Construction Update Newsletter
MAY 2015
Brick by Brick
Telecris Plasma Resources - Flint, Michigan
Completed Milestones » Interior Lay-Out and Framing » Roof Installation » RTUs Set
» MEP Rough-In
» Permanent Power & Gas
Executive Summary
New Facility Rendering
Building through the Michigan winter is never an easy task. Thanks to the hard work of all our trade contractors we were able to stay on schedule. It feels like just yesterday that Dan and I were going over the coordination of snow removal and roof installation, and now we are installing casework and starting interior finishes. Over the next month we will be finishing up the project. From asphalt to final paint it will be a very busy site. The final few weeks will consist of flooring, wall protection, casework and all the MEP finishes. A site can change dramatically from day-to-day; one day it’s primer and cement floor, the next we have our wall covering installed and the flooring complete. All of this progress makes the project move fast and you have a front row seat to all of it! Brad Giha, Project Manager bradg@elzinga-volkers.com
Employee Patio
Employee Break Room
www.elzinga-volkers.com
Project Progress Photos
SPOTLIGHT ON SAFETY Just because the project is wrapping up doesn’t mean that we let up on our site safety requirements. Hard hats and safety glasses should still be worn at all times, and high visibility clothing should be worn outside. Even in these final stages, accidents can happen. We have had zero accidents on this project so far, and we don’t want our first one now!
Processing
Quality Manager’s Office
South Elevation
www.elzinga-volkers.com
The Look Ahead
The next four weeks will be very exciting. We will be completing both the interior and exterior work onsite. On the interior, we are currently working on casework and wall protection along with all the MEP finishes. On the exterior we are finishing up some of the decorative stone and getting a start on the landscaping. Next week we will start flooring and finish up the majority of the interior work, and the following week we will complete the concrete and paving. In just a few short weeks, the building will be ready for turn over! Dan Faulkner, Field Manager danf@elzinga-volkers.com
Upcoming Milestones » Wall Coverings » Final Mechanical, Electrical and Plumbing » Wall Protection » Final Paint » Interior Windows » Asphalt
Exam Room
» Landscaping & Irrigation
Project Progress and Major Milestones Progress
The Monthly Funny
SUBCONTRACTOR
SPOTLIGHT HighPoint Electric HighPoint Electric has been instrumental in the success of this project. We have had a number of changes and adjustments come up over the past few weeks that have been necessary to complete the project. Highpoint has been there every step of the way to get it completed without breaking the schedule. Dan and I really appreciate their extra effort!
Ready for Move In Interiors Complete Drywall Complete Mechanical, Electrical, Plumbing Rough-In Wall Framing Structural Steel Site Work