Building Boven | February Newsletter

Page 1

ISSUE

16

FEBRUARY 2020

BUILDING BOVEN Holland Hospital - Boven Birth Center Renovation - Construction Update Newsletter

PROJECT MANAGEMENT UPDATE The space has really taken shape and within the next few months the finishes will make this phase feel like it is part of the hospital. On the north side, all the rooms are painted and casework is almost completely installed. The bathroom tile is looking really nice as well. To keep the construction space separate from the occupied space we had to build a temporary wall. The wall on the construction side only gives us an 18� Julie Cole-Bouwens Assistant Project Manager corridor to access two of the triage rooms. Luckily, the construction team JulieC@elzinga-volkers.com was able to deliver materials through the windows in order to get through the tight spaces. Don’t worry, this corridor is temporary and once the space is done we will demolish this wall. In addition, you may have noticed the family waiting area above the loading dock had glass installed! The team is really proud of how it turned out. The other window units above the loading dock will be replaced in the spring.

FUN FACT The city of Wuhan, China, completed a makeshift emergency hospital to treat patients infected with the coronavirus in just 10 days. The emergency medical facility is made up of two floors and has several isolation wards. It can hold up to 1,000 patients. Using pre-fabricated units was key to constructing a new building at such a fast speed.

www.elzinga-volkers.com


Building Boven - Construction Update Newsletter Holland Hospital - Boven Birth Center - February 2020

Looking Ahead Nate Stuart, Field Manager NStuart@elzinga-volkers.com | 231.224.3561 With spring just a few weeks away, we are excited to see the color that it brings outside. We have also added a lot of color to the walls in Boven and our carpenters are working diligently to install the casework and headwalls in the rooms. Data cables and wiring are being pulled into the space. Tile is being installed in the bathrooms and flooring install has begun. It will not be long before fixtures are being added. Just a few months are left until the completion of the project. We are also renovating the elevator lobby area, which includes two bathrooms and a conference room. So, even though we are beginning to see the light at the end of the tunnel, there is still a lot to complete before it is all said and done!

This month we would like to recognize the EV carpenters for the high quality work they are doing with casework install. The postpartum rooms are coming together and looking great!

Track the Project’s Progress as the View Takes Shape! MILESTONE: Phase 1 Complete

12/11/2017

MILESTONE: Phase 2 Complete

10/24/2018

MILESTONE: Project Complete

08/14/2019

10/25/2018

06/10/2020

08/15/2018

PHASE 1

PHASE 2

PHASE 3

www.elzinga-volkers.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.