UMRC HFA Expansion

Page 1

Building Together

Construction Update Newsletter

Issue

03 October 2013

United Methodist Retirement Communities HFA Expansion

Quadrant Diagram Explanation Due to the symmetrical configuration of the addition, Elzinga & Volkers has decided to phase the project in quadrants. You may hear someone on-site say, “Today, the floor slab in Quadrant #1 is being poured,” and find yourself asking where, exactly, that is. The quadrant system is simple to follow, and you’ll even find a color coded

Upcoming Milestones

diagram to reference on-site. The north

»» Building foundation complete »» First course of asphalt paving »» Underground utilities complete

point of the building is Quadrant #1, the east side is Quadrant #2, the south point is Quadrant #3 and the west side on-site diagram.

Chelsea, Michigan

is Quadrant #4. Below is the referenced & PROFESSIONALS

RES RES

RES

RES

RES

RES

SOILED UTILITY

RES

RES

DINING

RES

RES

SITTING

Q4

RES

DINING

RES

RES

RES

Q2

FAMILY DINING

OFF.

RES

SERVING

RES

CORR

RES

CORR

RES

RES

RES

RES

CORR

RES

CORR. RES

RES

Q3 GREAT ROOM

TOWN CENTER

RES

RES

PORCH

CORR.

PORCH RES

VEST.

& CONSTRUCTION PROFESSIONALS

CORR

RES

RES

RES

RES

STORAGE

RES

CLEAN LINEN

RECEIVING

02 STOR

PORCH

RES

RES

LOUNGE

WOMEN

RES

RES

RES

OFFICE

DINING

RES

CLEAN LINEN

CORR.

KITCHEN

RES

DINING

RES

RES

KITCHEN

RES

RES

RES

RES

LIVING

SOILED UTILITY

TUB RM

CLEAN

RES

RES

LIVING

RES

CORR.

RES

RES

RES

RES

MEN

EMPOYEE LOCKER/ LOUNGE

ELEC

CORR.

CORR.

KITCHEN

LIVING

RES

ACTIVITIES

CORR

RES

SUPPLY

RES

MED

RES

CAFE

DINING

SOILED LAUNDRY UTILITY

CORR RES

OFFICE

SOILED LAUNDRY UTILITY

RES

LIVING

RES

OFFICE

CLEAN

RES

LOUNGE

RES

RES

TABLES/ CHAIRS

CORR.

TUB RM

RES

RES SOILED

RES

RES

RES

RES

RES

ELEC

MULTI-PURPOSE/ CHAPEL

RES

MECHANICAL

KITCHEN

RES

RES

EXAM

RES

RES

ELECT. RES

LIBRARY

CORR.

RES

CORR

OFFICE

RES

DINING

RES

MECH RES

OFFICE

MAINSTREET

RES

RES

LIBRARY

LOBBY

MAINTENANCE

RES

RES RES

OFFICE

CORR

PORCH LOUNGE

RES

ELEC

SALON

KITCHEN

RES

INFO TECH.

SITTING

CONFER.

FAM. GAME ROOM

OFFICE

DRY STOR

RES

RES

CORR.

The building’s footprint is quickly taking shape as crews from Creative Cement and Moretti Foundation Co. installed “trench footings,” which uses the earth as a mold for the concrete. A machine cuts a trench in the earth to a specified depth and width. The concrete is poured in and, with set compaction, the sides and bottom of the trench hold the concrete in place until in cures. This method is a major advantage since it is almost twice as fast as traditional strip footings and formed walls, and it does not sacrifice quality or strength. Rest assured that the new expansion will TOWSLEY settle on aVILLAGE solid foundation. OVERALL PLAN

THERAPY PORCH

RES

RES

KITCHEN

CORR.

OFFICE

RES

CORR

RES

CORR.

CLEAN LINEN

CORR.

RES

LIVING

DINING

FITNESS RES

ACTIVITIES

LIVING

CORR

RES

RES

RES

RES

RES

RES

PORCH

RES

CORR.

CORR.

CORR.

DINING

RES

RES

RES

KITCHEN

RES

RES

RES

RES

DINING

RES

RES

RES

RES

TUB RM

KITCHEN

LIVING

RES

LOUNGE

RES

RES

LOUNGE

RES

RES

RES

PORCH

PORCH

RES

ACTIVITIES

RES

RES

RES

PORCH

With the exterior walls of the building defined, crews

805 West Middle

H-KPG.

RES

RES

SPA

RES

RES

LOUNGE

L'DRY

SOILED LAUNDRY UTILITY

RES

RES

RES

CORR

PORCH

LOUNGE

HFA Addition and Renovations

CORR RES

PORCH

RES

RES

LIVING

RES

RES

CORR

RES

RES

The project has reached a major milestone in the last two weeks with the installation of our concrete footings and beginning foundations. RES

RES

issued for

RES

RES

CORR.

RES

SOILED

RES

RES

ACTIVITIES RES

OFFICE

date

RES

PORCH

RES

MED

PERMIT BIDS

RES

CORR

CLEAN

from Godwin Plumbing started installing underground sanitary piping. All underground piping must be installed and inspected before we can lay the concrete floor slabs. Other work on-site includes: installing concrete block at the building footings, installing underground storm water piping and laying the new road that loops around the building addition. Offsite, work has begun on the wood wall sections for the building, which will be pre-manufactured and assembled on-site.

PERMIT SET

Q1

RES

RES

RES

Out of the Ground

RES

08.05.13

GREAT ROOM

06.17.13

Executive Summary

VEST.

RES

With all this activity, safety and cooperation on-site are critical. Thank you to all the tradespeople for their commitment to keeping the project on track and keeping each other safe! 40 pearl st., n.w. suite 900 grand rapids, michigan (616)451-3041 (fax) 451-3713

ONSTRUCTION

- John Parker, Project Manager file no.

jparker@elzinga-volkers.com

11-10

sheet no.

A1.1 www.elzinga-volkers.com


Project Progress Photos

Trenching for footings

Safety Spotlight Steel bars embedded in the concrete reinforce building foundations. When these bars protrude from the concrete to allow other materials or concrete pours to connect, special caps are placed to reduce the risk of someone being impaled if they fall onto that area of the site. You can see thousands of these little orange caps on large construction sites, including ours.

Bottom rebar layer for footings in footing trench

& CONSTRUCTION PROFESSIONALS

Foundation insulation set in trench

www.elzinga-volkers.com


Two Week Look Ahead

On-site work will move along quickly in the upcoming weeks. Moretti Foundation Co. will continue pouring the building’s foundations. Godwin Plumbing will run the under-slab sanitary plumbing that will eventually service the new sixty-six resident restrooms. After underground plumbing is installed, Higgins Excavating will lay and compact the sand base, giving the concrete slab a sturdy foundation to rest on. Creative Cement will then begin pouring the concrete slabs. They plan to pour all 47,000 square feet in only four pours! This means the site will bustle with concrete truck activity each day of this efficient, speedy pouring. - Jordan Gougeon, Asst. Project Manager jordang@elzinga-volkers.com

SUBCONTRACTOR

SPOTLIGHT In this issue, we would like to recognize the efforts of Creative Cement and Moretti Foundation Co. who are responsible for installing our building’s foundation.

Vertical threaded rods in finished footings

From day one on the site, both firms have performed extremely

Project Progress and Major Milestones

well and stayed right on schedule. Thank you to both companies and all your tradespeople for their efforts on the project.

Ready for Move In Interiors Complete Drywall Complete

Pouring trench footings

Building Enclosed Steel/Wood Framing Complete Foundations Complete

Finishing topside of footings

& www.elzinga-volkers.com

CONSTRUCTION PROFESSIONALS


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.