Industrialized Building System (IBS)

Page 1

GROUP MEMBER:


Concepts and Framework……………………………………… 02

IBS Score Calculation…………………………………… 63

Conclusion……………………………………………………… 65

IBS Components ………………………………………………..…… 15

Sequence Of Construction…………………………………….. 38

Drawings………………………………………………………………….. 45

References……………………………………………………… 67



Introduction of Industrialised Building System (IBS)

Advantages

Cost saving

Short Construction Time

Less labour required

Minimal Wastage

Disadvantages

Lack of aesthetics value

IBS components are expensive

Lack of skilled labours

Improper planning leads to failure


Types of Industrialised Building System (IBS)

Hamakareem.M, n.d)

Precast Concrete System

Blockwork System

Steel Frame System

Steel Formwork System

Prefabricated Timber System


Introduction to Blockwork System

Concrete Masonry Unit (CMU)

Figure 1.7: Blockwork often used to build internal walls and retaining walls (universalsoloads, 2018)

Solid Concrete Block

Hollow-core Block


Advantages ● ● ● ●

Disadvantages ●

Figure 1.8: Blockwork wall (anuntul, 2012)


Figure 1.9: Solid Block Wall (CivilBlock, 2014)

Figure 1.10: Hollow-core concrete block (Lawsons, n.d)


Figure 1.11: Concrete stretcher block (

)

Figure 1.12: Concrete corner block (

Figure 1.13: Concrete pillar block (

)

)


Figure 1.14: Frogged brick block (

)

Figure 1.15: Bullnose block (

Figure 1.16: Lintel block (

)

)


Figure 1.17: Partition concrete block (

Figure 1.18: Jamb concrete block (

)

)


Figure 1.19: The weigh batcher is used to measure the proper amounts of each material (Concrete Block, n.d)

Selection and proportion of Ingredients

Figure 1.20: The concrete comes off a conveyor and is forced into molds. The rotating brushes remove loose material. (Concrete Block, n.d)

Mixing of ingredients

Figure 1.21: In the block machine, the concrete is forced downward into molds (Concrete Block, n.d)

Molding

Figure 1.22: The curing rack is rolled onto a set of rails and moved into a curing kiln.(Concrete Block, n.d)

Curing


Figure 1.23: Layout ("Concrete Block Walls", 2018)

1. Layout

Figure 1.24: Positioning the first block ("Concrete Block Walls", 2018)

2. Mixing

Figure 1.25: Applying mortar ("Concrete Block Walls", 2018)

3. Apply Mortar


Figure 1.26: Aligning using string ("Concrete Block Walls", 2018)

4. Filling

Figure 1.29: Laying mesh("Concrete Block Walls", 2018)

7. Laying metal lath

Figure 1.27: Building paper as control joint ("Concrete Block Walls", 2018)

5. Control Joints

Figure 1.30: Laying top course block ("Concrete Block Walls", 2018)

8. Setting top course block

Figure 1.28: Applying mortar ("Concrete Block Walls", 2018)

6. Strike the Mortar

Figure 1.31: Capping ("Concrete Block Walls", 2018)

9. Capping


Case Study

Sekolah Menengah Kebangsaan Bandar Enstek Education school with facilities for secondary science, art streams and handicapped students Bandar Baru Enstek, Negeri Sembilan 24 months Ministry of education NIL Management Consultancy yed Ahmad Ibrahim Associate Architects Sdn Bhd ATE Consult Sdn. Bhd. Dasacon Sdn. Bhd. Integrated Brickwork System Load Bearing Blockwork System

Figure 1.33: SMK Bandar Enstek (Foursquare, 2016)

Structural: Slab: Precast concrete slab Roof : Prefab metal roof truss

0.8 1.0

Full IBS Factor Full IBS Factor

Wall : Blockwork System

0.5

Partial IBS Factor

Foundation

Prefabricated concrete staircase Prefabricated concrete slab Prefabricated blockwork Prefabricated metal roof truss

Figure 1.32: Construction of SMK Bandar Enstek (Foursquare, 2016)




Block work wall arrangement

, the most used bond and is composed of . Since there are no headers in this bond, metal ties are usually used. Running bond is used largely in cavity wall construction and veneered walls of brick, and often in facing tile walls where the bonding may be accomplished by extra width stretcher tile.

â—? â—?

Easy to execute Provide more strength across vertical planes than stack bond

Figure 2.8: Details of blockwork arrangement (Lee, 2018)

Figure 2.7: Running bond blockwork arrangement (Lee, 2018)


Grouting and reinforcing

Joint reinforcement is used in addition to when bond beams are spaced at more than 1200mm. It is a ladder of 9 gauge (3.7mm) galvanized wire , which positions a wire in the centre of each block faceshell. It is spaced at either a maximum of 600mm, 400mm for stack pattern, or at 400mm in seismic zones. Joint reinforcement resists wall cracking and can contribute to the horizontal steel area in the wall.

A control joint is a , but with a on one side so that tensile stress cannot develop across the joint. If control joints are not provided, a concrete masonry wall may crack as it shrinks over time.

Grout & Reinforcing where required Terminate horizontal joint reinforcement at control joint

Building paper Grout fill

Horizontal steel bars

Caulking joint

Figure 2.9: Joint reinforcement (Yuen, 2018)

Figure 2.10: Details of control joint (Yuen, 2018)


Grouting and reinforcing

Grouting techniques have been developed to ensure that walls are completely grouted Low- and high-lift grouting are both traditional grouting methods, with the difference being the height of lift. Lifts five feet or less are considered low lift, while lifts greater than five feet are considered to be high lift.

Stop grout 1� form top of pour to create shear key

U- block units w/ solid bottom at bond beam course

Grout in bond beams & reinforced vertical cells placed in top of wall after wall has been laid up.

Cells containing reinforcement are filled solidly with grout; vertical cells should provide a continuous cavity free of mortar dropping

Vertical reinforcement for closed- end concrete masonry units can be set after wall has been laid.

Cleanout openings @ base of vertically reinforcement cells, 32� O.C max spacing for solid grouted walls. Remove mortar droppings through cleanouts and verify placement & location of vertical reinforcement; form over openings before placing grout

Rebar positioner, wall tie or other device to position vertical reinforcement, as required. Horizontal reinforcement placed in bond beams as wall is laid up Note: Grout lifts not to exceed 5ft.

Standard cmu w/ cross webs knocked out/ at bond beam course Metal lath, mesh, or wide screen placed in mortar joints under knockout bond beam courses to prevent filing of ungrouted cells Figure 2.11: Grouting procedure (Yuen, 2018)


Wall to Wall Connection

Advantages Block system ●Good heat & sound insulation; energy saving ●2 hours fire rating approved by Sirim ●Cheaper and simple footing along the wall is required for single storey

Grout and reinforcing

Block produced by machine ●Quality control ●Better strength ●No cracks ●Consistent size and compaction

50% interlocking to bond walls Control joint

Speed of erecting Block Wall ●3 to 4 times faster than conventional method ●Environmentally friendly; less formworks ●Consistent size; less wastage Load Bearing Wall ●Need no formwork as columns and beams are cast within blocks ●Save ~ 2/3 of reinforcement compared to conventional method

Web wall

Control joint

Flange wall

Figure 2.12: Details of intersection wall (Yuen, 2018)


Column and Beam

Reinforcing bar Concrete masonry bond beam units

610 x 610 corner bar at intersection ef

Bond beam reinforcing Control joint

Hollow core stretcher block

Vertical reinforcement Figure 2.14: Bond beam plan detail (Yuen, 2018)

Figure 2.13: Details of column and beam (Yuen, 2018)


Length as required to develop reinforcement

Grout and reinforcing as required

Flange wall

Rake out mortar for control joint

Knock out face shell of bond beam unit for continuous grout & reinforcement

Rake out mortar for control joint Web wall Figure 2.15: Bond beams at intersecting walls (Yuen, 2018)


Precast Hollow core slab

Advantages ● ●

● ● ●

● ●

Disadvantages ● ●

Figure 2.16: Hollow core slab (Hardprecast, 2018)


1

1. Loading to site

2

3 Figure 2.21: Sectional view of hollow core slab (Lee, 2018)

Figure 2.17: Loading (Orak factory,2015)

2. Hoisting

1 Figure 2.18: Hoisting (Orak factory,2015)

3. Grouting 2

Figure 2.19: Grouting (Wikizie,2018)

Figure 2.22: Details of Hollow core slab (Lee, 2018)

4. Finishing

Figure 2.20: Screeding (Wikizie,2018)


Figure 2.23: Slab to internal beam connection (Tan, 2018)

Figure 2.24: Connection of different levels of slab (Yuen,2018)


1 This detail shows a precast concrete plank bearing at an exterior CMU wall. The wall has horizontal joint reinforcement at 16″ o.c. vertically. The plank has reinforcement and grout at the keyways, and the floor bears on a concrete masonry unit (CMU) bond beam. The wall is grouted and reinforced vertically as required, and the bars are lapped to achieve sufficient development strength per structural design. The brick veneer is not shown for clarity.

3

2

4

5 6 11 7 9

8

10

13

11 12

Figure 2.25: Slab to external wall connection (Yuen 2018)


1

This detail shows a precast concrete plank bearing at an interior CMU wall. The wall has horizontal joint reinforcement at 16″ o.c. vertically. The plank has continuous reinforcement and grout at the keyways, and the floor bears on an interior CMU bond beam. The wall is grouted and reinforced vertically as required, and the bars are lapped to achieve sufficient development strength per structural design.

2

4

5 6

3

8 7

9

10

Figure 2.26: Slab to internal wall connection (Yuen, 2018)


Door and Window

Figure 2.28: Elevation view of door connection (Tan, 2018)

Figure 2.27: Door and window connection (Lee, 2018)


Staircase

Advantages ● ●

● ●

Disadvantages ●

Figure 2.29: Precast staircase (Staircase design,2018)


Figure 2.30: Craft template (stair kosour, 2018)

1. Craft template

Figure 2.31: During installation (stair kosour, 2018)

2. During installation

Figure 2.32: Finishing (stair kosour, 2018)

3. Finishing


1

1 1

3

2

3

3 4

5

Figure 2.33: Stair to floor connection (Lee, 2018)

Stair to Floor Connection

2 4

Figure 2.34: Landing to wall connection (Lee, 2018)

Landing to Wall Connection

1 2

4

2 3

Figure 2.35: Landing to down riser connection (Lee, 2018)

Figure 2.36: Landing to up riser connection (Lee, 2018)

Landing to Down Riser Connection

Landing to Up Riser Connection



Advantages ● Apex Joint

Web Joint

● ● ● ● ●

Web Joint

Disadvantages ●

Heel Joint

● Figure 2.42: Roof truss joint connection (Tan, 2018)


3 Cladding to batten load transfer through self-drilling screw

1 2 6 5

4

Figure 2.43: Roof truss joint connection (Tan, 2018)

Batten to rafter load transfer through self-drilling screw

Figure 2.44: Batten to roofing and truss connection (Yuen, 2018)


Ceiling

Galvanized Steel Wire

Wall Angle

Main Runner

Cross Tee

Figure 2.45: Ceiling connection (Lee, 2018)


Toilet Pod

Integrated, pretested plumbing and electric, code compliant & ready for final hookup

● ●

Completely finished interior clean & ready to use

● ● ●

Moisture-resistant abuse resistant wallboard, glued & screwed to framing

Waterproof, thin profile subfloor supports floor finish while providing a seamless transition to the adjoining floor.

Figure 2.46: Toilet pod detail (Tan, 2018)

Advantages Faster construction programmes for accelerated occupation Cost savings over traditional on-site installation Elimination of many on-site health and safety issues Highest standards of quality control Minimal on-site skilled labour required


Installation of Toilet Pod

Figure 2.47: On site delivery (oldcastlesurepods, 2017)

Figure 2.51: MEP connections (oldcastlesurepods, 2017)

Figure 2.48: Hoisting (oldcastlesurepods, 2017)

Figure 2.52: Toilet pod detail (oldcastlesurepods, 2017)

Figure 2.49: Toilet pod in building (oldcastlesurepods, 2017)

Figure 2.53: Exterior finish (oldcastlesurepods, 2017)

Figure 2.50: Toilet pod in final location (oldcastlesurepods, 2017)

Figure 2.54: Toilet pod (oldcastlesurepods, 2017)



Construction Process on Site

Figure 3..1 : Excavation (Youtube,2017)

Figure 3.2: Formwork for foundation (Shutterstock,2018)

Figure 3.3: Strip foundation (Shutterstock,2018)

Setting out and excavation

Construction of Formwork

Footing


Construction Process on Site

Figure 3.4 : Foundation wall (Binaan,2017)

Foundation wall A wall built from the concrete strip foundation to the height of the placement of hollow core slab. Besides,

Figure 3.5: Backfilling (Construction Mentor,2017)

Backfilling

Figure 3.6: Installation of Slab (Binaan,2017)

Installation of Slab Hollow core slabs are then installed and attached by reinforcement bars then filling with sand-cement grout.


Construction Process on Site

Figure 3.7: Installation of Walls & Toilet pod (Binaan,2017)

Installation of Walls & Toilet pod

Figure 3.8: Installation of Lintel & Beam (Youtube,2018)

Installation of Lintel & Beam

Figure 3.9 : Construction of 3 storeys (Wallnet,2017)

Repeat the same procedure


Construction Process on Site

Figure 3.10: Installation of trusses and battens(Youtube,2018)

Figure 3.11: Corrugated steel roofing (rockthelhc,2018)

Installation of roof trusses and battens

Installation of Roofing

Figure 3.12 : Completed blockwork house (Youtube, 2018)

Finishes


Construction Process of Model

Figure 3.13: Strip foundation (Tan 2018)

Figure 3.14: Partial wall (Tan 2018)

Figure 3.15: Cast in situ slab (Tan 2018)

Figure 3.16: External & Internal Wall (Tan 2018)

Figure 3.17: Lintel (Tan 2018)

Figure 3.18: Hollow core slabs (Tan 2018)

Figure 3.19: Solid CMU encloses perimeter (Tan 2018)

Figure 3.20: External & Internal Wall (Tan 2018)


Construction Process of Model

Figure 3.21: Screeding (Tan 2018)

Figure 3.22: Lintel (Tan 2018)

Figure 3.23: Construction of second floor (Tan 2018)

Figure 3.25: Final Model (Tan 2018)

Figure 3.24: Construction of roof (Tan 2018)



1

1A

2

3

4

4A

5

6

7

7A

8

9

8A

10 10A

9A

11

12

13 13A

14

16 16A

15

21600

2400

9600

200

600

1200

200

2400

600

1200

600

200

200

2200

2400

9600

200

2200

200

600

1200

A

WD 1

3600

A1

WD 1

WD 1

BEDROOM 3

MASTER BEDROOM

WD 1

MASTER BEDROOM

BEDROOM 3

11.52 SQM

6.96 SQM

6.96 SQM

FFL 0.00

FFL +0.20

FFL +0.20

600

200

400 200

B1

UP 50

DR 1

DR 1

YARD

5.72 SQM

5.72 SQM

FFL +0.15

FFL +0.15

7

WD 1

DN 50

F G

600 400 200 400

WD 2

3.36 SQM

C'

8.88 SQM

DR 1

BATH 2 DN 50

DR 1

DR 1

1

FFL +0.20

3.36 SQM

MASTER BATHROOM

FFL +0.20

3

BEDROOM 2

FFL +0.15

8.32 SQM

FFL +0.20

FFL +0.15

WD 2

DN 50 CORRIDOR

DN 50

3.36 SQM

600

E1

MASTER BATHROOM

WD 1

DN 50

200 400

10000

E

8.32 SQM

DR 1

DR 1

5

CORRIDOR

WD 2

FFL +0.20

DR 1

YARD

DR 1

11.52 SQM

FFL +0.20

DR 1

B

D

1200

2400

B

DR 1

C

200

200

A

600

FFL +0.15

BEDROOM 2

C

8.88 SQM

FFL +0.20

UP KITCHEN

KITCHEN

6.6 SQM

6.6 SQM

FFL +0.20

FFL +0.20

DR 1

DN 50

BATH 2 3.36 SQM

FFL +0.15

WD 2

CORRIDOR 18.72 SQM

H

FFL +0.15

H1 2600

DN 50

BALCONY 2.86 SQM

FFL +0.15

DN 50

DR 3

LIVING ROOM

DINING AREA

10.4 SQM

7.72 SQM

FFL +0.20

FFL +0.20

DR 2

FOYER

FOYER

1.28 SQM

1.28 SQM

FFL +0.20

FFL +0.20

UP 50

UP 50

DINING AREA

DR 2

DR 3

LIVING ROOM

7.72 SQM

10.4 SQM

FFL +0.20

FFL +0.20

BALCONY 2.86 SQM

FFL +0.15

I

200

WD 3

I1 A'

B' 1 unit area

= 76.98 SQM

Corridor area

= 18.72 SQM

N

Total floor area = 76.98 + 18.72 + 76.98 = 172.68 SQM

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.1.1 GROUND FLOOR PLAN

Date

5 October 2018

Scale

1:75

Drawn by

01 001

17

Checked by Page number

SHEET NO.

28 September 2018

46


1

1A

2

3

4

4A

5

6

7

7A

8

9

8A

10 10A

9A

11

12

13 13A

14

16 16A

15

21600

2400

9600

200

600

1200

200

2400

600

1200

600

200

200

2200

2400

9600

200

2200

200

600

1200

A

WD 1

3600

A1

WD 1

WD 1

WD 1

MASTER BEDROOM

MASTER BEDROOM

BEDROOM 3

BEDROOM 3

11.52 SQM

6.96 SQM

6.96 SQM

FFL +3.45

FFL +3.45

FFL +3.45

600

200

DR 1

400 200

DR 1

DR 1

YARD

5.72 SQM

5.72 SQM

FFL +3.40

FFL +3.40

7

WD 1

DN 50

G

600

MASTER BATHROOM

400 200 400

MASTER BATHROOM

FFL +3.45

WD 2

3.36 SQM

C'

8.88 SQM

DR 1

BATH 2 DN 50

DR 1

DR 1

1

FFL +3.45

3.36 SQM

8.32 SQM

3

BEDROOM 2

FFL +3.40

DN 50 CORRIDOR

DN 50

FFL +3.45

FFL +3.40

WD 2

WD 1

DN 50

3.36 SQM

600

F

8.32 SQM

200 400

10000

E1

WD 2

DR 1

DR 1

5

CORRIDOR

E

FFL +3.45

DR 1

YARD

B1

11.52 SQM

DR 1

B

D

1200

2400

B

DR 1

C

200

200

A

600

FFL +3.40

BEDROOM 2

C

8.88 SQM

FFL +3.45

UP KITCHEN

KITCHEN

6.6 SQM

6.6 SQM

FFL +3.45

FFL +3.45

DR 1

DN 50

BATH 2 3.36 SQM

FFL +3.40

WD 2

CORRIDOR 18.72 SQM

H

FFL +3.40

H1 2600

DN 50

BALCONY 2.86 SQM

FFL +3.40

DN 50

DR 3

LIVING ROOM

DINING AREA

10.4 SQM

7.72 SQM

FFL +3.45

FFL +3.45

DR 2

FOYER

FOYER

1.28 SQM

1.28 SQM

FFL +3.45

FFL +3.45

UP 50

UP 50

DINING AREA

DR 2

DR 3

LIVING ROOM

7.72 SQM

10.4 SQM

FFL +3.45

FFL +3.45

BALCONY 2.86 SQM

FFL +3.40

I

200

WD 3

I1 A'

B' 1 unit area

= 76.98 SQM

Corridor area

= 18.72 SQM

N

Total floor area = 76.98 + 18.72 + 76.98 = 172.68 SQM

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.1.2 FIRST FLOOR PLAN

Date

5 October 2018

Scale

1:75

Drawn by

02 002

17

Checked by Page number

SHEET NO.

28 September 2018

47


1

1A

2

3

4

4A

5

6

7

7A

8

9

8A

10 10A

9A

11

12

13 13A

14

16 16A

15

21600

2400

9600

200

600

1200

200

2400

600

1200

600

200

200

2200

9600

200

2400

2200

200

600

1200

A

WD 1

3600

A1

WD 1

WD 1

WD 1

MASTER BEDROOM

MASTER BEDROOM

BEDROOM 3

BEDROOM 3

11.52 SQM

6.96 SQM

6.96 SQM

FFL +6.65

FFL +6.65

FFL +6.65

600

200

DR 1

400 200

DR 1

DR 1

YARD

5.72 SQM

5.72 SQM

FFL +6.60

FFL +6.60

13

WD 1

DN 50

F G

600

MASTER BATHROOM

400 200 400

MASTER BATHROOM

FFL +6.65

WD 2

3.36 SQM

C'

8.88 SQM

DR 1

BATH 2 DN 50

DR 1

DR 1

19

FFL +6.60

BEDROOM 2

C

8.88 SQM

DN

FFL +6.65

3.36 SQM

8.32 SQM

17

BEDROOM 2

FFL +6.60

DN 50 CORRIDOR

DN 50

FFL +6.65

FFL +6.60

WD 2

WD 1

DN 50

DR 1

DR 1

15

8.32 SQM

3.36 SQM

600

E1

WD 2

200 400

10000

CORRIDOR

E

FFL +6.65

DR 1

YARD

B1

11.52 SQM

DR 1

B

D

1200

2400

B

DR 1

C

200

200

A

600

FFL +6.65

KITCHEN

KITCHEN

6.6 SQM

6.6 SQM

FFL +6.65

FFL +6.65

DR 1

DN 50

BATH 2 3.36 SQM

FFL +6.60

WD 2

CORRIDOR 18.72 SQM

H

FFL +6.60

H1 2600

DN 50

BALCONY 2.86 SQM

FFL +6.60

DN 50

DR 3

LIVING ROOM

DINING AREA

10.4 SQM

7.72 SQM

FFL +6.65

FFL +6.65

DR 2

FOYER

FOYER

1.28 SQM

1.28 SQM

FFL +6.65

FFL +6.65

UP 50

UP 50

DINING AREA

DR 2

DR 3

LIVING ROOM

7.72 SQM

10.4 SQM

FFL +6.65

FFL +6.65

BALCONY 2.86 SQM

FFL +6.60

I

200

WD 3

I1 A'

B' 1 unit area

= 76.98 SQM

Corridor area

= 18.72 SQM

N

Total floor area = 76.98 + 18.72 + 76.98 = 172.68 SQM

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.1.3 SECOND FLOOR PLAN

Date

5 October 2018

Scale

1:75

Drawn by

03 003

17

Checked by Page number

SHEET NO.

28 September 2018

48


1

1A

2

3

4

4A

5

6

7

7A

8

9

8A

10 10A

9A

11

12

13 13A

14

16 16A

15

21600

2400

9600

200

1200

2400

200

600

1200

600

200

2200

200

2400

200

2200

200

600

1200

600

200

1200

2400

600

200

200

A

600

9600

3600

A1

FALL 30º

E1 F G

400 200 400

E

600

D

200 400

C

10000

B1

600

400 200

B

H

FALL 30º

I

200

2600

H1

I1

N

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.2 ROOF PLAN

Date

5 October 2018

Scale

1:75

Drawn by

04 004

17

Checked by Page number

SHEET NO.

28 September 2018

49


16A 16

13A 13

14

15

12

11

10A 10

9A

9

8

8A

7A

7

5

6

4A

4

2

3

1A

1

21600

2400

9600

200

600

1200

2400

200

600

1200

600

200

2200

200

9600

200

2400

200

2200

600

1200

600

200

2400

1200

600

200

ROOF LVL (FFL +9.60)

SECOND FLOOR LVL (FFL +6.65)

FIRST FLOOR LVL (FFL +3.45)

(FFL +0.20) GROUND FLOOR LVL GROUND LVL (FFL 0.00) BL 5

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.3.1 NORTH ELEVATION

Date

5 October 2018

Scale

1:75

Drawn by

05 005

17

Checked by Page number

SHEET NO.

28 September 2018

50


1

1A

2

3

4

4A

5

6

7

7A

8

9

8A

10 10A

9A

11

12

13 13A

14

16 16A

15

21600

2400

9600

200

600

1200

2400

200

600

1200

600

200

2200

200

9600

200

2400

2200

200

600

1200

600

200

2400

1200

600

200

ROOF LVL (FFL +9.60)

SECOND FLOOR LVL (FFL +6.65)

FIRST FLOOR LVL (FFL +3.45)

(FFL +0.20) GROUND FLOOR LVL GROUND LVL (FFL 0.00)

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.3.2 SOUTH ELEVATION

Date

5 October 2018

Scale

1:75

Drawn by

06 006

17

Checked by Page number

SHEET NO.

28 September 2018

51


I1

200

I

H1

A

2600

7200

ROOF LVL (FFL +9.60)

SECOND FLOOR LVL (FFL +6.65)

FIRST FLOOR LVL (FFL +3.45)

GROUND FLOOR LVL (FFL(FFL +0.20) +0.20) GROUND FLOOR LVL GROUNDGROUND LVL (FFLLEVEL 0.00) (FFL 0.00)

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.3.3 EAST ELEVATION

Date

5 October 2018

Scale

1:75

Drawn by

07 007

17

Checked by Page number

SHEET NO.

28 September 2018

52


I

H1

A

I1

10000

7200

2600

200

ROOF LVL (FFL +9.60)

SECOND FLOOR LVL (FFL +6.65)

FIRST FLOOR LVL (FFL +3.45)

BL 3

GROUND FLOOR LVL (FFL +0.20) GROUND LVL (FFL 0.00)

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.3.4 WEST ELEVATION

Date

5 October 2018

Scale

1:75

Drawn by

08 008

17

Checked by Page number

SHEET NO.

28 September 2018

53


I1

A

10000

ROOF LVL (FFL +9.60) BL 1 BL 4

SECOND FLOOR LVL (FFL +6.65) BL 6

BL 2

FIRST FLOOR LVL (FFL +3.45)

GROUND FLOOR LVL (FFL +0.20) GROUND LVL (FFL 0.00)

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.4.1 SECTION A-A'

Date

5 October 2018

Scale

1:75

Drawn by

09 009

17

Checked by Page number

SHEET NO.

28 September 2018

54


I

H1

A

I1

10000

7200

2600

200

ROOF LVL (FFL +9.60)

SECOND FLOOR LVL (FFL +6.65)

FIRST FLOOR LVL (FFL +3.45)

GROUND FLOOR LVL (FFL +0.20) GROUND LVL (FFL 0.00)

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.4.2 SECTION B-B'

Date

5 October 2018

Scale

1:75

Drawn by

10 010

17

Checked by Page number

SHEET NO.

28 September 2018

55


16A 16

13A 13

14

15

12

11

10A 10

9A

9

8

8A

7A

7

5

6

4A

4

2

3

1A

1

21600

2400

9600

200

600

1200

2400

200

600

1200

600

200

2200

200

9600

200

2400

2200

200

600

1200

600

200

1200

2400

600

200

ROOF LVL (FFL +9.60)

SECOND FLOOR LVL (FFL +6.65)

FIRST FLOOR LVL (FFL +3.45)

(FFL +0.20) GROUND FLOOR LVL GROUND LVL (FFL 0.00)

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.5 SECTIONAL PERSPECTIVE C-C'

Date

5 October 2018

Scale

1:75

Drawn by

11 011

17

Checked by Page number

SHEET NO.

28 September 2018

56


PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.6 AXONOMETRIC

Date

5 October 2018

Scale

1:250

Drawn by

12 012

17

Checked by Page number

SHEET NO.

28 September 2018

57


1

1A

2

3

4

4A

5

6

7

7A

8

9

8A

10 10A

9A

11

12

13 13A

14

16 16A

15

21600

2400

9600

200

1200

2400

200

600

1200

600

200

2200

200

2400

200

2200

200

600

1200

600

200

1200

2400

600

200

200

A

600

9600

3600

A1

E1 F G

400 200 400

E

600

D

200 400

C

10000

B1

600

400 200

B

H

I

200

2600

H1

I1

N

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.7 FOUNDATION PLAN

Date

5 October 2018

Scale

1:75

Drawn by

13 013

17

Checked by Page number

SHEET NO.

28 September 2018

58


1

1A

2

3

4

4A

5

6

7

7A

8

9

8A

10 10A

9A

11

12

13 13A

14

16 16A

15

21600

2400

9600

200

1200

2400

200

600

1200

600

200

2200

200

2400

200

2200

200

600

1200

600

200

1200

2400

600

200

200

A

600

9600

A1 SL1

SL1

SL1

3600

SL1

SL11

SL11

B

F G

600

400 200

E1

SL3

SL7

SL3

SL7

400 200 400

E

SL12

SL11

SL13

600

D

SL2

SL2

SL7

SL3

SL7

SL3

SL8

SL4

SL13

SL15 200 400

C

10000

B1

SL4

SL8

SL13

SL13

H SL15

H1 SL9

2600

SL5

SL13

SL13

SL9

SL5

SL9

SL5

SL10

SL6

I

200

SL15 SL5

SL9

SL6

SL10

SL14

SL14

SL16

I1

N

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.8 STRUCTURAL FIRST & SECOND FLOOR PLAN

Date

5 October 2018

Scale

1:75

Drawn by

14 014

17

Checked by Page number

SHEET NO.

28 September 2018

59


1

1A

2

3

4

4A

5

6

7

7A

8

9

8A

10 10A

9A

11

12

13 13A

14

16 16A

15

21600

2400

9600

200

1200

2400

200

600

1200

600

200

2200

200

2400

200

2200

200

600

1200

600

200

1200

2400

600

200

200

A

600

9600

3600

A1

E1 F G

400 200 400

E

600

D

200 400

C

10000

B1

600

400 200

B

H

I

200

2600

H1

I1

N

PROJECT TITLE

DRAWING TITLE

DRAWING NO. Starting Date

TAYLOR’S UNIVERSITY Wisdom • Integrity • Excellence

BLD 61403 BUILDING TECHNOLOGY 1 PROJECT 1 INDUSTRIALISED BUILDING SYSTEM

4.9 STRUCTURAL ROOF PLAN

Date

5 October 2018

Scale

1:75

Drawn by

15 015

17

Checked by Page number

SHEET NO.

28 September 2018

60



IBS Score Calculation

690.72 SQM

84.2 x 3 = 252.6 66.4 x 3 = 199.2 451.8m

0.5 0.5

172.68 / 690.72 = 0.25

50 x 0.7 x 0.25 = 8.75

345.36 / 690.72 = 0.5

50 x 0.8 x 0.5 = 20

172.68 / 690.72 = 0.25

50 x 1.0 x 0.25 = 12.5

1.0

41.25

252.6 / 451.8 = 0.56 199.2 / 451.8 = 0.44

20 x 0.5 x 0.56 = 5.6 20 x 0.5 x 0.44 = 4.4

1.0

10

42 / 48 x 100% = 88% 39 / 39 x 100% = 100% 100% 62 / 92 x 100% = 67.4%

4 4 4 2

3/3 x 100% = 100% 3/3 x 100% = 100% 3/3 x 100% = 100%

2 2 2 20 71.25



Conclusion

IBS score of 71.25/100, t



References



Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.