Monthly Report for November 2024

Page 1


STATUS REPORT

TA 2025

NOVEMBER 2024

DAYS TO TA 2025

KEY HIGHLIGHTS:

BOW TIE SESSIONS FOR ALL PLANTS ARE IN PROGRESS FOR EVALUATING THE POSSIBILITIES OF SHIFTING TA FROM NOVEMBER 2025 TO APRIL 2026

REROUTING OF TA MANPOWER/EQUIPMENT PRS WITH THE ACTUAL AMOUNT

TA MODIFICATION & CAPEX DASHBOARD

TA

DASHBOARD

ACTIVITY STATUS

Completed Activities:

Issuance of TA Roadmap (Rev-04)

BOW-TIE sessions for Urea & Utilities Plant for evaluating the possibilities of shifting the TA from November 2025 to 1st April 2026 - Delay in the delivery of new Urea Stripper For Ammonia & Methanol Plants to be done in December 2024

Combined meeting between Security, Logistics and Planning Teams

Updating the list of CAPEX and modifications for TA2025 Meetings with Operations, Engineering, Maintenance, and Inspection teams completed

Issued Package Contracts PRs (for Recurrent Services): 41 PRs routed to Procurement, 1 PR under signature/preparation

Issued Vendor (FSE) PRs: 38 PRs routed to Procurement, 2 PRs under signature/preparation

Issued Vendor (Spare Part) PRs: 15 PRs routed to Procurement, 12 POs issued by Procurement, 3 POs pending issuance by Procurement

OngoingActivities:

Majormachinessparepartscheckingbyvendor/OEMisinprogress

MaterialreservationforInst/Elect/Civilstaticequipment/NRVsisinprogress.

Technicalevaluation&issuanceoffinalrecommendationmemosforpackagecontracts servicesisinprogress:19memosissuedtoprocurement,1POissuedbyProcurement

Technicalevaluation&issuanceoffinalrecommendationmemosforvendorservices(FSEs)is inprogress:18memosissuedtoprocurement1POissuedbyProcurement

MaterialreservationforPMordersandCMordersisinprogress:92%and73%completed respectively

TurnaroundCMorderassessmentisinprogress:79%completed

ACTIVITY STATUS

PlannedActivities-December2024:

TostartissuanceofPOsforVendorServices

TosubmitdetailedassessmentforCritical/MajorJobs

TostartmeetingfordiscussiononMods&Capex-Firstround

TostartmeetingonmanagementdecisiononexactTAcommencementdate.

ToprovideconfirmationtoallcontractorsofexactTAcommencementdate[Ifdate changed]

TocontinueOverseasFAT

TocompleteissuanceofMajorJobsBarCharts(Rev-01)

TocompleteissuanceofFinalRecommendationforManpower&RentalEquipment.

ToconductmeetingwithProcurement&WH#6

Toconductcombinedmeetingpresentation#4

ToIssueJobList(Rev-04)

Concerns:

DelayinthedeliveryofnewUreaStripper

IssuanceofTAManpower&Equipment:ReroutingofManpower&EquipmentPRswiththe actualamountPartialfundsreceivedfromEngineering

SAPHana:mergingofPRsassignedtomultipleTA&EngineeringAccounts

MaterialreservationforPMorders:92%completed

MaterialreservationforCMorders:73%completed.

ROADMAP S-CURVE

Cause of Slippage:

Issuance of PRs for Package Contracts: 98% completed

Final recommendation for Package Contracts: 20/42 issued

Final recommendation for manpower and equipment in progress: 18 manpower issued 4 equipment issued

Issuance of POs for manpower and equipment: in progress.

Issuance of PRs for Vendor services: 38/40 issued

Issuance of Package Contracts Services POs: in progress.

Kick-off Meeting with Manpower & Equipment Suppliers

CM MATERIAL STATUS

Major Rotary Reservation Status

Minor Rotary Reservation Status

70%

PR STATUS

Concerns&ActionPlan:

FinalizetheissuanceofremainingPOsforSparePartsInspection ExpediteissuanceofPOsforDirectManpower&EquipmentHiring.

CAPEX PROJECTS TIMELINE

LV-08009** Routine HIMA ESD System* PO Incl FSE

2 0 2 4 2 0 2 5 T A Expected to be delivered on 13.12.2025

E-0704 E-8601 E-8602A/B/C E-8604* Inhouse Installation

Methanol PG Cooler E-1201** PR#7236 (AO)

LV-82011 HV-82005 HV-82008**** Inhouse Installation

Passivation Air Compressor** PO Includes FSE

Electronic Governor MT-0701 & MR-1401* PO Includes FSE

Super Cup Trays R-8201** PR#7244 (AO)

42 Fans for Air Cooler ** PO Incl FSE

33kV SWBD 61MS5-1** PO Includes FSE

PV-52201/351 & PV-52401/402**** In-House Installation

MD-6102 PLC* PR Includes FSE

D-1501** In-House Installation

E-0001B** PR#7216 (TE)

E-0003** PR#7216 (TE)

Urea 2200 MTPD - PSV-8105 PSV-8106 PSV-8107 PSV-8108 **** Inhouse Installation

Urea 2200 MTPD - HV-82009 MOV-82003**** In-House Installation

Urea ESD**** ENG PR Includes FSE

Honeywell DCS* PO Includes FSE

Ammonia PG Cooler E-0301** PR#7241 (AO)

Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE

HP Carbamate Seperator D-8201*** PR#7244

Urea Stripper E-8201*** PR#7244 (AO)

Ammonia Plant

CONFIRMED MAJOR JOBS

Methanol Plant

CONFIRMED MAJOR JOBS

Urea Plant

Utilites Plant

BOW-TIE sessions for all Plants to evaluate the possibilities of shifting the TA from November 2025 to 1st April 2026 - Delay in the delivery of new Urea Stripper

BOW-TIE sessions for all Plants to evaluate the possibilities of shifting the TA from N ripper

Regular Meeting with Inspection Team - Turnaround Preparation