Construction Update Newsletter August 2018

Mercy Health Saint Mary’s - Ninth Floor Renovation

Siding removal and new window installation

www.elzinga-volkers.com www.elzinga-volkers.com


Inside Scoop - Construction Update Newsletter Mercy Health Saint Mary’s - Ninth Floor Renovation - August 2018

Finished Corridor

Patient Room Casework

Charting and Temp Nurse’s Station

PM Update Happy Summer Everyone! Although the fun and the heat remains, this happy season is unfortunately flying by! Thankfully, on a similar pace, our progress on the 9th floor renovation continues to thrive. In our last update we had wrapped up phase 1 and were well underway with phase 2. I am pleased to report today that phase 2 was delivered on time and is now assisting with “deliveries” of its own. These 10 post-partum rooms, and related support areas, are all currently occupied and fully operational. Now on to phase 3, temporary walls have been constructed and demolition is nearly complete. Crews have been busy capping, cutting, removing walls, chipping out flooring, taking down ceilings and essentially stripping the space to its original structure. Following demo, we will be laying out walls and tying in systems from the 8th floor. As mentioned in the previous Inside Scoop, it is a complex task to tie in the mechanical, electrical and plumbing from the operating 8th floor. Areas will need to be shut down on the 8th floor as crews work section by section cutting holes in the 9th floor slabs, running new drain lines, adding/adjusting duct work, building fire rated shafts, getting inspections and then reconstructing everything back to its original state. This activity is very time consuming and critical to the overall schedule. While it is only the beginning, we are looking forward to this final stage which will mark the completion of construction on the 9th floor. Brett Lesiewicz Project Manager brettl@elzinga-volkers.com

Track the Project’s Progress as the View Takes Shape!

Phase 1

Phase 2

Phase 3A

Phase 3B

www.elzinga-volkers.com www.elzinga-volkers.com


Inside Scoop - Construction Update Newsletter Mercy Health Saint Mary’s - Ninth Floor Renovation - August 2018

Upcoming Milestones • Completion of Demolition • Wall Layout

• Complete through floor tie-ins

• MEP Rough-Ins

Our contractor spotlight this month goes to Allied Mechanical Services (AMS). AMS has been leading the charge on communicating with the eighth floor to determine a plan for coordinating shut downs and tie ins. The team members from AMS have been professional in their actions, timely in their delivery and dedicated to maintaining quality.

Phase 3 Full Demolition

Corridor Pre Demolition

Thank you for the great work AMS!

Phase 3 Framing

www.elzinga-volkers.com www.elzinga-volkers.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.