ABPL20033 Construction Analysis A1

Page 1

ABPL20033 - Construction Analysis, Semester 2 - 2019 Dr Alberto Pugnale, Subject coordinator Dr Sofia Colabella, Senior Tutor Yan He, Tutor: Anastasia Sklavakis Yan He, 980426, 08/08/19 John Wardle Architects By Lake Wendouree House Tutorial no. 24 ASSIGNMENT 1

Melbourne School of Design, photo by Sofia Colabella


CONSERVATORY

1C

Floor System Reinforcement steel being installed and allow concrete to be poured and cure, once the concrete cure to adequate strength, install the waterproof membrane

03

Wall Systems After prototyping the bricks for patterns and finishes, the brick work being done and then it would be reviewed

07

10 08

10 05

04 07

Wall Systems Install Timber Veneer Panels (TV-01) in the conservatory room and thermal insulation on the external wall of the house with thickness of 120mm

BED Rm 4

1C

Services and Finishing Trades Marble countertop are fabricated and set up in the conservatory Window Systems Install double fixed glazing and operable glass louvres are built by AGP Group Services and Finishing Trades Random Stone Paving are paved in conservatory, finish putting the floor finishes Intermediate Floor Structure Timber strip flooring being installed and trimmed. Install thermal insulation on level one floor between floor joists

Structural System Reinforcement steel bars being installed and timber framing start from bottom level up to the first floor

Window Systems External door frames should be fixed and doors are fabricated

08

ABPL20033 - 2019, Yan He | 980426 |Tutorial 24 | Anastasia Sklavakis | p. 2

BED Rm 3


06

04

Roof System Install metal Roofing with base metal thickness of 0.42mm. Install safety mesh on the roof generally for contractor safety. Cover the structure with waterproof membrane Plumber fix the gutters before roof covering. Install thermal insulation (IN-02) Bradford Gold ceiling batts and Bradford Anticon Roof Blanket under. Install flashing, roof shading and cappings on the roof. Faรงade cladding fix system and then install the final roof cladding to that.

05

09 10

07

BEDROOM 4

Intermediate Floor Structure Carpenter will place the bearers first, then the timber joists. Timber strip flooring being installed and trimmed. Install thermal insulation (IN-03) on level one floor between floor joists.

09 Ceiling Structure 1 9mm villaboard (CL-03) fully taped onto the ceiling of conservatory. Allow 200mm minimum clearamce for spaces building louver actuators. Carpet finish over structural flooring

10

08 CONSERVATORY

Natural Ground Line

Services and Finishing Trades Random Stone Paving being built.Finish putting the floor finishes

01

03

Foundation Systems Demolishing work being undertaken. Excavation by machines and the uneven ground was filled in.

10

Structural System Reinforcement steel bars being installed. Timber framing start from bottom level up to the first floor. Ceiling Structure 13mm Plasterboard install on bedroom ceiling. Services and Finishing Trades Install air conditioiner fancoil unit.

Wall Systems Brick work being done. Waterproofing layer for bricks being install. Install the thermal insulation on the external wall with thickness of 120mm. Openings for windows & doors are left during brickworks. Lintels being install. Install VM zinc cladding on the east facade Window Systems Window manufacturers start to do measurement. Timber, windows and doors are fabricated Window frames (180 x 60 aluminium mullion) should be placed and finished by dulux powder coat. Vertical bulb seals down mullions and to the edge of the glass louvres Install flashing under timber window sill Install double glazing using the crane Paint Finish for external and internal timber window frames.

Floor System Reinforcement steel being installed. The concrete pouring into the mould. Allow concrete to cure once the concrete cure to adequate strength. Waterproofing membrane is being installed. Void former being installed Services and Finishing Trades Marble countertop are fabricated and set up in the conservatory.

ABPL20033 - 2019, Yan He | 980426 |Tutorial 24 | Anastasia Sklavakis | p. 2


Construction stages 1-5, summary

STAGE 01. Foundation systems: Excavation, demolition, footing 1.1 After obtaining building permit, hoardings are being wrapped 1.2 Demolishing work being undertaken and the debris and rubbishes are carried out of the site 1.3 Excavation by machines such as backhoe and a bulldozer to clean the crew clears the site of rocks, debris and trees 1.4 Site office is established and temporary services being set up 1.5 Site set out: Land surveyor works out the site boundary and boundary are pegged 1.6 Complete layout is marked on the ground with accurate dimension and orientation

STAGE 02. Foundation systems: Retainment and service pipes layout 2.1 Measuring out the design on the site 2.2 The foundation is laid out: Conduct the earthworks, level the site and put up the wooden formwork being as a template for pouring the concrete for footings 2.3 All the drains are now put in place 2.4 Install moisture barrier and special mesh for termite protection 2.5 Install rigid foam and rebar before pouring concrete slabs 2.6 In-ground service pipes are set out: Electrical outlets and plumbing pipes that run through the slab 2.7 Trenches being dug and footings has been digged out

STAGE 03. FLOOR SYSTEM: BASEMENT AND GROUND FLOOR STRUCTURE 3.1 Install formwork for blinding concrete and to rich ground adequate bearing capacity 3.2 Before pouring the concrete, the engineer would typically inspect 3.3 Reinforcement steel being installed and then prepare to the concrete pouring into the mould, allow concrete to cure once the concrete cure to adequate strength 3.4 After the concrete is cured, waterproofing membrane is being installed 3.5 Lay the sand bed 3.6 Void former being installed

STAGE 04. STRUCTURAL SYSTEM: PREPARATION AND COMPLETION OF BUILDING FRAME/STRUCTURE 4.1 Reinforcement steel bars being installed 4.2 Timber framing start from bottom level up to the first floor 4.3 Roof trusses get fixed in place 4.4 The installation of internal and external support structure has been done 4.5 Engineers, plumbers and electricians are able to install pipes for water, gas and power

ABPL20033 - 2019, Yan He | 980426 |Tutorial 24 | Anastasia Sklavakis | p. 2

STAGE 05. INTERMEDIATE FLOOR STRUCTURE 5.1 scaffolding start to be built to get to higher ground 5.2 Carpenter will place the bearers first, then the timber joists 5.3 Timber strip flooring being installed and trimmed 5.4 Install thermal insulation (IN-03) on level one floor between floor joists


Construction stages 6-10, summary

STAGE 06. ROOF SYSTEM: ROOF STRUCTURE AND COVER 6.1 Roof frames being constructed and put into the right position 6.2 Install metal Roofing (RF-01) over bedroom 4 with base metal thickness of 0.42mm 6.2 Install safety mesh on the roof generally for contractor safety 6.3 Cover the structure with waterproof membrane Plumber fix the gutters before roof covering to ensure that the guttering will fall to the position of the downpipes. 6.3 Install thermal insulation (IN-02) Bradford Gold ceiling batts and Bradford Anticon Roof Blanket under 6.4 Install flashing, roof shading and cappings on the roof 6.5 They have got the Façade cladding fix system and then install the final roof cladding to that, the light weight claddings such as timber and zinc are recommended to use

STAGE 07. WALL SYSTEMS: EXTERNAL WALLS AND CLADDINGS

STAGE 08. WINDOW SYSTEMS

7.1 Prototyping the bricks for patterns and finishes 7.2 Once determined the final plan, the brick work being done and then it would be reviewed for the façade 7.3 Waterproofing layer for bricks 7.4 Install the thermal insulation (IN-01) on the external wall of the house with thickness of 120mm 7.5 Openings for windows & doors are left during brickworks. Lintels being install 7.6 Install VM zinc cladding on the east facade of bedroom 4

8.1 Window manufacturers start to do measurement 8.2 Timber, windows and doors are fabricated 8.3 Window frames (180 x 60 aluminium mullion) should be placed in the right positions in the brick wall and finished by dulux powder coat in the conservatory. 8.4 Vertical bulb seals down mullions and to the edge of the glass louvres 8.5 Install flashing under timber window sill 8.6 Install double glazing using the crane 8.7 Paint Finish PA-08 for External timber window frames and PA-07 for internal timber window frames 8.8 External door frames should be fixed. After brickwork get completed, and doors could be installed

STAGE 09. INTERNAL PARTITIONS AND CEILING STRUCTURE 9.1 9mm villaboard (CL-03) fully taped onto the ceiling of conservatory and 13mm Plasterboard install on bedroom 4’s ceiling 9.2 Allow 200mm minimum clearamce for spaces building louver actuators 9.3 Install claddings (CD-05) on soffit level 9.4 Carpet finish over structural flooring 9.5 Joinery work: Timber Veneer Panels (TV-01) in the conservatory room

ABPL20033 - 2019, Yan He | 980426 |Tutorial 24 | Anastasia Sklavakis | p. 2

STAGE 10. SERVICES AND FINISHING TRADES 10.1 Install air conditioiner fancoil unit 10.2 Complete the services rough in: Rough in the mechanical system and electrical wiring system, the electrician will finish the internal lighting and power cables. Install the plumbing systems 10.3 Joinery: Use Select Grade Solid Timber (TM-02) for design features such as cabinets, shelving and architraves in bedroom 10.4 Random Stone Paving (ST-02) for conservatory and the outside courtyard 10.5 Finish putting the floor finishes 10.6 Marble countertop are fabricated and set up in the conservatory