AUGUST, 2020
INSIDE SCOOP - CLARK AT KELLER LAKE
Safety Days Count:
4,829
No Lost Time Injuries
As of 8/5/2020
NICK NOVAKOSKI
PROJECT MANAGER
Greetings all,
Welcome to the August edition of Inside Scoop. This summer has flown by and progress on site continues on at a fast pace as well. July was an extremely busy and critical month for the project as we reached our first big milestone on the project. On buildings one and two, the pre-cast concrete columns, beams and floor planks were completed, enclosing the parking garage below. This was a critical time for us because the pre-cast installation drives a huge portion of this project. It now allows us to open buildings one and two for the remaining concrete work, and shortly after that, wall framing can begin. Transitioning to building three, the past month saw a tremendous amount of progress. On the first floor, the concrete slab on grade has been poured opening up the building for interior framing in the coming months. Also on the first floor, the exterior wall framing has begun with wall sheathing following close behind. Significant progress has been made on the second and third floors of building three. Most notably, the exterior and interior wall panels have been installed and the electricians have been busy laying out boxes for the switches and outlets. Looking forward to next month. The project will continue to be visibly different with each passing day, enjoy watching the progress. Until Next Month, Nick Novakoski Project Manager NickN@ev.construction
TRADE CONTRACTOR
SPOTLIGHT We would like to recognize JB Builders for doing a great job onsite with wood framing. They are responsible for constructing all of the wood exterior and interior walls along with the wood floor and roof systems. When you see those walls going up so fast, it’s because of the great job these guys are doing with quality and safety along with fast installation. A big thanks to Jeff, Mike and the rest of the crew!
Building Three, Wall Framing.
FIELD MANAGEMENT TEAM
&
E.J. Calloway Field Manager
Dan Jenema Sr. Field Manager
August Project Milestones Coming up in August, we will be wrapping up the framing on building three and really start to see the wood structure on building one. Site grading is wrapping up this month, as well as, concrete walls, foundations and flat work. Our plumbers, electricians and HVAC contractors will be busy onsite with installing in wall rough-ins and other important systems. We will also have partial, permanent power fired up soon which will allow us to get rid of some of those noisy generators!
Building Three, Exterior Insulation
Building Three, Wall Framing.
Pre-cast Columns
Pre-cast Installation
TRACK THE PROJECT’S PROGRESS Tree Clearing & Sitework Building Concrete & Precast Concrete
Structural Steel & Wood Framing Building Dried In Drywall Interior Finishes Project Complete
DEC JAN 2019 2020
FEB 2020
MAR 2020
APR 2020
MAY 2020
JUN 2020
JUL 2020
AUG 2020
SEP OCT NOV DEC JAN FEB 2020 2020 2020 2020 2021 2021
MAR 2021
APR 2021
MAY 2021
JUN 2021
JUL 2021
AUG SEP 2021 2020