Inside Scoop_Clark at Keller Lake_July 2020

Page 1

JULY, 2020

INSIDE SCOOP - CLARK AT KELLER LAKE

Safety Days Count:

4,795

No Lost Time Injuries

As of 7/2/2020

NICK NOVAKOSKI

PROJECT MANAGER

Greetings all,

Welcome to the July edition of Inside Scoop. As we begin the summer months in Michigan, the project continues to pick up momentum even with the recent heat wave. While project progress is the utmost importance, we also want to make sure that the team onsite is safe from heat exhaustion. We are taking additional precautions like ensuring water is available, offering additional breaks and monitoring workers for signs and symptoms of heat exhaustion. The heat presents a unique challenge for us but we have a great plan in place to make sure everyone is safe. Moving on to the project, progress continues to roll along nicely. Over the past month the structural steel for building three has been completed and the second floor slab has been poured. This will make way for our first shipment of wall panels to arrive in the coming weeks. On the first floor of building three and in the parking garage, Godwin Plumbing has been installing all of the underground plumbing that will serve the entire facility. In building two, concrete is almost complete and the masons are wrapping up the last of the stair and elevator shafts. This opens buildings one and two for our precast plank installation that will serve as the base for those buildings. This work is scheduled to start after the holiday. As stated last month, “this past month has been a busy one for us” and it will continue to get busier as the months go by. Lastly, I want to wish everyone a fun and safe 4th of July. I hope you all are able to get away from the busyness of life and enjoy some relaxation. Until next month, Nick Novakoski, Project Manager NickN@ev.construction

TRADE CONTRACTOR

SPOTLIGHT

This month we would like to recognize the Allied Electric team for the effort they put forth installing the underground electric onsite. Allied has stayed on top of submittals, RFI’s and material procurement. It has been a pleasure working with Dave, Garett and Alex. Keep on rockin’ boys!


Building Two, Stair Shaft Three.

FIELD MANAGEMENT TEAM

&

E.J. Calloway Field Manager

Dan Jenema Sr. Field Manager

July Project Milestones We will be looking forward to finishing rough grading, concrete foundation walls and precast this month. All three are major driver’s to keep the project on schedule.

Building One Parking Lot Entrance Concrete Formwork

Building Three, Second Floor Slab

Building Three, Second Floor Pour

Building Three, Underground Plumbing

We look forward to starting metal and wood wall framing this month as well as bringing more MEP trades onsite.

TRACK THE PROJECT’S PROGRESS Tree Clearing & Sitework Building Concrete & Precast Concrete

Structural Steel & Wood Framing Building Dried In Drywall Interior Finishes Project Complete

DEC JAN 2019 2020

FEB 2020

MAR 2020

APR 2020

MAY 2020

JUN 2020

JUL 2020

AUG 2020

SEP OCT NOV DEC JAN FEB 2020 2020 2020 2020 2021 2021

MAR 2021

APR 2021

MAY 2021

JUN 2021

JUL 2021

AUG SEP 2021 2020