PROJECT MANAGEMENT UPDATE Welcome back to this month’s edition of Building Together!

Matt Wintjes Assistant Project Manager

Another phase has been completed for the construction team and we are moving full steam ahead. The north wing of the Kresge renovations wrapped up the last week of May with final state inspections and resident moves. We have now shifted to the west wing, making great progress thus far. Over the past month, the existing furniture has been cleaned out of the wing and the demolition trade contractor, Dobie Construction, has had full access to remove walls, ceilings and flooring in preparation for the new layout in the resident rooms and modern finishes. The first and second floor demo is complete and the new interior walls for the bathrooms have been constructed. A critical component during this phase of construction, called “rough-in”, includes the mechanical, electrical and plumbing trade contractors. Rough-in consists of these trades installing all of their conduits, pipes, wiring and ductwork in preparation for new wall board and ceilings to be installed, closing everything in. In order to complete this portion of work, we have had to undergo some noisy periods, which consisted of coring holes between the two floors and saw cutting concrete to allow for underground plumbing. Once all the rough-in inspections are complete, the interiors trade contractor, Acoustic Ceiling & Partition, can start hanging the new wall board.

www.elzinga-volkers.com www.elzinga-volkers.com


Building Together | Construction Update Newsletter UMRC - Chelsea, MI - June 2019 KRESGE RENOVATIONS | UP NEXT Moving further into Phase 3 of the Kresge renovation, the focus has been on MEP rough-in. From the plumbers removing concrete and installing pipe, to the heating and cooling tradesmen installing their HVAC units, it has been a busy and productive month of June for all the trades. Moving into the month of July, we expect to see drywall being installed and finished on both floors as well as starting to paint both floors and work on MEP finishes. As we draw closer to the end of this phase, planning has already started for both Phases 4 and 5. Our team spotlight this month focuses on Quality Air Heating and Cooling. Quality Air does a great job of working with and around the other trades on the project, while at the same time maintaining a safe environment and delivering high quality work. Nate and his crew have been a pleasure to have on the job site, and we look forward to working with them on the remainder of this project.

TRACK THE PROJECT’S PROGRESS AS THE VIEW TAKES SHAPE! 12/18

01/19

02/19

03/19

04/19

05/19

06/19

07/19

08/19

09/19

10/19

11/19

12/19

FINAL INSPECTION & CLEANING INTERIOR FINISHES FINAL INSPECTION & CLEANING POOL CONSTRUCTION

INTERIOR FINISHES

RENOVATIONS (THROUGH 2020)

KRESGE EXPANSION

MCMULLEN WELLNESS CENTER

KRESGE RENOVATIONS