Renew Magazine - Quarter 3, 2020. Energy Efficiency Focus

Page 32

32 offshore

Motor repair highlights flaw in original design Sulzer explains how it solved cooling issues which had been identified when an offshore gas compressor motor was being rebuilt to improve its reliability.

H

igh pressure gas compressors are vital pieces of equipment that reduce the volume of a gas before it is transferred to shore from a floating production storage and offloading (FPSO) vessel. The owner of one such unit off the coast of Ghana called Sulzer in to carry out an inspection, which uncovered a long-term defect that needed to be resolved. Initially, the original equipment manufacturer (OEM) was contacted and asked to undertake a repair of the motor. A repair of the connections was completed, but as soon as the motor was restarted, it immediately failed. At this point the OEM suggested that an offshore rewind would not be possible, and the platform operator did not think the motor could be removed for an onshore repair. Sulzer’s Regional Sales Director in Ghana is in regular contact with the operators of the FPSO. Although they are well-acquainted with Sulzer’s expertise in pump design, manufacturing and maintenance, other areas of the company’s knowledge had remained unexplored. During one particular meeting, the issue with the highpressure gas compressor motor was raised and Sulzer offered to investigate. Working on offshore vessels, especially those involved in the oil and gas industry, requires specialised training to ensure everyone’s safety. Fortunately, Sulzer has a number of suitably qualified engineers, and some of these were dispatched to the FPSO to carry out an initial inspection. Testing of the windings found very low insulation resistance readings and various discussions were held to determine the best course of action. The motor would need to be dismantled to locate the problem and Sulzer’s initial suggestion was a complete rewind, performed onboard the vessel. FINDING THE BEST SOLUTION Once Sulzer’s engineers had the motor separated into its component parts, they discovered that it would be possible to remove the motor from its operating position and transport it to an onshore location. This presented a number of advantages to the repair project, not least the ability to carry out a full-load test on the motor once it had been repaired. It transpired that the gas compressor had been modified to increase its output and this had required additional power from the motor. In fact, rather than operating at 8.5MW, the motor was being required to supply 9.3MW, so the ability to deliver full-load testing as part of the project would offer very good confidence levels in the future reliability of the motor. Meanwhile, once the decision to complete the rewind onshore had been made, Sulzer’s field service engineers took all the necessary measurements of the windings and sent the information to the Falkirk Service Centre in

Quarter 4 2020

Scotland. The coil data was verified and issued to the Birmingham Service Centre in the UK, which has a 24hour high voltage (HV) coil manufacturing facility. At the same time, the motor was air-freighted to Falkirk, where the rewind would be completed. Marc Stuart, Service Centre Manager in Falkirk, explained: “In these applications, speed of response is very important; downtime on such vital pieces of equipment can run into millions of dollars. We fully expected to complete this project within the 45 days that had been agreed with the customer and we worked round-theclock to get the stator rewound and the motor reassembled.” The new windings, designed and manufactured in Birmingham, have increased the copper content by 1.82% by using the latest in insulation material technology, which has improved since the original coils were manufactured. Even this modest increase will have an impact on efficiency and the operating temperatures of the coils.

“Rather than operating at 8.5MW, the motor was being required to supply 9.3MW.”

PROFESSIONAL COOPERATION For projects of this size, Sulzer works with ATB Laurence Scott, which is also an OEM for high voltage motors, and has one of the largest motor test beds in the UK. This facility was used to carry out a full-load test, which was witnessed by Sulzer and staff from the FPSO. Since the motor had been in operation for almost ten years, no significant issues were expected. However, during the full-load test, a cooling issue with the original design was identified where air flows www.theaemt.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.