Vibrant Life Communities - Lodge II

Page 1

ISSUE

01

DECEMBER 2014

Vibrant Views

Construction Update Newsletter

Vibrant Life Communities - Lodge II

Upcoming Milestones »» »» »» »» »» »» »»

Executive Summary Starting Up!

We are excited to announce that the project is underway! You may have noticed the excavating truck progressing forward with the exterior work. They have been busy digging trenches for the underground utilities and preparing the grade for the new addition.

Selective Demolition √ Pour Frost Walls √ Pour Concrete Slab Framing in the new addition Plumbing rough-ins Mechanical rough-ins Electrical rough-ins

happened. The floors, ceilings and finishes are completely stripped out, and the building feels bare right now. However, the interior rough-ins are proceeding, and it will be wonderful to see the space transform into a home for those who require assisted living. - John Parker, Project Manager jparker@elzinga-volkers.com

If you haven’t been inside the building lately, it may be difficult to imagine all the interior work that has

SPOTLIGHT ON SAFETY Bartz & Co. has been doing a great job at keeping the site safe during

Area C

Area B

site work and excavation! They have placed orange barrier safety fences around the trenches to keep other

Floor Plans for Vibrant Life Communities - Lodge II

jobsite personnel a safe distance away from the trench. They have also been wearing their personal protective equipment. Keep up the good work, Bartz & Co.!

Area A

Throughout the course of the project, we will frequently mention areas of the floor plan where we are working. Refer to this map to see where these areas are situated and how they connect with one another!

www.elzinga-volkers.com


Project Progress Photos

MEET RON

Reframed trusses for new mechanical unit

Elzinga & Volkers is pleased to introduce you to Ron Hendrickson. Ron is the field manager who runs the dayto-day construction on your project site. With over 30 years of construction experience, he is the right guy for this project. Every other weekend, he returns home to his wife and three

Getting ready to pour concrete

sons in Wisconsin. He enjoys hunting, fishing and watching the Green Bay Packers. Also, I bet you didn’t know, that Ron is a National Match High Power Rifle Scooter!

Trenches for site utilities

www.elzinga-volkers.com


Four Week Look Ahead

Selective demolition is complete in all three areas of the building. Framing of Area A and Area B are complete and framing of the new addition will begin in two weeks. In addition, the plumbing, mechanical and electrical contractors are finishing up roughing-in the utilities. The concrete trucks will be on-site this week to pour the addition in Area C. Next week, the new mechanical unit above the ceiling will be hooked up. The drywall in Area B will start in three weeks, and Area A will begin a week later. By the end of January we will have painted walls! - Julie Cole, Project Coordinator juliec@elzinga-volkers.com

SUBCONTRACTOR

SPOTLIGHT This month’s spotlight goes out to Accurate Plumbing. Renovations take a great deal of investigation and diligence in order to work with the existing systems. Accurate Plumbing’s crew has been great

Demolition in Area B

to work with and they are focused on getting the job done correctly. We appreciate their dedication to

Project Progress and Major Milestones

this project. Thank you, Accurate Plumbing!

Ready for Move In Interiors Complete Framing in Area B Drywall Complete Framing Complete Foundations Complete

Existing interior finishes have been removed

Demolition Complete

& www.elzinga-volkers.com