Biomat USA - Kalamazoo, Michigan
Upcoming Milestones »» Donor Dock Kiosk Completion: 12.22.14 »» Phase 1 Punch List: 12.22.14 »» New Donor Floor Transition (Phase 1): 12.28.14
Meet Your Team!
Executive Summary Name: Mike Kloosterman Role: Project Manager Did you know? Mike has run a total of 18 marathons (not all at once)!
Welcome to On Location!
My name is Mike Kloosterman and I am the Project Manager for the General Contractor overseeing the construction of your new space. Together with Field Manager Larry Wolters, I will help coordinate the nuts and bolts of the building process. Over the last few months you may have seen Larry and I walking around your existing space. During that time we were investigating and roughing in new services to facilitate the construction of your new center. Larry and our sub-contractors have made great strides in completing the new freezers, processing room, repair room, and donor exit vestibule. All of these spaces
add up to our initial phase of construction. In the next few weeks we will be putting the final pieces together for the completion of Phase 1. When you ring in the new year, you’ll also have a brand new Donor Floor! Thank you for helping in this initial transition and continuing to work with us throughout the construction process… March will come quickly, we promise! Happy Holidays!
- Mike Kloosterman, Project Manager mkloo@elzinga-volkers.com
Name: Larry Wolters Role: Field Manager Did you know? Larry is a huge baseball fan and never misses spring training!
Processing transaction windows
www.elzinga-volkers.com
Project Progress Photos
SPOTLIGHT ON SAFETY A term you might hear on our site
New donor dock stations (before)
but may not be familiar with is PPE, which stands for Personal Protective Equipment. Examples of PPE include items such as gloves, high visibility clothing, foot and eye protection, protective hearing devices and hard hats. Some of these items, like hard hats and eye protection, are required 100% of the time on-site, while others, like gloves, are required only when performing certain tasks. Elzinga & Volkers exceeds MiOSHA standards
Progress on new donor dock stations
when it comes to PPE to ensure that all of our workers return home safe every day.
Processing area
www.elzinga-volkers.com
Two Week Look Ahead
The next two weeks will represent the final push for completing your new donor floor. Currently we are working on the ceramic tile, wall coverings, ceilings, HVAC systems, & lighting. Next week we will begin installing the flooring and start putting the final touches on all of the finishes for city inspections at the end of the week followed by Grifols final review on 12-22-14. The big day to look forward to is Sunday night 12-28-14 where the switch from the old donor floor to the new will finally happen! We will be working around the clock from now until then to make sure we are ready!
SUBCONTRACTOR
- Larry Wolters, Field Manager l.wolters@elzinga-volkers.com
SPOTLIGHT Highpoint Electric is installing the electrical systems for Biomat Kalamazoo. Highpoint has been an excellent partner on several E&V projects, and we’re glad they are able to help us out once again for Biomat!
RTU stands
Project Progress and Major Milestones Phase 1 Ready for Move In Interiors Complete Drywall Complete
Recessed freezer pit
Mechanical, Electrical, Plumbing Rough-In Wall Framing Demolition
Processing room window
& www.elzinga-volkers.com
CONSTRUCTION PROFESSIONALS