Latin America Fit-Out Cost Guide 2019/2020 Edition

Page 1

LATIN AMERICA FIT-OUT COST GUIDE 2019/20 Edition


CONTENTS 2 WELCOME 3 TRADITIONAL VS. AGILE 4 LAYOUTS 12 PRICING ASSUMPTIONS 13 COMPARATIVE FIT COST PER COUNTRY 25 FIT-OUT COST INDEX | LATAM 27 TECHNOLOGY AND EVOLUTION OF OFFICE SPACE 31 FURNITURE 33 PROCUREMENT & PROGRAMME 35 WORKPLACE TRENDS AND COMMON PRACTICES

1

LATAM FIT-OUT COST GUIDE


WELCOME

JUAN ESTEBAN ZABALA ALZATE Managing Director CBRE | Project Management Latin America & Caribbean

Latin America is an attractive region for growth. Our clients are constantly looking for better ways to expand their operations and, more specifically, build offices that guarantee their strong presence. This is why I’m pleased to present our latest LatAm Fit-Out Cost Guide as a tool to support them to make the best decisions for their projects in each market. No matter the budget or expectations, it's imperative for us to be able to answer one common question: "How much will my new office cost?" As the best partners in Project Management services, CBRE is uniquely qualified to provide comparable costs and metrics to uncover how to best allocate and maximize budget to fulfil their expectations.

characteristics, they should be able to use any of the specifications provided as reference. They are categorized broadly into three scenarios basic, medium and high-, each one associated with the corresponding budget that helps to make approximate comparisons between very diverse options. We want to present this tool as a reflection of CBRE Project Management’s capabilities, hoping that will help our team to get the most out of it when planning projects and understand the value of our role as a partner focused on its client’s benefits.

For this purpose, this CBRE Cost Guide for Corporate Interiors was created, ensuring we provide key data as a background in the planning state of every new project. This data gathering process involved a benchmark of our previous projects located by city. CBRE has produced a typical design for 1.000 square meters fit-out suitable for Latin America markets, and using our local teams to scale different scenarios in each market, gathering project cost information for identical spaces in each location. Though not all projects have the same MATTHEW EASTWOOD Head of EMEA Projects CBRE Global Workplace Solutions, EMEA

CBRE PROJECT MANAGEMENT

2


TRADITIONAL VS. AGILE WORKPLACE The terms ‘traditional’ and TRADITIONAL AGILE ‘agile’ refer here to the design The traditional layout is characterised by the The agile layout is characterised by a wide range of office interiors, usually space having a large number of private offices, of work settings which support ‘activity based the size, location and specification of which are working’. This is a shared working environment reflecting the function and determined by the occupier’s status within the with few, if any, desks or rooms allocated to culture of the occupying organisation. Executive assistants typically sit individuals. Personal lockers are provided in organisation. There is, of directly outside their managers’ offices, while the place of under-desk pedestals. The space is course, a broad spectrum of rest of the workforce is accommodated either in designed to foster high-levels of interaction and workplace models in existence open plan or group rooms with no desk sharing. knowledge sharing by providing a wide choice Desks tend to be large and often incorporate of meeting spaces, both open and enclosed. across the region, but these can furniture screens to provide an element of privacy. A number of small rooms and semi-enclosed be distilled broadly into these There is usually a high dependency on paper spaces support the need for individual focused storage in these environments and little in the way work. The emphasis of the agile workplace is very two types. of supplementary workspaces, apart from a suite of predominantly large meeting rooms.

3

LATAM FIT-OUT COST GUIDE

much on the user experience and the wellness and wellbeing of employees. The space itself is designed to be flexible, adaptable and dynamic.


LAYOUTS This guide presents general arrangements of an office floor plate of 1,000 sq m (10,764 sq ft) usable area to suit both traditional and agile ways of working. AREA SCHEDULE

The workplace settings in the agile layout reflect the collaborative and flexible work environment, whereas the traditional layout focuses more on private work settings.

It is likely many businesses will choose a hybrid of the two working styles depending on their needs and operations. The three specification levels of basic, medium and high, as outlined in the following pages, are compatible with either layout.

TRADITIONAL

Traditional Space designation

Area net (sq m)

Work settings

Open plan desks

299

47

Desks in shared room

85

12

Private offices

133

7

Meeting rooms

146

7

Informal meeting spaces

18

2

Tea point

14

Support space

51

Reception

42

Circulation space

212

Total

1,000

75

AGILE

Agile Space designation

Area net (sq m)

Work settings

365

70

Study pods (open plan)

70

14

Meeting rooms

110

8

Quiet rooms

24

4

Informal meeting spaces

44

4

Coffee lounge

60

5

Recreation room

10

Support space

35

Open plan desks/benches

Reception/lounge

70

Circulation space

212

Total

1,000

105

CBRE PROJECT MANAGEMENT

4


BASIC SPECIFICATION ASSUMPTIONS Internal partitions • Predominantly medium acoustic rated plasterboard partitions (single-skin construction) • Single glazed partitions to meeting rooms with solid timber door sets • Fixed plasterboard wall instead of movable walls Wall finish • Painted dry lined partitions throughout • Painted feature walls to lift lobby and reception Floor finish • Medium grade carpet tiles to open plan offices, lift lobby, reception, collaboration and client facing areas • Vinyl floor finish to coffee lounge/tea points Ceiling finish • Re-use existing ceilings • Plasterboard margins to meeting rooms Fittings, furniture and equipment • Proprietary joinery with laminate finish to copy/print areas and tea points • Non-bespoke reception desk Mechanical • Minimal modifications to the existing space heating/cooling • Minimal modifications to the existing air treatment Electrical • Existing lighting to be re-used and reconfigured to suit new layout • New pendant luminaires above reception desk

5

LATAM FIT-OUT COST GUIDE

WORKPOINTS


RECEPTION

COFFEE LOUNGE

MEETING ROOM

COLLABORATION AREA

CBRE PROJECT MANAGEMENT

6


MEDIUM SPECIFICATION ASSUMPTIONS Internal partitions • Increased use of glazed partitions instead of plasterboard • Acoustic-rated single glazed partitions to meeting rooms with framed glazed door sets • Acoustic treatment to partitions (double-skin construction with acoustic infills) • Hardwood veneer and medium acoustic rated manually operated movable walls Wall finish • Painted dry lined partitions throughout • Painted feature wall to client facing meeting rooms • Back painted glass feature walls to lift lobby and reception • Floor to ceiling photo/graphics wallpaper applied in four locations Floor finish • Medium-grade carpet tiles to open plan offices, collaboration and client facing areas • Ceramic tiles to lift lobby, reception and coffee lounge/tea points Ceiling finish • New feature plasterboard ceilings to reception, lift lobby, client-facing areas and coffee lounge • Plasterboard margins to meeting rooms Fittings, furniture and equipment • Resin top finish to tea points with high gloss laminate cupboards • Proprietary laminate joinery for copy/print joinery • Bespoke hardwood and glass reception desk Mechanical • Moderate modifications to the existing space heating/cooling and air treatment Electrical • Existing lighting to be re-used and reconfigured to suit new layout, supplemented by new luminaires to collaboration spaces • Specialist lighting to reception, client facing and coffee lounge spaces • Modifications to existing BMS and lighting controls

7

LATAM FIT-OUT COST GUIDE

WORKPOINTS


RECEPTION

COFFEE LOUNGE

MEETING ROOM

COLLABORATION AREA

CBRE PROJECT MANAGEMENT

8


HIGH SPECIFICATION ASSUMPTIONS Internal partitions • Increased use of glazed partitions instead of plasterboard • High acoustic rated double glazed partitions to meeting rooms with framed glazed door sets • Acoustic treatment to partitions (slab-to-slab construction or acoustic infills above ceiling and within floor void) • Hardwood veneer and high acoustic rated semi-automatic movable walls Wall finish • Painted dry lined partitions throughout • Applied finishes to feature walls in client meeting rooms • Stone feature walls to lift lobby • Video wall to reception • Floor to ceiling photo/graphics wallpaper applied in four locations Floor finish • High grade carpet tiles to open plan offices, collaboration and client facing areas • Porcelain tiles or stone to lift lobby and reception • Hardwood flooring to coffee lounge/tea points Ceiling finish • New feature timber raft ceiling to reception and client facing meeting rooms • New feature plasterboard ceilings to lift lobby, internal meeting rooms and coffee lounge with plasterboard margins • New metal plank ceiling system throughout office space Fittings, furniture and equipment • Resin top finish to tea point with high gloss laminate cupboards • Specialist joinery for copy/print areas • Bespoke joinery construction (encasement) for video wall to reception • Booth seating (adjacent to reception) built as joinery item rather than as furniture solution • Bespoke illuminated glass and stainless steel reception desk with integrated data and power Mechanical • Moderate modifications to the existing space heating, cooling and air treatment • Local temperature control /adjustment in meeting rooms and booths Electrical • Existing lighting re-used and part new lighting to office areas • High-end specialist lighting to reception, client facing, collaborative and coffee lounge spaces • Modifications to BMS and lighting controls with scene setting 9

LATAM FIT-OUT COST GUIDE

www.klstudio.mk contact@klstudio.mk

WORKPOINTS


RECEPTION

COFFEE LOUNGE

MEETING ROOM

COLLABORATION AREA

CBRE PROJECT MANAGEMENT

10


11

LATAM FIT-OUT COST GUIDE


PRICING ASSUMPTIONS A detailed quantity measure has been carried out using the traditional and agile layouts for the three levels of specifications (basic, medium and high). These layouts have been priced locally within each market to capture the costing information along with typical procurement and programme data. Prices for each location identified in this guide are based on the following assumptions: • The building is A class in Shell Space conditions and is located in the central business district. • The base date for the pricing information in this document is August 2019, and reflects both the inflation rates and the exchange rates corresponding to each country at that moment in time • Premises are in good condition and have all necessary infrastructure (suitable baseline requirements of HVAC and power supply, etc) • This is a generic design which does not take into account cultural differences and country specific space planning considerations or local regulations

CBRE Barcelona Office

• This guide does not consider shape variations of the building which may impact fit factors • FF&E is new, no reuse considered • Ordinary timetable for construction works has been contemplated • If the scope of your requirements varies significantly from the design information included in this report, please do not hesitate to contact the Project Management team locally

CBRE PROJECT MANAGEMENT

12


COMPARATIVE FIT COST PER COUNTRY ARGENTINA TRADITIONAL FIT-OUT COST GUIDE

BUENOS AIRES & CORDOBA

FEATURES

COST BREAKDOWN

CORDOBA

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

75

127

127

209

209

>

HARD COST

586

734

734

1,300

1,300

>

FURNITURE

81

160

160

658

658

>

TOTAL FIT OUT COST

742

1,021

1,021

2,167

2,167

>

BASIC

MEDIUM

HIGH

SOFT COST

7%

12%

10%

HARD COST

57%

72%

60%

FURNITURE

8%

16%

30%

TOTAL FIT OUT COST

73%

100%

100%

AGILE FIT-OUT COST GUIDE FEATURES

COST BREAKDOWN

BUENOS AIRES

13

LATAM FIT-OUT COST GUIDE

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

79

134

134

220

220

>

HARD COST

617

773

773

1,369

1,369

>

FURNITURE

85

168

168

693

693

>

TOTAL FIT OUT COST

782

1075

1,075

2,282

2,282

>

BASIC

MEDIUM

HIGH

SOFT COST

7%

6%

10%

HARD COST

57%

34%

60%

FURNITURE

8%

7%

30%

TOTAL FIT OUT COST

73%

47%

100%


BRAZIL TRADITIONAL FIT-OUT COST GUIDE

SÃO PAULO, RIO DE JANEIRO, CURITIBA & BELO HORIZONTE

FEATURES

COST BREAKDOWN

BELO HORIZONTE

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

55

85

85

170

>

170

HARD COST

535

625

625

1,430

>

1,430

FURNITURE

160

255

255

290

>

290

TOTAL FIT OUT COST

750

965

965

1,890

>

1,890

BASIC

MEDIUM

HIGH

SOFT COST

6%

9%

9%

HARD COST

55%

65%

76%

FURNITURE

17%

26%

15%

TOTAL FIT OUT COST

78%

100%

100%

AGILE FIT-OUT COST GUIDE FEATURES

SÃO PAULO

RIO DE JANEIRO

COST BREAKDOWN

CURITIBA

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

55

85

85

180

>

180

HARD COST

520

570

570

1,360

>

1,360

FURNITURE

210

320

320

475

>

475

TOTAL FIT OUT COST

785

975

975

2,015

>

2,015

BASIC

MEDIUM

HIGH

SOFT COST

6%

9%

9%

HARD COST

53%

58%

67%

FURNITURE

22%

33%

24%

TOTAL FIT OUT COST

100%

100%

100%

CBRE PROJECT MANAGEMENT

14


CHILE SANTIAGO

TRADITIONAL FIT-OUT COST GUIDE FEATURES

COST BREAKDOWN

SANTIAGO

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

85

120

120

220

>

220

HARD COST

490

535

535

770

>

770

FURNITURE

175

215

215

335

>

335

TOTAL FIT OUT COST

750

870

870

1,325

>

1,325

BASIC

MEDIUM

HIGH

SOFT COST

11%

14%

17%

HARD COST

65%

61%

58%

FURNITURE

23%

25%

25%

TOTAL FIT OUT COST

100%

100%

100%

AGILE FIT-OUT COST GUIDE

COST BREAKDOWN

FEATURES

15

LATAM FIT-OUT COST GUIDE

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

90

125

125

220

>

220

HARD COST

470

515

515

620

>

620

FURNITURE

235

265

265

465

>

465

TOTAL FIT OUT COST

795

905

905

1,305

>

1,305

BASIC

MEDIUM

HIGH

SOFT COST

11%

14%

17%

HARD COST

59%

57%

48%

FURNITURE

30%

29%

36%

TOTAL FIT OUT COST

100%

100%

100%


COLOMBIA BOGOTA & MEDELLIN

TRADITIONAL FIT-OUT COST GUIDE FEATURES

COST BREAKDOWN

MEDELLIN

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

115

150

150

195

>

195

HARD COST

390

495

495

810

>

810

FURNITURE

125

190

190

225

>

225

TOTAL FIT OUT COST

630

835

835

1,230

>

1,230

BASIC

MEDIUM

HIGH

SOFT COST

18%

18%

16%

HARD COST

62%

59%

66%

FURNITURE

20%

23%

18%

TOTAL FIT OUT COST

100%

100%

100%

AGILE FIT-OUT COST GUIDE FEATURES

COST BREAKDOWN

BOGOTA

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

120

150

150

210

>

210

HARD COST

375

470

470

770

>

770

FURNITURE

175

225

225

335

>

335

TOTAL FIT OUT COST

670

845

845

1,315

>

1,315

BASIC

MEDIUM

HIGH

SOFT COST

18%

18%

16%

HARD COST

56%

55%

59%

FURNITURE

26%

27%

25%

TOTAL FIT OUT COST

100%

100%

100%

CBRE PROJECT MANAGEMENT

16


COSTA RICA SAN JOSE

TRADITIONAL FIT-OUT COST GUIDE FEATURES

COST BREAKDOWN

SAN JOSE

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

90

120

100

120

>

150

HARD COST

410

550

570

650

>

800

FURNITURE

150

180

190

230

>

250

TOTAL FIT OUT COST

650

850

860

1,000

>

1,200

BASIC

MEDIUM

HIGH

SOFT COST

14%

12%

13%

HARD COST

65%

65%

67%

FURNITURE

21%

23%

21%

TOTAL FIT OUT COST

100%

100%

100%

AGILE FIT-OUT COST GUIDE

COST BREAKDOWN

FEATURES

17

LATAM FIT-OUT COST GUIDE

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

95

126

105

126

>

158

HARD COST

431

578

599

683

>

840

FURNITURE

158

189

200

242

>

263

TOTAL FIT OUT COST

683

893

903

1,050

>

1,260

BASIC

MEDIUM

HIGH

SOFT COST

14%

12%

13%

HARD COST

65%

65%

67%

FURNITURE

21%

23%

21%

TOTAL FIT OUT COST

100%

100%

100%


MEXICO MEXICO CITY, GUADALAJARA, MONTERREY & QUERETARO

TRADITIONAL FIT-OUT COST GUIDE FEATURES

COST BREAKDOWN

MONTERREY

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

102

121

122

182

183

>

HARD COST

445

558

559

840

841

>

FURNITURE

182

223

224

286

287

>

TOTAL FIT OUT COST

729

902

905

1,309

1,309

-

BASIC

MEDIUM

HIGH

SOFT COST

14%

13%

14%

HARD COST

62%

62%

64%

FURNITURE

25%

25%

22%

TOTAL FIT OUT COST

100%

100%

100%

AGILE FIT-OUT COST GUIDE GUADALAJARA

FEATURES

QUERETARO

COST BREAKDOWN

MEXICO CITY

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

102

132

133

203

204

>

HARD COST

445

564

565

852

853

>

FURNITURE

182

185

186

297

298

>

TOTAL FIT OUT COST

729

882

885

1,352

1,355

>

BASIC

MEDIUM

HIGH

SOFT COST

14%

15%

15%

HARD COST

61%

64%

63%

FURNITURE

25%

21%

22%

TOTAL FIT OUT COST

100%

100%

100%

CBRE PROJECT MANAGEMENT

18


GUATEMALA GUATEMALA

TRADITIONAL FIT-OUT COST GUIDE FEATURES

COST BREAKDOWN

GUATEMALA

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

66

99

100

124

125

225

HARD COST

650

849

850

1,349

1,350

2,350

FURNITURE

150

199

200

349

350

850

TOTAL FIT OUT COST

866

1,147

1,150

1,822

1,825

3,425

BASIC

MEDIUM

HIGH

SOFT COST

82

112

175

HARD COST

750

1,100

1,850

FURNITURE

175

275

600

1,006

1,486

2,625

TOTAL FIT OUT COST

AGILE FIT-OUT COST GUIDE

COST BREAKDOWN

FEATURES

19

LATAM FIT-OUT COST GUIDE

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

66

99

100

124

125

225

HARD COST

450

584

585

749

750

950

FURNITURE

125

184

185

199

200

450

TOTAL FIT OUT COST

641

867

870

1,072

1,075

1,625

BASIC

MEDIUM

HIGH

SOFT COST

82

112

175

HARD COST

517

667

850

FURNITURE

155

192

325

TOTAL FIT OUT COST

754

971

1,350


PANAMA PANAMA

TRADITIONAL FIT-OUT COST GUIDE FEATURES

PANAMA

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

90

120

120

165

>

165

HARD COST

710

900

900

1,285

>

1,285

FURNITURE

200

280

280

400

>

400

1,000

1,300

1,300

1,850

>

1,850

TOTAL FIT OUT COST

COST BREAKDOWN

BASIC

BASIC

MEDIUM

HIGH

SOFT COST

9%

9%

9%

HARD COST

71%

69%

69%

FURNITURE

20%

22%

22%

TOTAL FIT OUT COST

100%

100%

100%

AGILE FIT-OUT COST GUIDE FEATURES

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

95

125

125

170

>

170

HARD COST

680

850

850

1,225

>

1,225

FURNITURE

275

345

345

550

>

550

1,050

1,320

1,320

1,945

>

1,945

TOTAL FIT OUT COST

COST BREAKDOWN

BASIC

BASIC

MEDIUM

HIGH

SOFT COST

9%

9%

9%

HARD COST

65%

64%

63%

FURNITURE

26%

26%

28%

TOTAL FIT OUT COST

100%

100%

100%

CBRE PROJECT MANAGEMENT

20


PERU LIMA

TRADITIONAL FIT-OUT COST GUIDE FEATURES

COST BREAKDOWN

LIMA

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

25

50

45

130

>

135

HARD COST

400

420

570

480

>

600

FURNITURE

80

65

170

100

>

205

TOTAL FIT OUT COST

505

535

785

710

>

940

BASIC

MEDIUM

HIGH

SOFT COST

9%

18%

14%

HARD COST

79%

68%

64%

FURNITURE

12%

14%

22%

TOTAL FIT OUT COST

100%

100%

100%

AGILE FIT-OUT COST GUIDE

COST BREAKDOWN

FEATURES

21

LATAM FIT-OUT COST GUIDE

BASIC

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

26

53

47

137

>

142

HARD COST

420

441

599

504

>

630

FURNITURE

84

68

179

105

>

215

TOTAL FIT OUT COST

530

562

824

746

>

987

BASIC

MEDIUM

HIGH

SOFT COST

9%

6%

14%

HARD COST

79%

73%

64%

FURNITURE

12%

22%

22%

TOTAL FIT OUT COST

100%

100%

100%


TRINIDAD TRADITIONAL FIT-OUT COST GUIDE

PUERTO ESPAÑA

FEATURES

PUERTO ESPAÑA

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

161

211

211

250

>

250

HARD COST

1,300

1,700

1,700

2,000

>

2,000

FURNITURE

150

200

200

250

>

250

1,611

2,111

2,111

2,500

>

2,500

TOTAL FIT OUT COST

COST BREAKDOWN

BASIC

BASIC

MEDIUM

HIGH

SOFT COST

10%

10%

10%

HARD COST

81%

81%

81%

FURNITURE

9%

9%

9%

100%

100%

100%

TOTAL FIT OUT COST

AGILE FIT-OUT COST GUIDE FEATURES

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

162

213

213

253

>

253

HARD COST

1,235

1,615

1,615

1,900

>

1,900

FURNITURE

225

300

300

375

>

375

1,622

2,128

2,128

2,528

>

2,528

TOTAL FIT OUT COST

COST BREAKDOWN

BASIC

BASIC

MEDIUM

HIGH

SOFT COST

10%

10%

10%

HARD COST

76%

76%

76%

FURNITURE

14%

14%

14%

TOTAL FIT OUT COST

100%

100%

100%

CBRE PROJECT MANAGEMENT

22


BARBADOS BRIDGETOWN

TRADITIONAL FIT-OUT COST GUIDE FEATURES

BRIDGETOWN

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

178

228

228

278

>

278

HARD COST

1,400

1,800

1,800

2,200

>

2,200

FURNITURE

200

250

250

300

>

300

1,778

2,278

2,278

2,778

>

2,778

TOTAL FIT OUT COST

COST BREAKDOWN

BASIC

BASIC

MEDIUM

HIGH

SOFT COST

10%

10%

10%

HARD COST

79%

79%

79%

FURNITURE

11%

11%

11%

TOTAL FIT OUT COST

100%

100%

100%

AGILE FIT-OUT COST GUIDE FEATURES

COST BREAKDOWN

LATAM FIT-OUT COST GUIDE

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

181

232

232

282

>

282

HARD COST

1,330

1,710

1,710

2,090

>

2,090

FURNITURE

300

375

375

450

>

450

1,811

2,317

2,317

2,822

>

2,822

TOTAL FIT OUT COST

23

BASIC

BASIC

MEDIUM

HIGH

SOFT COST

10%

10%

10%

HARD COST

73%

74%

74%

FURNITURE

17%

16%

16%

TOTAL FIT OUT COST

100%

100%

100%


CAYMAN TRADITIONAL FIT-OUT COST GUIDE

GEORGE TOWN

FEATURES

GEORGE TOWN

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

222

272

272

311

>

311

HARD COST

1,800

2,200

2,200

2,500

>

2,500

FURNITURE

200

250

250

300

>

300

2,222

2,722

2,722

3,111

>

3,111

TOTAL FIT OUT COST

COST BREAKDOWN

BASIC

BASIC

MEDIUM

HIGH

SOFT COST

10%

10%

10%

HARD COST

81%

81%

81%

FURNITURE

9%

9%

9%

100%

100%

100%

TOTAL FIT OUT COST

AGILE FIT-OUT COST GUIDE FEATURES

MEDIUM

HIGH

USD PER SQM

USD PER SQM

USD PER SQM

SOFT COST

223

273

273

313

>

313

HARD COST

1,710

2,090

2,090

2,375

>

2,375

FURNITURE

300

375

375

450

>

450

2,233

2,738

2,738

3,138

>

3,138

TOTAL FIT OUT COST

COST BREAKDOWN

BASIC

BASIC

MEDIUM

HIGH

SOFT COST

10%

10%

10%

HARD COST

77%

76%

76%

FURNITURE

13%

14%

14%

TOTAL FIT OUT COST

100%

100%

100%

CBRE PROJECT MANAGEMENT

24


Fran

1

kfur t

1.98

2.50

0.9

1.9

2

Sea

2

8

1.50

ic o C i ty

1.80

1.00

Mex

ttl e

1.8

2.00

0.9

mb ai

San Fra

o

Pari

Dall as

1.18

1.00

CBRE leads the market in benchmarking the trends amongst progressive corporations who have recognised Space-as-a-Service as a requirement to Buenos Aires achieve the goals of corporate strategies. A key trend identified is the larger portions of capital expenditure demanded for technology to support the development of smart offices. The modern workforce expects an po re Singa equally modern office to optimise productivity. This is fast becoming a focus for companies to attract and retain talent.

0.50

1.68 1.6 2

4 1.3

Syd

i gha

1.3

nta

Paulo

o ng

SĂŁ o

gK

Madrid

Hon

1.43

1.57

on

1.38

Lond

LATAM FIT-OUT COST GUIDE

1.36

Dublin

25

1

1.6

5

Atla

n Sh a

1.63

1.24

The Global Index presented is a guide only. For budget estimates on specific projects, please contact the CBRE Project Management Division lead from the relevant market who can provide you with relevant and accurate information.

To kyo

0

1.20

We will continue to discuss technology & the evolution of office space and its impact in a separate column of the cost guide.

s

1.74

The risks associated with uncertainly can be somewhat mitigated in corporate real estate investments through robust benchmarking which includes 7 categories of capital cost in 23 key global markets.

Mu

2.09

0.90

otĂĄ Bo g

The tariffs that countries slap on each other are further compounded by escalating unpredictability in foreign exchange. The result of the uncertainty has driven what has been an experiment in the use of co-working space to a legitimate corporate real estate strategy.

New York

Santiag

Trade wars have become synonymous with uncertainty. What started off between the US and China has now escalated to include Europe. In what was unthinkable 2 years ago, Manufacturing industries are starting to leave China in what could create a domino effect on other industries.

nc is co

FIT-OUT COST INDEX | LATAM

ne y

Chicago

Jo han n

es bur g


CBRE PROJECT MANAGEMENT

26


TECHNOLOGY AND THE EVOLUTION OF OFFICE SPACE A digitally enabled office is no longer the domain of tech giants, but of businesses across all sectors. Companies must accept that what was once optional, is now inevitable. Office space is now a service, made to fit business strategies where productivity is synonymous with technology enabled collaboration, and employees demand modern conveniences and seamless technology integration so they can focus on the tasks at hand. Driving this technology investment shift is the demand for a unified visual display and communication platform. To collaborate, people need places to connect. However this is a fundamental need and employees are demanding more from their workplace; they expect high-speed Wi-Fi, wireless charging, personalisation, online room booking, environmental controls and so on, hence companies evolving to deliver these in order to attract and retain talent. As a result, 70% of companies plan to increase investment in real estate technology within the next three years, and 30% see smart building technology as a factor in choosing a building. Investment in workplace technology was growing steadily for several years until, unexpectedly, in 2018 we saw a doubling of spend in workplace technology. This can be attributed to a combination of increased adoption and implementation of workplace strategy, and environments being designed for collaboration. The technology to create a more efficient workplace is now in our hands, or more accurately, in our smartphones. To achieve

27

LATAM FIT-OUT COST GUIDE

corporate goals, company strategies have to drive the technology which should be designed and oriented to support how we work, how we connect with colleagues, and how to make routine and administrative actions simple, allowing greater productivity. The step-change of unified communication and display technology in commercial offices is just the beginning. Technology enabled devices make it possible to collect data from all aspects of the corporate office, including BMS, security, lighting, meeting rooms and furniture to name a few. All are sources of data; however, it is not until information is analysed and used properly that it benefits people and the business. In smart offices, data can and is being collected to help create a more efficient workplaces and reduce carbon footprints. Strategies to achieve business goals are being rewritten. The goals of productivity and profitability remain; however, the journey and the platform to achieve these are changing. Companies are asking: What does "smart" building mean for me? What does "smart" office mean for my business? What is our "smart" vision and how does this support our corporate strategies? Answering these questions and developing a technology brief that supports corporate strategies will provide the basis for developing “space as a service” and the journey towards developing a suitable smart office.

The commercial office industry is recognising technology as a core requirement of an attractive, collaborative work environment. Due to the criticality of integrated technologies and smart workplaces, there's an increasing demand for project management teams with the right technical skillset to get the brief, budget, design and implementation right. This is important when a “result-oriented workforce” demands a superior knowledge-based work environments that improve productivity and allow connection, collaboration and inspiration. These effects also reach landlords who want to have desirable assets. Demands have evolved from sustainable and green buildings to providing infrastructure to accommodate smart offices. We are transitioning to a new office experience that demands an evolution of the standard commercial building and transformation of our physical space.


TRADITIONAL AV SPECIFICATION DESCRIPTION Space type

Basic

Medium

AGILE AV SPECIFICATION DESCRIPTION High

Space type

Basic

Medium

High

Reception area

Company information or brand specific content displayed on LED signage screen

Multiple LED screens displaying specifically developed content

Video wall or bespoke AV installation providing bespoke or real-time information specific to client brand

Reception area

Company information or brand specific content displayed on LED signage screen

Multiple LED screens displaying specifically developed content

Video wall or bespoke AV installation providing bespoke, interactive or realtime information specific to client brand

Desk area

No AV

TV screen fed direct from building TV distribution

TV/signage screen fed from client IPTV or signage system

Desk area

No AV

TV screen fed direct from building TV distribution

Lift lobby

No AV

TV screen fed direct from building TV distribution

TV/signage screen fed from client IPTV or signage system

TV/signage screen fed from client IPTV or signage system

Lift lobby

No AV

Large meeting rooms

Single LED screen with wired presentation facilities and a desktop conference phone

Dual LED screen with the addition of wireless presentation system, touch screen controls and built in audio conferencing with ceiling speakers

As per the medium specification with the addition of HD video conferencing and interactive collaboration tools such as touch screen LED screens

TV screen fed direct from building TV distribution

TV/signage screen fed from client IPTV or signage system

Large meeting rooms

Single LED screen with wired presentation facilities and a desktop conference phone

Single LED screen with wired presentation facilities and an IP conference phone

Single LED screen with wireless presentation facilities and an IP conference phone

Interactive touch screen with wireless presentation and IP conference phone and VC camera

Dual LED screen with the addition of wireless presentation system, touch screen controls and built in audio conferencing with ceiling speakers

As per the medium specification with the addition of HD video conferencing and interactive collaboration tools such as interactive touch screen LED screens

Medium meeting room

Small meeting rooms

No AV

IP desk phone

IP desk phone and VC camera

Single LED screen with wired presentation facilities and an IP conference phone

Single LED screen with wireless presentation facilities and an IP conference phone

Interactive screen with wireless presentation and IP conference phone and VC camera

Comms room

Centralised AV equipment

Centralised AV equipment

Centralised AV equipment

Small meeting rooms

No AV

IP desk phone

IP desk Phone and VC camera

Informal meeting spaces

No AV

Content sharing screens

Content sharing and collaboration screens

Alternative workspaces

Large LED screen with wireless presentation wipe clean whiteboard

Wireless presentation to large LED Screen, video and audio conference enabled

Interactive whiteboard, LED screen and collaboration facilities with immersive features

Comms room

Centralised AV equipment

Centralised AV equipment

Centralised AV equipment

Medium meeting room

These technology benchmarks are in line with the specifications outlined in this guide for a 1,000 sq m fit-out. Please note that import taxes may be applicable and actual client requirements can vary and may sit outside of these benchmark ranges depending on specific technology requirements and size of fit-out.

CBRE PROJECT MANAGEMENT

28


29

LATAM FIT-OUT COST GUIDE


SECURITY Tenant security systems typically consist of two main elements, electronic access control and CCTV.

opportunities to streamline system administration and enhance the visitor management process.

These systems monitor the point of entry into the tenant’s office demise and to secure areas such as the IT comms room, high value storage or the HR office. In a multi tenanted building the landlord will have already installed security systems managing access and monitoring for the main building entrances and common areas. The security system can operate standalone within the tenant demise or be interfaced with a compatible landlord system, which provides

Both CCTV and access control systems will typically be Internet Protocol (IP) based, meaning they connect over the structured cabling and network infrastructure. This deployment methodology removes the requirement for multiple types of cabling. This provides opportunities to interface the security systems with any other IP based systems to create workflows, collate data and cause and effect based outcomes which is the basis for starting to create a ‘Smart Building’.

The management interface for security systems will be accessible over the network or consolidated to view alongside other building systems.

IT Tenants’ IT installations typically include structured cabling, and wired and wireless network equipment. Monitors and desk phones are considered user’s equipment and typically don’t sit within the fit-out budget; however, the placement of these components is essential to any workplace strategy. Clients’ existing equipment may not enable changes in the working styles and practices, which are often the driving force behind office relocations, so proper advice should be taken on how to engage with the latest technology early in the planning stages. Wi-Fi technology is sufficiently reliable as a primary method of connectivity for user devices within an agile working environment, but there will always be a requirement for a structured cabling system. This will typically be installed

within the raised floor and ceiling void to provide connection for fixed IT, AV, security and any other IP based products. The growth in integrated and smart buildings is motivating an increase in IP devices that are network connected, this will need to be given due consideration when producing technology budgets. Although additional IT infrastructure is required to support these systems, this is offset by savings in other packages. As more systems become IP-based, the reliance on connectivity to the Local Area Network (LAN) means that new switches and firewalls are typically procured rather than relocated during an office move. One of the drivers for this is that contractors are reliant on network connectivity to commission IP-based building systems.

Wireless access points installed within or beneath the ceiling void will provide users with connectivity to the Internet and the ability to work anywhere within the office. Full Wi-Fi coverage within the office is a key requirement for agile and traditional office working environments. It is critical that IT budgeting is considered early in the project and with a holistic view in order to achieve the savings that smart building technology, the Internet of Things (IoT) and systems convergence can offer.

CBRE PROJECT MANAGEMENT

30


FURNITURE As employers grapple with rising healthcare costs an area historically often overlooked as contributing to employee health and well-being is the workplace. Aside from lunchtime yoga and salads on the cafeteria menu, the approach to well-being at work often fails to look at the bigger picture and address the underlying issues that contribute to poor health: a sedentary lifestyle and work-related stress.

SO HOW CAN A BUILDING MAKE PEOPLE HEALTHIER? NUDGE BETTER BEHAVIOURS

REDUCE STRESS LEVELS

GIVE EMPLOYEES CONTROL

With training in psychology and architecture, Haworth’s Dr. Michael O’Neill has spent decades researching the connection between buildings, worker health and performance. O’Neill advocates for a combination of “nudges” and “micro-controls” that help employees make better decisions.

Beyond movement and healthier choices, the interior design of a building can play a role in reducing stress, the single biggest enemy of wellbeing. A person’s body reacts automatically to stressful events, like deadlines and production pressures, by releasing hormones into the bloodstream.

Research has shown that an additional way to reduce workplace stress is to give people control over their physical workspace.

A nudge is never about taking choice away from somebody. It’s about making the best obvious and easy choice. One way to nudge people to make a healthier choice is by encouraging them to ditch the lift in favour of climbing stairs.

The most dangerous is cortisol, part of the body’s natural fight-or-flight mechanism. Elevated cortisol levels are tied to a host of health issues, from heart disease to lower cognitive abilities. Providing opportunities to connect to nature in the workplace can help. Studies have shown that taking at least 20 minutes out of your day to stroll or sit in a place that makes you feel connected with nature will significantly lower stress hormone levels.

A Harvard study found that taking eight flights of stairs a day lowers average early mortality risk by 33 percent. The key is making the staircase a central element in the building, so people are drawn to take the steps.

31

LATAM FIT-OUT COST GUIDE

At the individual level, it can involve letting people choose a space for the task at hand, so they can do their best individual work and or providing furnishings that can be moved to adjust to someone’s body or workstyle. Giving workers power over small adjustments in their individual work environment ultimately allows them more control over their work process. At the organizational level, create policies and a culture that gives employees permission to choose a range of workspaces that best meets their needs.


Approximate lead time for furniture deliver.

THE APPROXIMATE DELIVERY TIME IS: CHAIRS Country

WORKSTATIONS

CARPET

Imported

National

Imported

National

Imported

National

Sum of the regular Tax

Argentina

120+

60

180

60

60

0

16%

Bahamas

90

30

90

0*

75

0*

7%

Barbados

90

45

120

30

70

30

12%

120

45

120

45

120

45

19%

Cayman Islands

60

0*

90

45

90

0*

19%

Chile

45

30

60

0*

45

0*

22%

Colombia

60

0*

90

45

90

60

19%

Costa Rica

60

0*

60

45

60

30

16%

Ecuador

45

30

75

30

60

30

45%

Guadalajara

60

0

45

30

60

N/A

18%

Guatemala

60

0*

90

45

90

30

12%

Mexico City

60

0

45

30

45

N/A

35%

Monterrey

60

0

45

30

120

N/A

25%

Panama

60

0*

90

45

100

45

20%

Peru

75

0*

75

45

60

30

13%

Queretaro

60

0

45

30

45

N/A

30%

Trinidad & Tobago

90

45

90

120

45

0*

35%

Turks & Caicos Islands

90

30

120

60

60

30

16%

Venezuela

30

120

30

45

60

45

16%

Brazil

*Subject to stock availability, otherwise 60 days

CBRE PROJECT MANAGEMENT

32


PROCUREMENT & PROGRAMME Understanding how a project will be procured and how long it will take by identifying the key milestones is critical to developing an accurate business case. There can be significant variances in in lead times and task durations from one country to the next. This can have a material impact on the viability of a business case and ultimately the decision on whether to proceed with a project. Depending on the location in question, key parameters to consider include: local standards, procurement strategy, statutory approvals and regulations, lead time, importation, religious festivals and public holidays, as well as internal client approvals and sign-off gateways. This local understanding may prompt a review of a project’s procurement of phasing strategy to maintain and achieve the desired programme, whilst minimising any impact on a client’s core business.

33

LATAM FIT-OUT COST GUIDE

While furniture is often seen as a small part of the overall project, it typically has a major impact on end user satisfaction, so it is important to understand furniture lead times and any import restrictions and to allow for these in the programme. The impact of Brexit is still unclear and extra consideration may need to be given to projects in the UK. Products are often sourced from across the EMEA region and new restrictions may have a tangible impact on lead times and budgets.

PROCUREMENT ROUTES

It is also important to consult IT, Security and AV teams so that install, testing and commissioning periods can be programmed in line with the desired completion date.

DESIGN AND BUILD • Tender documents outlining employers requirements, prepared by client/consultant team usually in the form of a brief, i.e. performance criteria • Single contractor appointed and contributes specialist knowledge into design process • Contractor has full design responsibility • Design and construction can occur concurrently

It is recommended to obtain professional programme advice as early as possible in order to give a client the maximum choice regarding the delivery strategy. This advice may come from a programme manager at the initial capital planning stage, or a local project manager who can support the transaction team when developing business case strategies. CBRE’s specialists in programme and project teams across EMEA have provided information relating to the key milestones of our medium specification 1,000 sq m fit0out project. The graph overleaf illustrates the typical timeframes for completing the fit-out using the most common procurement route in each location.

TRADITIONAL • Consultant team appointed by client and prepares fully detailed drawings, specification and pricing documents • Client retains the design risk • Contractor’s Design Portion can be incorporated • Tendered on construction stage design information

CONSTRUCTION MANAGEMENT • Client procures design as per the traditional route • Construction manager appointed to coordinate trade contractors • Trade contracts let on a package by package basis • Client generally retains design and construction risk • Design and construction can occur concurrently


FIT OUT COST GUIDE FIT OUT COST GUIDE

COMMON DATA ANALYSIS COMMON DATA ANALYSIS

1000 SQ.M. PROJECT – TIMELINE IN WEEKS 1000 SQ.M. PROJECT – TIMELINE IN WEEKS 0 10 20 30 40 0

10

20

30

ARGENTINA ARGENTINA12 WEEKS

40

DESIGN

50

60 50

0

70 60

10

26 WEEKS

100

50

5 WEEKS 13 WEEKS 18 WEEKS

24 WEEKS

TURKS & CAICOS ISLANDS

12 WEEKS 14 WEEKS 12 WEEKS 14 WEEKS

12 WEEKS 18 WEEKS

26 WEEKS

30 WEEKS

26 WEEKS 12 WEEKS 11 WEEKS 12 WEEKS 11 WEEKS

BAHAMAS 11 WEEKS 15 WEEKS 28 WEEKS

23 WEEKS 23 WEEKS

BARBADOS 11 WEEKS 15 WEEKS

16 WEEKS 14 WEEKS 16 WEEKS 14 WEEKS

26 WEEKS 30 WEEKS 30 WEEKS

TRINIDAD & TOBAGO 11 WEEKS 15 WEEKS

COSTA RICA 10 WEEKS COSTA RICA

14 WEEKS 10 WEEKS 14 WEEKS

26 WEEKS 24 WEEKS

MEXICO CITY

24 WEEKS

11 WEEKS 15 WEEKS

CAYMAN ISLANDS 10 WEEKS CAYMAN ISLANDS

26 WEEKS

12 WEEKS 10 WEEKS 12 WEEKS 22 WEEKS 22 WEEKS

GUATEMALA 3 WEEKS GUATEMALA

QUERÉTARO 11 WEEKS 15 WEEKS 26 WEEKS

GUADALAJARA

12 WEEKS WEEKS 1215 WEEKS

11 WEEKS 15 WEEKS

15 WEEKS

26 WEEKS

COLOMBIA COLOMBIA11 WEEKS

13 WEEKS 11 WEEKS 13 WEEKS

MONTERREY 24 WEEKS 24 WEEKS

26

40

24 WEEKS

24 WEEKS

3 WEEKS

30

100 90

PERÚ

14 WEEKS 10 WEEKS 14 WEEKS

BRAZIL BRAZIL

80

20

TOTAL

90

10 WEEKS 14 WEEKS

26 WEEKS

VENEZUELA 10 WEEKS VENEZUELA

ECUADOR ECUADOR

80 70

TOTAL

CONSTRUCTION

PANAMA

14 WEEKS 12 WEEKS 14 WEEKS

CHILE CHILE

CONSTRUCTION

DESIGN

11 WEEKS 15 WEEKS 26 WEEKS

LATAM FIT-OUT COST GUIDE

26

LATAM FIT-OUT COST GUIDE

CBRE PROJECT MANAGEMENT

34


WORKPLACE TRENDS AND COMMON PRACTICES Perhaps not unexpectedly, the greatest challenge facing building occupiers over the last 12 months has been economic uncertainty. This is particularly true for those in the Professional Services industry, although challenges vary across different sectors: Technology Companies are most concerned with workforce/talent preferences, whereas in the Banking & Finance sector the main challenge is technology disruption (large year’s overall greatest challenge) and for Life Sciences the main concern is tighter regulation or legislation.

35

LATAM FIT-OUT COST GUIDE

Last year, cost-reduction was the single most important driver of CBRE clients’ strategy. This year cost reduction has dropped, employee engagement, talent attraction and development have risen. In short, people are becoming an increasingly important consideration. It looks increasingly as though buildings that offer an adaptable mix of fit-out types, traditional vs. flexible space, diverse working environments, price points and amenity & tech enablement will compete best for occupiers. There is continued growth in corporate demand for flexible space, with companies expecting to make significant use of it the next three years. While cost reduction and accommodating short-term demand, increases are still the main motives, the use of flexible space as a way of attracting and retaining talent is ten percentage is higher than a year ago. In other words, companies increasingly view flexible space as a way of supporting their talent agenda, and in many cases, are still at an experimental stage of deciding the best approach to the issue.


CBRE PROJECT MANAGEMENT

36


LOCATION

FLOOR OCCUPANCY RATE (square meters per person)

Argentina

8

Bahamas

10

Barbados

15

Brazil

7

Cayman Islands

7

Chile

10

Colombia

8

Costa Rica

6

Ecuador

10

Guadalajara

9

Guatemala

9

Mexico City

11

Monterrey

11

Panama

10

Peru

8.5

Queretaro

11

Trinidad & Tobago

15

Turks & Caicos Islands

10

Venezuela

16

37

LATAM FIT-OUT COST GUIDE

The most common practice to determine

floor occupancy is to have it be dictated by the Municipality in accordance with slab area, floor height and staircase width


CONDITIONS SPACE BEFORE INTERVENTION CONDITIONS

ELECTRICITY CONDITIONS

BASE BUILDING ELECTRICITY DELIVERY RATE

POWER GENERATOR SERVES

Core & Shell

220-240

Argentina

Peru

50 Watts per square meter

Brazil

Argentina

Argentina

Both are applicable. 3A Buildings normally offers power generator for common and internal areas.

Barbados

Brazil

Bahamas

Brazil

Cayman Islands

Common and internal areas in the office.

Cayman Islands Chile Colombia Costa Rica Ecuador Guadalajara Mexico City Monterrey Peru Queretaro Trinidad & Tobago Warm Shell

Generally delivered to floors at 110–120 volts Guadalajara Queretaro Bahamas Barbados Cayman Islands Colombia Ecuador Trinidad & Tobago

Chile Colombia Costa Rica Ecuador Guadalajara Guatemala Monterrey

Panama Turks & Caicos Islands

Cayman Islands Colombia Guatemala Trinidad & Tobago

Queretaro

Common areas only, including elevator/lifts/escalators.

Turks & Caicos Islands

Argentina Chile

Turks & Caicos Islands

80 per SQM

Venezuela

Costa Rica

Mexico City

Ecuador

Generally delivered to floors at 110–240 volts.

Varies. There is no

Bahamas Guatemala

Barbados

Chile Costa Rica Guatemala Mexico City Monterrey Panama

standard defined Barbados Brazil Panama

Guadalajara Mexico City Monterrey Panama Peru Queretaro

Peru

Depends on building

Trinidad & Tobago

Bahamas

Venezuela

Turks & Caicos Islands

Only the 10% of the building in Caracas have power generator.

CBRE PROJECT MANAGEMENT

38


LEASE LEASE ADJUSTMENT RATE Chile uses UF as a currency which changes daily responding to inflation.

LEASE PERIOD LENGHT

LEASE ADJUSTMENT RATE

3 years

Annually

Argentina

Argentina

Bahamas

Barbados

Barbados

Brazil

Argentina

Costa Rica

Cayman Islands

Bahamas

Guadalajara

Chile

Barbados

Monterrey

Colombia

Brazil

Queretaro

Costa Rica

Colombia

Trinidad & Tobago

Ecuador

Costa Rica

Turks & Caicos Islands

Guadalajara

Ecuador

Venezuela

Guatemala

Guadalajara

5 years

Mexico City

Guatemala

Brazil

Monterrey

Mexico City

Cayman Islands

Panama

Monterrey

Chile

Peru

Panama

Colombia

Queretaro

Peru

Ecuador

Trinidad & Tobago

Queretaro

Guatemala

at renewal

Trinidad & Tobago

Mexico City

Bahamas

Turks & Caicos Islands

Panama

Turks & Caicos Islands

Venezuela

Peru

Monthly

Landlord decides

Cayman Islands

Venezuela

Chile Is agreed between both parties and set on lease contract

Cayman Islands

Lease adjustment rate

Location

Lease period

Location

Annually

16

3 years

10

at renewal

2

5 years

9

Monthly

1

The types of contract depend on the area rented, the agreements reached after commercial negotiations with the landlord, and the local market's current situation.

39

LATAM FIT-OUT COST GUIDE

Available

Available

HVAC - Class B buildings

HVAC - Class B buildings


RESTORATIONS Tenant must completely restore the space back to original conditions, including installation removals Argentina Bahamas Brazil Cayman Islands Colombia Costa Rica Ecuador Peru Turks & Caicos Islands Tenant must restore the space back to original conditions, no installation removals Chile Guatemala Panama The space will be return in good state of conservation, any refurbishing will be property of the landlord at the end of the contract. Venezuela Can be responsibility of either the landlord or tenant, but ultimately it's the landlord's prerogative to decide whether to keep some of the improvements made before. Barbados Trinidad & Tobago No obligations identified in lease contract. Guadalajara Mexico City Monterrey Queretaro

CBRE PROJECT MANAGEMENT

40


CHARGES CONDOMINIUM CHARGES

TENANT IMPROVEMENT ALLOWANCE

CCTV on all public areas, lighting in all public areas, cleaning for all public areas, elevators/lifts maintenance, power generator manteinance and/or fuel

A common practice.

Costa Rica

Bahamas

CCTV on all public areas, lighting in all public areas, cleaning for all public areas, elevators/lifts maintenance, power generator use, power generator manteinance and/ or fuel, facade cleaning of windows and glazing from outside of the building, security

Cayman Islands

Panama CCTV on all public areas, lighting in all public areas, cleaning for all public areas, water (fornecimento), elevators/lifts maintenance, power generator use, power generator manteinance and/or fuel, facade cleaning of windows and glazing from outside of the building, security

Chile Turks & Caicos Islands Is a common practice. However need approval of the landlord. Venezuela Is lately becoming popular depending on the property and the landlord

Argentina Bahamas

Colombia

Barbados

Not a normal practice. Tenant must perform and pay for all tenant improvement works.

Brazil Chile

Argentina

Colombia

Brazil

Ecuador

Costa Rica

Peru Trinidad & Tobago Turks & Caicos Islands Venezuela CCTV on all public areas, lighting in all public areas, cleaning for all public areas, water (fornecimento), elevators/lifts maintenance, power generator use, power generator manteinance and/or fuel, facade cleaning of windows and glazing from outside of the building, security, landscaping, irrigation

Ecuador Guadalajara Guatemala Mexico City Monterrey Panama

Cayman Islands

Peru

CCTV on all public areas, lighting in all public areas, cleaning for all public areas, water (fornecimento), elevators/lifts maintenance, power generator use, power generator manteinance and/or fuel, facade cleaning of windows and glazing from outside of the building, Security, only for public areas and parking levels.

Queretaro

Guadalajara

Trinidad & Tobago

Guatemala Mexico City Monterrey Queretaro

41

LATAM FIT-OUT COST GUIDE

Varies Barbados


IVA (OR VAT) TAX Is not refundable. Clients usually budget their construction projects at gross price

LOCATION

Brazil

WHAT IS AN USUAL MUNICIPALITY PERMIT APPROVAL TIME FRAME IN YOUR LOCATION, IF THE PROJECT IS LOCATED INSIDE A HISTORICAL AREA?

LOCATION

REGULAR TAX % APPLICABLE ON CONSTRUCTION SERVICES

Argentina

21%VAT (refundable) + 5.5% IIBB (nonrefundable)

Costa Rica

Argentina

Up to 120 days

Ecuador

Bahamas

Up to 120 days

Bahamas

0%

Guadalajara

Barbados

More than 120 days

Barbados

VAT 17.5%

Considering interior fit-out exclusively,

Brazil

15%-20%

historical area is not a restriction.

Cayman Islands

Tax not applicable

Guatemala Mexico City

Brazil

Monterrey

Cayman Islands

More than 120 days

Chile

19%

Panama

Chile

More than 120 days

Colombia

1 -1.5%

Queretaro

Colombia

More than 120 days

Costa Rica

13%

Venezuela

Costa Rica

Up to 120 days

Ecuador

12%

Is refundable, so my clients usually budget their construction projects at Net price

Ecuador

More than 120 days

Guadalajara

16%

Guadalajara

More than 120 days

Guatemala

12%

Guatemala

More than 120 days

Mexico City

16%

Mexico City

N/A

Monterrey

16%

Monterrey

N/A

Panama

7%

Colombia

Panama

More than 6 months, almost a year, depending the kind of proyect.

Peru

18%

Peru

Peru

Up to 120 days

Queretaro

16%

Trinidad & Tobago

Queretaro

N/A

Trinidad & Tobago

VAT 12.5%

Not applicable

Trinidad & Tobago

Up to 120 days

Turks & Caicos Islands

0%

Bahamas

Turks & Caicos Islands

Up to 120 days

Venezuela

25%

Cayman Islands

Venezuela

Up to 120 days

Argentina Barbados Chile

Turks & Caicos Islands Barbados Trinidad & Tobago

CBRE PROJECT MANAGEMENT

42


KEY CONTACTS LATIN AMERICA & CARIBBEAN

COLOMBIA

JUAN ESTEBAN ZABALA Managing Director office: +571 5185292 juan.zabala@cbre.com

FELIPE DEFRANCISCO WIESNER Project Management Director office: +57 1 5185263 felipe.defrancisco@cbre.com

ARGENTINA

COSTA RICA

ANA GONZÁLEZ FERRERO Project Management As. Director office: +54 11 4590 5700 ana.gonzalez2@cbre.com

JEANNETTE JIMÉNEZ Project Manager office: +506 7024 6933 jeannette.jimenez@cbre.com

BRAZIL

MEXICO

HENRIQUE CICCHETTO Project Management Director office: +55 11 5185-4688 henrique.cicchetto@cbre.com.br

OLIVER JAIMES Project Management Director office: 52 (55) 4165 7475 | oliver.jaimes@cbre.com

CHILE KEITH CARRIZO Project Management Director office: +562 2562 2616 keith.carrizo@cbre.com

DISCLAIMER 2019-2020 CBRE CBRE Ltd has taken every care in the preparation of this report. The sources of information used are believed to be accurate and reliable, but no guarantee of accuracy or completeness can be given. Neither CBRE, nor any CBRE company, nor any director, representative or employee of CBRE company, accepts liability for any direct or consequential loss arising from the use of this document or its content. The information and opinions contained in this report are subject to change without notice. No part or parts of this report may be stored in a retrieval system or reproduced or transmitted in reprographics, recording or otherwise, now known or to be devised without prior consent from CBRE.


CBRE PROJECT MANAGEMENT

44


www.cbre.com