Upcoming Milestones »» »» »» »» »» »» »» »»

Executive Summary

to get the job done! Thank you for your hard work and cooperation!

Many projects, especially remodels, are not what they appear. Oftentimes, we run into unexpected challenges on the site. These challenges can affect schedule and cause coordination concerns, but luckily we have a great group of subcontractors that are able to adjust and modify their scopes and schedules for the success of the project. Chelsea Lumber, BMC Masonry, Lansing Glass, Dependable Fire Protection, Accurate Plumbing, Maurer Heating, Deisler Electric and Bartz Excavating have all stepped up on this project. No matter what the scope change or schedule tweak, they are always there

It is exciting to see the project come together. The lodge continues to show progress with each passing week. The new addition is framed, the walls are up, and the entryway is starting to look more inviting. All of the mechanical, electrical and plumbing rough-ins have been completed, and the building is transforming into a whole new structure.

Coming Together!

SPOTLIGHT ON SAFETY A term you might hear on our site but may not be familiar with is PPE, which stands for Personal Protective Equipment. Examples of PPE include items such as gloves, high visibility clothing, foot and eye protection, protective hearing devices and hard hats. Some of these items, like hard hats and eye protection, are required 100% of the time on-site, while others, like gloves, are required only when performing certain tasks. Elzinga & Volkers exceeds MiOSHA standards when it comes to PPE to ensure that all of our workers return home safe every day.

Pour Concrete Slab √ Framing in the new addition √ Plumbing rough-ins √ Mechanical rough-ins √ Electrical rough-ins √ Roof installation in the New Addition Flooring Installed in Area B Painting Complete in Area B

Area C

- John Parker, Project Manager jparker@elzinga-volkers.com

Area B

Floor Plans for Vibrant Life Communities - Lodge II

Area A

Throughout the course of the project, we will frequently mention areas of the floor plan where we are working. Refer to this map to see where these areas are situated and how they connect with one another! www.elzinga-volkers.com


Project Progress Photos

MEET JORDAN

New entry way canopy

Elzinga & Volkers is pleased to introduce you to Jordan Gougeon. Jordan was recently promoted to project manager and handles the business aspect of the day-to-day construction in Durand. Jordan received his bachelor degree from Michigan State University. In his spare time, Jordan enjoys taking advantage of all Grand Rapids has to offer. He also enjoys visiting car shows, spending time outdoors, and being part of the Grand Rapids Young Professional Group.

New walls and textured ceilings

Make sure to congratulate Jordan next time you see him!

Framing and fire caulking in the new addition

www.elzinga-volkers.com


Four Week Look Ahead

We have started floor preparation in addition to texturing and painting the ceilings, and the interior finishes are underway. This is certainly the most difficult and time-sensitive phase. Communication and coordination between subcontractors is vital to make this phase a success. We are gearing up to start installing all the new door frames. After the floor prep is complete, the new flooring will be installed. In addition, the kitchenette will receive new cabinetry next month. - Julie Cole, Project Coordinator juliec@elzinga-volkers.com

SUBCONTRACTOR

SPOTLIGHT This month’s spotlight goes out to Chelsea Lumber. With framing changes taking place, Chelsea was able to re-frame five of the existing rooms in the same day. They have been focused on getting the job

Plumbing rough-ins in the new bathrooms

done correctly and going above and beyond to make it happen. We appreciate all of their dedication

Project Progress and Major Milestones

to this project. Ron has enjoyed working with Matt and Craig on-site. Thank you, Chelsea Lumber!

Ready for Move In Interiors Complete New lounge space in Area B Drywall Complete Framing Complete Foundations Complete Demolition Complete

New window between B126 and B117

& www.elzinga-volkers.com

CONSTRUCTION PROFESSIONALS


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.