Nuts & Bolts
Rest Haven Homes
Executive Summary
With the phase two demo complete, the old spa room is beginning to transform! New walls have been erected and drywall is hung in the spa, break room, and resident room. Tile installation is ongoing in this phase and once that is complete, we will start putting paint on the walls. The spa will come to life when we set the new tub and fixtures. After that, we will make the final mechanical and plumbing connections, and install final lighting and flooring in the resident room and break room. Completing this phase will allow us to start work on phase three, known as ‘Love Short’. Maria Nykerk, Project Manager 616.392.2383
November 2014
Issue 4
Resident Room
Project Look Ahead
We are starting to put up finishes in this phase, and we look forward to setting the tub and fixtures so we can finish the plumbing and mechanical work in the spa room. The completion of the spa is in sight, just in time to start Love Short. Scott Jesko, Field Manager 616.836.9273
Office Space
Spa Room
Upcoming Milestones »» »» »» »»
Painting Spa Fixtures Final MEP Work Spa Phase Completion
A lot of people ask why the 3rd phase is called ‘Love Short’. We are working in the L-shaped part of the facility, called the Love Wing. We are renovating all of the rooms in the shorter hallway of the two that make up the ‘L’, and for this reason, it has been nicknamed ‘Love Short’!