On Location September 2014
J.O. Galloup Company - New Distribution Center and Warehouse
Upcoming Milestones » Completion of the roof system » Concrete placement for slabs on grade » Asphalt paving
& CONSTRUCTION PROFESSIONALS
www.elzinga-volkers.com
®
® ®
®
The Look Ahead
As the roofing wraps up and windows are installed, the concrete will be poured for the slab on grade in the warehouse and cold storage areas. Interior metal stud framing, mechanical, plumbing and electrical rough-ins have begun for the office space, and drywall will be installed soon. Site concrete is underway, and the base coat of asphalt paving will be installed in the next couple weeks. Ryan Geurink, Field Manager 616.821.0519
Executive Summary
With the arrival of fall, cool weather is already upon us. We have been blessed with very little rain and plenty of sunshine these last couple weeks of September, which has been great for the crews installing the roof system. We are anticipating a very busy month of October as metal stud framing has already started on the mezzanine, masonry is going up in the warehouse and the office space, slabs will be poured and the mechanical electrical systems will be installed in the warehouse. This nice weather has also facilitated the exterior painting and site concrete work, as well as a couple last precious rides on my motorcycle for the year!
SUBCONTRACTOR
SPOTLIGHT
Buist Electric is installing the electrical systems for J.O. Galloup. Buist has been an excellent partner on several E&V projects, and we’re glad they are able to help us out once again for J.O. Galloup!
Fall loading...
Clayton Martin, Senior Project Manager 616.392.2383
Download 45% complete