Status Report 2024 October

Page 1


STATUS REPORT

TA 2025

OCTOBER 2024

DAYS TO TA 2025

KEY HIGHLIGHTS:

96% OF PM MATERIAL RESERVATION COMPLETED

REROUTING OF TA MANPOWER/EQUIPMENT PRS WITH THE ACTUAL AMOUNT

TA MODIFICATION & CAPEX DASHBOARD

TA PR DASHBOARD

TA MAINTENANCE WORK ORDER DASHBOARD >

ACTIVITY STATUS

CompletedActivities:

StartedthefirstroundofmeetingsforJobListdiscussions

ConductedCombinedMeetingPresentation#3

HeldmeetingwithProcurement&Warehouse#5

ConductedTAAuditmeeting#06.

IssuedPackageContractsPRs(forRecurrentServices):41PRsroutedtoProcurement,1PR undersignature/preparation

IssuedVendor(FSE)PRs:38PRsroutedtoProcurement,2PRsundersignature/preparation

IssuedVendor(SparePart)PRs:15PRsroutedtoProcurement,11POsissuedbyProcurement, 4POspendingissuancebyProcurement.

OngoingActivities:

Majormachinessparepartscheckingbyvendor/OEMisinprogress

IssuanceofTARoadmap(Rev-04)isinprogress.

MaterialreservationforInst/Elect/Civilstaticequipment/NRVsisinprogress

IssuanceofMajorJobsbarcharts(Rev-01)isinprogress

Technicalevaluation&issuanceoffinalrecommendationmemosforpackagecontracts servicesisinprogress:15memosissuedtoprocurement,1POissuedbyProcurement

Technicalevaluation&issuanceoffinalrecommendationmemosforvendorservices(FSEs)is inprogress:13memosissuedtoprocurement

MaterialreservationforPMordersandCMordersisinprogress:96%and75%completed respectively

TurnaroundCMorderassessmentisinprogress:80%completed.

UpdatingthelistofCAPEXandmodificationsforTA2025isinprogressMeetingswith Operations,Engineering,Maintenance,andInspectionteamsareongoingApproximately 100%ofthetargetachieved

ACTIVITY STATUS

PlannedActivities-November2024:

TostartissuanceofPOsforVendorServices

PreparelistsofVendors&PackageContractsServicesinitiatedbyTechnicalServices

TostartShelfLifeItemProcurementandBeltJoints

ToconductOverseasFAT.

Concerns:

IssuanceofTAManpower&Equipment:rerouted21PRswiththeactualamountPartialfunds receivedfromEngineering

MaterialreservationforPMorders:96%completed.

MaterialreservationforCMorders:75%completed

ROADMAP S-CURVE

CauseofSlippage:

IssuanceofTARoadmapRev-04:70%completed.

IssuanceofPRsforPackageContracts:90%completed

FinalrecommendationforPackageContracts:15/42issued

Finalrecommendationformanpowerandequipmentinprogress:16manpowerissued,3 equipmentissued

IssuanceofPOsformanpowerandequipment:inprogress.

IssuanceofPRsforVendorservices:38/40issued

IssuanceofPackageContractsServicesPOs:inprogress

Kick-offMeetingwithManpower&EquipmentSuppliers

CM MATERIAL STATUS

Major Rotary Reservation Status

Minor Rotary Reservation Status

72%

PR STATUS

Concerns&ActionPlan:

FinalizetheissuanceofremainingPOsforSparePartsInspection ExpediteissuanceofPOsforDirectManpower&EquipmentHiring.

2 0 2 4 2 0 2 5 T A

CAPEX PROJECTS TIMELINE

LV-08009** Routine HIMA ESD System* PO Incl FSE

42 Fans for Air Cooler ** PO Incl FSE

33kV SWBD 61MS5-1** PO Includes FSE

D-1501** In-House Installation

E-0704 E-8601 E-8602A/B/C E-8604* Inhouse Installation

Methanol PG Cooler E-1201** PR#7236 (AO)

LV-82011 HV-82005 HV-82008**** Inhouse Installation

Passivation Air Compressor** PO Includes FSE

Electronic Governor MT-0701 & MR-1401* PO Includes FSE

Super Cup Trays R-8201** PR#7244 (AO)

Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE

PV-52201/351 & PV-52401/402**** In-House Installation

MD-6102 PLC* PR Includes FSE

E-0001B** PR#7216 (TE)

E-0003** PR#7216 (TE)

Urea 2200 MTPD - PSV-8105 PSV-8106 PSV-8107 PSV-8108 **** Inhouse Installation

Urea 2200 MTPD - HV-82009 MOV-82003**** In-House Installation

Urea ESD**** ENG PR Includes FSE

Honeywell DCS* PO Includes FSE

Ammonia PG Cooler E-0301** PR#7241 (AO)

HP Carbamate Seperator D-8201*** PR#7244

Urea Stripper E-8201*** PR#7244 (AO)

Ammonia Plant

CONFIRMED MAJOR JOBS

Methanol Plant

CONFIRMED MAJOR JOBS

Urea Plant

Utilites Plant

Management Meeting to discuss the Replacement of two end and two side walls at the Methanol Reformer (North & East Walls) in TA 2025.

Meeting with Operations, Engineering & Maintenance: To discuss TA 2025 Urea Plant Jobs - Mods + Capex

Meeting with Medical Team - Turnaround Preparation

Meeting with Logistics Team - Turnaround Preparation