A master programme gant chart

Page 1

ID

WBS

Task Mode

Task Name

Duration

ARC 503 Housing Project

110 days? Thu 09/01/14Wed 11/06/1

Start

Finish

Predecessors

1

1

2

1.1

3

1.1.1

Appointment of Team

2 days

Thu 09/01/14 Fri 10/01/14

4

1.1.2

Feasability Study

5 days

Mon 13/01/14Fri 17/01/14 3

5

1.1.3

Tender period

14 days

Mon 20/01/14Thu 06/02/143,4

6

1.1.4

Tender Check

5 days

Fri 07/02/14 Thu 13/02/143,4,5

7

1.1.5

Appointment of Contractor

4 days

Fri 14/02/14 Wed 19/02/144,5,6

8

1.1.6

Detailied design

35 days

Mon 13/01/14Fri 28/02/14 3

Civil works

Start

11/06

110 days? Thu 09/01/14Wed 11/06/1

9

1.1.7

14 days

Thu 20/02/14Tue 11/03/14

10

1.1.7.1

Clear lot

4 days

Thu 20/02/14 Tue 25/02/14 7,3,4,5,6

11

1.1.7.2

Mark out site

4 days

Wed 26/02/14Mon 03/03/1410

12

1.1.7.3

Drainage works

3 days

Tue 04/03/14 Thu 06/03/1411

13

1.1.7.4

Sewer Works

3 days

Tue 04/03/14 Thu 06/03/1411

14

1.1.7.5

External services

3 days

Fri 07/03/14 Tue 11/03/14 11,12,13

15

1.1.8

21 days

Tue 04/03/14Tue 01/04/14

16

1.1.8.1

Excavation foundation footings

7 days

Tue 04/03/14 Wed 12/03/1411

17

1.1.8.2

Auger work

4 days

Thu 13/03/14 Tue 18/03/14 16

18

1.1.8.3

Steel reinforcement , cage and spacers

6 days

Wed 19/03/14Wed 26/03/1416,17

19

1.1.8.4

Piling and concrete work

4 days

Thu 27/03/14 Tue 01/04/14 17,18

20

1.1.9

Oversite slab

4 days

Wed 02/04/14Mon 07/04/1418,19

21

1.1.10

Super Structure

35 days?

Tue 08/04/14Mon 26/05/1

22

1.1.10.1

Framing timbre frame

2 days

Tue 08/04/14 Wed 09/04/1420

23

1.1.10.2

Masonary walls/ Brickwork and Blockwork14 days

Tue 08/04/14 Fri 25/04/14 16,20

24

1.1.10.3

Partitions

1 day?

Thu 10/04/14 Thu 10/04/1422

25

1.1.10.4

Interior doors

1 day?

Mon 26/05/14Mon 26/05/1434

26

1.1.10.5

Pre cast concrete floor

1 day?

Mon 28/04/14Mon 28/04/1422,23,24

27

1.1.10.6

Concrete stairs

7 days

Tue 29/04/14 Wed 07/05/1426

28

1.1.10.7

Erect scaffolding

7 days

Mon 28/04/14Tue 06/05/14 23

29

1.1.10.8

Structural openings

6 days

Wed 07/05/14Wed 14/05/1423,28

30

1.1.10.9

Roof

21 days

Mon 28/04/1 Mon 26/05/1

31

1.1.10.9

Timbre frame

4 days

Wed 07/05/14Mon 12/05/1423,28

32

1.1.10.9

Roof lights

3 days

Tue 13/05/14 Thu 15/05/1431

33

1.1.10.9

Tiling

7 days

Fri 16/05/14 Mon 26/05/1431,32

34

1.1.10.9

Exterior

20 days

Mon 28/04/1 Fri 23/05/14

35

1.1.10.9

Cladding

4 days

Mon 28/04/14Thu 01/05/1423

36

1.1.10.9

windows

7 days

Thu 15/05/14 Fri 23/05/14 23,29,28

37

1.1.10.9

Exterior Doors

2 days

Thu 15/05/14 Fri 16/05/14 23,29

38

1.1.10.9

Gutters and outlets

3 days

Fri 02/05/14 Tue 06/05/14 35

39

1.1.11

Plumbing / piping installation

37 days

Tue 08/04/14Wed 28/05/1

40

1.1.11.1

1st fix

3 days

Tue 08/04/14 Thu 10/04/1420

41

1.1.11.2

2nd fix

3 days

Mon 26/05/14Wed 28/05/1423,24,37,36

42

1.1.12

3 days

Mon 26/05/1 Wed 28/05/1

43

1.1.12.1

1st fix

3 days

Mon 26/05/14Wed 28/05/1436

44

1.1.12.2

2nd Fix

3 days

Mon 26/05/14Wed 28/05/1423,24,37,36

45

1.1.13

Painting and decorating

6 days

Thu 29/05/14 Thu 05/06/1441

46

1.1.14

Cleaning

3 days

Fri 06/06/14 Tue 10/06/14 41,45

47

1.1.15

Landscaping

18 days?

Mon 19/05/1 Wed 11/06/1

48

1.1.15.1

Fencing

4 days

Mon 19/05/14Thu 22/05/1431,37,38

49

1.1.15.2

Tarmac

3 days

Mon 26/05/14Wed 28/05/1436

50

1.1.15.3

Gate

1 day

Fri 23/05/14 Fri 23/05/14 48

51

1.1.15.4

Finish

1 day?

Wed 11/06/14Wed 11/06/1446

Project: master programme gant Date: Wed 20/05/15

an '14 13 Jan '14 20 Jan '14 27 Jan '14 03 Feb '14 10 Feb '14 17 Feb '14 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 Apr '14 05 May '14 12 May '14 19 May '14 26 May '14 02 Jun '14 09 Jun '14 16 WT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SM 11/06

Foundations

Electrical Installation

11/03

Task

Milestone

Project Summary

External Milestone

Inactive Milestone

Manual Task

Manual Summary Rollup

Start‐only

Deadline

Critical Split

Split

Summary

External Tasks

Inactive Task

Inactive Summary

Duration‐only

Manual Summary

Finish‐only

Critical

Progress

Page 1