Construction Design

Page 1

AND BUILDING TECTONICS

Accoding to the conceptual sketches, the building is a concrete building with pocket windows forming a pattern on northern facade, with balconies concealed behind. The north-eastern facade is filled with curtain wall glazing. The building also has a metal roof with flat roof terrace concealed behind the roof form.

The building tectonics respect the design intents by using the relevant materials.

The northern facade is built with precast concrete panels. The upper levels of the facade have openings with balconies behind. Meanwhile, the ground floor level has double glazed windows. These openings and windows together form a unique pattern on the concrete facade.

The north-eastern facade is built with curtain wall glazing on upper levels. Taking in consideration of climate condition, the curtain wall facade is further fitted with operable aluminium louvres to manipulate sun levels into the interior.

The building has a metal roof with flat roof terrace concealed behind the roof form. The roof itself also acts as parapet along the terrace for fall prevention.

The entrance at the ground floor level has a unique form unlike the upper levels. It is signified with curve wall which takes reference from the curve shape along western facade (refer to A101 and A102).

Green buffer strip with deciduous plants is designed between building and road to act as windbreak, provide shading and some sound insulation. It also provides aesthetic and environmental values. Some parts of the ground are installed with permeable pavers to provide walking path to the visitors.

DESIGN INTENT
JIA MIN CHEONG PROJECT THE PADDOCK BATMAN AVENUE VICTORIA DRAWING HERO IMAGE

LEGEND

ADJACENT BUILDING

EXPLANATORY SCHEDULE

STRUCTURAL GRID

The building is a irregular-shape building with curves and wide angles. The structural grid is imposed according to the shape of the building. The distance of gridline is spaced at most 7500mm, which is the maximum span of post tension slab.

PLACEMENT OF STRUCTURAL ELEMENTS IN PLAN

The building core is placed along the southern wall. It is formed out of lift and fire stairs core, and acts as a combination of shear wall and sway frame. This offers lateral stability to the building. The structural columns are distributed at intersection points of grid lines. They give stability in two orthogonal directions from the building core. The main stairs are placed between gridlines to avoid cutting through slab hence avoiding the need of additional structural support.

A C D

BIRRARUNG MARR

SCALE 1:100

DRAWN BY JM CHEONG

DATE 05.09.2022

REVISION 10.10.2022

PROJECT

A1.01

6130 4370 R5000 A C D E 1 2 5 6 4 3 E D C A' A 1 2 3 4 FIRE STAIRS FIRE CONTROL ROOM G B B 35o 7500 7500 7500 6400 7500 7340 7500 7500 5850 7500 GF ROOM 4 52.2m2 GF ROOM 3 35.8m2 GF ROOM 2 51.0m2 GF ROOM 1 46.2m2 ENTRANCE AND FOYER GF ROOM 5 53.4m2 GF ROOM 6 52.2m2 GF ROOM 7 43.3m2 GF ROOM 8 52.2m2 FIRE EXIT CORE 145 o 3580 A A A201 A201 28° F 6980 1980 2400 6560 COL. NGL 4,900 FFL 5,050 FALL1:80 W01 W03 W04 W05 W06 W07 W08 W02 D01 D02 D03 D04 D05 D06 D07 D08 D10 D09 D11 D12 D13 D14 CP1 SF1 CP2 SF1 CP2 COL. COL. CP1 CP1 CP1 CP1 CP1 SF1 SF1 SF1 SF1 SF1 SF1 SF1 SF1 SF1 SF1 SF1 SF1 SF1 1960 ROOFLINE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE CP1 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 2580 R2500 5710 COL. COL. COL. COL. COL. COL. CP1 CP2 SF1 150mm THK PRECAST CONCRETE PANEL MIN 10mm GAP 90mm STEEL STUD FRAME WITH SARKING 13mm GYPSUM BOARD FINISHES NOTE: O/A WALL TO ACHIEVE MIN THERMAL RATING OF R2.8 150mm CONCRETE PANEL RAW FINISHES 120mm STEEL STUD FRAME 13mm GYPSUM BOARD FINISHES AT BOTH SIDES INSULATION AS REQUIRED BY ACOUSITC ENG
HERO IMAGE
WALL FLOOR CONCRETE SLAB FLOOR WITH 10mm THK EPOXY CONCRETE SEALER CONCRETE PAVING SLABS ON BEDDING SAND PERMEABLE PAVERS CERAMIC TILES
OVERHANG ROAD
GABION WALL
THE PADDOCK BATMAN AVENUE
JIA MIN CHEONG
VICTORIA
DRAWING GROUND FLOOR PLAN
DRAWING NO.
E D C A' A G
F 2
The structural grid and placement of structural elements in plan are repeated across floors (refer further to A102). This ensures the stability gets all the way down to the ground foundation while leading to a more economical structure.
B

1960 ROOFLINE

EXPLANATORY SCHEDULE

PRECAST CONCRETE PANEL FACADE - 150mm thick

- 40 MPa reinforced concrete - reinforced with SL92 in centre line of panel The precast concrete panels are load bearing hence they transfer vertical load from other building elements and cannot be removed without affecting the strength and stability of the building. They also provide lateral stabilty as they are able to resist wind and seismic forces.

Concrete precast panels also provide high weather and thermal resistance at the same time offering aesthetic value.

The facade is penetrated with openings (for balconies) and double glazed windows (with overhangs to provide shading at northern facade) that form unique pattern on the facade.

CURTAIN WALL w. ALUMINIUM LOUVRES FACADE - glazing panel size; 3830H x 1800W - SHGC 0.25, Uw 2.0

- powdered coated aluminium for operable vertical louvres

The curtain wall facade is non-load bearing facade and is used to admit northern sunlight into the interior. Operable louvres are used to enable manipulation of sun level into the interior.

JIA MIN CHEONG

SCALE 1:100

DRAWN BY JM CHEONG

DATE 05.09.2022

REVISION 10.10.2022

PROJECT THE PADDOCK BATMAN AVENUE VICTORIA DRAWING

A C D E 1 2 5 6 4 3 E D A' A 1 2 3 4 B B 35o 7500 7500 7500 6400 7500 7340 7500 7500 5850 7500 2F ROOM 5 52.2m2 2F ROOM 4 35.8m2 2F ROOM 3 51.0m2 2F ROOM 2 30.7m2 2F ROOM 1 59.8m2 2F ROOM 6 53.4m2 2F ROOM 7 52.2m2 2F ROOM 8 43.3m2 ENTRANCE AND FOYER BRIDGE 145 o 3580 28° PERIMETERBALCONY FIRE STAIRS STORE ROOM CORE C G F 6980 1980 2400 6560 FFL 14,050 A A A201 A201 W18 W20 W21 W23 W17 W16 W22 W23 W24 W25 D32 D30 D33 D31 D34 D35 D36 D37 D38 D39 D40 D41 D42 D43 D44 CP3 SF1 CP2 SF1 CP2 COL. COL. CP3 CP3 CP3 CP1 CP1 CP1 CP1 CP1 CP1 SF1 SF1 SF1 SF1 SF1 SF1 SF1 SF1 CP1 CP2 SF1 150mm THK PRECAST CONCRETE PANEL MIN 10mm GAP 90mm STEEL STUD FRAME WITH SARKING 13mm GYPSUM BOARD FINISHES NOTE: O/A WALL TO ACHIEVE MIN THERMAL RATING OF R2.8 150mm CONCRETE PANEL RAW FINISHES 120mm STEEL STUD FRAME 13mm GYPSUM BOARD FINISHES AT BOTH SIDES INSULATION AS REQUIRED BY ACOUSITC ENG
W19 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE 100ø DP HPDE R5000 2580 COL. COL. COL. COL. COL. COL. SF2 CP3 150mm CONCRETE PANEL RAW FINISHES MIN 10mm GAP 12mm COMPRESSED FIBRE CEMENT WALL LINING SF2 120mm STEEL STUD FRAME 13mm GYPSUM BOARD FINISHES AT INTERIOR 12mm COMPRESSED FIBRE CEMENT WALL LINING INSULATION AS REQUIRED BY ACOUSITC ENG SF2 SF2 HERO IMAGE 6130 4370 ADJACENT BUILDING WALL FLOOR CONCRETE SLAB FLOOR WITH 10mm THK EPOXY CONCRETE SEALER CONCRETE PAVING SLABS ON GROUT SCREED TO FALL 1:80 AND WATERPROOFING MEMBRANE CERAMIC TILES SF1 SF1 SF1 SF1 SF1 BIRRARUNG MARR LEGEND
DRAWING
A1.02
SECOND FLOOR PLAN
NO.

1. STRUCTURAL GRID

The structural grid is imposed according to the shape of the building. The distance of gridline is spaced at most 7500mm, which is the maximum span of post tension slab.

2. BUILDING CORE The building core is placed along the southern wall. It is formed out of lift and fire stairs core, and acts as a combination of shear wall and sway frame. This offers lateral stability to the building.

3. STRUCTURAL COLUMNS

The columns are distributed at intersection points of grid lines. They give stability in two orthogonal directions from the building core.

4. MAIN STAIRS

The main stairs are placed between gridlines to avoid cutting through slab hence avoiding the need of additional structural support.

5. STRUCTURAL LAYOUT ON DIFFERENT FLOORS

The structural grid and placement of structural elements in plan are repeated across floors. This ensures the stability gets all the way down to the ground foundation while leading to a more economical structure.

EXPLANATORY SCHEDULE

STEEL FRAMING - Grade 250, thickness range 5-150mm - univeral beams, c channels, rectangular hollow sections, bolted or welded based on structural requirement according to engineering details Steel stud walls are designed for inner layer of building enclosure and interior walls. Steel has a higher strength-to-weight ratio when compared to concrete and timber. Hence steel enables longer spans at smaller dimensions, which results in more open floor plans. Steel also provides greater resistance to wind and seismic loads. Additionally, steel provides high fire, moisture and weather resistance.

POST-TENSION SLAB

- 40 MPa reinforced concrete, 220mm thick - Span up to 7500 mm

The use of high strength steel tendons enable formation of a much thinner slab with a longer span. Hence post-tension slab spreads the load over a wider area, which results in smaller footings being required.

CONCRETE SUSPENDED GROUND SLAB - 32 MPa reinforced concrete, 150mm thick - reinforcement required at top to deal with shrinkage cracking and bending of slab over beams - reinforcement required at bottom to deal with bending between ribs Site is classified as P, with reactive soils, hence is difficult to build on. Suspended slab is chosen as it requires less groundwork than concrete slab on ground.

CONCRETE SLAB ROOF - 40 MPa reinforced concrete, 250mm thick - top and bottom reinforcement Concrete slab roof can withstand higher amount of foot traffic. It also provides high weather and thermal resistance.

PILE FOOTING - 450mm diameter pile - reinforcement: 6 M20 bars with R6 spiral ligature Site is classified as P, hence deep footing is required to reach hard strata for stability.

JIA MIN CHEONG

SCALE 1:100

DRAWN BY JM CHEONG

DATE 05.09.2022

REVISION 10.10.2022

1 7330 8470 2570 7500 4370 8960 SITE BOUNDARY 4500 4500 4500 CL 3830 450 220 CL 3830 450 220 CL 3800 450 250 FFL 5,050 NGL 4,900 FFL 9,550 FFL 14,050 FFL 18,750 2F ROOM 2 1F ROOM 2 GF ENTRANCE AND FOYER CENTRAL CIRCULATION CENTRAL CIRCULATION CENTRAL CIRCULATION 2F WET AREA 1F WET AREA GF WET AREA LIFT, PLANT ROOM AND FIRE STAIRS BALCONY BALCONY 2 5 3 4 ROAD RAILWAY TRACK SCREW PILE TO REACH BASALT LAYER, DEPTH OF SCREW PILE TO BE CONFIRMED BY FURTHER GEOTECHNICAL INVESTIGATION CANTILEVERED BRIDGE BIRRARUNG MARR CONCRETE PLANTER VERTICAL SCREEN WALL SLIGHT SLOPE 1:80 TO DRAIN WATER AWAY FROM THE ASSEMBLY GREEN BUFFER STRIP (w. DECIDUOUS PLANTS) FOR SHADING, WIND BREAK AND SOUND INSULATION 200 1350 GABION WALL FALL 1:80 FALL 1:80 SILTY CLAY BASALT SUMMER SUN WINTER SUN STRONG WINTER WIND AS THE SITE FACES VAST RAILWAY TRACK AND WIND IS NOT BLOCKED BY OBSTRUCTION. STRONG NOISE AND VIRATION FROM THE RAILWAY TRACK WEAK SUMMER WIND AS WIND IS BLOCKED BY TREES IN THE PARK 02 01 SECTION A-A STRUCTURAL DIAGRAM A201 A201 SCALE 1:100 @ A1 NOT TO SCALE
DRAWING
DRAWING NO. A2.01
PROJECT THE PADDOCK BATMAN AVENUE VICTORIA
NORTH-SOUTH SECTION
COL. A C D 1 2 E D C A' A G B 2 COL. A C D E 5 6 4 3 E D C A' A G B B 3 4 1 COL. A C D E 1 2 5 6 4 3 D C A' A G B B F 2 3 4 1 COL. A C D 1 2 E D C A' A G B 2 3 4 STORE ROOM A C D 1 2 5 6 4 3 D C A' A G B B F 3 4 1

THK COMPRESSED FIBRE CEMENT EXTERIOR LINING

BALCONY

INTERIOR

EXPLANATORY SCHEDULE

INVERTED FLAT ROOF SYSTEM

This is a form of flat roof which the waterproofing layer is beneath the thermal insulation. Waterproofing membrane is protected by the insulation from damage caused by weather flunctuations and roof traffic.

Roof can hence withstand longer period and require lower maintenance than conventional roof system Roof is sloped to fall at 1:80 to enable adequate drainage.

THERMAL INSULATION

Rigid extruded polystyrene insulation (Kingspan GreenGuard GG300 insulation board) is fitted to roof to reduce heat loss through roof.

Earthwool insulation batts (R>5.0) are fitted above suspended ceiling panels to reduce heat flows out through ceiling and across floor levels. Earthwool insulation batts (R>2.5) are fitted in steel stud walls to reduce heat flows out through wall by 80%.

ACOUSTIC INSULATION

Earthwool insulation batts are fitted into external walls, internal walls and ceilings. The insulation batts help to control the transfer of external noise to interior and the transfer of internal noise between rooms. The insulation is estimated to reduce the noise transfer by 70%.

MOISTURE PROTECTION

Sloped surfaces, weathering and capping are designed for adequate water drainage.

Upstands are created along roof edge, thresholds and junctions to act as barrier against water penetration.

Drips are created to pull the adhering water free of projecting surfaces and walls.

Waterproofing materials and flashings are used to act as barrier against water penetration. Subsills, drain and gutter are used to allow adequate water drainage.

VISUAL AND GLARE CONTROL

Double glazing is used at all windows and curtain walls. The glazing used has values of SHGC 0.25 and Uw 2.0. Double glazing provides benefit such as increased insulation, reduced condensation and reduced noise transfer.

Overhangs are designed at north facing window to provide horizontal shading (northern sun shading at 52 degrees in Melbourne according to ‘Energy Smart Housing Manual 2018’ ). Operable aluminium louvres are installed at curtain wall facade to provide shading and enable manipulation of sun level into the interior (refer to A102).

CHEONG

REVISION 10.10.2022

DRAWING

LYSAGHT LONGLINE 305® COLORBOND ROOFING SHEET INSTALLED TO MANUFACTURER'S DETAILS PURPOSE FOLDED COLORBOND PARAPET CAPPING, OVERLAPPING FIBRE CEMENT LINING AND METAL ROOF SHEET COLORBOND BOX GUTTER ACO BuildLine GALVANISED STEEL GRATED ROOF DRAIN 12mm THK COMPRESSED FIBRE CEMENT SOFFIT GALVANISED STEEL FRAMING ACCORDING TO ENGINEERING DETAILS 150mm THK PRECAST CONCRETE PANEL PROVIDE 80mm SLAB REBATE AT THRESHOLD TO FORM UPSTAND AGAINST WATER PENETRATION 120mm THK STUD FRAME WALL DOUBLE GLAZED GLASS FOLDING DOOR 220mm THK POST-TENSION CONCRETE SLAB 5mm DIA. SUSPENSION ROD ALUMINIUM FURRING CHANNEL 13mm THK GYPSUM BOARD CEILING FINISHES GALVANISED STEEL C CHANNEL 13mm THK GYPSUM BOARD INTERIOR WALL FINISHES 20mm HARDWOOD REVEAL, CONCEALING ALUMINIUM WINDOW FRAME, ENABLING ZERO THRESHOLD VIEW FROM THE INTERIOR DOUBLE GLAZED WINDOW 10mm THK EPOXY CONCRETE SEALER PROVIDE 120mm UPSTAND TO FORM BARRIER AGAINST WATER PENETRATION THE TWO UPSTANDS FORM LABYRINTH TO PREVENT INGRESS OF WATER 150mm THK CONCRETE SUSPENDED GROUND SLAB 10mm THK EPOXY CONCRETE SEALER PRECAST CONCRETE SILL, WITH UPSTAND AND DRIP GROOVE, SLOPED TO DRAIN WATER AWAY FROM THE ASSEMBLY SLIGHT SLOPE 1:80 TO DRAIN WATER AWAY FROM THE ASSEMBLY 12mm THK COMPRESSED FIBRE CEMENT WALL LINING DRAINAGE PIPE CAST INTO SLAB 400 X 400 X 30mm CONCRETE PAVING SLAB ON SUPPORTS 120mm THK Kingspan GreenGuard GG300 INSULATION BOARD 2 LAYER MASTIC ASPHALT WATERPROOFING 50mm CONCRETE SCREED TO 1:80 FALL FALL 1:80 12mm
400
CEMENT TILES HIGH STRENGTH, NON SHRINK
SREED TO FALL 1:80 WATERPROOFING MEMBRANE ACO BuildLine
PRECAST CONCRETE
HORIZONTAL
PRECAST
WITH DRIP GROOVE, SLOPED TO DRAIN WATER AWAY FROM THE ASSEMBLY PRECAST CONCRETE WEATHERING, WITH DRIP GROOVE, SLOPED TO DRAIN WATER AWAY FROM THE ASSEMBLY FALL 1:80 DRAINAGE PIPE CAST INTO SLAB WATERPROOFING MEMBRANE Kingspan GreenGuard GG300 INSULATION BOARD, UPSTAND ACCORDING TO MANUFACTERER'S DETAILS FALL 1:10 1:12 FALL 1:10 1:12 PROVIDE 30mm UPSTAND TO FORM BARRIER AGAINST WATER PENETRATION PRECAST CONCRETE PANEL JOINT WITH SEALANT AND BACKING ROD EARTHWOOL INSULATION BATTS EARTHWOOL INSULATION BATTS FALL 1:80 01 02 NORTHERN FACADE SECTION A301 A301 PART HERO IMAGE SCALE 1:20 @ A1 NOT TO SCALE
GF ENTRANCE AND FOYER MIN CHEONG
X 400 X 30mm
GROUT,
GALVANISED STEEL GRATED BALCONY DRAIN
OVERHANG, WITH DRIP GROOVE, ACT AS FIXED
SHADING DEVICE (NORTHERN SUN SHADING AT 52 DEG.)
CONCRETE SILL,
JIA
THE PADDOCK BATMAN AVENUE VICTORIA
NORTHERN FACADE DETAILS DRAWING NO. A3.01
PROJECT
DRAWN BY JM
DATE 05.09.2022

PURPOSE FOLDED COLORBOND PARAPET CAPPING, OVERLAPPING FIBRE CEMENT LINING AND METAL ROOF SHEET

12mm THK COMPRESSED FIBRE CEMENT EXTERIOR LINING

EXPLANATORY SCHEDULE

CONCRETE TO STEEL FRAME CONNECTION

Installed according to engineering details

INVERTED FLAT ROOF SYSTEM

This is a form of flat roof which the waterproofing layer is beneath the thermal insulation. Waterproofing membrane is protected by the insulation from damage caused by weather flunctuations and roof traffic.

LYSAGHT LONGLINE 305® COLORBOND ROOFING SHEET INSTALLED TO MANUFACTURER'S DETAILS

GALVANISED STEEL FRAMING ACCORDING TO ENGINEERING DETAILS

GALVANISED STEEL FIXING BRACKET

Kingspan GreenGuard GG300 INSULATION BOARD, UPSTAND ACCORDING TO MANUFACTERER'S DETAILS

GALVANISED

ACO BuildLine GALVANISED STEEL GRATED ROOF DRAIN

DRAINAGE PIPE CAST INTO SLAB

FINISH GRATED TRENCH WITH BACKING ROD AND SILICONE SEALANT 400 X 400 X 30mm CONCRETE PAVING SLAB ON SUPPORTS

ADJUSTABLE PEDESTAL SUPPORT

120mm THK Kingspan GreenGuard GG300 INSULATION BOARD

2 LAYER MASTIC ASPHALT WATERPROOFING 50mm CONCRETE SCREED TO 1:80 FALL

FALL 1:80

Roof can hence withstand longer period and require lower maintenance than conventional roof system

Roof is sloped to fall 1:80 at the edge to enable adequate drainage.

MOISTURE PROTECTION

Sloped surfaces, weathering and capping are designed for adequate water drainage.

Upstands are created along roof edge, thresholds and junctions to act as barrier against water penetration.

Drips are created to pull the adhering water free of projecting surfaces.

Waterproofing materials and flashings are used to act as barrier against water penetration. Subsills, drain and gutter are used to allow adequate water drainage.

MOISTURE PROTECTION - DRAINAGE

ACO Buildline Grated Drain

This is shallow drainage channel with grates that are suitable for outdoor usage. The grate is slip resistant and provides zero threshold for disability access.

The balcony drain is connected to subsill of galvanised steel door sill to allow for condensate drainage.

12mm THK COMPRESSED FIBRE CEMENT SOFFIT

GALVANISED STEEL FIXING BRACKET COLORBOND BOX GUTTER

PRECAST CONCRETE SILL, WITH DRIP GROOVE,

02 01

ROOF-FACADE JUNCTION

INTERIOR BALCONY

DOUBLE GLAZED GLASS FOLDING DOOR

SCALE 1:10

X 400 X 30mm CEMENT TILES HIGH STRENGTH, NON SHRINK GROUT, SREED TO FALL 1:80

WATERPROOFING MEMBRANE

BALCONY FLOOR THRESHOLD JUNCTION

@ A1

DRAINAGE

PROVIDE 80mm SLAB REBATE AT THRESHOLD TO FORM UPSTAND AGAINST WATER PENETRATION

GALVANISED STEEL ANGLE FIXED TO CONCRETE SLAB

DATE 05.09.2022

REVISION 10.10.2022

PROJECT THE PADDOCK BATMAN AVENUE VICTORIA

DETAILS DRAWING

STEEL COVER FLASHING FALL 1:10 1:12 ROOFING SHEET TURNED DOWN CREATES DRIP TO DIRECT WATER INTO GUTTER GALVANISED STEEL RHS WELDED TO ROOF TRUSS COLORBOND CLADDING TURNED DOWN TO CREATE DRIP TO STOP WATER TRACING UNDER SOFFIT LINING GALVANISED STEEL FIXING BRACKET 10mm SHADOWLINE WITH FLEXIBLE SEALANT CONCRETE TO STEEL FRAME CONNECTION ACCORDING TO ENGINEERING DETAILS
400
SLOPED TO DRAIN WATER AWAY FROM THE ASSEMBLY FALL 1:80
PIPE CAST INTO SLAB WATERPROOFING MEMBRANE, TURNED UP AT EDGE TO CREATE UPSTAND 150mm THK PRECAST CONCRETE PANEL 12mm THK COMPRESSED FIBRE CEMENT WALL LINING, FIXED TO WALL BY FIXING BRACKET 10mm AIR GAP FINISH
ACO BuildLine GALVANISED STEEL GRATED BALCONY DRAIN ROD AND
GRATED TRENCH WITH BACKING
SILICONE SEALANT
GALVANISED STEEL DOOR SILL WITH DRAINAGE SUBSILL TO REMOVE MOISTURE ENTERING FRAME
10mm SHADOWLINE WITH FLEXIBLE SEALANT Hardie™ POWDER-COATED ALUMINIUM EDGE BASE TRIM, UNDERLAP FIBRE CEMENT LINING
SCALE 1:10
A302 A302
SCALE 1:10 @ A1
JIA MIN CHEONG
SECTION
NO. A3.02
DRAWING
DRAWN BY JM CHEONG

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.