE TYRES) TO BE REMOVED 436.1m2
D
A-103
BOUVERIE ST REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
E
CLIENT
RMIT DANIEL MAUNDERS
F
PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
EXISTING AND DEMOLITION PLAN DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
LANSDOWNE PL EXISTING BUILDING 25m (71-79 BOUVERIE ST)
SCALE
1 : 100
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD EXISTING BUILDING 16m (23-37 LANSDOWNE PL)
A-102
18-214
A
EXISTING BUILDING 16m (INDEPENDENT DISABILITY SERVICE) COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
EXISTING BUILDING 11m (HIDDEN FOREST)
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
EXISTING BUILDING 20m (FORMER PRIMARY SCHOOL)
EXISTING BUILDING 25m (71-79 BOUVERIE ST)
EXISTING BUILDING (BRIDGESTONE TYRES) TO BE REMOVED
QUEENSBERRY ST
NOTES
EXISTING BUILDING 12m (CARLTON TRAM SUBSTATION)
FFL 29.000 GROUND FLOOR
EXISITNG BUILDING 11m (HIDDEN FOREST)
EXISTING BUILDING 20m (PIXEL BUILDING)
EXISTING BUILDING (BRIDGESTONE TYRES) TO BE REMOVED
BOUVERIE ST
LANSDOWNE PL
EXISTING BUILDING 10m (THE SPANISH ACQUISITION)
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
FFL 29.000 GROUND FLOOR CLIENT
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 EXISTING CONDITION / DEMOLITION ELEVATION DATE
08/01/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 100
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
EXISTING BUILDING 12m (CARLTON TRAM SUBSTATION)
EXISTING BUILDING (BRIDGESTONE TYRES) TO BE REMOVED
QUEENSBERRY ST
A-103
18-214
A
EXISTING BUILDING 25m (71-79 BOUVERIE ST)
FFL 29.000 GROUND FLOOR
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
DRAWING TITLE
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
1
A-501
1
2
3
4
2
5
A-501
DOOR LEGEND
7272
DT01: DWELLING DOOR DOOR DIMENSION DOOR COMPANY
9272
9272
DT02: ROOM DOOR DOOR DIMENSION DOOR COMPANY DT03: CAVITY DOOR (STUDIO) DOOR DIMENSION DOOR COMPANY
STORAGE
2
DT04: AUTOMATIC DOOR (COS) DOOR DIMENSION DOOR COMPANY 2
BIKE STORE
A-502
A-502
9300
4450
DT05: SERVICE DOOR DOOR DIMENSION DOOR COMPANY DT06 RETAIL DOOR DOOR DIMENSION DOOR COMPANY DT07: REFUSE DOOR DOOR DIMENSION DOOR COMPANY
1
2100
A-502
10950
4800 2850
WALL LEGEND
2850
DESCRIPTION
20/08/2018
PROJECT SETUP
FT01: STONE FLOOR STONE TILE DIMENSION TILE COMPANY NAME
FT03: POS FLOOR STONE TILE DIMENSION TILE COMPANY NAME
2500
COMMS
DATE
FT02: TOILET FLOOR TILE DIMENSION TILE COMPANY NAME
SWITCHBOARD ROOM
FIRE PUMP ROOM
REV A
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
2750
E
WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE
CLIENT
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
BASEMENT FLOOR PLAN DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
As indicated @A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-201
18-214
A
WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE 1
A-501
2
A-501
WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE WT11: RETAIL CURTAIN WALL CURTAIN WALL
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
1
A-502
FLOOR LEGEND
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
1
2
3
4
1
A-401
5
1
6
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
FT01: STONE FLOOR STONE TILE DIMENSION TILE COMPANY NAME
NOTES
FT02: TOILET FLOOR TILE DIMENSION TILE COMPANY NAME
WALL LEGEND WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
FT03: POS FLOOR STONE TILE DIMENSION TILE COMPANY NAME
2
A-501
FLOOR LEGEND
A-501
A
WINDOW LEGEND
WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WI01: CORRIDOR WINDOW WINDOW NAME WINDOW DIMENSION
WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WI02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION
WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE
WI03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION
WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE
WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION 7272
RETAIL 1
B
RETAIL 2
RETAIL 3
WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE
WI05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION
RETAIL 4
WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE
DOOR LEGEND DT01: DWELLING DOOR DOOR DIMENSION DOOR COMPANY
2
2
A-502
4700
4450
6303
A-502
6153
3120
WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
DT03: CAVITY DOOR (STUDIO) DOOR DIMENSION DOOR COMPANY
WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE WT11: RETAIL CURTAIN WALL CURTAIN WALL
DT05: SERVICE DOOR DOOR DIMENSION DOOR COMPANY
GAS METER ROOM
DT06 RETAIL DOOR DOOR DIMENSION DOOR COMPANY
20372
ELECTRICITY SERVICE ROOM
1
A-502
2100
5901
1
A-502
DT02: ROOM DOOR DOOR DIMENSION DOOR COMPANY
DT04: AUTOMATIC DOOR (COS) DOOR DIMENSION DOOR COMPANY
2750
2
A-402
C
WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
LOBBY
DT07: REFUSE DOOR DOOR DIMENSION DOOR COMPANY
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
MAIL 2630
D WATER METER ROOM
COMM
CLIENT
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 GROUND FLOOR PLAN
5878
KITCHEN
CL
DRAWING TITLE
CAFE 2500
REFUSE STORAGE
3600
5900
DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
As indicated
3030
@A1
2550
1050
3000
FEMALE TOILET
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
3698
MALE TOILET
1400
FIRE CONTROL ROOM
9978
A-202
18-214
A
F 1
2
A-501
A-501
1
A-402
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
10300
E
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
1
2 5000
3
5
22660
A-401
1500
WT02
4
1
4950
WT01
5000
WT02 WT01 WT02
1
6
WT01
WT02
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
6210
WT01
WT01
2
A-501
NOTES
WT02
A-501
DOOR LEGEND
A WI05
FT03
WI03
WI02
FT01
FT03
DT01: DWELLING DOOR DOOR DIMENSION DOOR COMPANY
WT02 WT09
REF.
WT09 WT02 4772
DT02: ROOM DOOR DOOR DIMENSION DOOR COMPANY
WT09
WT09
FT03
FT01
DT03: CAVITY DOOR (STUDIO) DOOR DIMENSION DOOR COMPANY
WT01
DT04: AUTOMATIC DOOR (COS) DOOR DIMENSION DOOR COMPANY
STUDIO TYPE 02 FT01
WT09
222 36 m²
WI03
DT05: SERVICE DOOR DOOR DIMENSION DOOR COMPANY
WT02
REF.
100
DT02
B WT01
WT09
DT02
2
3500
221
WT02 REF.
FT02
2
DT02
FT02
A-502
5000
A-502
WI03
FT01
FT01
WT06
2000
2
68 m²
WT05
37 m² WI02
DT07: REFUSE DOOR DOOR DIMENSION DOOR COMPANY WALL LEGEND
A-401
223
STUDIO TYPE 01
DT06 RETAIL DOOR DOOR DIMENSION DOOR COMPANY
WT01
2 BEDROOM TYPE 01
DT03 WT01
3000
2000
WT02
3000
FT01
FT02 WT05
WT06 LIFT CORE
DT02
WI04
WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE
DT02 WT02
WI04 DT01
CL
1400
WI01 EQ
EQ
A-502
2100
1
650
EQ
20372
WT01
150
1300 CL
650
EQ
CL DT01
224
FT01
332
48 m²
DT01
WT09
16 m² 150
DT05
ELECTRICAL C L
EQ DT05 EQ
DT01
1
A-602
CL GAS METER
WT01 2850
WT06 WT02
FT01
DT05 COMMS
REF. FIRE STAIRCASE WT01
238 WI03
BIN CHUTE
FT01
REF. FT01
12 m²
WT05
DT02 2 BEDROOM TYPE 02
600
WT01
DT02
DT02
1 BEDROOM TYPE 02 226
WT06
WT09 2407
DT02 3000
WT02 2772
WT06
FT01
FT01
WT09
4000
WT09 FT03
WI04 REF.
F
1600
2250
WI04
2
A-501
A-501
1
A-402
1
Level 01
1 : 50
WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
WT11: RETAIL CURTAIN WALL CURTAIN WALL FLOOR LEGEND FT01: STONE FLOOR STONE TILE DIMENSION TILE COMPANY NAME FT02: TOILET FLOOR TILE DIMENSION TILE COMPANY NAME
WINDOW LEGEND
2600
1
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
FT03: POS FLOOR STONE TILE DIMENSION TILE COMPANY NAME
WI04
9307
A-203
WT01
DT02
FT02
FT03
WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE
WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE
70 m²
FT01 5650
225
FT02
WT06
60 m²
WT02
WT06
WT05
2200
WT09
WI02
3000
FT01
E
WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE
WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE
2000
1600
1
A-502
FT03 EQ DT05 EQ
DT01
WATER
WI03
D
CORRIDOR
WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE
1 BEDROOM TYPE 01
DT01
150
C
WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WT01
WT09
2500
2
A-402
DT02
DT01
FT02
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WI01: CORRIDOR WINDOW WINDOW NAME WINDOW DIMENSION WI02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION
CLIENT
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
TYPICAL LOWER FLOOR PLAN (1/F) DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
As indicated @A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-203
18-214
A
WI03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION WI05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
WI03 WT05
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
1
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
A-501
1
2
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
3
4
1
A-401
5
2
6
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
A-501
DOOR LEGEND DT01: DWELLING DOOR DOOR DIMENSION DOOR COMPANY
A
NOTES
DT02: ROOM DOOR DOOR DIMENSION DOOR COMPANY DT03: CAVITY DOOR (STUDIO) DOOR DIMENSION DOOR COMPANY DT04: AUTOMATIC DOOR (COS) DOOR DIMENSION DOOR COMPANY
1000
4400
WT02
WT01
WT02
WT01
WT02
WT01
WT01
WT01
WT01
WT02
DT05: SERVICE DOOR DOOR DIMENSION DOOR COMPANY
FT03
WT09
WI02
WI02
WI02
WT06
DT06 RETAIL DOOR DOOR DIMENSION DOOR COMPANY DT07: REFUSE DOOR DOOR DIMENSION DOOR COMPANY
FT02
WT06 WT06
B
WT02
WI03 DT02
2000
ROOM FLOOR
ROOM FLOOR
REF. 1412
FT02
2
WT09
WT05 WT06
229
A-401
FT03
1 BEDROOM
FT01: STONE FLOOR STONE TILE DIMENSION TILE COMPANY NAME
WT06
47 m² 2
DT03
STUDIO
A-502
WT01
2
DT02
A-502
93 REF.
39 m² 2
A-402
ROOM FLOOR
ROOM FLOOR
LIFT SHAFT
DT01
WINDOW LEGEND
FT02
WI03
WT01
C WT01
WT01
A-502
CORRIDOR WI01
WT01
WI05
FT01 WT01
13 m² DT05
DT01 WT01
WATER
REF.
DT05
DT05
ELECTRICAL
GAS METER
DT01
WT06
WT04
WI02
3 BEDROOM
FIRE STAIRCASE WT04
WT04
WT01
BIN CHUTE
E
228
231
WT01
2400
227
WT09 WT02
DT02
DT03
41 m² WT01
WT06
WT06
ROOM FLOOR
DT02 WT09
DT02
WT09
WT06 WT02
3000
FT02 WT06
FT03
ROOM FLOOR WI04
WI04
WI04
WI03
WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE
FT03 FT02 WT06
WT01 WT02
WT01
WT01
WT02
WT01
WT01
F
1
A-501
1
A-402
WT02
2
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
TYPICAL UPPER FLOOR PLAN (6/F)
WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE
DATE
WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
A-501
CLIENT
WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE
WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE
WT02
DESCRIPTION
WI05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WT06 WI03
DATE
WALL LEGEND
100 m²
12 m²
ROOM FLOOR STUDIO
REV
WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION
ROOM FLOOR
WT04
DT05 COMMS
WI02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION WI03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION
DT02
WT06
WT06 WI05
1
A-502
ROOM FLOOR WT02
WI01: CORRIDOR WINDOW WINDOW NAME WINDOW DIMENSION
230 REF.
WT02 WT01 WT01
WI03 DT03
DT01
1
D
WT01
WT04 WT04
FT02: TOILET FLOOR TILE DIMENSION TILE COMPANY NAME FT03: POS FLOOR STONE TILE DIMENSION TILE COMPANY NAME
DT01 WI03
FLOOR LEGEND
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
As indicated @A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-204
18-214
WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE WT11: RETAIL CURTAIN WALL CURTAIN WALL COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
WI02
WT02
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS.
1
2
3
1
A-501
1
A-401
4
2
5
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
6
NOTES
A-501
A
B 2
A-401
2
2
A-502
A-502
2
A-402
C 1
1
A-502
A-502
REV
DATE
DESCRIPTION
D
CLIENT
RMIT DANIEL MAUNDERS PROJECT
E
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 COS LEVEL 05 DATE
09/20/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 50
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-205
F
1
A-501
1
A-402
18-214
2
A-501
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
DRAWING TITLE
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
1
2
3
4
1
2
A-501
5
6
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
A-501
NOTES
DOOR LEGEND
A
DT01: DWELLING DOOR DOOR DIMENSION DOOR COMPANY DT02: ROOM DOOR DOOR DIMENSION DOOR COMPANY -
WT02
WT01
WT02
WT01
WT02
WT01
WT02
WT01
WT02
WT01 WT02
WT01
DT03: CAVITY DOOR (STUDIO) DOOR DIMENSION DOOR COMPANY
WT02
DT04: AUTOMATIC DOOR (COS) DOOR DIMENSION DOOR COMPANY
WT02
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
DT05: SERVICE DOOR DOOR DIMENSION DOOR COMPANY
LT06
LT07
DT06 RETAIL DOOR DOOR DIMENSION DOOR COMPANY
B LT07
DT07: REFUSE DOOR DOOR DIMENSION DOOR COMPANY
2
A-401
WT10 LT06
WINDOW LEGEND
WT10 LT06
WI01: CORRIDOR WINDOW WINDOW NAME WINDOW DIMENSION
LT06 FT01
2
A-502
2
LT06
LT06
A-502
WI02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION
WT02 LT06 2
A-402
WT10
LT06
LT06
WT01
WI03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION
LT06
WT02
WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION
LT06 WT02 LT06 WT01
WT04
WT10
WT04
WT06
WT04
LT06
C
LT06
WT02 WT01WT02
FT01
WT1000.519
1
A-502
WT01
FT01
00.517
LT06
WT02 WT10 00.503
WT01
D
00.499
00.501
LT06
WT10
LT06
LT06
00.516
LT06
WT10 WT04
WT01
E
WT02
WT04
WT04
FLOOR LEGEND
WT02
FT02: TOILET FLOOR TILE DIMENSION TILE COMPANY NAME
WT01
FT03: POS FLOOR STONE TILE DIMENSION TILE COMPANY NAME
LT06
WT02
A-502
FT01: STONE FLOOR STONE TILE DIMENSION TILE COMPANY NAME
00.502
LT06 LT06
1
WT01
WI05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
LT06
WALL LEGEND
LT06
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
CLIENT
WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
LT06 FT01
FT01
WT04
WT10
WT10
WT01
WT10
WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WT02 LT07 LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
LT06
WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE
LT07
LT06
WT02
WT02
WT01
WT01
WT02
WT01
WT02
WT01
WT02 WT01
WT02
WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE
F 1
A-501
1
A-402
2
A-501
WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
RMIT DANIEL MAUNDERS PROJECT
DRAWING TITLE
ROOF PLAN DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
As indicated @A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-206
18-214
A
WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE WT11: RETAIL CURTAIN WALL CURTAIN WALL
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
WT10 WT01
GENERAL NOTES
1
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
2
A-501
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
A-501
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
1
2
3
1
A-401
4
5
6
LIGHTING LEGEND LT01: TRACK LIGHT (SHORT) DIMENSION AND BULB NO. LIGHT COMPANY NAME
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
NOTES
LT02: TRACK LIGHT (LONG) DIMENSION AND BULB NO. LIGHT COMPANY NAME
A
LT03: DOWN LIGHT BULB DIMENSION LIGHT COMPANY NAME LT04: WALL MOUNTED LIGHT BULB DIMENSION LIGHT COMPANY NAME LT05: POS LIGHT BULB DIMENSION LIGHT COMPANY NAME LT06: ROOFTOP LIGHT (BOLLARD) LIGHT DIMENSION LIGHT COMPANY NAME LT07: ROOFTOP LIGHT (POLE) LIGHT DIMENSION LIGHT COMPANY NAME
B
LT08: RECESSED LIGHT BULB DIMENSION LIGHT COMPANY NAME CEILING LEGEND 2
2
A-502
A-502
CT01: CORRIDOR CEILING RECESSED CEILING FINISHING NAME CT02: DWELLING CEILING TIMBER PANEL DIMENSION FINISHING NAME
2
CT03: BATHROOM CEILING TILE DIMENSION TILE NAME
A-402
CT04: POS CEILING EXPOSED CONCRETE WINDOW LEGEND
C 1
1
A-502
A-502
WI01: CORRIDOR WINDOW WINDOW NAME WINDOW DIMENSION WI02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION
D
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
WI03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION WI05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE
F
WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE
1
A-402
1
A-501
2
A-501
CLIENT
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
GROUND RCP DATE
27/08/18
CHECKED
DK&CW
APPROVED
DM
SCALE
1 : 50
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-301
18-214
A
WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE
COPYRIGHT
WT11: RETAIL CURTAIN WALL CURTAIN WALL
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
WALL LEGEND
E
GENERAL NOTES
1
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
2
A-501
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS.
A-501
DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
2
3 500
4
1
A-401
CL
CL
2575
5 CL
500
6
DO NOT SCALE OFF DRAWINGS.
LIGHTING LEGEND 546
LT01: TRACK LIGHT (SHORT) DIMENSION AND BULB NO. LIGHT COMPANY NAME
LT03
CL
LT05
LT05
LT05
LT03
LT03 LT03 LT03
LT03
LT03
REF.
3100
LT02
2500
LT05 CT02
LT02
LT02
LT03
LT04: WALL MOUNTED LIGHT BULB DIMENSION LIGHT COMPANY NAME
LT03
LT03
LT05: POS LIGHT BULB DIMENSION LIGHT COMPANY NAME
LT03
LT03
LT06: ROOFTOP LIGHT (BOLLARD) LIGHT DIMENSION LIGHT COMPANY NAME
LT02 LT03
LT03
LT03 CT02
LT03 CT02
LT05
500
CL
LT03 CL
LT03 LT03 LT03 LT03
LT03
LT03 LT01
REF.
B
CT02
LT03
LT01
LT03
LT01
LT03
LT01 LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT03 REF.
LT03
LT03
LT04
LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT03
CL
CL
A-502
CT01: CORRIDOR CEILING RECESSED CEILING FINISHING NAME
LT03
LT03 LT03
CT02: DWELLING CEILING TIMBER PANEL DIMENSION FINISHING NAME
LT03 LT03 LT03
DT01
LT03
CEILING LEGEND 2
LT03
LT03
LT04
C
CT03 CT02
CT03: BATHROOM CEILING TILE DIMENSION TILE NAME
LT03
DT01
LT05 LT02
CT01
1
DT01
A-502
DT01
D
LT03 LT03
LT03
DT05
DT01
LT03
LT03
E
A-502
CT02
LT01 LT03
LT03
LT03
LT03
DT05 LT03
LT02
LT02 REF.
LT03
LT05
CT02
LT03 LT04
LT03
LT03
LT03
LT03
LT03
CT03
LT03
LT02
LT03
LT03
LT03
LT03
LT03
LT01
LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT05
CT03
LT02
CT02
LT01
2772
LT03
LT03 LT02
LT01
LT04 LT03
LT03
LT01
LT03
LT05 CT02
LT01
LT03
LT03
LT03
CT02
CT02
REF.
LT05
F
WI01: CORRIDOR WINDOW WINDOW NAME WINDOW DIMENSION
A-402
1
A-501
2
A-501
DATE
DESCRIPTION
20/08/2018
PROJECT SETUP
WI03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION
WI05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION WALL LEGEND
CLIENT
RMIT DANIEL MAUNDERS PROJECT
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE
DRAWING TITLE
TYPICAL LOWER FLOOR RCP
WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE
DATE
WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE
SCALE
WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE
1
REV A
WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION
REF. LT03
CT04: POS CEILING EXPOSED CONCRETE WINDOW LEGEND
WI02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION
LT03 LT03
LT05
1
LT03
LT03
LT03
LT03 LT03
LT03 LT01
DT01
CT02
LT03
LT03
LT07: ROOFTOP LIGHT (POLE) LIGHT DIMENSION LIGHT COMPANY NAME LT08: RECESSED LIGHT BULB DIMENSION LIGHT COMPANY NAME
LT03
CT03
4150 1600
LT03
1750
CT03
LT03
LT03
LT03
LT03
LT03 1750
2
LT04 LT04
DT01
A-402
2
A-401
CT03
A-502
LT03
LT03
LT01
LT01
LT03
LT03
LT01
LT03
CT02 2
LT03 LT03
LT03
LT03: DOWN LIGHT BULB DIMENSION LIGHT COMPANY NAME
LT05
CT02
LT03
NOTES
LT02: TRACK LIGHT (LONG) DIMENSION AND BULB NO. LIGHT COMPANY NAME
250
500
A
USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE
27/08/18
CHECKED
DK&CW
APPROVED
DM
1 : 50
@A1
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-302
18-214
A
WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE WT11: RETAIL CURTAIN WALL CURTAIN WALL
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
1
GENERAL NOTES THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS. COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES.
1
2
3
4
1
1
A-401
A-501
5
2
6
DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
A-501
LIGHTING LEGEND
NOTES
LT01: TRACK LIGHT (SHORT) DIMENSION AND BULB NO. LIGHT COMPANY NAME
A
LT02: TRACK LIGHT (LONG) DIMENSION AND BULB NO. LIGHT COMPANY NAME LT03: DOWN LIGHT BULB DIMENSION LIGHT COMPANY NAME 1800
LT05
LT04: WALL MOUNTED LIGHT BULB DIMENSION LIGHT COMPANY NAME LT05: POS LIGHT BULB DIMENSION LIGHT COMPANY NAME
LT05 LT03
LT03
LT03
LT06: ROOFTOP LIGHT (BOLLARD) LIGHT DIMENSION LIGHT COMPANY NAME
LT05
LT03
B
LT02
LT02
LT02 LT03
REF. LT03
LT03
LT03
LT03
LT03
2
A-401
LT03
LT04 LT03
LT03
LT03
LT03
LT03
LT03
LT03
LT03
3000
LT01 2
93
LT04
2
LT03
LT03
LT03
LT05
LT03
LT03 REF.
39 m²
A-402
LT03
LT03
STUDIO
A-502
LT03
LT03
LT03 LT03
LT03
LT03
LT03
C
LT03
LT04
LT03
CT03: BATHROOM CEILING TILE DIMENSION TILE NAME
LT03
LT01
1
A-502
REF.
A-502
REF.
CT01: CORRIDOR CEILING RECESSED CEILING FINISHING NAME CT02: DWELLING CEILING TIMBER PANEL DIMENSION FINISHING NAME
LT03
LT03 1
LT03
LT08: RECESSED LIGHT BULB DIMENSION LIGHT COMPANY NAME CEILING LEGEND
LT03
LT03 LT03
D
2
A-502
LT07: ROOFTOP LIGHT (POLE) LIGHT DIMENSION LIGHT COMPANY NAME
CT04: POS CEILING EXPOSEDLEGEND CONCRETE WINDOW WI01: CORRIDOR WINDOW WINDOW NAME WINDOW DIMENSION WI02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION
LT03
LT02 LT02
LT02
LT02
LT02
LT03
REV
DATE
DESCRIPTION
WI03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION
LT03
LT03
LT03 LT01
E
LT01 LT05
LT03
LT03
LT03
LT03
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
LT03 LT03
LT03
LT03
LT04
LT03
LT03
LT03
LT03
LT03
WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE
LT03
LT03
LT05
LT04
LT05
LT03
LT03
LT03
LT03
LT03
LT03
LT03
WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE
1700
LT03 LT03
LT03
LT03
4800
F
1
A-501
1
A-402
WI05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION WALL LEGEND
LT05
WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE
2
RMIT DANIEL MAUNDERS PROJECT
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053 DRAWING TITLE
TYPICAL UPPER FLOOR RCP DATE
08/27/18
CHECKED
DK&CW
APPROVED
DM
WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE
SCALE
WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE
STATUS
PROJECT #
DRAWING NUMBER
REVISION
WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE A-501
CLIENT
1 : 50
@A1
DD
A-303
18-214
WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE WT11: RETAIL CURTAIN WALL CURTAIN WALL
COPYRIGHT
TWO ARCHITECTS Architects BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9998 8887 GROUP NAME.COM
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
LT03
6
5
WT02
FFL 69.000 ROOFTOP
4
WT02
3
2
WT02 WT02
WT02
WT02
WT02
570
569
WT02
WT02
553
552
WT09 572
571
WT02 WT02
WT09 555
554
WT02
538
537
536
535
WT02
WT02
519
518
WT02
WT02
WI02
WI02
WT02
WT02
FFL 62.000 Level 09
WT02 WT02
WT02
WT02
WT09
FFL 58.500 Level 08
WT09 522
521
520
WT02
WT02 WT02
WT02
WT02
WT09
FFL 55.000 Level 07
WT09 WI03
WI02
WI02
WT02
WT02
WT02
FFL 51.500 Level 06
A
WT09
WT02
FFL 55.000 Level 07
B
FFL 65.500 Level 10
WT02 WT02 WT02 WT02 WT02 WT02 WT01 WT01 WT01 WT01 WT01 WT01 539
FFL 58.500 Level 08
C
WT09 556
WT09
D
FFL 69.000 ROOFTOP
WT02 WT02
FFL 62.000 Level 09
E
WT09 573
FFL 65.500 Level 10
F
1
WT02
WT02
FFL 51.500 Level 06
2
A-601
FFL 48.000 Level 05
WT02
WT02
WT02 WT02
WT02
WT02
FFL 48.000 Level 05
WT02
WT09
WT09
513
511
WT09
514 FFL 44.500 Level 04
WT02
WT02
WT02
WT02
WT02
FFL 44.500 Level 04
WT02
WT02 WT09
WT09
497
495
WT09
498 FFL 41.000 Level 03
WT02
WT01
WT01 WT02
WT09
WT01 WT01 WT02 WT02
WT02
WT09
481
WT01 WT01 WT02
479
FFL 41.000 Level 03
WT09
482 FFL 37.500 Level 02
WT02
WT02
WT02 WT02
WT09
WT02
WT02
FFL 37.500 Level 02
WT02 WT09
WI03
WI03
WT09
WI02 FFL 34.000 Level 01
WT02
WT02
WT02
WT02
WT02
WT02
FFL 34.000 Level 01
FFL 29.000 GROUND FLOOR
FFL 29.000 GROUND FLOOR
1
A-401
ELEVATIO NORTH
GENERAL NOTES
2
A-401
1 : 100
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
ELEVATION EAST
1 : 100
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
ELEVATIONS - NORTH & EAST
SCALE @A1
1 : 100
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-401
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
1
1
A-402
2
3
4
5
A
6
FFL 69.000 ROOFTOP
FFL 69.000 ROOFTOP
FFL 65.500 Level 10
FFL 65.500 Level 10
FFL 62.000 Level 09
FFL 62.000 Level 09
FFL 58.500 Level 08
FFL 58.500 Level 08
FFL 55.000 Level 07
FFL 55.000 Level 07
FFL 51.500 Level 06
FFL 51.500 Level 06
FFL 48.000 Level 05
FFL 48.000 Level 05
FFL 44.500 Level 04
FFL 44.500 Level 04
FFL 41.000 Level 03
FFL 41.000 Level 03
FFL 37.500 Level 02
FFL 37.500 Level 02
FFL 34.000 Level 01
FFL 34.000 Level 01
FFL 29.000 GROUND FLOOR
FFL 29.000 GROUND FLOOR
ELEVATION SOUTH
GENERAL NOTES
2
A-402
1 : 100 NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
ELEVATION WEST
B
D
E
F
1 : 100
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
C
ELEVATIONS - SOUTH & WEST
SCALE @A1
1 : 100
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-402
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
WINDOW LEGEND
A
B
C
D
E
A
F
B
C
D
E
F
WI01: CORRIDOR WINDOW WINDOW NAME WINDOW DIMENSION
FLOOR LEGEND FT01: STONE FLOOR STONE TILE DIMENSION TILE COMPANY NAME FT02: TOILET FLOOR TILE DIMENSION TILE COMPANY NAME
1
A-651 FFL 69.000 ROOFTOP
WI02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION
FFL 69.000 ROOFTOP
WI03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION
FT03: POS FLOOR STONE TILE DIMENSION TILE COMPANY NAME
FFL 65.500 Level 10
WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION WI05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION
FFL 65.500 Level 10
DOOR LEGEND DT01: DWELLING DOOR DOOR DIMENSION DOOR COMPANY FFL 62.000 Level 09
DT02: ROOM DOOR DOOR DIMENSION DOOR COMPANY
FFL 62.000 Level 09
DT03: CAVITY DOOR (STUDIO) DOOR DIMENSION DOOR COMPANY
1
A-503 FFL 58.500 Level 08
DT04: AUTOMATIC DOOR (COS) DOOR DIMENSION DOOR COMPANY
FFL 58.500 Level 08
DT05: SERVICE DOOR DOOR DIMENSION DOOR COMPANY FFL 55.000 Level 07
DT06 RETAIL DOOR DOOR DIMENSION DOOR COMPANY
FFL 55.000 Level 07
DT07: REFUSE DOOR DOOR DIMENSION DOOR COMPANY CEILING LEGEND FFL 51.500 Level 06
CT01: CORRIDOR CEILING RECESSED CEILING FINISHING NAME
FFL 51.500 Level 06
CT02: DWELLING CEILING TIMBER PANEL DIMENSION FINISHING NAME
1
A-652
FFL 48.000 Level 05
FFL 48.000 Level 05
CT03: BATHROOM CEILING TILE DIMENSION TILE NAME CT04: POS CEILING EXPOSED CONCRETE
FFL 44.500 Level 04
WALL LEGEND
FFL 44.500 Level 04
1
A-504
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
2
A-503 FFL 41.000 Level 03
WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE
FFL 41.000 Level 03
WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE FFL 37.500 Level 02
WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE
FFL 37.500 Level 02
WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE FFL 34.000 Level 01
WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE
FFL 34.000 Level 01
WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE
FFL 29.000 GROUND FLOOR
WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
FFL 29.000 GROUND FLOOR
WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE FFL 24.000 BASEMENT FLOOR
1
A-501
Section A
GENERAL NOTES
WT11: RETAIL CURTAIN WALL CURTAIN WALL
FFL 24.000 BASEMENT FLOOR
2
A-501
1 : 100 NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
Section B
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
1 : 100 CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
SCALE @A1
As indicated
SECTION A & B
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
CHECKED
APPROVED
DK&CW DM
0
0.5 1
2
3
5.0M
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-501
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
6
5
4
3
2
1
1
520
3
4
5
6
2
A-505
FFL 69.000 ROOFTOP
FFL 69.000 ROOFTOP
FFL 65.500 Level 10
FFL 65.500 Level 10
FFL 62.000 Level 09
FFL 62.000 Level 09
FFL 58.500 Level 08
FFL 58.500 Level 08
75
2
75
FFL 55.000 Level 07
FFL 55.000 Level 07
FFL 51.500 Level 06
FFL 51.500 Level 06
1
A-505
FFL 48.000 Level 05
FFL 48.000 Level 05
FFL 44.500 Level 04
FFL 44.500 Level 04
2
A-504
FFL 41.000 Level 03
FFL 41.000 Level 03
1
A-601
FFL 37.500 Level 02
FFL 37.500 Level 02
FFL 34.000 Level 01
FFL 34.000 Level 01
FFL 29.000 GROUND FLOOR
FFL 29.000 GROUND FLOOR
FFL 24.000 BASEMENT FLOOR
1
A-502
FFL 24.000 BASEMENT FLOOR
Section C
GENERAL NOTES
2
A-502
1 : 100 NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
Section D
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
1 : 100 CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
SCALE @A1
1 : 100
SECTION C & D
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-502
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
2
B
1
C
A-502
A-502
D
E
FFL 58.500 Level 08
2
1
A-503
1
A-502
Section - APARTMENT UPPER
A-502
CEILING LEGEND FLOOR LEGEND CT01: CORRIDOR CEILING RECESSED CEILING FT01: STONE FLOOR FINISHING NAME STONE TILE DIMENSION TILE COMPANY NAME WINDOW LEGEND CT02: DWELLING CEILING TIMBER PANEL DIMENSION FT02: TOILET FLOOR WI01: CORRIDOR WINDOW FINISHING NAME TILE DIMENSION WINDOW NAME TILE COMPANY NAME WINDOW DIMENSION CT03: BATHROOM CEILING TILE DIMENSION WI02: LIVING ROOM WINDOW FT03: POS FLOOR STONE TILE DIMENSION WINDOW NAME TILE NAME TILE COMPANY NAME WINDOW DIMENSION CT04: POS CEILING WI03: BEDROOM WINDOW EXPOSED CONCRETE WINDOW NAME WINDOW DIMENSION WALL LEGEND WI04: TOILET WINDOW WINDOW NAME WT01: FACADE WALL (H) WINDOW DIMENSION 100mm TIMBER FIN WI05: KITCHEN WINDOW 200mm PRECAST CONCRETE WINDOW NAME WINDOW DIMENSION WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE
1 : 20
A
2
B
C
A-502
D
1
A-502
DOOR LEGEND WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN DT01: DWELLING DOORPRECAST CONCRETE 200mm DOOR DIMENSION LT01: TRACK LIGHT (SHORT) DIMENSION AND BULBDOOR NO. COMPANY WT04: CORE WALL FINISHING LIGHT COMPANY NAMEDT02: ROOM DOOR 300mm PRECAST CONCRETE DOOR DIMENSION LT02: TRACK LIGHT (LONG) DOOR COMPANY DIMENSION AND BULB NO. WT05: DWELLING DIVIDER (STUDIO) CLADDING LIGHT COMPANY NAMEDT03: CAVITY DOOR DOOR DIMENSION 200mm PRECAST CONCRETE LT03: DOWN LIGHT DOOR COMPANY WT06: INTERNAL BULB DIMENSION DT04: AUTOMATIC DOOR (COS) ROOM DIVIDER CLADDING LIGHT COMPANY NAMEDOOR DIMENSION 100mm PRECAST CONCRETE DOOR COMPANY LT04: WALL MOUNTED LIGHT DT05: SERVICE WT07: DOOR TOILET WALL BULB DIMENSION CLADDING LIGHT COMPANY NAMEDOOR DIMENSION DOOR COMPANY 100mm PRECAST CONCRETE LT05: POS LIGHT DT06 RETAIL DOOR WT08: EXTERNAL BI-FOLDING BULB DIMENSION DOOR DIMENSION BI-FOLDING WINDOW LIGHT COMPANY NAMEDOOR COMPANY 100mm PRECAST CONCRETE REFUSE DOOR LT06: ROOFTOP LIGHTDT07: (BOLLARD) DOOR DIMENSION LIGHT DIMENSION WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW LIGHT COMPANY NAMEDOOR COMPANY 100mm PRECAST CONCRETE LT07: ROOFTOP LIGHT (POLE) WT10: ROOFTOP GARDEN LIGHT DIMENSION 100mm TIMBER FIN LIGHT COMPANY NAME 100mm PRECAST CONCRETE LT08: RECESSED LIGHT WT11: RETAIL CURTAIN WALL BULB DIMENSION CURTAIN WALL LIGHT COMPANY NAME LIGHTING LEGEND
FFL 41.000 Level 03
2
1
A-502
2
A-503
Section - APARTMENT LOWER
GENERAL NOTES
A-502
1 : 20
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
SCALE @A1
As indicated
SECTION E & F
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
CHECKED
APPROVED
DK&CW DM
0
0.5 1
2
3
5.0M
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-503
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
1
4
3
A-501
2
DOOR LEGEND
1
DT01: DWELLING DOOR DOOR DIMENSION DOOR COMPANY DT02: ROOM DOOR DOOR DIMENSION DOOR COMPANY
FFL 44.500 Level 04
DT03: CAVITY DOOR (STUDIO) DOOR DIMENSION DOOR COMPANY DT04: AUTOMATIC DOOR (COS) DOOR DIMENSION DOOR COMPANY DT05: SERVICE DOOR DOOR DIMENSION DOOR COMPANY DT06 RETAIL DOOR DOOR DIMENSION DOOR COMPANY DT07: REFUSE DOOR DOOR DIMENSION DOOR COMPANY
LIGHTING LEGEND LT01: TRACK LIGHT (SHORT) DIMENSION AND BULB NO. LIGHT COMPANY NAME LT02: TRACK LIGHT (LONG) DIMENSION AND BULB NO. LIGHT COMPANY NAME LT03: DOWN LIGHT BULB DIMENSION LIGHT COMPANY NAME FFL 41.000 Level 03
LT04: WALL MOUNTED LIGHT BULB DIMENSION LIGHT COMPANY NAME LT05: POS LIGHT BULB DIMENSION LIGHT COMPANY NAME LT06: ROOFTOP LIGHT (BOLLARD) LIGHT DIMENSION LIGHT COMPANY NAME
1
2
A-504
A-501
Section - CORRIDOR 02
1 : 20 2
B
LT07: ROOFTOP LIGHT (POLE) LIGHT DIMENSION LIGHT COMPANY NAME
CEILING LEGEND
A-502
1
C
D
A-502
CT01: CORRIDOR CEILING RECESSED CEILING FINISHING NAME
E
LT08: RECESSED LIGHT BULB DIMENSION LIGHT COMPANY NAME
CT02: DWELLING CEILING TIMBER PANEL DIMENSION FINISHING NAME
WALL LEGEND
CT03: BATHROOM CEILING TILE DIMENSION TILE NAME
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE
CT04: POS CEILING EXPOSED CONCRETE
WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WINDOW LEGEND
WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE
WI01: CORRIDOR WINDOW WINDOW NAME WINDOW DIMENSION
WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE
WI02: LIVING ROOM WINDOW WINDOW NAME WINDOW DIMENSION
WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE
WI03: BEDROOM WINDOW WINDOW NAME WINDOW DIMENSION
FFL 41.000 Level 03
2
1
A-504
GENERAL NOTES
1
A-502
Section - CORRIDOR 01
A-502
1 : 20
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
SCALE @A1
As indicated
SECTION G & H
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
09/19/18
CHECKED
APPROVED
DK&CW DM
0
0.5 1
WI04: TOILET WINDOW WINDOW NAME WINDOW DIMENSION
WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE
WI05: KITCHEN WINDOW WINDOW NAME WINDOW DIMENSION
WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE
FLOOR LEGEND
WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
FT01: STONE FLOOR STONE TILE DIMENSION TILE COMPANY NAME
WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE
FT02: TOILET FLOOR TILE DIMENSION TILE COMPANY NAME
WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE
FT03: POS FLOOR STONE TILE DIMENSION TILE COMPANY NAME
WT11: RETAIL CURTAIN WALL CURTAIN WALL
2
3
5.0M
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-504
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
5 WALL LEGEND
4
2
A-501
1
A-501
WT01: FACADE WALL (H) 100mm TIMBER FIN 200mm PRECAST CONCRETE WT02: FACADE WALL (V) 100mm TIMBER FIN 200mm PRECAST CONCRETE WT03: FACADE WALL (SOUTH) 100mm TIMBER FIN 200mm PRECAST CONCRETE WT04: CORE WALL FINISHING 300mm PRECAST CONCRETE WT05: DWELLING DIVIDER CLADDING 200mm PRECAST CONCRETE WT06: INTERNAL ROOM DIVIDER CLADDING 100mm PRECAST CONCRETE WT07: TOILET WALL CLADDING 100mm PRECAST CONCRETE WT08: EXTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE WT09: INTERNAL BI-FOLDING BI-FOLDING WINDOW 100mm PRECAST CONCRETE FFL 69.000 ROOFTOP
WT10: ROOFTOP GARDEN 100mm TIMBER FIN 100mm PRECAST CONCRETE WT11: RETAIL CURTAIN WALL CURTAIN WALL
2
1
A-501
A-501
FLOOR LEGEND FT01: STONE FLOOR STONE TILE DIMENSION TILE COMPANY NAME FT02: TOILET FLOOR TILE DIMENSION TILE COMPANY NAME
CEILING LEGEND DOOR LEGEND CT01:DWELLING CORRIDORDOOR CEILING DT01: RECESSED CEILING DOOR DIMENSION FINISHING NAME DOOR COMPANY
FT03: POS FLOOR STONE TILE DIMENSION TILE COMPANY NAME
6
2
5
DT02: DOORCEILING CT02:ROOM DWELLING DOOR DIMENSION TIMBER PANEL DIMENSION DOOR COMPANY FINISHING NAME
4
A-501
DT03: CAVITY DOOR (STUDIO) CT03: DIMENSION BATHROOM CEILING DOOR TILE DIMENSION DOOR COMPANY TILE NAME DT04: AUTOMATIC DOOR (COS) DOOR CT04: DIMENSION POS CEILING DOOR COMPANY EXPOSED CONCRETE
FFL 51.500 Level 06
DT05: SERVICE DOOR DOOR DIMENSION DOOR COMPANY LIGHTING LEGEND DT06 RETAIL DOOR DOOR LT01:DIMENSION TRACK LIGHT (SHORT) DIMENSION AND BULB NO. DOOR COMPANY LIGHT COMPANY NAME DT07: REFUSE DOOR DOOR DIMENSION LT02: TRACK LIGHT (LONG) DOOR COMPANY DIMENSION AND BULB NO. LIGHT COMPANY NAME LT03: DOWN LIGHT BULB DIMENSION LIGHT COMPANY NAME LT04: WALL MOUNTED LIGHT BULB DIMENSION LIGHT COMPANY NAME LT05: POS LIGHT BULB DIMENSION LIGHT COMPANY NAME LT06: ROOFTOP LIGHT (BOLLARD) LIGHT DIMENSION LIGHT COMPANY NAME LT07: ROOFTOP LIGHT (POLE) LIGHT DIMENSION LIGHT COMPANY NAME FFL 48.000 Level 05
LT08: RECESSED LIGHT BULB DIMENSION LIGHT COMPANY NAME 2
A-501
GENERAL NOTES
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
SCALE @A1
As indicated
SECTION I & J
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
09/19/18
CHECKED
APPROVED
DK&CW DM
0
0.5 1
2
3
5.0M
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-505
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
1 : 20
1
A-502
C 1
A-502
A-601
ELEVATION TYPICAL FACADE 1 : 20
2
FFL 34.000 Level 01
FFL 37.500 Level 02
FFL 41.000 Level 03
FFL 44.500 Level 04
FFL 48.000 Level 05
D
NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
TYPICAL FACADE WALL SECTION 01
SCALE @A1
1 : 20
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
27/08/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-601
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
A-601
SECTION TYPICAL FACADE 1
FFL 34.000 Level 01
FFL 37.500 Level 02
FFL 41.000 Level 03
FFL 44.500 Level 04
FFL 48.000 Level 05
6 GENERAL NOTES
2
A-602
4
6
6
6 2
FFL 37.500 Level 02
FFL 37.500 Level 02
FFL 37.500 Level 02
FFL 34.000 Level 01
FFL 34.000 Level 01
FFL 34.000 Level 01
A-602
4
A-602
A-602
C
1
1
A-502
A-502
3
A-602
3
A-602
D
1
A-602
TYPICAL FACADE DETAIL 01
GENERAL NOTES
1 : 10 NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
2
A-602
TYPICAL FACADE DETAIL 02
3
A-602
1:5 REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
TYPICAL FACADE DETAIL 03
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
4
A-602
1:5
TYPICAL FACADE WALL SECTIONS 02
08/01/18
CHECKED
APPROVED
DK&CW DM
TYPICAL FACADE DETAIL 04
SCALE @A1
As indicated
0
0.5 1
2
3
5.0M
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-602
1:5
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
FFL 69.000 ROOFTOP
1
A-651
CONSTRUCTION DETAIL 01
GENERAL NOTES
1:5 NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
CONSTRUCTION DETAILS
SCALE @A1
1:5
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-651
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
E
F
FFL 48.000 Level 05
1
A-652
CONSTRUCTION DETAIL 02
GENERAL NOTES
1:5 NOTES
THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL RELEVANT CONTRACTS, SPECIFICATIONS AND DRAWINGS.
REV
DATE
DESCRIPTION
A
20/08/2018
PROJECT SETUP
CLIENT
DRAWING TITLE
PROJECT
DATE
RMIT DANIEL MAUNDERS
CONSTRUCTION DETAILS
SCALE @A1
1:5
0
0.5 1
2
3
5.0M
COPYRIGHT OF THIS DRAWING IS VESTED IN THE ARCHITECTS. DIMENSIONS ARE IN MILLIMETRES AND LEVELS ARE IN METRES. DO NOT SCALE OFF DRAWINGS. USE FIGURED DIMENSIONS ONLY. CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCING WORK.
E:\!RMIT\2018_Sem_2\Elective Revitism\Model\1. Revit\Revitism 180920.rvt
PROJECT INVERSION 81/89 BOUVERIE ST, CARLTON VIC 3053
08/01/18
CHECKED
APPROVED
DK&CW DM
STATUS
PROJECT #
DRAWING NUMBER
REVISION
DD
A-652
18-214
A
COPYRIGHT
TWO ARCHITECTS. Pty Ltd BLD 100 VICTORIA St, Melbourne Vic 3000 T +613 9654 6227 jcba.com.au
MINUTES
DANNY (DONG WOO) KWAK S3278341 CAMELLIA KA YEE WONG S3695085 TUTOR: DANIEL MAUNDERS
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Meeting Minutes Date held Time Location
Meeting Minutes
21/07/18 19:00 100.07.001
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Date held Time Location
Invitees
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Invitees
Name Danny Kwak Ka Yee Wong
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Name Danny Kwak Ka Yee Wong
Week 01 Item
29/07/18 19:00 100.07.001
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Week 02 Site Analysis 1. Return to site to take photos and measurement. 2. Take note of viewing options, North/East/South/West. 3. Solar analysis, rough estimates on surrounding building heights. 4. Site access analysis, make notes on significant interchanges 5. Traffic analysis, average day in three time periods 6. Vegetation analysis, make notes on significant landscape Research 1. Research apartment building types, 5 studies each 2. Research different Target Audiences 3. Read BCA & BADS & City of Melbourne’s guide Revit 1. Setup revit file and make site plan page
Action K.W & D.K K.W & D.K K.W & D.K K.W & D.K K.W & D.K K.W & D.K
√ √ √ √ √ √ √
K.W & D.K K.W & D.K K.W & D.K
√ √
D.K
√
Item
Concept Design 1. Make conceptual mass model x 5 Company Logo 1. Design Company Detail (Name, Logo) Revit 1. Setup Title Sheet 2. Demolition Plan & Elevation 3. Site Plan
Action K.W
√ √
D.K
√
D.K D.K D.K
√ √ √
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Meeting Minutes Date held Time Location
Meeting Minutes
04/08/18 19:00 100.07.001
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Date held Time Location
Invitees
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Invitees
Name Danny Kwak Ka Yee Wong
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Name Danny Kwak Ka Yee Wong
Week 03 Item
11/08/18 19:00 100.07.001
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Week 04 Research 1. Research apartment facade precedent studies, 5 studies each Revit 1. Basement floor plan 2. Ground floor plan 3. Typical floor plan 4. Roof plan
Action K.W & D.K
√ √
K.W K.W D.K D.K
√ √ √ √
Item
Research 1. Research apartment and lobby ceiling design, 5 studies each Revit 1. Ground floor RCP 2. Typical apartment units RCP
Action K.W&D.K
√ √
K.W D.K
√ √
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Meeting Minutes Date held Time Location
Meeting Minutes
18/08/18 19:00 100.07.001
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Date held Time Location
Invitees
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Invitees
Name Danny Kwak Ka Yee Wong
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Name Danny Kwak Ka Yee Wong
Week 05 Item
25/08/18 19:00 100.07.001
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Week 06 Research Action 1. Research materials for ceiling, flooring, internal walls and facade K.W & D.K
√ √
Revit 1. Elevations x 4 2. Sections x 4
√ √
K.W D.K
Item
Research 1. Research facade construction details Revit 1. Typical facade section x 2
Action K.W&D.K
√ √
K.W&D.K
√
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Meeting Minutes Date held Time Location
Meeting Minutes
31/08/18 19:00 100.07.001
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Date held Time Location
Invitees
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Invitees
Name Danny Kwak Ka Yee Wong
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Name Danny Kwak Ka Yee Wong
Mid-semester Item
08/09/18 19:00 100.07.001
Revit 1. Amend drawings according to the comments recieved on 22/08/2018
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Week 07 Action K.W & D.K
√ √
Item
Research 1. Research rooftop garden construction details 2. Research construction details of transfer slab Revit 1. Construction details of rooftop garden 2. Construction details of transfer slab
Action D.K K.W
√ √
D.K K.W
√ √
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Meeting Minutes Date held Time Location
Meeting Minutes
20/09/18 19:00 100.07.001
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Date held Time Location
Invitees
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Invitees
Name Danny Kwak Ka Yee Wong
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Name Danny Kwak Ka Yee Wong
Week 08 Item
23/09/18 19:00 100.07.001
Revit 1. Review the structural system 2. Amend drawings according to the comments recieved on 20/09/2018 3. Construction details of central-hunged bifolding windows
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Week 09 Action K.W & D.K K.W & D.K
√ √ √
D.K
√
Item
Revit 1. Dimensions for the floor plans 2. Annotation of wall types 3. Annotation of window types 4. Annotation of door types 5. Annotation of mis 6. Door Schedule 7. Window Schedule 8. Wall Schedule
Action K.W&D.K D.K D.K D.K D.K K.W K.W K.W
√ √ √ √ √ √ √ √ √
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Meeting Minutes Date held Time Location
Meeting Minutes
29/09/18 19:00 100.07.001
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Date held Time Location
Invitees
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Invitees
Name Danny Kwak Ka Yee Wong
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Name Danny Kwak Ka Yee Wong
Week 10 Item
06/10/18 19:00 100.07.001
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Week 11 Revit 1. Solar Analysis 2. Refine facade construction details 3. Refine transfer beam construction details
Action D.K&K.W D.K K.W
√ √ √ √
Item
Revit 1. Update all the plans with annotations and dimensions 2. Update elevations with annotations and dimensions 3. Update sections with annotations and dimensions 4. Update construction details with annotations and dimensions 5. Update typical sections with annotations and dimensions 6. Update all the schedules
Action K.W & D.K K.W & D.K K.W & D.K K.W & D.K K.W & D.K K.W & D.K
√ √ √ √ √ √ √
Building 100 Victoria St, Carlton VIC 3000 (T) +61 03 9999 8888 (F) +61 03 9999 8887 dynamicarchitects@gmail.com www.dynamicarchitects.com.au
Meeting Minutes Date held Time Location
13/10/18 19:00 100.07.001
Subject Project Job no.
Designer Meeting Project Inversion 18-214
Invitees Name Danny Kwak Ka Yee Wong
Company DK Urban Design KYW Architects
Contact 0412 345 678 0412 234 567
Week 12 Item
Revit 1. Finalise every drawing packages for issue
Action D.K&K.W
√ √