St. Mary's Educational Center July Edition

Page 1

July 2016

THE BLUEPRINT BULLETIN St. Mary’s Education Center Construction Newsletter

Executive Summary

The dog days of summer are upon us, but it has been anything but slow on our job site. We now have all the block walls in place and are making the tricky connections between the old and the new buildings. Our construction team has started the difficult task of extending both the main stairs and the elevator up to the new second floor. This is by far the most complicated part of the project but things continue to go well and we remain on schedule. Mike Parker Senior Project Manager

Fundraising Update $5,800,000

$4,350,000

$2,900,000

$1,450,000

“Lord, you have been our dwelling place through throughout all generations…. From everlasting to everlasting you are God.” – Psalm 90

www.elzinga-volkers.com


From the Parish Dear Friends,

FUN

I don’t know about you, but my summer is being measured by building progress rather than dates! It is amazing to look at pictures of our property before the construction began and to now see how the building is taking shape and changing the landscape. While there have been a few setbacks with leaking water and other minor problems, overall things are moving forward very well and we are very much looking forward to being in our new education center and school building in late November or early December. A huge thank you to all of the contractors who are working so hard to create a first-class facility for teaching our children!

T

FAC

Around 20,000 workers helped build the Taj Mahal, a famous mausoleum and landmark in Agra, India, that attracts millions of visitors every year.

Father Dave

tion.

s in

u ing o

gniz

Reco

tner r par

The Blueprint Bulletin | June 2016

truc cons

Titan Interiors

Grand Rapids, Michigan

Bennett Steel

Grand Rapids, Michigan www.elzinga-volkers.com


Upcoming Activities • Installation of steel joists for the roof.

• Installation of rubber roofing.

• Continued plumbing and • Begin interior framing electrical rough-ins. on the second floor. • Extension of the stairs and elevator shaft. Doug Eddy Field Manager

The ABC’s of Construction EIFS - Exterior Insulating and Finish System; exterior wall cladding system consisting primarily of polystyrene foam board with a textured acrylic finish that resembles plaster or stucco.

Click here to view live footage of the construction!

Track the Project’s Progress as the View Takes Shape!

Excavation

Foundations

Exterior Walls

Roofing

Interior Walls

Drywall

Paint

Flooring

Owner Move In


Turn static files into dynamic content formats.