v Dark cladded timber for aesthetic purposes. Installed using a groove and tongue joint.
v Concrete formwork – o Concrete is left for 21 days before it can be stripped o Block wall – vertical bar (reinforcement) o Walls rebated for timber seats o Oregon –leaves a pattern finish on the concrete for aesthetic purposes o LVL -‐ laminated veneer lumber, often use as infill frame v Structural System: o Timber framing o Steel framework – prefabricated and therefore quickly built
ENVS10003 Constructing Environments A03 – Final Journal Submission
641144 Josh Davis
v Retaining Wall: -‐ -‐
Main purpose of the retaining wall is to protect the foundations It also ensures that the concrete fill is held in place until set. (Remains erect and reinforced)
v Roofing Layers: 1. Purlins 2. Sound & Insulation 3. 25ml timber floor 4. Bluetongue sheets 5. Battens 6. Insulation 7. Roof Sheeting *Acoustic Purposes
ENVS10003 Constructing Environments A03 – Final Journal Submission
641144 Josh Davis
References: Ching, F., 2008. Building Construction Illustrated. 4th Edition. Wiley & Sons, Inc.,