Construction Update Newsletter

MAY 2015

Brick by Brick

Talecris Plasma Resources - Anderson Indiana

Completed Milestones

Excavation & Site Work Exterior Light Poles Underground Electrical Underground Plumbing Concrete Footers & Slab Structural Steel & Roof Decking Exterior Framing Exterior Sheathing

Meet Your Team!

  

 

Name: Brad Giha Role: Project Manager Did you know? Brad started his career in construction over 10 years ago as a carpenter!

Executive Summary Welcome to On Location!

Hello! My name is Brad Giha and I am the project manager for the new Talecris Plasma Resources in Anderson, Indiana. I would also like to introduce our site manager for the project, Jim Carr. Jim and I bring a combined 40 plus years of construction experience to this project. This project is nearing its sixth month of construction and is progressing nicely. Over the past months we have completed a multitude of activities. Excavation & Site work

Interior Framing

Underground Electrical

Underground Plumbing

Concrete Footers & Slab

Structural Steel & Roof Decking

Exterior Framing

Exterior Sheathing

We have completed a significant amount of work, but there is much more to come. I am excited to see this project progress and I know with all the hard work of Talecris Plasma Resources and Elzinga & Volkers we will be successful! Brad Giha, Project Manager bradg@elzinga-volkers.com

Sanilac Steel installing the roof deck

www.elzinga-volkers.com


Project Progress Photos

SPOTLIGHT ON SAFETY An estimated 2.3 million construction workers, or 65% of the construction industry, work on scaffolds. Protecting workers from scaffold-related accidents may prevent some of the 4,500 injuries and 60 deaths every year. Faulty design and inadequate construction are sometimes involved, but in most cases, scaffold accidents are caused by careless maintenance and improper use. On our site, we ensure scaffolding safety by:

Exterior framing

» Performing daily inspections prior to use

Bar joist completed and decking started

» Boarding, fencing and fastening all platforms » Avoiding a stockpile of materials or overloading them » Forbidding their use during storms or high winds » Clearing the area surrounding the scaffolding

Exterior sheathing completed on north elevation

www.elzinga-volkers.com


The Look Ahead

With winter now in our rear view mirror, we are putting the petal to the metal. We are working on all facets of the project. On the interior we are finishing drywall and working on above ceiling MEP work. Once complete with the finishing we will be priming and starting ceiling grid. On the exterior we are completing the brick, starting exterior concrete and finishing up some of the storm sewer. Dan Faulkner, Field Manager danf@elzinga-volkers.com

Upcoming Milestones

SPOTLIGHT

» Drywall Finished and Paint Ready

» Ceiling Grid

» Exterior Brick Completed

» Casework Install

Fredrick’s Contracting

» Exterior Glazing

Throughout this project Fredericks Contracting has been a tremendous help, no matter what is needed they are willing to assist. Both Jim Carr and Janice Stamper have been great to work with. They have been a great team to work with.

» Metal Wall Panels » MEP Above Ceiling Work

Condenser supports

TRADE CONTRACTOR

» Exterior Concrete » Retaining Walls

» Walls Primed

Project Progress and Major Milestones Phase 1

The Monthly Funny Ready for Move In

Interiors Complete Drywall Complete Mechanical, Electrical, Plumbing Rough-In Wall Framing Structural Steel Site Work

& www.elzinga-volkers.com

CONSTRUCTION PROFESSIONALS


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.