MUNICIPAL FOCUS: ETHEKWINI

Emergency rehabilitation

of the Seaward Road Bridge The Seaward Road Bridge crossing the Umhlatuzana River in Durban underwent a partial collapse during heavy flooding in April 2019. The common practice worldwide would have been to demolish and rebuild. In this particular case, eThekwini Municipality’s in-house engineering team developed a novel and sustainable alternative, partially reconstructing and lengthening the continuous post-tensioned concrete deck. By Peter Fenton, Jitesh Harripershad & Luke Reid*

C

onstructed in 1979, the Seaward Road Bridge supports the only direct access between the Umhlatuzana Industrial Park and major road, rail and sea connections in the direction of the Port of Durban. The 150 m five-span bridge crosses a complex curve in the river, which was originally intended to be canalised. Progressive flooding first eroded the river’s eastern embankment immediately upstream of the bridge, redirecting the flow directly toward the face of the eastern abutment. The saturated abutment fill pushed the precast piles out of position, then sheared them off. Without the piles, the abutment collapsed, taking a section of the bridge deck with it. The remainder of the deck was not strong enough to per form without the abutment’s support. The deck subsequently twisted over sideways on its bearings and the end span slumped down. Fortunately, no people were harmed in the vicinity during or after the collapse.

Old and new deck sections came together to form the upgraded Seaward Bridge

Access to the industrial park now required an additional 5 km detour over a nearby hill along steep, narrow, winding suburban roads, where trucks had previously been completely forbidden. This was a hazard for both the large trucks carr ying shipping containers and heavy machiner y, and the local residents, including children walking to school. Congestion from trucks queuing to navigate difficult portions of road could introduce long delays in accessing the industrial park, holding up work and reducing productivity. Pressure to replace the bridge as soon as possible came from both the residential and industrial areas.

Analysing the problem A rudimentary environmental impact assessment for the bridge reconstruction was quickly approved as part of a package of emergency flood repairs on the river. Funding was provided via a Municipal Finance Management Act (No. 56 of 2003) Section 36(1)(a)(i) emergency procurement process

with a shortened tender duration. The original as-built drawings were successfully tracked down, and a detailed inspection conducted to map the extent of the strain damage. In terms of the final remediation solution developed, a key advantage was that the prestress cable layout in the bridge deck was extremely simple. All the prestress cables terminate in couplers between the construction stages. In principle, a replacement deck was only needed in two of the bridge’s original five spans. The original prestress couplers at the construction joint could be used to connect the new deck to the salvaged deck and share its loads. But first the team would need to dismantle a structure that was never meant to be tampered with once completed.

The solution: sewing a prestressed bridge deck back together The existing deck was completely remodelled and analysed using modern design codes and software. Two key challenges


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Milling in the compact class

3min
page 53

Mapei: 85 years old and still looking to the future

4min
pages 50-52

The evolution of a screening legend

9min
pages 44-47

The act of refuge

2min
page 41

BIM is not a software application

5min
pages 42-43

One small sensor helps

2min
page 40

Teamwork needed to rebuild SA’s economy

4min
pages 34-35

What could cause fouling of membranes?

2min
page 33

Kuils River corridor plan unlocks development

6min
pages 36-37

Gabions build a foundation for SMME development

5min
pages 38-39

Think and act globally, execute locally

4min
pages 30-32

Legacy infrastructure: the hidden threat

2min
page 27

Moving people and the economy

6min
pages 28-29

Certification provides assurance and is more than a test report

7min
pages 24-26

Leading from the front

6min
pages 22-23

Building knowledge, delivering insight

5min
pages 18-19

Bridging the gap between emerging and established contractors

5min
pages 20-21

Infrastructure news from around the continenent

5min
pages 8-9

Product leadership doesn’t happen by chance

6min
pages 12-13

The value of connectivity

3min
pages 10-11

Emergency rehabilitation of the Seaward Road Bridge

8min
pages 14-17

Editor’s comment

5min
pages 5-6

President’s comment

2min
page 7
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.