Liberty High School Priority 1 Projects
July 6, 2015
Liberty Independent School District 2015 Bond Plan
i
01
Program of Spaces & Existing Conditions Liberty High School Addition and Renovation Priority 1 Projects
Liberty ISD 2015 Bond Projects
Program of Spaces
Liberty High School - Band & Choir Addition & Theatre Renovation Priority 1 Projects
Band and Choir Addition Band
Band Hall
Theatre Conversion of Bankhall into LHS Theatre 5,320 3.600
Practice Rooms
320
Office
150
Library
200
School Inventory Storage
200
Percussion Storage
200
Uniform Storage
200
Color Guard
200
Exterior Storage
250
Choir Choir Hall
Notes 1. Total Gross for Choir & Music Addition derived from a 1.25 factor added to the program of spaces. This information will assist in area requirements for a free-standing as well as an attached addition that will require stand alone MEP systems seperate from the existing building MEP systems. 2. A phasing requirement consideration is needed to build and occupy the band hall of the new facility prior to or in conjunction with conversion of existing band hall into “Black Box.”
3,670 2,400
Practice Rooms
320
Piano Lab
200
Office
150
Library
200
Uniform Storage
200
Prop Storage
200
Common Practice Room Rehearsal Music Theory/Composition Restrooms & Dressing
1,000
Restrooms
400
Dressing Rooms
500
Director’s Restroom & Shower
100
Support
420
Mechanical
200
Electrical
100
Data
60
Custodial
60
Total Net Area Circulation, Wall, MEP Etc. Total Gross Gross/Net
Liberty ISD 2015 Bond Projects: Priority 1
10,410 2,603 13,013 1.25
03
Program of Spaces
Liberty HS - Ag & Construction Addition & Renovations/Bus Transport Priority 1 Projects
Agriculture Addition and Renovation
LHS Ag Addition Computer Lab Classroom Restrooms Dressrooms
Support Mechanical Electrical Data Custodial
Total Net Area Circulation, Walls, MEP, etc. Total Gross Gross/Net
2,200 1,000 750 200 250 220 100 60 60 0
2,420 605 3,025 1.25
Notes 1. The current consideration is to convert the existing Auto Tech/Construction Science Building into the future Agriculture Facility. 2. The conversion will include both renovation and an addition of the existing Auto Tech/Construction Science Building to function as the new Agriculture Facility. 3. As a stand alone facillity, upgrage and addition to existing MEP and other systems will be required. AG has heavy venitlation, ventilation and plumbing/gas requirements to accomodate welding. 4. Included in the phasing, the scope of work will require conversion of the existing AG into the Construction Science Facility.
Bus Transportation Center 2015 Bond Plan Projects
Shop Area (2 Mechanics & 1 Helper) Shop Area (4 Bays) Bus Wash Bay Shop Office Shop Break Room Parts Storage Shop Restroom, Lockers & Showers Net Area Circulation, Walls, MEP Gross Area Net/Gross
9,350 5,500 2,250 150 150 800 500 9,350 2,338 11,688 1.25
Notes 1. Project scope involves relocation of existing bus and transportation facility at Liberty Stadium to a new location adjacent to Liberty High School. 2. Current consideration is that access to the new facility will be directly from Panther Lane which is a wide roadway that is currently underutilized. 3. Adjequate surface parking will be required in conjuction with and adjacent to the built Shop Area.
Liberty ISD 2015 Bond Projects: Priority 1 04
Program of Spaces Liberty HS -Athletics Priority 1 Projects
Girls’s Athletics
Shared Athletic Facilities Training Room
1,710
Office
120
Storage
150
Whirlpool/Ice
200
Training Room Garage Storage
1,000 240
Team Room
800
Laundry
600
Weight Room
0
Girls’s Coaches
800
Girl’s Athletic Coordinator
150
Office ( 10 -12 work stations)
400
Lockers, Restrooms, Showers
400
Girl’s Athletic Locker Rooms
3,200
Varsity - 50 Players (24”x24”x72”)
800
JV/Freshman- 100 players (24”x24”x36” dbl tier)
800
Multi-Sports - 150 players 18”x18”x36” dbl tier)
800
Restroom & Showers
800
Girl’s Athletic Equipment Storage
700
Volleyball
100
Basketball
100
Softball
100
Athletic Director
Track
100
Office ( 10 -12 work stations)
Golf & Tennis
100
Lockers, Restrooms, Showers
Uniform Storage
200
Boy’s Athletics Boy’s Coaches
Boy’s Athletic Locker Rooms
0
0
Varsity - 50 Players (24”x24”x72”) JV/Freshman- 100 players (24”x24”x36” dbl tier) Multi-Sports - 150 players 18”x18”x36” dbl tier) Restroom & Showers
Boy’s Athletic Equipment Storage Football Basketball Baseball Track Soccer
0
Support
420
Mechanical
200
Electrical
100
Data
60
Custodial
60
Total Athletics
Total Net Area Circulation, Walls, MEP Total Gross Area Net/Gross
8,280 2,070
10,350 1.25
Uniform Storage
Notes: 1. Project scope related to athletics primarily focuses on a series of shared athletic facilities and expansion of girl’s athletic facilities. 2. Shared facilities consist of Training, Team Room and Support Spaces. The existing weight room will remain retain in current use. 3. Girl’s facilities include athletic locker rooms, equipment storage and coach’s offices. 4. Locate new athletic facilities in proximity to existing gym and athletic areas. Liberty ISD 2015 Bond Projects: Priority 1
06
Existing Aerial Site Images Site Vicinity
Libery High School Project Site
T STA WY
EH S 146
WALMART
G PIN
ER
NT
CE
OP
SH
227
H
RT
Heights Baptist Church
NO LIBERTY MIDDLE SCHOOL
IN
MA
ET
RE
ST
LIBERTY HIGH SCHOOL
JEFFERSON DRIVE
JEFFERSON DRIVE
H
RT
NO
IN
MA
ET
RE
ST
227
N
H
RT
NO
I MA
ET
RE
ST
0
50’
100’
200’
300’
600’
SITE PLAN
Liberty ISD 2015 Bond Projects: Priority 1
Existing Aerial Site Images Neighborhood Aerial View
Heights Baptist Church
LIBERTY MIDDLE SCHOOL
LIBERTY HIGH SCHOOL 0
JEFFERSON DRIVE
Liberty ISD 2015 Bond Projects: Priority 1
25’
50’
100’
SITE PLAN
150’
300’
Existing Aerial Site Images School Site Aerial
Construction Science
Autotech
Ag Mech & Metal
Gymnasium Weight Room
Boy’s Fieldhouse Panther Lane
Gymnasium
Annex SE
Cafeteria Kitchen Music
Theatre Art
Entry
s Stre
et
LIBERTY MIDDLE SCHOOL
Texa
Heights Baptist Church
Plymouth
Street
Administration
Academic Classrooms
LIBERTY HIGH SCHOOL 0
15’
30’
60’
90’
180’
SITE PLAN
JEFFERSON DRIVE
Liberty ISD 2015 Bond Projects: Priority 1
Existing Site Images
Liberty High School Exterior - West Side
Liberty ISD 2015 Bond Projects: Priority 1
Existing Site Images
Liberty High School Exterior - West Side
Liberty ISD 2015 Bond Projects: Priority 1
Existing Site Images
Liberty High School Exterior - West Side
Liberty ISD 2015 Bond Projects: Priority 1
Existing Site Images
Liberty High School Exterior - West Side
Liberty ISD 2015 Bond Projects: Priority 1
Existing Floor Plan Liberty High School Color Code Plan
Academic Classrooms & Labs
Circulation
Entry
Choir
Drama Auditorium
Cafeteria Gymnasium
Administration
Art
Kitchen Band
First Floor Plan 1’
Liberty ISD 2015 Bond Projects: Priority 1
8’
32’
64’
Existing High School Liberty High School Aerial View
EXISITING AUTOTECH & CONSTRUCTION
EXISITING GYMNASIUM
EXISITING BAND & CHOIR MAIN ENTRY
Liberty ISD 2015 Bond Projects: Priority 1
Existing High School Liberty High School Aerial Plan View
PANTHER LANE
PANTHER LANE
PANTHER LANE
Liberty ISD 2015 Bond Projects: Priority 1
Project Design Options Liberty High School Addition and Renovation Priority 1 Projects
Liberty ISD 2015 Bond Projects: Priority 1
Option 1: Attached Program Additions Liberty High School Additions and Renovation
Music & Choral are attaced to the existing high school and linked via exisiting interior corridor. Access to Girl’s Fieldhouse via covered canopy. Existing transformer retained in existing location.
Pro’s
Con’s
Connected - more secure.
Triggers fire sprinkler ($600,000).
Proximity/Adjacent to Programs.
More exterior wall required to construct - increase construction cost. Might be more difficult to work into new HS plan. Requires we reroute Service Drive. Existing gasline conflict. MOST EXPENSIVE OPTION.
Liberty ISD 2015 Bond Projects: Priority 1
Option 1
Liberty High School Aerial View 1
ADDITION AUTOTECH ADDITION GIRLS ATHLETICS
TRANSFORMER TO REMAIN
RENOVATION THEATRE ARTS
ADDITION BAND & CHOIR
Liberty ISD 2015 Bond Projects: Priority 1
Option 1
Liberty High School Aerial View 2
Existing Transformer
ADDITION GIRLS ATHLETICS
Reroute Service Drive
Liberty ISD 2015 Bond Projects: Priority 1
ADDITION BAND & CHOIR
Option 1 Liberty High School Aerial View 3
RENOVATION THEATRE ARTS
ADDITION GIRLS ATHLETICS
Liberty ISD 2015 Bond Projects: Priority 1
Option 1
Liberty High School Aerial View 4
Liberty ISD 2015 Bond Projects: Priority 1
Option 1 Liberty High School Aerial View 5
ADDITION BAND & CHOIR ADDITION GIRLS ATHLETICS
ADDITION AUTOTECH
TRANSPORTATION CENTER
RENOVATION THEATRE ARTS
Liberty ISD 2015 Bond Projects: Priority 1
Option 2: Consolidated Addition Liberty High School Additions and Renovation
Music & Choral are consolidated to the new Girl’s Field House Addition to create one building addition. This option does not incurr any conflict with existing transformer operation and location.
Pro’s Does not trigger fire sprinkler.
Not connected/stand alone, but semi-secure.
Does not require rerouting of service drive.
Not preferred adjacency.
Less exterior walls. Easier to fit into a new HS plan. LEAST EXPENSIVE- MOST ECONOMICAL OPTION
Liberty ISD 2015 Bond Projects: Priority 1
Con’s
Option 2
Liberty High School Aerial View 1
ADDITION AUTOTECH
ADDITION GIRLS ATHLETICS
TRANSFORMER TO REMAIN
SECURE FENCING
Liberty ISD 2015 Bond Projects: Priority 1
Option 2
Liberty High School Aerial View 2
Liberty ISD 2015 Bond Projects: Priority 1
Option 2 Liberty High School Aerial View 3
Liberty ISD 2015 Bond Projects: Priority 1
Option 2
Liberty High School Aerial View 4
Liberty ISD 2015 Bond Projects: Priority 1
Option 2 Liberty High School Aerial View 5
ADDITION BAND & CHOIR ADDITION GIRLS ATHLETICS
THEATRE ARTS
ADDITION AUTOTECH
TRANSPORTATION CENTER
Liberty ISD 2015 Bond Projects: Priority 1
Option 3: Consolidated Addition with Courtyard Liberty High School Additions and Renovation
Music & Choral are consolidated with Girl’s Field House into one Addition. This option does require movement of transformer but not not require existing building sprinkler.
Pro’s Does not trigger fire sprinkler. Better proximity than Option 2. Less exterior walls. Semi-secure building access. MIDDLE EXPENSE OPTION
Liberty ISD 2015 Bond Projects: Priority 1
Con’s Requires moving transformer and underground service to new transformer locaiton. Not connected but secure.
Option 3
Liberty High School Aerial View 1
TRANSPORTATION CENTER
ADDITION AUTOTECH
ADDITION GIRLS ATHLETICS
TRANSFORMER TO MOVED
ADDITION BAND & CHOIR
RENOVATION THEATRE ARTS
SECURE FENCING
Liberty ISD 2015 Bond Projects: Priority 1
Option 3
Liberty High School Aerial View 2
Liberty ISD 2015 Bond Projects: Priority 1
Option 3 Liberty High School Aerial View 3
Liberty ISD 2015 Bond Projects: Priority 1
Option 3
Liberty High School Aerial View 4
Liberty ISD 2015 Bond Projects: Priority 1
Option 3 Liberty High School Aerial View 5
ADDITION BAND & CHOIR ADDITION GIRLS ATHLETICS
THEATRE ARTS
ADDITION AUTOTECH
TRANSPORTATION CENTER
Liberty ISD 2015 Bond Projects: Priority 1
New High School with Proposed Addition Liberty High School Additions and Renovation
Liberty ISD 2015 Bond Projects: Priority 1
New High School Liberty High School Aerial View 1
ADDITION GIRLS ATHLETICS
MUSIC & CHOIR
Liberty ISD 2015 Bond Projects: Priority 1
New High School Liberty High School Aerial View 2
Liberty ISD 2015 Bond Projects: Priority 1
New High School Liberty High School Aerial View 3
Liberty ISD 2015 Bond Projects: Priority 1
New High School Liberty High School Aerial View 4
Liberty ISD 2015 Bond Projects: Priority 1
New High School Liberty High School Aerial View 5
Liberty ISD 2015 Bond Projects: Priority 1
Liberty Independent School District 2015 Bond Plan Project Summary and Overview Renovations, Additions and New Construction Projects
Liberty High School: Priority 1 Projects
July 6, 2015