ID
WBS
Task Mode
Task Name
Duration
ARC 503 Housing Project
110 days? Thu 09/01/14Wed 11/06/1
Start
Finish
Predecessors
1
1
2
1.1
3
1.1.1
Appointment of Team
2 days
Thu 09/01/14 Fri 10/01/14
4
1.1.2
Feasability Study
5 days
Mon 13/01/14Fri 17/01/14 3
5
1.1.3
Tender period
14 days
Mon 20/01/14Thu 06/02/143,4
6
1.1.4
Tender Check
5 days
Fri 07/02/14 Thu 13/02/143,4,5
7
1.1.5
Appointment of Contractor
4 days
Fri 14/02/14 Wed 19/02/144,5,6
8
1.1.6
Detailied design
35 days
Mon 13/01/14Fri 28/02/14 3
Civil works
Start
11/06
110 days? Thu 09/01/14Wed 11/06/1
9
1.1.7
14 days
Thu 20/02/14Tue 11/03/14
10
1.1.7.1
Clear lot
4 days
Thu 20/02/14 Tue 25/02/14 7,3,4,5,6
11
1.1.7.2
Mark out site
4 days
Wed 26/02/14Mon 03/03/1410
12
1.1.7.3
Drainage works
3 days
Tue 04/03/14 Thu 06/03/1411
13
1.1.7.4
Sewer Works
3 days
Tue 04/03/14 Thu 06/03/1411
14
1.1.7.5
External services
3 days
Fri 07/03/14 Tue 11/03/14 11,12,13
15
1.1.8
21 days
Tue 04/03/14Tue 01/04/14
16
1.1.8.1
Excavation foundation footings
7 days
Tue 04/03/14 Wed 12/03/1411
17
1.1.8.2
Auger work
4 days
Thu 13/03/14 Tue 18/03/14 16
18
1.1.8.3
Steel reinforcement , cage and spacers
6 days
Wed 19/03/14Wed 26/03/1416,17
19
1.1.8.4
Piling and concrete work
4 days
Thu 27/03/14 Tue 01/04/14 17,18
20
1.1.9
Oversite slab
4 days
Wed 02/04/14Mon 07/04/1418,19
21
1.1.10
Super Structure
35 days?
Tue 08/04/14Mon 26/05/1
22
1.1.10.1
Framing timbre frame
2 days
Tue 08/04/14 Wed 09/04/1420
23
1.1.10.2
Masonary walls/ Brickwork and Blockwork14 days
Tue 08/04/14 Fri 25/04/14 16,20
24
1.1.10.3
Partitions
1 day?
Thu 10/04/14 Thu 10/04/1422
25
1.1.10.4
Interior doors
1 day?
Mon 26/05/14Mon 26/05/1434
26
1.1.10.5
Pre cast concrete floor
1 day?
Mon 28/04/14Mon 28/04/1422,23,24
27
1.1.10.6
Concrete stairs
7 days
Tue 29/04/14 Wed 07/05/1426
28
1.1.10.7
Erect scaffolding
7 days
Mon 28/04/14Tue 06/05/14 23
29
1.1.10.8
Structural openings
6 days
Wed 07/05/14Wed 14/05/1423,28
30
1.1.10.9
Roof
21 days
Mon 28/04/1 Mon 26/05/1
31
1.1.10.9
Timbre frame
4 days
Wed 07/05/14Mon 12/05/1423,28
32
1.1.10.9
Roof lights
3 days
Tue 13/05/14 Thu 15/05/1431
33
1.1.10.9
Tiling
7 days
Fri 16/05/14 Mon 26/05/1431,32
34
1.1.10.9
Exterior
20 days
Mon 28/04/1 Fri 23/05/14
35
1.1.10.9
Cladding
4 days
Mon 28/04/14Thu 01/05/1423
36
1.1.10.9
windows
7 days
Thu 15/05/14 Fri 23/05/14 23,29,28
37
1.1.10.9
Exterior Doors
2 days
Thu 15/05/14 Fri 16/05/14 23,29
38
1.1.10.9
Gutters and outlets
3 days
Fri 02/05/14 Tue 06/05/14 35
39
1.1.11
Plumbing / piping installation
37 days
Tue 08/04/14Wed 28/05/1
40
1.1.11.1
1st fix
3 days
Tue 08/04/14 Thu 10/04/1420
41
1.1.11.2
2nd fix
3 days
Mon 26/05/14Wed 28/05/1423,24,37,36
42
1.1.12
3 days
Mon 26/05/1 Wed 28/05/1
43
1.1.12.1
1st fix
3 days
Mon 26/05/14Wed 28/05/1436
44
1.1.12.2
2nd Fix
3 days
Mon 26/05/14Wed 28/05/1423,24,37,36
45
1.1.13
Painting and decorating
6 days
Thu 29/05/14 Thu 05/06/1441
46
1.1.14
Cleaning
3 days
Fri 06/06/14 Tue 10/06/14 41,45
47
1.1.15
Landscaping
18 days?
Mon 19/05/1 Wed 11/06/1
48
1.1.15.1
Fencing
4 days
Mon 19/05/14Thu 22/05/1431,37,38
49
1.1.15.2
Tarmac
3 days
Mon 26/05/14Wed 28/05/1436
50
1.1.15.3
Gate
1 day
Fri 23/05/14 Fri 23/05/14 48
51
1.1.15.4
Finish
1 day?
Wed 11/06/14Wed 11/06/1446
Project: master programme gant Date: Wed 20/05/15
an '14 13 Jan '14 20 Jan '14 27 Jan '14 03 Feb '14 10 Feb '14 17 Feb '14 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 Apr '14 05 May '14 12 May '14 19 May '14 26 May '14 02 Jun '14 09 Jun '14 16 WT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SM 11/06
Foundations
Electrical Installation
11/03
Task
Milestone
Project Summary
External Milestone
Inactive Milestone
Manual Task
Manual Summary Rollup
Start‐only
Deadline
Critical Split
Split
Summary
External Tasks
Inactive Task
Inactive Summary
Duration‐only
Manual Summary
Finish‐only
Critical
Progress
Page 1