Model – Final Model Submission Construction Design (ABPL30041_2020_SM1)
Student name: Yan He Student number: 980425 Tutorial group: 06 Tutor:Andy Bosworth Section C
FRONT VIEW
Loads transfer RIGHT VIEW
FRONT VIEW
LEFT VIEW
Exisiting concrete slab
Ground water (depth below ground 800mm1400mm)
SILTY CLAY (high plasticity) SANDY CLAY (medium plasicity)
ROCK (suitable for supporting) GROUND CONDITION
Loads transfer
Pushed away when digging holes
Precast reinforced concrete
Segmental driven piles (350MM square pile) FOUNDATION
Under plank beam Full depth beam
Camber is induced in hollowcore slab
GROUND BEAMS
Base plate with anchor bars casting in
Starter bars
GROUND CONNECTIONS
Adjustable clips to adjust the level of suspended ceiling
Suspended flush plasterboard ceiling Soffit lining
SUSPENDED CEILING
Double glazed fixed glass window with 16mm airgap
Aluminium glazing adaptor Timber stud frame work: Kiln Dried Hard Wood
Support bracket Reinforcement of precast concrete panel
PRECAST CONCRETE PANEL & WINDOW
Wall tie & precast wall connection Bent plate clip with anchor bars
Panel connection Welded plate with N16 anchor full strength butt weld to plate
PRECAST CONCRETE PANEL
13mm flush plasterboard wall lining on stud frame Thermal/acoustic polyester batt insulation 20mm cavity continuous sarking double layers of 13mm plasterboard 50mm sound absorbent 90mm timber stud 70mm timber stud
TIMBER STUD WALL
aluminium screen sunshading
80x40x4mm aluminium channel gutter
75x75x3 square hollow section with Full Strength Butt Weld connections
WINDOWS
Cast in plate to precast facade with 6CFW site weld to frame colour matched caulking
Steel top hat section fixed to steel sub-frame using screws
continuous RFL sarking aluminium panel cladding
WINDOWS WITH CLADDING
Plasterboard ceiling on batten
First floor carpet
Ground floor Suspended flush plasterboard ceiling FLOORS & CEILINGS
Beam with Shortcrete for Fire protection 700WB115
Beam & hollowcore connection plate cleat with screw bolts installed
STEEL FRAMING
300PFC
Cleat with bolts bolted in joist C25019 Column & beam connection The cleat is welded on the column and it is bolted into the beam 200UC52
STEEL FRAMING
530UB92
End plate with 2M20 bolts in 200UC52
STEEL FRAMING
Flashing turn down Folded colorbond metal flashing
Wall tie & beam connection The cleat is welded on the column and it is bolted into the beam Wall tie: 250PFC
STEEL FRAMING
Need to re-spray the paint to avoid corrosion If hole is drilled on site Safety mesh
Loads transfer
Briding for purlin allows the purlin to resist wind loads
Mezzanine Hangers: 2 no. of M20 Rods hold the Mezzanine Beam Roof bracing: prevent buckling or rotation of trusses
ROOFING
colorbond metal sheet roof 3mm think Styrofoam thermal spacers Blanket sarking
Carpet 25mm THK structural particle board floor
Balustrade ROOFING & BALUSTRADE
metal deck is thin and need to be coated roof sheet need to be overlap according to the wind direction
Fix the roof sheets screw the sheet into purlin
ROOFING