Table 6-2: Durfee Avenue Countermeasure Concept Costs

Table 6-2: Durfee Avenue Countermeasure Concept Costs

COUNTERMEASURE DESCRIPTION UNIT COST UM QUANTITY LENGTH WIDTH COST

Advertisement

Concrete or Pavement Construction (low cost options use pavement markings)

Crossing Island Concrete curbs and sign(s) $20,000 EA 1

Bulb Out / Turn Wedge

Pavement Markings

High Visibility Crosswalks Pavement markings with 'buttons' and rubber turn wedges $2,500 EA 9

Continental spaced to avoid vehicle wheels $5,500 EA 6 Bicycle vs Vehicle Conflict Markings Green w/ white edges, 50 ft length $6,000 EA 8 $20,000 $22,500

$33,000 $48,000

Signs or Signal Infrastructure

Pedestrian Signal - New Mast, power, concrete median, crosswalk $198,000 EA 2

INT = Intersection, Qty = Quantity, L = Length, W = Width, EA = Each, SF = Square Feet, LF = Linear Feet $396,000 Total $519,500

Pedestrian crossing mid-block on Durfee Avenue at Legore Elementary School Existing bicycle lane on Durfee Avenue