TA2025-Monthly-Report-February-2025

Page 1


STATUS REPORT

TA 2025

FEBRUARY

2025

DAYS TO TA 2025

KEY HIGHLIGHTS:

48 NOS OF POS ISSUED FOR 16 NOS. OF MANPOWER/EQUIPMENT PRS AND 6 NOS OF PRS ARE WAITING FOR BUDGET ALLOCATION/COMPLETION

TA MODIFICATION & CAPEX DASHBOARD

TA PR DASHBOARD

TA MAINTENANCE WORK ORDER DASHBOARD

ACTIVITY STATUS

Completed Activities:

Coordination and meetings for hotel arrangements for vendors and travel logistics with the HR and Logistics sections have commenced

Prepared List of Critical & None Critical Valves for Gland packing (by Plants Operation).

Started Major/Critical jobs Schedules Review meetings & Finalization

Completed Issuance of Job list (Rev-05)

Conducted Meeting with Procurement & Warehouse Team

Ongoing Activities:

Blocking of Stock Materials is in progress 91% completed

Major machines spare parts checking by vendor/OEM is in progress. 80% completed

Detailed assessment for Critical/Major Jobs is in progress

Technical evaluation & issuance of final recommendation memos for manpower/equipment services is in progress: 22 final recommendation memos issued to procurement; 48 POs issued by Procurement for 16 PRs

Technical evaluation & issuance of final recommendation memos for package contracts services is in progress: 30 final recommendation memos issued to procurement; 4 POs issued by Procurement for 4 PRs

Technical evaluation & issuance of final recommendation memos for vendor services (FSEs) is in progress: 33 final recommendation memos issued to procurement 3 POs issued by Procurement for 3 PRs

Material reservation for PM orders and CM orders is in progress: 94% and 80% completed respectively

Turnaround CM order assessment is in progress: 87% completed

ACTIVITY STATUS

PlannedActivities-March2025:

StartObtainingCopyofVendorsID(Passport)&CVsforReview/Approval

FinalizeimplementationofTArecommendations

DeliverofCapexItems

IssuanceofBarchartsforMajorJobs(Rev-02).

OrganizationCharts(ALLevel)

DocumentSubmissionbyContractorforalltypeofservices(FinalDocsby30042025)

Concerns:

DelayinthedeliveryofnewUreaStripper

MaterialreservationforPMWorkOrders:94%completed

MaterialreservationforCMWorkOrders:80%completed.

ROADMAP S-CURVE

Cause of Slippage:

Final recommendation for Hiring of Manpower and Equipment: 22/27 FRs issued

Final recommendation for Package Contracts: 30/42 issued

Final recommendation for Vendor Services: 33/39 issued.

Issuance of POs for Manpower: 42 POs issued for 13 PRs, POs to be issued for another 9 PRs

Issuance of POs for Equipment: 6 POs issued for 3 PRs, POs to be issued for another 2 PRs.

Issuance of Package Contracts Services POs: 4 POs issued for 4 PRs, POs to be issued for another 38 PRs.

Kick-off Meeting with Package Contractors (Technical)

Confirmation to be shared with all Contractors regarding the exact TA Commencement Date [If date changed]

CM MATERIAL STATUS

Major Rotary Reservation Status

Minor Rotary Reservation Status

PR STATUS

ActionPlan:

FinalizetheissuanceofremainingPOsforSparePartsInspection ExpediteissuanceofPOsforDirectManpower&EquipmentHiring.

TA AUDIT REPORT

2 0 2 4 2 0 2 5

CAPEX PROJECTS TIMELINE

HIMA ESD System* PO Incl FSE (Material Received)

42 Fans for Air Cooler ** PO Incl FSE

Methanol PG Cooler E-1201** PR#7236 (AO)

33kV SWBD 61MS5-1** PO Includes FSE (20/04/2025)

Passivation Air Compressor** PO Includes FSE

E-0003** PR#7216 (TE)

E-0704* Inhouse Installation

MD-6102 PLC* PR Includes FSE

LV-82011 HV-82005 HV-82008**** Inhouse Installation

Super Cup Trays R-8201** PR#7244 (AO)

Urea ESD**** ENG PR Includes FSE

Honeywell DCS* PO Includes FSE

HV-82009 ** Inhouse Installation

LV-08009** Routine

PSV-5253****

E-8601 E-8602A/B/C E-8604*, D1501**, Inhouse Installation, E-0001B**PR#7216 (TE)

PV-52201/351 & PV52401/402**** In-House Installation

Electronic Governor MT-0701 & MR-1401* PO Includes FSE

HSV-52236 & HSV-52336*

Ammonia PG Cooler E-0301** PR#7241 (AO) HP Carbamate Seperator D-8201*** PR#7244

Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE B-5203 ESD ****

Urea 2200 MTPD - MOV-82003**** In-House Installation

Urea Stripper E-8201*** PR#7244 (AO)

Expected to be delivered on 19.11.2025

Ammonia Plant

CONFIRMED MAJOR JOBS

Methanol Plant

CONFIRMED MAJOR JOBS

Urea Plant

Utilites Plant