BUILDING TOGETHER United Methodist Retirement Communities | Chelsea
ISSUE
18 JULY 2019
AERIAL VIEW OF THE PROJECT SITE
Drywall Going In
PROJECT MANAGEMENT UPDATE
Matt Wintjes Assistant Project Manager
The construction team is on the final stretch to turning over another phase of the Kresge renovations. Over the course of the last month, the majority of the work has been focused on finishing rough-in’s for the new mechanical, electrical, plumbing and fire suppression systems. As I’m sure you are aware, we’ve had a handful of shutdowns requiring the construction team to drain particular systems within the existing building (fire suppression lines, plumbing lines, etc.) to complete a tie-in and then to re-energize the system. All of the rough-in inspections have been completed and the walls are now closed up. We are in the process of finishing, along with completing the hard lid and acoustical ceilings. With the heat and humidity that this summer has shared with us, one challenge the construction team has had to overcome is maintaining a cool and conditioned space in order to mitigate any excess moisture in the wall board and assist in drying the wall board joint compound. Since the mechanical systems will not be operational until the tail-end of this phase, we have had to supplement with large portable A/C and dehumidification units. As with the last phase, all the trade contractors have been working effectively and efficiently in the small footprint they are confined to. Stay tuned as we make our final push in August, with final turnover scheduled in the first half of September.
www.elzinga-volkers.com www.elzinga-volkers.com
Building Together | Construction Update Newsletter UMRC - Chelsea, MI - July 2019 KRESGE RENOVATIONS | UP NEXT As we move into the final month of Phase 3 for the Kresge Skilled Nursing renovation, the trades are about to begin applying the finishes for their respective portions of the project. Drywall has been installed and finished on both floors and the painting process has started. MEP rough ins are now completed, and the trades are ready to begin working on MEP finishes. The month of August will be over before we know it, and it will be time to begin Phase 4. Our team spotlight this month focuses on Dobie Construction. Dobie construction has done a great job during the whole project of staying on schedule and producing high quality work. During the month of July, Mike and Raymond (pictured below) did an excellent job of completing the bathroom door swap in the resident rooms. Working in occupied space can present some new challenges, and we can’t thank these guys enough for how smoothly this process went. We look forward to working with Dobie Construction in Phases 4 and 5.
Firestopping West Wing
West Wing Rough-In
Dobie Construction Team
TRACK THE PROJECT’S PROGRESS AS THE VIEW TAKES SHAPE! 12/18
01/19
02/19
03/19
04/19
05/19
06/19
07/19
08/19
09/19
10/19
11/19
12/19
FINAL INSPECTION & CLEANING INTERIOR FINISHES FINAL INSPECTION & CLEANING POOL CONSTRUCTION
INTERIOR FINISHES
RENOVATIONS (THROUGH 2020)
KRESGE EXPANSION
MCMULLEN WELLNESS CENTER
KRESGE RENOVATIONS
www.elzinga-volkers.com