JEFF POND AFFORDABLE ALTERNATIVE SIMON TICKELL
PROJECT DELIVERY METHODS OVERVIEW PROJECT DELIVERY METHODS OVERVIEW PROJECT DELIVERY METHODS OVERVIEW PROJECT DELIVERY METHODS OVERVIEW DESIGN BID BUILD tradtional practice DESIGN BID BUILD tradtional practice DESIGN BIDproject BUILD tradtional practiceARCHITECT
Low-Bidder
ARCHITECT
OWNER
OWNER
Best Value
Most Qualified
Procurement Low-Bidder Best Value METHODS Most Qualified PROJECT PROJECT DELIVERY OVERVIEW DELIVERY METHODS OVERVIEW DELIVERY METHODS OVERVIEW delivery overview PROJECT DELIVERY METHODSPROJECT OVERVIEW Low-Bidder Best Value Most Qualified Procurement PROJECT DELIVERY METHODS OVERVIEW Low-Bidder Best Value Most Qualified Lump-Sum GMP Cost+ Procurement
GENERAL CONTRACTOR GENERAL CONTRACTOR GENERAL CONTRACTOR
MOST COMMON
COMMON
MOST COMMON MOST COMMON
ARCHITECT OWNER
DESIGN BUILD
Procurement
COMMON
RARE
COMMON
MOST COMMON
RARE
DESIGN BID BUILD COMMON
ARCHITECT
Compensation
COMMON
RARE
contract with the owner/client provide with the designs for a project. The owner holds a separatetocontract a contractor In the traditional method of practice, an architect is in a project.the Thework owner holds a separate contract a contractor to perform to complete the project; oftenwith for an agreed contract with the owner/client to provide the designs for a perform the work to complete the project; often for upontofee. The owner maintains a fair amount of control as an theagreed project. The owner holds a separate contract with a contractor upon fee.between The owner a fair amount of control ‘go between’ themaintains two contractually separate entities;as the to perform the work tothecomplete the project; often entities; for an agreed between’ contractually separate those‘go building thebetween project and two those providing the information upon building fee. The the owner maintains a fair amountthe of control as the project and those providing information to dothose so.
COMMON
OWNER CONTRACTOR
‘godobetween’ between the two contractually separate entities; to so. those building the project and those providing the information
OWNER
CONTRACTOR
CONTRACTOR
CONTRACTOR
GENERAL CONTRACTOR
* *
Cost+ Compensation RARE-
TEAM
Cost+
COMMON CM as
COMMON
Best Value
Most Qualified
MOST ARCHITECT COMMON
COMMON owner’s agent
Lump-Sum OWNER COMMON
COMMON
COMMON
GMP
Cost+
COMMON
RARE
GENERAL CONTRACTOR
RARE developer
DEVELOP/ DESIGN/BUILD TEAM
PUBLIC ENTITY
In DESIGN BUILD, a team of architects, designers, engineers Public Private and buildersBridging performs service to complete a project from its Partnership inception through to its completion. In this method of practice there is a single contractual relationshipDESIGN/BUILD between the owner/ OWNER
CONTRACTOR CONTRACTOR OWNER
GMP
CONSTRUCTION MANAGER
DESIGN/BUILD TEAM
OWNER
ARCHITECT
CONTRACTOR
ARCHITECT
GENERAL CONTRACTOR
Low-Bidder
Procurement RARE
DESIGN CONSULTANT
In the traditional method of practice, an architect is in a In the CONSTRUCTION MANAGER AT RISK delivery method, a In DESIGN BUILD, a team of architects, designers, engineers CM as owner’s contract with theagent owner/client to provide the designs for a CM serves as an advisor to the owner/client during design but multiple primes and builders performs service to complete a project from its CM as owner’s agent project. The owner holds a separate contractmultiple with a contractor then returns to a more at risk role during construction. Having primes CONSTRUCTION MANAGER
DESIGN/BUILD TEAM DESIGN/BUILD
Lump-Sum
GMP
COMMON
design and construction professionals allows for a streamlined process.
MOST Most QualifiedCOMMON
OWNER
Lump-Sum
Most Qualified
In practices of INTEGRATED PROJECT DELIVERY the interests of all parties are aligned and each are in a relationship with OWNER
CONSTRUCTION MANAGER
DESIGN/BUILD TEAM
as significantly owner’s agent the others. The process for such practices CM bears to do so. Thesis Project Ojectives: through to its completion. In this methodMETHODS of practice PROJECT DELIVERY PROJECT DELIVERY OVERVIEW PROJECT DELIVERY METHODSinception OVERVIEW PROJECT PROJECT DELIVERY DELIVERY METHODS METHODS OVERVIEW OVERVIEW client and the DB team.METHODS This and early collaborationOVERVIEW between to perform the work to complete the project; often for an agreed a CM in this position allows for opportunities to fast-track but on how these agreements are written and the selection of the CONTRACTOR
CONSTRUCTION MANAGER
CONTRACTOR
CM as owner’s agent
_to investigate and identify the tools of the
tradtional practice tradtional practice
architect-led design build practice OWNER
MOST Procurement Procurement COMMON
ARCHITECT
MOST COMMON COMMON
COMMON RARE
OWNER
OWNER
_to identify a problem that can benefit from
Low-Bidder
Lump-Sum Lump-Sum GMP COMMON Compensation Compensation
GMP Cost+
COMMON RARE
GENERAL GENERAL CONTRACTOR CONTRACTOR
Procurement
RARE
OWNER
Lump-Sum
Cost+
RARE RARE CONSTRUCTION MANAGER AT RISK
RARE
RARE
Compensation
COMMON
project. The owner project. holdsThe a separate owner holds contract a separate with a contractor contract with a contractor to perform the work to perform to complete the work thetoproject; complete often theforproject; an agreed often for an agreed upon fee. The owner upon maintains fee. The owner a fair maintains amount ofacontrol fair amount as theof control as the Known from the start, any project will ‘go between’ between ‘go between’ the twobetween contractually the twoseparate contractually entities; entities; need aseparate designer and a builder. Regardlessthe as information to when either party those building the those project building and the those project providing and those the information providing The owner (or in some cases a CM) is brought on to the project, in most to do so. to do so. holds the prime contract for each
Best Value
Most Qualified
MOST COMMON
RARE
CM as owner’s agent
DESIGN/BUILD TEAM GMP COMMON
methods of practice the architect and entity and is ultimately the decision the general contractor hold separate maker, responding to both the contracts with the owner; each with architect and the contractor. a defined scope of work and process of doing things that separtes the two entities. This is the “over-the-wall” method.
CONSTRUCTION MANAGER
CONSTRUCTION MANAGER
ARCHITECT
CONTRACTOR
CONTRACTOR
CONTRACTOR
CONTRACTOR
and sub-contractors as well. This divide has been grown to themultiple point that in todays practices it legal, cultural and at times very adversarial.
CM as owner’sCM agent as owner’s agent
client and the DB team. This and early collaboration between design and construction professionals allows for a streamlined process.
CONTRACTOR
CONTRACTOR
CONTRACTOR
OWNER
CONTRACTOR
Low-Bidder
Bridging
COMMON multiple primes Procurement
Cost+
PUBLIC ENTITY
Best Value
GMP
Cost+
COMMON
RARE
Bridging
Partnership Most Qualified
Best Value
RARE
COMMON
MOST COMMON
GMP
Cost+
RARE
COMMON
Lump-Sum RARE
DEVELOP/ DESIGN/BUILD TEAM
In practices of INTEGRATED PROJECT DELIVERY the interests of all parties are aligned and each are in a relationship with DESIGN/BUILD OWNER TEAM the others. The process for such practices bears significantly on how these agreements are written and the selection of the agent CM as owner’s players involved. Often times IPD will include either front or developer back end services to a project (ie. feasability study or facility DESIGN CONSULTANT DEVELOP/ maintainance.) PUBLIC DESIGN/BUILD CONSTRUCTION MANAGER
*
DESIGN/BUILD TEAM
ARCHITECT
OWNER
CONTRACTOR
*
PUBLIC ENTITY
DESIGN/BUILD TEAM
Low-Bidder
Procurement
Compensation
GENERAL CONTRACTOR
Bridging
CONTRACTOR
COMMON
COMMON
OWNER
ARCHITECT
Most Qualified
Public Private
Partnership COMMON
Lump-Sum
consultants
ARCHITECT
OWNER
DEVELOP/ DESIGN/BUILD TEAM
ARCHITECTMOST
OWNER
Compensation
RARECOMMON
DESIGN/BUILD TEAM
developer
DESIGN CONSULTANT
players involved. Often times IPD will include either front or back end services to a project (ie. feasability study or facility maintainance.) Public Private
developer
CONTRACTOR
DESIGN CONSULTANT
primesmultiple primes
DESIGN BUILD DIFFERENCE As a project develops the need to TEAM communicate across the boundry
ENTITY
Public may be Private imperative but also difficult Partnership as each side tries not to induce any further liability. The onwer may in this instance be stuck in the middle of an adverse relationship between the design side and the construction side of the project.
mediator, arbitraitor in an unfamiliar world
CONTRACTOR
ARCHITECT
OWNER
CONTRACTOR
sub-contractors
builder
adapted from gluckplus.com
trends in the market ARCHITECT-LED DESIGN/BUILD 6.1%
5.2%
12%
12% 33.5%
percentage of market
paths and informed documentation
DESIGN BUILD DIFFERENCE
inception through to its completion. In this method of practice there is a single contractual relationship between the owner/
DBB CMAR DB
under a design build model, with critical
then returns to a more at risk role during construction. Having a CM in this position allows for opportunities to fast-track ARCHITECTbut ARCHITECT ARCHITECT by the same token often requires compensation agreements In this model the designers OWNER team OWNER OWNER OWNER to be made (often GMP) on partial designs. Construction of architects, engineers, and other GENERAL GENERAL management services come atis acontractually premium and are contractual consultants separated CONTRACTOR CONTRACTOR from the builder’s team of contractors agreement withdesigner the owner that separate from design services.
process.
INTEGRATED PROJECT DELIVERY
thepractices of design build Inarchitecture In DESIGN BUILD, a team of architects, designers, engineers In the CONSTRUCTION MANAGER AT RISK delivery method, a the traditionalInmethod the traditional of practice, method an architect of practice, is inana architect is in a and builders performs service to complete a project from its CM serves aswith an advisor totraditional the owner/client during design but contract with thecontract owner/client with the to owner/client provide the designs to provide for the acommon designs for a struggle practice (DBB) DESIGN BUILD DIFFERENCE... DESIGN BUILD DIFFERENCE... _develop a project as it were to be built
ARCHITECT
DESIGN BUILD
Low-Bidder Low-Bidder Best Value Best Most Value Qualified Most Qualified ARCHITECT
TEAM
CM professionals as owner’s agent design and construction allows for a streamlined
ARCHITECT
CONSTRUCTION MANAGER
C.M. AT RISK
DESIGNDESIGN BID BUILD BID BUILD ARCHITECT
there is a single contractual relationship between the owner/
multiple upon fee. The owner maintains a fair amount of control as primes the by the same token often requires compensation agreements client and the DB team. This and early collaboration between OWNER OWNER ‘go between’ between the two contractually separate entities; to be made (often on partial designs. Construction design and construction professionals allows GMP) for a streamlined GENERAL those building the project and those providingprocess. the information management services come at a premiumCONTRACTOR and are contractual to do so. agreement with the owner that separate from design services.
unit cost
cost growth
construction speed
delivery speed
schedule growth
trends show DB as a viable way of reducing costs and project delivery time
41% 28%
2005
2013
trends show DB practice increasing in the the construction market
Low-Bid
Procurement
RARE
COMMON
RARE Compensation COMMON VARIATIONS:
RARE
ARCHITECT
OWNER
GENERAL CONTRACTOR
Cost+
GMP
OWNER
Best Value
RARE
MOST COMMON
COMMON
Compensation
CONSTRUCTION MANAGER
Low-Bidder
INTEGRATED PROJECT DELIVERY
RARE
COMMON
Low-Bidder Best Value RARE Procurement
COMMON
Lump-Sum
DESIGN BUILD
COMMON
Most Qualified
ARCHITECT
inception through to its completion. In this method of practice DESIGN/BUILD OWNER TEAM there is a single contractual relationship between the owner/ COMMON Compensation
COMMON VARIATIONS: CONSTRUCTION MANAGER
MOST COMMON
Best Value
CONSTRUCTION GENERAL client and the DB team. This and early collaboration between MANAGER AT RISK CONTRACTOR ARCHITECT
ARCHITECT
OWNER
Low-Bidder
Compensation
In DESIGN BUILD, a team of architects, designers, engineers Procurement and builders performs service to complete a project from its OWNER
ARCHITECT
OWNER
BUILD
Procurement
RARE
OWNER
In the traditional method of practice, an architect is in a In thewith traditional method oftopractice, an architect is ina a contract the owner/client provide the designs for
C.M. AT RISK
RARE
Lump-Sum GMP Cost+ Lump-Sum GMP Cost+ tradtional practice COMMON RARE RARE Compensation DESIGN Lump-Sum RAREGMP COMMON RARECost+ Compensation
COMMON
DESIGN/BUILD TEAM
OWNER
Data from the McGraw Hill Construction 2014 SmartMarket Report entitled Project Delivery Systems
Lump-S
Compensation
RARE
the design build difference AR CH ITDESIGN/BUILD ARCHITECT-LED ECT -LE DD ESI GN /BU ILD ARCHITECT-LED DESIGN/BUILD OW NE OWNER R
OWNER
ARCHITECT-LED DESIGN/BUILD
ARCHITECT-LED DESIGN/BUILD In the case of ARCHITECTLED DESIGN/BUILD Team, the
Architect-led Design Build: design and construction happens are engaged early in the project allowing for
AR ARCHITECT-LED D DESIGN/BUILD
designer is the owners point of continued feedback between parties that can help inform the design process contact. Similar to the process of bridging where the owners
design consultant may hand down initial designs down to In the casea of ARCHITECTmore integrated DB Team, ARCHITECT-LED LED DESIGN/BUILD Team, the the architect-led model works DESIGN/BUILD designer isdevelop the owners point ofan informed DESIGN to perserve contact. Similar the process designtointent from the start of of bridgingthewhere the through owners construction project design consultant may hand to completion. AR down initial designs down to CH In th DE ITE a more integrated e DB Team, ARCHITECT-LED SIG CT LED case o works the architect-led model N/B -LED des DESIG f ARC DESIGN/BUILD igton perserve HIT N UIL develop er is /BUanIL informed E con D D T CTtac the the start t. from design eaof of b intent o ridg Simila wners m, th dethe r to construction ing through poin e sig project wh the nc t of e d p re o o to completion. ro Provides a single point of contact owner and a management of wn for nthe init sultan the ow cess a m that ialfosters tcollaboration consultants and subcontractors ners not adversity o ma yh the re inte desig and ns arc gra dow hite ted dev n ctD elo to B led p to des mo Team ig p the n inte erserv del w , o p n e to c roject t from an in rks form om thro the p u e s leti Pro on. gh co tart of d nstrand a management of con vides Provides a single point of contact for the owner ucti sult a s on not adversity consultants and subcontractors that fosters collaboration ants ingle and poin sub t of con con trac tac tors t for tha the t fo ste owner rs c olla and a bor ma atio nag n n em ot a ent dve of rsit y
CONSTRUCTION
ARCHITECT-LED DESIGN/BUILD Architect-led Design/Build: with architects on site, fast tracking benefits from being more informed and properly managed thanks to the feedback model that DB provides
Early with engagement with helps constru Early engagement construction to understand and to tailor cost and tailorcost design the design realitiest of a budget
trade
A
trade
B
DESIGN CONSTRUCTION DESIGN
TIME SAVED CONSTRUCTION
FEEDBACK throughout project timeline
Single point of contact for owner, with designer Creativity through collaboration Control of means and methods
trade
C
DESIGN CONSTRUCTION CONSTRUCTION
ARCHITECT-LED DESIGN/BUILD Early engagement with construction allows for a properly managed phased construction
My investigations of Architect-led Design/ Build identified areas and processes in the making of architecture that this method of practice can exercise more control over than traditional practice. The issue of affordable housing is
Engagement with construction process helps to understand cost Less value engineering, Fewer change orders
one that is relevent and of increasing concern in our cities today. Additionally an affordable housing project comes with certain constraints that present challenges for any way of practicing
Quick, responsive feedback Properly managed, properly phased construction
architecture. Nonetheless, Philadelphia City Council has identified this as a crisis that can be overcome. Using this as a preface, I chose to further my investigationof Design/Build by applying it’s ideals to an affordable housing project in North Philadelphia.
DIAMOND STREET SITE
I chose to look for a site for this project in
small scale development of infill lots
the Lower North District of Philadelphia. This area has some of the highest vacany rates in the city and has been identified in some areas as a good place to focus BREWERYTOWN SITE
efforts of rebuilding and development.
medium scale development on parcel assembleges
I looked at three sites to start to develop my project witht the idea that I could establish a SMALL, MEDIUM, LARGE approach to doing things. I used both the
CRUZ REC. SITE
Lower North District Plan and guidelines
large scale development on single large parcel
from the Philadelphia Land Bank to help determine the feasibilty of these sites and to help ground my project.
B u c k s C o u n t y
Create jobs Upper Far Northeast District
Lower Far Northeast District Pennypack Park
M o n t g o m e r y C o u n t y
PROJECT OPPORTUNITES Recommended Areas for Development and Higher Density i
Central Northeast District
Upper North District Upper Northwest District
I-76
Lower Northwest District
Lower Northeast District
Fern Rock Transportation Center
Tacony Creek Park
Wissahickon Valley Park
North Delaware District Frankford Transportation Center
North District I-95
M o n t g o m e r y C o u n t y
River Wards District
West Park District Fairmount Park
Lower North
D
Cobbs Creek
West District Market Street
University Southwest District
la
w
r ve Ri
PUBLICALLY OWNED LAND
I-676
Metropolitan Center
N e w J e r s ey
Central District
69th St. Transportation Center
e
e ar
South District Broad Street
D e la w a r e C ou n t y
Lower Southwest District
Lower South District Sports Complex FDR Park
I-76
VACANT PARCEL
Navy Yard Franklin Square
Logan Square
N e w I-95
Philadelphia International Airport
J e r s e y
VACANT TAX DELINQUENT
Convention Center
City Hall
Rittenhouse Square
2
Philadelphia2035: Lower North District Plan
480 Acres
Washington Square
VACANT BUILDING
CRUZ REC.
TAX DELINQUENT PUBLICALLY OWNED
AMONDSTREET AMOND STREET OCCUPIED
VACANT BLDG. VACANT LOT PARKING
LAND BANK DECISION TREE...
YARD GARDEN PARKING VACANT LAND VACANT BUILDING OCCUPIED PUBLICALLY OWNED TAX DELINQUENT
...for vacant parcels.
LAND BANK DECISION TREES...
GARDEN
...for vacant parcels.
...for vacant buildings
YARD SUPPORT THE END USE IDENTIFIED IN THE PLAN
FEW
FEW
DIAMOND STREET SITE
PHILADELPHIA LAND BANK DECISION TREES...
HOUSING
MOST
DEMOLISH & ASSESS OPPORTUNITIES FOR THE LAND
STABILIZE & PACKAGE WITH ADJACENT PARCELS
HOUSING HOU HHO OOUUUSIN SSIIN SIN ING
HOLD/ASSEMBLE FOR HOUSING
MOST
BREWERYTOWN SITE
CRUZ RECREATION SITE
REFER TO L&I FOR POTENTIAL DEMOLITION
...for vacant parcels. SUPPORT THE END USE IDENTIFIED IN THE PLAN
SUPPORT THE END USE IDENTIFIED IN THE PLAN
HOUSING
HOUSING
HOLD/ASSEMBLE FOR HOUSING
FEW
FEW
FEW
FEW
...for vacant buildings. STABILIZE & PACKAGE WITH ADJACENT PARCELS
priliminary blocking for each site...
DEMOLISH & ASSESS OPPORTUNITIES FOR THE LAND
REFER TO L&I FOR POTENTIAL DEMOLITION
STABILIZE & PACKAGE WITH ADJACENT PARCELS
DEMOLISH & ASSESS OPPORTUNITIES FOR THE LAND
REFER TO L&I FOR POTENTIAL DEMOLITION
INSULATED RAINSCREEN FACADE ASSMBLY (FIELD INSTALLED)
Ultimately I looke towards modular, prefabrication as a way to develop the three site together. The idea was that, in reality this would done to help cut cost and hopeful benefit from the economy of scale when using a system of similar components. Ideally this would help reduce the burdered on subsidies.
Cost Comfort Air Quality
Cost Comfort Air Quality
SINGLE TOP PLATE 2X8 CEILING FRAMING GYPSUM WALL BOARD 1 ½” INTEGRATED SHEATHING/INSULATION PANELS
Cost Comfort Air Quality
Cost Comfort Air Quality
Cost Comfort Air Quality
SPRAY FOAM DENSE PACK CELLULOSE FURRED OUT WIRING CHASE 2X6 FRAMING @24” O.C. 2X12 FLOOR FRAMING 2” XPS INSULATION
Cost Comfort Air Quality
foundation line
Cost Comfort Air Quality
2X6 IN-LINE FRAMING @24” O.C.
Utilize various strategies of advanced farming techniques
DOUBLE STUD CORNERS less waste; less thermal bridging
to reduce material waste, increase insulation and decrease thermal bridging
*EFFICIENT USE OF MATERIAL
14’-5½”
16’ INSULATED ACTUAL SIZED HEADERS
36’
40’
44’
32”
4’
4’ *EFFICIENT USE OF MATERIAL
SINGLE STUD R.O. no cripple or jack studs
10’-8”
Cost Comfort Air Quality
mate line Cost Comfort Air Quality
8’-8”
Additionally, adopting some of the ideals of Passive House design, the units constructed would be highly insulated so they may be conditioned using simple systems at a relatively low cost to the occupant.
2X6 FRAMING @24” O.C. INTEGRATED VAPOR BARRIER W/ FLASHING TAPE
THE LAYER CAKE scheme The module can be design in a way that is compatible with the nature of different sites. The kit of parts and floor plans can be consistent from location to location but the facade and the way in which the building meets the ground will vary. Using this method you could imagine a number of modules being built awaiting a site to selected and prepared.
DIAMOND STREET SITE
BREWERYTOWN SITE
CRUZ RECREATION SITE continuous vapor barrier epdm roofing membrane flashing cap
continuous vapor barrier
module mate line
2” Xps insulation
MINERAL wool insulation panel wood support metal decking
Layer 1 development
module mate line flashing insulated concrete formwork vapor barrier membrane cement board skirt
12x24” CONTINUOUS CONCRETE FOOTING
module mate line
steel post and beam wood frame build-out foundation anchors
4” concrete slab
CRUSHED STONE to frost depth (min 36”) CRUSHED STONE 18x36” CONTINUOUS CONCRETE grade beam
2” XPS INSULATION CRUSHED STONE
MODS and FACADES
continuous vapor barrier
3-4” Xps insulation 4” concrete slab
wood frame parapet steel angle parapet support fascia board/panel
12”Ø x 60”d (estimated) COlumn foundation
19th St.
N Uber St.
20th St.
DIAMOND STREET SITE
Diamon
d St.
SITE PLAN
0
UNIT PLANS
0
8
64
16
up up
up
up
up up up
up
up up
up
up
up up
up
up up
up
up
up
up
up
up
up
up
up
up
up
up
up
entry level
lower level
2 bedroom lower unit
up
1 bedroom accessible lower unit
2nd floor
3rd floor
2 bedroom upper unit
up
up
street elevation
ramping at entry
building section
on site vs. offsite work
prefab module constructed on site excavation/site work
mechanical zoning
each unit of the duplex has a separate ERV unit to control ventilation and air temperature
final section and elevation details
BREWERYTOWN SITE up up
up up up up
up
27th St.
Etting St.
up
Martson St.
28th St.
up
Master St.
0
up
UNIT PLANS
0
8
16
up
typical
accessible
1 bedroom street level units
3 bedroom upper level unit
1 bedroom upper level unit
2 bedroom corner units
64
0
street elevation
32
up
0
section through stair tower
16
section through typical grouping up
typical grouping
grouping at corner above commericial space
street level units upper level units
up up up up
up up up
up up
up
on site vs. offsite work
prefab module constructed on site excavation/site work
mechanical zoning
each grouping of units shares a larger ERV unit and heating system located in the common basement
final section and elevation details
4th St.
nce St. N. Lawre
Orkney S
5th St.
t.
CRUZ RECREATION SITE
Harlan St.
Master St.
0
UNIT PLANS
0
8
16
2 bedroom corridor unit
2 bedroom courtyard unit
1 bedroom courtyard unit
floor 1
floor 2
floor 3
3 bedroom street level rowhouse
1 bedroom corridor unit
64
front elevation (Master St.)
side elevation (N Lawrence St.)
cross section through
courtyard elevation/section
ground floor plan
2nd floor plan
3rd floor plan
4th floor plan
5th floor balconies
on site vs. offsite work
prefab module constructed on site excavation/site work
mechanical zoning
each of the defined zones shares a rooftop ERV and heating system while the street level units each contain their own system
final section and elevation details