IMIESA October 2021

Page 32

RENEWABLE ENERGY & ELECTRIFICATION

Recommissioning Unit 1 at Eskom’s Drakensberg plant

M

ar thinusen & Coutts (M&C), a division of Actom, completed a significant rewind in midNovember 2020 after being contracted by Voith Hydro, based in Germany, to wind the stator of Unit 1 at Eskom’s Drakensberg pump storage scheme. The massive stator winding contract, performed by a winding team from M&C under the supervision of Voith, was the final stage in the refurbishment of three of the station’s four 250 MW motor-generator units. Eskom engaged Voith to refurbish Unit 1. M&C has worked with Voith over several years on projects that include a stator rewind at Eskom’s Ingula pumped storage scheme. The 6.5 m diameter stator was wound in situ under Voith’s supervision after removal of the rotor. Deploying a Voith-supplied winding kit, the winding teams were required to install a total of 720 heavy-duty stator bars that had to be connected in an extremely complex bus arrangement. “Our teams had to undergo special training by Voith technicians before getting started on it,” explains Richard Botton, CEO, M&C.

30

IMIESA October 2021

Recommissioning Covid-19 travel restrictions at the time prevented Voith from flying one of its senior engineers from Germany to recommission the unit. In response, Voith requested M&C to complete this phase of the project, which was carried out by Rob Melaia, executive: Engineering & Technical, M&C. Previous power plants commissioned by Melaia as part of M&C contracts include the N’zilo hydro station in Katanga province, DRC, in 2013 and the SA Bureau of Standards’ National Electrical Test Facility’s High Power test laboratory in Gauteng last year. Senior technicians at Voith’s head office in Heidenheim, Germany, provided detailed instructions on the required procedures. “By the time I got there, I was thoroughly briefed about what I was required to do. The process was challenging, and I had to give it all my attention,” explains Melaia. “The one single thing that gave me the greatest confidence was knowing that M&C had done the winding of the stator. I wouldn’t have felt so confident if anyone else had done it.” M&C successfully performed the recommissioning of Unit 1 over a period of five days in March 2021.

DRAKENSBERG PUMPED STORAGE SCHEME Location Northern Drakensberg, KwaZuluNatal, close to the town of Bergville History Construction of the scheme started in 1974 and the last unit was put into commercial operation in 1981. A special feature of the station is that it is constructed entirely underground with only a dam wall, lift shaft buildings and transmission lines visible at the surface. The four reversible pump turbines are situated 52 storeys below ground level. Technical details - 4 x 250 MW generating sets - Installed capacity of 1 000 MW - Nominal operating head of 450 m (Source: Eskom)


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Labour-intensive construction is a technology

5min
pages 46-47

Low-volume roads: potential and pitfalls

10min
pages 48-50

Bundle transport planning capabilities to improve public transport

7min
pages 36-37

Local launch for structural adhesive

2min
page 57

Putting old tyres back on the road, sustainably

3min
page 45

Setting the standard for earthmoving proficiency

5min
pages 54-56

Indian contractor sets new slipform paving records

4min
pages 51-52

Wind atlas available for South Africa

2min
page 33

Recommissioning Unit 1 at Eskom’s Drakensberg plant

2min
page 32

A greener future through convergence

3min
page 31

Climate action plan for Johannesburg

4min
pages 28-29

Renewables, energy storage and the future of smart cities

2min
page 30

100 Mℓ of water from Ndlambe desal plant

1min
page 23

Leak detection in the Mother City

3min
page 26

Integrated intelligence to solve wastewater challenges

3min
page 27

Model available for efficient landscape water use

2min
page 22

How municipalities can effectively manage groundwater resources

5min
pages 24-25

Intelligent pipeline inspection using CCTV technology

4min
pages 20-21

Infrastructure news from around the continent

5min
pages 18-19

Procurement – from an engineer’s perspective

5min
pages 16-17

Quality aggregate at the heart of construction success

6min
pages 8-9

The implementation of the BUILD programme

5min
pages 12-13

Leveraging Industry 4.0 for a post- Covid-19 recovery

7min
pages 14-15

President’s comment

2min
page 7

Wire and stone

6min
pages 10-11

Editor’s comment

4min
pages 5-6
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.