Meeting Agenda 9:00 – 10:00 AM • Consultant Team Update 30 min • Project Partner Updates 15 min • Project Schedule & Next Steps 5 min • Questions & Discussion 10 min

Green Infrastructure Design Development (Task 3)

• Compile GIS mapping

• Inventory public and institutional properties

• Identify existing GI

• Identify planned capital improvements

& Selection

• Desktop screening

• Property owner interviews

• Field inventories (20 to 40 sites)

• Green infrastructure concepts (up to 15)

• Technical Memo

• 5 projects

• Field survey

• Test pits & infiltration testing

• Wetland delineation

• Preliminary layout

• Opinion of cost

• Technical Memo

• 3 projects

• Level of detail to support local/state permitting

1. Data Gathering & Review 2. Project Screening 3. Preliminary Design 3. Permit Level Design

Consultant Team Update

Task 3 – Design Development

• GIS Data Gathering and Review (80% complete)

Existing watershed characteristics & conditions

− Support desktop screening of GI opportunities and watershed plan update

Outstanding GIS data and information requests

• Awaiting Bloomfield storm system data. Currently using 2010 data.

• Requested information on observed flooding locations (MDC, Hartford, Bloomfield, West Hartford)

• Requested existing GSI and planned capital improvements (retrofit opportunities). Partners to review and confirm.

• Draft inventory of public (municipal and state) and institutional properties Parcel Owner Parcel Address University of Hartford 200 Bloomfield Ave, West Hartford, CT Watkinson School 180 Bloomfield Ave, Hartford, CT City of Hartford Board of Education 415 Granby St, Hartford, CT State of Connecticut 61 Woodland St, Hartford, CT University of Connecticut School of Law 55 Elizabeth St, Hartford, CT Town of Bloomfield 800 Bloomfield Ave, Bloomfield, CT St. Francis Hospital 113 Woodland Street, Hartford, CT Hartford Seminary Foundation 77 Sherman Street, Hartford, CT
Consultant Team Update Task 3 – Design Development

Consultant Team Update

Task 3 – Design Development

Desktop screening criteria

− Impervious cover

− Soils

Proximity to & condition of river/riparian corridor

− Storm drainage and combined sewer systems

− Parcel size

− Existing flooding

Consultant Team Update

Task 3 – Design Development

GI Property Owner

Interviews

Draft Questionnaire

Consultant Team Update

Task 3 – Design Development (Next Steps)

Finish compiling project GIS database

Complete inventory of public and institutional properties

Identify and map locations of existing and planned stormwater retrofits (MS4 and other projects)

Complete research of ongoing and planned projects & capital improvements • Desktop screening (select sites) • Property owner interviews • Field inventories (20-40 sites)

Consultant Team Update Task 4 – Watershed Plan Update

Preliminary existing conditions watershed maps

WATERSHED MANAGEMENT PLAN

WATERSHED OVERVIEW

48,000 WATERSHED POPULATION

HOW MUCH OF THE WATERSHED DOES EACH MUNICIPALITY COMPRISE? 74% BLOOMFIELD 22%

WHAT PERCENTAGE OF EACH MUNICIPALITY IS WITHIN THE NBPR WATERSHED?

BLOOMFIELD 68% WEST HARTFORD 17% HARTFORD 12% AVON 1% SIMSBURY 1% WINDSOR 1%
WEST HARTFORD 18% HARTFORD

WATERSHED MANAGEMENT PLAN

SUBWATERSHED & MAJOR STREAMS

28.6 SQUARE MILES TOTAL WATERSHED AREA

14 MAPPED SUBWATERSHEDS

4 MAJOR TRIBUTARIES

5.4 MILES NORTH BRANCH MAINSTEM (ABOVE GROUND)

0.5 MILES NORTH BRANCH MAINSTEM (BURIED)

WATERSHED MANAGEMENT PLAN

LAND COVER

UConn CLEAR – NOAA High Resolution Land Cover for Connecticut (2016)

• 1 meter resolution

• 3 categories of land cover

WATERSHED MANAGEMENT PLAN

WATER QUALITY IMPAIRMENTS

North Branch Park River-02

• Recreation (E. coli)

• Habitat for Fish, Other Aquatic Life and Wildlife (Cause Unknown)

North Branch Park River-01 (Conduit)

• Recreation and Habitat for Fish, Other Aquatic Life and Wildlife (Physical Substrate Habitat Alterations)

WATERSHED MANAGEMENT PLAN

FLOOD PRONE AREAS

FFEMA Mapped Flood Zones

Riverine/Overbank Flooding

Regulatory Floodplain

Other Documented or Observed Flooding Locations

Drainage Related or Riverine Flooding

• Streets/Intersections

• Neighborhoods

• Buildings (Basement Flooding)

• Parcels (Sites & Parking Lots)

• Culverts/Stream Crossings

Looking to add information to this map to inform GI site selection and concept development

Consultant Team Update

Task 4 –

Watershed Plan Update

• Watershed Based Plan

Format

− Modified approach based on feedback from CT DEEP and EPA

Web-based deliverable

• Project web app with interactive map (ArcGIS Experience Builder) (in progress)

• PDF format watershed management plan

− EPA Nine Elements

− Graphical format

Consultant Team Update

Task 5 –

Public Outreach & Community Engagement

Community Engagement Strategy

• Team Communications with Multiple Stakeholder groups

− Neighborhood Networks: NRZs and Farmers Market

− Faith Organizations, such as Immanuel Congregational Church

July 15th Walkshop

− Volunteer Service, Youth Employment, with Our Piece of the Pie

July 24th maintenance green infrastructure; August 21st bridge sidewalks and

July 25th Walkshop of Classical Magnet green infrastructure features

Institutional Property Managers

− K-12 Schools: Hartford Board of Education

Elected Officials and municipal staff

Consultant Team Update

Task 5 –

Public Outreach & Community Engagement

Community Engagement Strategy

• Distinct Team Tasks

− Fuss & O’Neill seeking site specific information

− Mary Pelletier (NCCD and Park Watershed) coordinate activities

− Brian Martin (Trust for Public Land)

• expand team understanding of community experiences

• Surveys and Questionnaires

• Other Strategies such as Walkshops and Meetings

Task 5 – Public Outreach & Community Engagement

Task 5 – Public Outreach & Community Engagement

July 15th Walkshop with Immanuel Congregational Church and Asylum Hill Neighborhood Association Green Committee, Park Watershed, NCCD, Trust for Public Land, and West End Civic Association

Consultant Team Update

Task 5 –

Public Outreach & Community Engagement

• Completed Public Outreach and Community Engagement Events

July 15th Walkshop with Immanuel Congregational Church and Asylum Hill Neighborhood Association Green Committee, and West End Civic Association

− Volunteer Service and Walkshop Asylum Hill Neighborhood Association Green Committee, Our Piece of the Pie Youth, City of Hartford and Ct Museum

August 22nd (Farmers Market) Park Watershed

Upcoming Public Outreach and Community Engagement Events

− West End Farmers Market: Clemens Green on Farmington Avenue

• September 19th Tuesday 4 – 6:30pm

• October 24th Tuesday 3 – 6pm

North Branch Cleanup: HIU 9-12noon Saturday, September 23rd

Project Partner Updates

North Branch Park River Drainage Study

− Sewer Separation Design (Granby Street and Blue Hills Avenue)

City of Hartford

− North Branch Park River debris removal efforts

CT DEEP Climate Resilience Fund Grant (Citywide flooding/climate resiliency assessment)

Others?

• MDC

Project Partner Updates

− CT DEEP Climate Resilience Fund Grant – Stormwater Authority

Feasibility Assessments

UConn CLEAR

Community Engagement/North End Flooding

EPA Region 1 & UNH Stormwater Center

− Granby Street Green Infrastructure Design

CT DEEP

CRCOG

Project Schedule

2023 2024 Task Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May 1. Quality Assurance Project Plan QAPP Approved - Task Completed 2. Project Advisory Committee Meetings 3. Design Development of Priority GI Projects 4. Watershed Plan Update 5. Public Outreach & Community Engagement 6. Project Meetings and Management 12 Months 6 Months 1 2 3 4 5 6 1 2 3 4 5 6 7 11 Months Advisory Committee Project Partners 8 9 Data Gathering & Review Project Screening & Selection Preliminary Design Permit Level Design

Upcoming Project Partners Meetings

• Meeting Schedule (Friday, 9-10 AM)

− October 13th

• GI site screening

December 8th

• Field work results and GI project concepts

4 additional meetings in 2024 (date and times to be determined) or another meeting added during autumn of 2023 depending upon development of project content

• Project designs and watershed management plan

Upcoming Advisory Committee Meetings

• Meeting Schedule (Thursday, 2-3 PM)

October 12th

December 7th

2 additional meetings in 2024 (date and times to be determined)

Next Steps

GI Design Development

− Incorporate observed flooding and GSI locations from partners and stakeholders into GI screening and watershed mapping

− Finalize desktop GI screening for review by Project Partners

− Interface with MDC project (NBPR field work and modeling)

− Conduct field inventories of potential GI sites

Watershed Plan Update

Finalize updated watershed mapping

− Submit watershed maps for review by Project Partners

Finalize and roll out project web app

Stakeholder Engagement

Continue public outreach and community engagement

North Central Conservation District

Questions and Discussion

Contacts:

Joanna Shapiro jshapiro@conservect.org

Erik Mas emas@fando.com

Mary Rickel Pelletier maryp@parkwatershed.org

Walker Holmes walker.holmes@tpl.org

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.