Executive Summary Welcome to Nuts & Bolts! Nuts & Bolts, your regular construction newsletter, will be used to keep you informed on the current progress of your project and upcoming milestones for the construction team. We will periodically highlight team members and project partners. Current project photos will give you a “peek inside� the construction areas. We hope this newsletter will be helpful and something you look forward to reading. So, now that you are properly introduced, please enjoy the first issue of Nuts & Bolts.
The kitchen expansion is off to a running start with the excavation, foundation, and masonry walls complete. We will soon be erecting steel and demolishing interior walls to open the new space to the existing building. Residents have enjoyed watching the activity on site and will be pleased to see activity ramping up even more in the coming weeks as we renovate the existing kitchen space. Maria Nykerk, Project Manager 616.392.2383
Masonry block is complete, and waterproofing is installed
Project Look Ahead
We’ve completed the exterior walls of the kitchen addition and are ready to begin the steel work. After we finish this portion, we will start working inside the existing kitchen, doing demolition and utility work to make way for the new kitchen equipment. At the same time, the roofer will take advantage of the summer weather to replace the roofing. Scott Jesko, Field Manager 616.392.2383
Upcoming Milestones »» Steel Erection »» Kitchen Demo »» Rooftop Equipment »» Installation of New Roofing
Footings & foundations being installed