G. Baker Detailing & Construction

Page 1

FINAL COURSE BOOKLET

TSM2006: DETAIL AND CONSTRUCTION DOCUMENTS

TERM: FALL 2021

INSTRUCTOR: MARY POLITES SUBMISSION BY: GREG BAKER DATE: DECEMBER 6, 2021

FINAL
BOOKLET GREG
TSM2006
A-0.0
COURSE
BAKER
COVER SHEET 12/06/2021

TABLE OF CONTENTS

CASE STUDY FORENSICS

A-1A : ASSIGNMENT 1A : CASE STUDY FORENSICS

A-1A.1.1 - A-1A.1.6 : CASE STUDY 1, PK ARKITEKTAR, HOLIDAY COTTAGES

A-1A.2.1 - A-1A.2.5 : CASE STUDY 2, ALLIED WORKS ARCH, CLYFFORD STILL MUSEUM

A-1A.3.1 - A-1A.3.9 : CASE STUDY 3, MICHAEL GREEN ARCH, WOOD INNOVATION DESIGN CENTRE

A-1B : ASSIGNMENT 1B : CASE STUDY FORENSICS

A-1B.1.1 - A-1B.1.2 : CASE STUDY 1, PK ARKITEKTAR, HOLIDAY COTTAGES

A-1B.2.1 - A-1B.2.2 : CASE STUDY 2, ALLIED WORKS ARCH, CLYFFORD STILL MUSEUM

A-1B.3.1 - A-1B.3.2 : CASE STUDY 3, MICHAEL GREEN ARCH, WOOD INNOVATION DESIGN CENTRE

A-1C : ASSIGNMENT 1C : CASE STUDY FORENSICS

A-1C.1.1 - A-1C.1.8 : CASE STUDY 1, PK ARKITEKTAR, HOLIDAY COTTAGES

A-1D : ASSIGNMENT 1D : CASE STUDY FORENSICS

A-1D.1.1 - A-1D.1.4 : CASE STUDY 1, PK ARKITEKTAR, HOLIDAY COTTAGES

TRANSFORMATION

A-2A : ASSIGNMENT 2A : TRANSFORMATION

A-2A.1.1 - A-2A.1.4 : MODIFIED CASE STUDY 1, PK ARKITEKTAR, HOLIDAY COTTAGES

A-2B : ASSIGNMENT 2B : TRANSFORMATION

A-2B.1.1 - A-2B.1.4 : MODIFIED CASE STUDY 1, PK ARKITEKTAR, HOLIDAY COTTAGES

A-2C : ASSIGNMENT 2C : TRANSFORMATION

A-2C.1.1 - A-2C.1.5 : MODIFIED CASE STUDY 1, PK ARKITEKTAR, HOLIDAY COTTAGES

12/06/2021

TABLE OF CONTENTS

B-1.1 : BIBLIOGRAPHY

FINAL COURSE BOOKLET
TSM2006
A-0.1

ASSIGNMENT 1A

SELECT 3 CASE STUDY PROJECTS, ONE LAYERED WALL SYSTEM, ONE MONOLITHIC WALL SYSTEM, AND ONE CURTAIN WALL SYSTEM. RESEARCH AND PROVIDE A BRIEF NARRATIVE FOR EACH CASE STUDY.

INCLUDE REFERENCE PHOTOS, TYPICAL FLOOR PLANS, BUILDING SECTIONS AND BUILDING ELEVATIONS.

ASSIGNMENT 1A

12/06/2021

FINAL COURSE BOOKLET
TSM2006
GREG BAKER
ASSIGNMENT 1A A-1A
FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-1A.1.1 ASSIGNMENT 1A LAYERED WALL SYSTEM
2
1
2
1 1
FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 1/8" = 1'-0" 1 01 GROUND FLOOR PLAN A-1A.1.2 ASSIGNMENT 1A LAYERED WALL SYSTEM N (1.1)
A-1A.1.3
A-1A.1.4
A-1A.1.4
A-1A.1.3
A-1A.1.5

1/8" = 1'-0"

FINAL COURSE BOOKLET
TSM2006
ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021
GREG BAKER
PK
ELEVATION
1/8" = 1'-0" 2 01 NORTH
1
ELEVATION A-1A.1.3 ASSIGNMENT
LAYERED WALL SYSTEM
01 EAST
1A
(1.1) (1.1)
FINAL COURSE BOOKLET
BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021
1 01 WEST ELEVATION
2 01 SOUTH ELEVATION A-1A.1.4 ASSIGNMENT 1A LAYERED WALL SYSTEM
GREG
1/8" = 1'-0"
1/8" = 1'-0"
(1.1) (1.1)
FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 1/8" = 1'-0" 1 01 SECTION A-1A.1.5 ASSIGNMENT 1A LAYERED WALL SYSTEM (1.1)

ARCHITECT:

LOCATION: YEAR: PROJECT NARRATIVE:

PK ARKITEKTAR BREKKUSKOGUR, ICELAND 2015

LOCATED NEAR LAKE LAUGARVATN IN ICELAND, THE VACATION COTTAGES PROVIDE PRIVACY AND AN INTIMATE EXPERIENCE WITH THE RURAL ENVIRONMENT. THE DISPLACED SOIL IS INTEGRATED WITH THE ROOFSCAPES AND WINDBARRIERS, ALLOWING FOR THE STRUCTURE TO NESTLE INTO THE LANDSCAPE (1.1).

THE LAYOUT OF THE COTTAGE IS LIMITED IN CIRCULATION AREA ALLOWING FOR LOWER COSTS IN CONSTRUCTION DETAILING, MATERIALS, AND MAINTENANCE WHILE CREATING AN INTERIOR SPACE THAT IS CONTECTED AND CLEAR (1.1). EXTERIOR MATERIALS MIMIC THE LOCAL VERNACULAR OF BURT WOOD CLADDING FOR PANELS AND CONCRETE FOR THE BASE. INTERIOR MATERIALS BRING THE OUTSIDE IN WITH THE SAME WOOD PANELING, HARDWOOD FLOORS AND SMOOTH CONCRETE. THE ROOF IS A PLANE OF VEGETATION THAT IS CONTINOUS WITH THE SITE. THE COMPACT SITE ALLOWED FOR A MINIMAL ENVIRONMENTAL IMPACT

THE DESIGN HAS ZERO CARBON FOOTPRINT AND IMPLEMENTS GEOTHERMAL HYDRO ENERGY WITH DRILLED SOURCES ON SITE (1.1).

SOURCES:

(1.1) "Vacation Cottages / PK Arkitektar" 18 Jan 2020. ArchDaily. Accessed 30 Aug 2021. <https://www.archdaily.com/778709/vacation-cottages-pk-arkitektar> ISSN 0719-8884

ASSIGNMENT 1A

12/06/2021

FINAL COURSE BOOKLET
TSM2006
GREG BAKER
PK ARKITEKTAR, HOLIDAY COTTAGES A-1A.1.6
LAYERED WALL SYSTEM
FINAL COURSE BOOKLET GREG BAKER TSM2006 ALLIED WORKS ARCHITECTURE, CLYFFORD STILL MUSEUM 12/06/2021 A-1A.2.1 ASSIGNMENT 1A MONOLITHIC WALL SYSTEM
2 A-1A.2.4 FINAL COURSE BOOKLET GREG BAKER TSM2006 ALLIED WORKS ARCHITECTURE, CLYFFORD STILL MUSEUM 12/06/2021 1/16" = 1'-0" 1 02 GROUND FLOOR PLAN A-1A.2.2 ASSIGNMENT 1A MONOLITHIC WALL SYSTEM N (2.1)
1 A-1A.2.4
FINAL COURSE BOOKLET
TSM2006
1/16" = 1'-0" 1 02 SECOND FLOOR PLAN A-1A.2.3 ASSIGNMENT 1A MONOLITHIC WALL SYSTEM N (2.1)
ALLIED WORKS ARCHITECTURE, CLYFFORD STILL MUSEUM 12/06/2021

(2.1)

1/16" = 1'-0" 1 02 SECTION 1

1/16" = 1'-0" 2 02 SECTION 2 (2.1)

ASSIGNMENT 1A

MONOLITHIC WALL SYSTEM

12/06/2021

FINAL
BOOKLET
COURSE
TSM2006
ALLIED WORKS ARCHITECTURE, CLYFFORD STILL MUSEUM A-1A.2.4

ARCHITECT:

LOCATION: YEAR:

PROJECT NARRATIVE:

ALLIED WORKS ARCHITECTURE DENVER, UNITED STATES 2011

THE CLYFFORD STILL MUSEUM IS LOCATED ON AN URBAN STREET INTERSECTION IN DENVER, COLORADO (2.1). LANDSCAPED AREAS PULL THE MASS OF THE CONCRETE STRUCTURE BACK FROM THE STREET TO CREATE PUBLIC GREEN SPACE ADJACENT TO OTHER CIVIC BUILDINGS. THE ENTRY IS FOUND BY FOLLOWING THE PATHS BELOW THE TREE CANOPY. NINE LIFETED GALLERIES ON THE INTERIOR VARY IN SIZE AS THEY SPACIALLY RESPOND TO THE EXHIBITS WITHIN.

TWO OUTDOOR TERRACES AND NATURAL LIGHT FROM SKYLIGHTS HELP TO BREAK UP THE INTERIOR SPACE AS BRIDGES CROSS OVER MAIN CIRCULATION (2.1).

CONCRETE MOLDS USED IN CONSTRUCTION CREATED VERTICAL LINE TEXTURE ON THE EXTERIOR FACADES, WHICH CAN BE EXPERIENCED AS YOU APPROACH THE MUSEUM (2.1). THE CAST IN PLACE CONCRETE WALLS HELP TO SHEILD THE CONTENTS OF THE EXHIBITS FROM THE INTENSE COLORADO SUN. IN ADDITION, THE SKYLIGHTS IMPLEMENT DIFFUSING GLASS AND OPERABLE SHADES TO CONTROL THE AMBIENT NATURAL LIGHT.

SOURCES:

(2.1) "Clyfford Still Museum / Allied Works Architecture" 31 Jan 2012. ArchDaily. Accessed 30 Aug 2021. <https://www.archdaily.com/203388/clyfford-still-museum-allied-works-architecture-2> ISSN 0719-8884

ASSIGNMENT 1A

12/06/2021

FINAL COURSE BOOKLET
TSM2006
ALLIED WORKS ARCHITECTURE, CLYFFORD STILL MUSEUM A-1A.2.5
MONOLITHIC WALL SYSTEM
FINAL COURSE BOOKLET GREG BAKER TSM2006 MICHAEL GREEN ARCHITECTURE, WOOD INNOVATION DESIGN CENTRE 12/06/2021 A-1A.3.1 ASSIGNMENT 1A CURTAIN WALL SYSTEM
A-1A.3.5 1 A-1A.3.6 1 A-1A.3.7 1 1 A-1A.3.8 FINAL COURSE BOOKLET
BAKER TSM2006
12/06/2021 1/16" = 1'-0" 1 03 GROUND FLOOR PLAN A-1A.3.2 ASSIGNMENT 1A CURTAIN WALL SYSTEM N (3.1)
A-1A.3.4 1 1A.3.5
GREG
MICHAEL GREEN ARCHITECTURE, WOOD INNOVATION DESIGN CENTRE
FINAL COURSE BOOKLET
TSM2006
1/16" = 1'-0" 1 03 FIFTH FLOOR PLAN A-1A.3.3 ASSIGNMENT 1A CURTAIN WALL SYSTEM (3.1)
GREG BAKER
MICHAEL GREEN ARCHITECTURE, WOOD INNOVATION DESIGN CENTRE 12/06/2021
FINAL COURSE BOOKLET
BAKER TSM2006 MICHAEL
12/06/2021 1/16" = 1'-0" 1 03 EAST ELEVATION A-1A.3.4 ASSIGNMENT 1A CURTAIN WALL SYSTEM (3.3)
GREG
GREEN ARCHITECTURE, WOOD INNOVATION DESIGN CENTRE
FINAL COURSE BOOKLET
TSM2006
1/16" = 1'-0" 1 03 SOUTH ELEVATION A-1A.3.5 ASSIGNMENT 1A CURTAIN WALL SYSTEM (3.3)
GREG BAKER
MICHAEL GREEN ARCHITECTURE, WOOD INNOVATION DESIGN CENTRE 12/06/2021
FINAL COURSE BOOKLET
BAKER TSM2006 MICHAEL
1/16" = 1'-0" 1 03 WEST ELEVATION A-1A.3.6 ASSIGNMENT 1A CURTAIN WALL SYSTEM (3.3)
GREG
GREEN ARCHITECTURE, WOOD INNOVATION DESIGN CENTRE 12/06/2021
FINAL COURSE BOOKLET
BAKER TSM2006 MICHAEL
ARCHITECTURE,
12/06/2021 1/16" = 1'-0" 1 03 NORTH ELEVATION A-1A.3.7 ASSIGNMENT 1A CURTAIN WALL SYSTEM (3.3)
GREG
GREEN
WOOD INNOVATION DESIGN CENTRE
FINAL COURSE BOOKLET
TSM2006
1/16" = 1'-0" 1 03 SECTION 1 A-1A.3.8 ASSIGNMENT 1A CURTAIN WALL SYSTEM (3.2)
GREG BAKER
MICHAEL GREEN ARCHITECTURE, WOOD INNOVATION DESIGN CENTRE 12/06/2021

ARCHITECT: LOCATION: YEAR: PROJECT NARRATIVE:

MICHAEL GREEN ARCHITECTURE ST PRINCE GEORGE, BC, CANADA 2014

THE WOOD INNOVATION AND DESIGN CENTRE IS A STRUCTURE THAT CLEARLY REPRESENTS AND CONTRIBUTES TO THE EDUCATION OF WOOD DESIGN THAT TAKES PLACE WITHIN (3.1). WHILE THE LOWER FLOORS ARE DEDICATED TO WOOD DESIGN EDUCATION, THE UPPER FLOORS HOUSE GOVERNMENT AND WOOD INDUSTRY ORGANIZATIONS TO CREATE AN ENVIRONMENT FOR LEARNING AND COLLABORATION IN THE COMMUNITY OF WOOD CONSTRUCTION.

THE EITGHT STORY BUILDING IS THE WORLD'S TALLEST ALL TIMBER OFFICE BUILDING, AT 97 FEET (3.4). THE ONLY CONCRETE USED IN THE STRUCTURE IS IN THE GROUND FLOOR SLAB. THE WALLS ARE MASS TIMBER WHILE BEAMS AND COLUMNS ARE GLULAM. SIMPLE WOOD CONSTRUCTION TECHNIQUES WERE USED FOR THE DETAILS.

WHILE EXEMPLIFYING THE POTENTIAL FOR WOOD CONSTRUCTING IN MID-RISE STRUCTURES, THE SPACES CREATED ON THE INTERIOR SHOW HOW THE OPORTUNITES FOR THE SUSTAINABLE MATERIAL (3.4).

SOURCES:

(3.1) "Wood Innovation Design Centre / Michael Green Architecture" 19 Jul 2020. ArchDaily. Accessed 30 Aug 2021.

<https://www.archdaily.com/630264/wood-innovation-design-centre-michael-green-architecture> ISSN 0719-8884

(3.2) Hooper, Emily. “Innovative Detail: Wood Innovation and Design Centre.” Architect Magazine, March 24, 2015.

<https://www.architectmagazine.com/technology/detail/innovative-detail-wood-innovation-anddesign-centre_o>

(3.3) “Governor General's Medal Winner: Wood Innovation and Design Centre.” Canadian Architect, June 22, 2019.

<https://www.canadianarchitect.com/governor-generals-wood/>

(3.4) “Wood Innovation and Design Centre.” Michael Green Architecture. Accessed September 6, 2021.

<http://mg-architecture.ca/work/wood-innovation-design-centre/>

ASSIGNMENT 1A

CURTAIN WALL SYSTEM

12/06/2021

FINAL COURSE BOOKLET
TSM2006
MICHAEL GREEN ARCHITECTURE, WOOD INNOVATION DESIGN CENTRE A-1A.3.9

ASSIGNMENT 1B

RESEARCH AND ANALYZE THE 3 CASE STUDIES IN MORE DEPTH. PREPARE ONE EXTERIOR WALL SECTION, ONE PLAN SECTION, AND ONE BUILDING AXONOMETRIC VIEW FOR EACH CASE STUDY.

ASSIGNMENT 1B

12/06/2021

FINAL COURSE BOOKLET
TSM2006
GREG BAKER A-1B
ASSIGNMENT 1B
FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 1/4" = 1'-0" 1 01 SECTION 2 A-1B.1.1 ASSIGNMENT 1B LAYERED WALL SYSTEM (1.2)
A-1B.1.2 2 A-1B.1.2 3 Sim

GREEN ROOF

STEEL ANGLE WATERPROOF MEMBRANE

BLOCKING SUPPORT FOR WOOD PANEL FACADE

TREATED WOOD PANEL FACADE

WINDOW FRAME WATERPROOF SILL

WOOD FRAMING

BLOCKING FOR INTERIOR WOOD PANELS INSULATION VENTILATION CONCRETE SLAB FOUNDATION

RIGID INSULATION

TREATED WOOD PANEL FACADE BLOCKING SUPPORT FOR WOOD PANEL FACADE WATERPROOF INSULATION INSULATION INTERIOR WOOD PANELS

FINAL COURSE BOOKLET GREG BAKER TSM2006
A-1B.1.2
PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 1/8" = 1'-0" 1 01 BUILDING AXON 1" = 1'-0" 2 01 WALL SECTION
ASSIGNMENT 1B LAYERED WALL SYSTEM 1" = 1'-0" 3 01 PLAN VIEW (1.2) (1.2) (1.1)(1.2)

2 A-1B.2.2 A-1B.2.2 3

FINAL COURSE BOOKLET
TSM2006 ALLIED WORKS ARCHITECTURE, CLYFFORD STILL MUSEUM 12/06/2021 A-1B.2.1 ASSIGNMENT 1B MONOLITHIC WALL SYSTEM 1/16" = 1'-0" 1 02 GROUND FLOOR PLAN 2 (2.2)
GREG BAKER

SKYLIGHT

ROOF MEMBRANE

PRE-CAST CONCRETE PARAPET CAP

RIGID INSULATION OVER AIR/VAPOR BARRIER PERFORATED ARCHITECTURAL CONCRETE CEILING

PRE-CAST ARCHITECTURAL CONCRETE WALL PANEL

RIGID INSULATION AND AIR/VAPOR BARRIER

ARCHICTECTURAL CONCRETE WALL CONCRETE FOOTER

02 BUILDING AXON

1/8" = 1'-0" 1

(2.2)

ARCHITECTURAL CONCRETE WALL

RIGID INSULATION

PRE-CAST ARCHITECTURAL CONCRETE WALL PANEL

12/06/2021

ALLIED WORKS ARCHITECTURE, CLYFFORD STILL MUSEUM

DETAIL

(2.2) (2.2)

FINAL COURSE BOOKLET
BAKER TSM2006
GREG
A-1B.2.2
ASSIGNMENT 1B
MONOLITHIC WALL SYSTEM 1/4" = 1'-0" 2 02 SECTION 3 1/2" = 1'-0" 3 02 ENLARGED PLAN
2 A-1B.3.2 A-1B.3.2 4 Sim FINAL COURSE BOOKLET GREG BAKER TSM2006 MICHAEL GREEN ARCHITECTURE, WOOD INNOVATION DESIGN CENTRE 12/06/2021 A-1B.3.1 ASSIGNMENT 1B CURTAIN WALL SYSTEM 1/16" = 1'-0" 1 03 GROUND FLOOR PLAN 2 (3.1)
ROOF
LAYERED
LAYERED
RIGID INSULATION CONCRETE SLAB ON GRADE
FOOTER PERIMETER
WINDOW
FINAL COURSE BOOKLET
TSM2006
1 03 BUILDING AXON A-1B.3.2 ASSIGNMENT 1B CURTAIN WALL SYSTEM 1/4" = 1'-0" 2 03 SECTION 2 1/4" = 1'-0" 3 03 SECTION 3 1/4" =
4 03 PLAN VIEW (3.1) (3.1) (3.1)(3.3) (3.1)
WOOD PANELING GLASS CURTAIN WALL
WOOD BEAM
WOOD BEAM WOOD PANELS
CONCRETE
WINDOW FRAME GLASS CURTAIN WALL
MULLION
GREG BAKER
MICHAEL GREEN ARCHITECTURE, WOOD INNOVATION DESIGN CENTRE 12/06/2021 1/8" = 1'-0"
1'-0"

ASSIGNMENT

1C

SELECT 1 CASE STUDY PROJECT TO INVESTIGATE IN GREATER DETAIL.

DEVELOP DRAWINGS FOR BUILDING ELEVATION DETAIL, WALL SECTION DETAIL, PLAN DETAIL, AND PARTITION DETAIL. IDENTIFY BUILDING ELEMENTS VISIBLE IN VIEW.

IDENTIFY BUILDING ELEMENTS IN THE CATEGORIES OF THE FOUNDATION SYSTEM, FLOOR SYSTEM, WALL SYSTEM, AND ROOF SYSTEM. DESCRIBE WHAT EACH MATERIAL/ELEMENT DOES FOR THE BUILDING SYSTEM.

RESEARCH CASE STUDY'S LOCATION, CLIMATE, AND BUILDING CODES FOR R-VALUES. IDENTIFY R-VALUE REQUIREMENTS FOR EACH OF THE FOUR DESCRIBED BUILDING SYSTEMS. IDENTIFY R-VALUES FOR MATERIALS WITHIN EACH BUILDING SYSTEM TO FIND THE REQUIRED R-VALUE FOR THE INSULATION WITHIN THE SYSTEM. SUGGEST AN INSULATION TYPE TO BE USED TO ACHIEVE REQUIRED TOTAL R-VALUE.

ASSIGNMENT 1C

12/06/2021

FINAL COURSE BOOKLET
BAKER TSM2006
GREG
ASSIGNMENT 1C A-1C
1 A-1C.1.2 Sim A-1C.1.3 2 FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 1/8" = 1'-0" 1 01 GROUND FLOOR PLAN 2 A-1C.1.1 ASSIGNMENT 1C LAYERED WALL SYSTEM N (1.1)
Sim FINAL COURSE BOOKLET
BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 1/4" = 1'-0" 1 01 SECTION 3 A-1C.1.2 ASSIGNMENT 1C LAYERED WALL SYSTEM (1.2)
A-1C.1.3 1
GREG

CHARRED WOOD CLADDING

WINDPROOF PAPER MINERAL WOOL INSULATION

FURRING STRIP PLYWOOD SHEET PLASTIC SHEET GYP WALL BOARD

GREEN ROOF

SOIL STEEL ANGLE

WATERPROOF MEMBRANE

AIR BARRIER

PLYWOOD SHEET

TREATED WOOD PANEL FACADE

WINDPAPER PLYWOOD SHEET

FURRING STRIP SUPPORT FOR WOOD PANEL FACADE

WOOD STUD

MINERAL WOOL INSULATION

GYP WALL BOARD

VERTICAL TREATED WOOD FACADE CLADDING, CHARRED GROUND

WINDPAPER, INSULATION COVER BEHIND WOOD CLADDING

TREATED WOOD PANEL FACADE

WINDOW FRAME WATERPROOF SILL BLOCKING FOR INTERIOR WOOD PANELS

WOOD FRAMING

PLYWOOD SHEET

INSULATION VENTILATION

CONCRETE SLAB FOUNDATION

MINERAL WOOL INSULATION WOOD JOIST THERMAL INSULATION CLOTH COVER WOOD CLAD CEILING DRAINAGE PIPE

GREEN ROOF BEYOND
FINAL COURSE BOOKLET
BAKER TSM2006 PK ARKITEKTAR,
COTTAGES 12/06/2021 3/4" = 1'-0" 1 01 WALL SECTION 2 3/4"
4 01 PARTITION SECTION 3/4" = 1'-0" 3 01 PLAN VIEW 2 3/4" = 1'-0" 2 01 ELEVATION DETAIL A-1C.1.3 ASSIGNMENT 1C LAYERED WALL SYSTEM (1.2) (1.6) (1.2) (1.6) (1.2) (1.6) (1.2) (1.6)
GREG
HOLIDAY
= 1'-0"

I. FOUNDATION SYSTEM----

DRAINAGE PIPE

HELPS TO COLLECT WATER AND TO REDISTRIBUTE AWAY FROM STRUCTURE DRAINAGE ROCK

COLLECTS MOISTURE AT GROUND AND DIRECTS AWAT FROM STRUCTURE AND TOWARDS DRAINAGE PIPE SYSTEM SUPPORTING SOIL

SOIL OUTSIDE OF FOUNDATION WALL PROVIDES LATERAL SUPPORT FOR STRUCTURE COMPACTED SOIL HELPS TO PROVIDE SUPPORT TO FOUNDATION CONCRETE FOOTING

DISTRIBUTES STRUCTURAL LOAD FROM FOUNDATION WALL PROTECTIVE CLOTH COVER

PROTECTS INSULATION AND HIDES INSULATION FROM VIEW THERMAL INSULATION

PREVENTS THERMAL HEAT LOSS FROM FOUNATION WALL INTO SOIL FOUNDATION WALL, CAST-IN-PLACE STRUCTURAL WALL BELOW GRADE TO SUPPORT LATERAL LOADS AND STRUCTURE ABOVE THERMAL INSULATION

PREVENTS THERMAL HEAT LOSS FROM FOUNATION WALL INTO SOIL SUPPORTING SOIL

SOIL BELOW FLOOR AND INSIDE OF FOUNDATION WALL PROVIDES SUPPORT FOR STRUCTURE

(1.1)(1.2)(1.6) (1.1)(1.2)(1.6)

II. FLOOR SYSTEM--

POLISHED CONCRETE SLAB ON GRADE FINISHED FLOOR, POURED ON SITE THERMAL INSULATION

PREVENTS THERMAL HEAT LOSS FROM CONCRETE SLAB INTO SOIL FROST-FREE GROUND FILLER (GRAVEL)

PREVENTS CAPILLARY GROUNDWATER RISE AND CONCRETE CRACKING FROM FREEZING SUPPORTING SOIL SOIL BELOW FLOOR AND INSIDE OF FOUNDATION WALL PROVIDES SUPPORT FOR STRUCTURE

FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 ASSIGNMENT 1C LAYERED WALL SYSTEM
A-1C.1.4

-----

----

III. WALL SYSTEM

WOOD PANEL CLADDING, CHARRED

EXTERIOR FINISH SYSTEM

WINDPROOF PAPER

PROVIDE PROTECTION AND COVER TO FURRING STRIPS HORIZONTAL FURRING STRIPS

PROVIDE MOUNTING FOR EXTERIOR WOOD CLADDING PLYWOOD SHEET

SHEETHING FOR SUPPORT OF EXTERIOR CLADDING SYSTEM MINERAL WOOL INSULATION

PROVIDES THERMAL INSULATION BETWEEN INTERIOR AND EXTERIOR WOOD FRAMING

STUD FRAMING SYSTEM, STRUCTURE OF EXTERIOR WALL SYSTEM PLASTIC SHEET

PROVIDES MOISTURE BARRIER FROM EXTERIOR GYPSUM WALL BOARD

PROVIDES FINISH FACE FOR INTERIOR PAINT OR MOUNDING FOR INTERIOR WOOD PANELS

IV. ROOF SYSTEM

(1.1)(1.2)(1.6) (1.1)(1.2)(1.6)

GREEN ROOF PLANTING

PLANTING ON GREEN ROOF, ENHANCES ENVIRONMENT SOIL

PROVIDES FIILTRATION OF WATER FROM GREEN ROOF WATER PROOF MEMBRANE

BARRIER OF RAINWATER FROM GREEN ROOF TO WOOD STRUCTURE AIR BARRIER

ALLOWS FOR AIR FLOW AND FOR MOISTURE PREVENTION PLYWOOD SHEET

PROVIDES SUPPORT FOR GREEN ROOF WOOD JOIST

ROOF STRUCTURE SYSTEM

MINERAL WOOL INSULATION

THERMAL INSULATION IN ROOF SYSTEM

RIGID INSULATION

THERMAL INSULATION IN ROOF SYSTEM CLOTH COVER

PROVIDES COVER OF INSULATION FROM VIEW AT INTERIOR WOOD CLADDING

INTERIOR FINISH SYSTEM OF CEILING

FINAL COURSE BOOKLET
BAKER TSM2006
ARKITEKTAR,
COTTAGES
GREG
PK
HOLIDAY
12/06/2021
A-1C.1.5 ASSIGNMENT 1C
LAYERED WALL SYSTEM
FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-1C.1.6 ASSIGNMENT 1C LAYERED WALL SYSTEM R-VALUE INSULATION REQUIREMENTS FOR ICELAND, CLIMATE ZONE 8 I. FOUNDATION SYSTEMR-10 II. FLOOR SYSTEMR-15 III. WALL SYSTEMR-20 IV. ROOF SYSTEMR-49 (1.5) (1.4) (1.3) SITE LOCATION: BREKKUSKOGUR, ICELAND (1.5)(1.6)

I. FOUNDATION SYSTEM R-VALUES

DRAINAGE PIPE

DRAINAGE ROCK

SUPPORTING SOIL CONCRETE FOOTING PROTECTIVE CLOTH COVER THERMAL INSULATION

FOUNDATION WALL, CAST-IN-PLACE THERMAL INSULATION

SUPPORTING SOIL

-0.08 0.06 ? 0.08 (8") ?0.78

R-10 REQUIRED

R-10 - R-0.78 = R9.22 TO BE PROVIDED BY TWO LAYERS OF INSULATION, @2" SHEETS

II. FLOOR SYSTEM R-VALUES

(1.5)(1.6) (1.5)(1.6)

POLISHED CONCRETE SLAB ON GRADE

THERMAL INSULATION

FROST-FREE GROUND FILLER (GRAVEL)

SUPPORTING SOIL

R-15 REQUIRED

R-15 - R-0.04 = R14.96 TO BE PROVIDED BY ONE LAYER OF INSULATION, @4" SHEETS

RIGID INSULATION = R-VALUE 2.6 (2) LAYERS OF 2" PERLITE EXPANDED RIGID INSULATION WILL PROVIDE R-VALUE OF 10. 0.08(5") ?0.04

RIGID INSULATION = R-VALUE 5 (1) LAYER OF 4" POLYSTYRENE EXTRUDED RIGID INSULATION WILL PROVIDE R-VALUE OF 20.

LAYERED WALL SYSTEM

12/06/2021

PK ARKITEKTAR, HOLIDAY COTTAGES

FINAL COURSE BOOKLET
TSM2006
GREG BAKER
A-1C.1.7
ASSIGNMENT 1C

III. WALL SYSTEM R-VALUE

W1 W2 W1 W1 = 2" WOOD STUD 2" / 24" = 9%

BATT INSULATION 24" OC

WOOD PANEL CLADDING, CHARRED

WINDPROOF PAPER

HORIZONTAL FURRING STRIPS

PLYWOOD SHEET

MINERAL WOOL INSULATION

WOOD FRAMING

PLASTIC SHEET

GYPSUM WALL BOARD

IV. ROOF SYSTEM R-VALUES

(1.5)(1.6) (1.5)(1.6)

GREEN ROOF PLANTING

SOIL

WATER PROOF MEMBRANE

AIR BARRIER

PLYWOOD SHEET

WOOD JOIST

MINERAL WOOL INSULATION

RIGID INSULATION

CLOTH COVER WOOD CLADDING

0.01.25(.5") ? 0.91(6") 0.0 .67(.5")

R-20 REQUIRED

R-VALUE AT STUDS IS 9.44 (9.44 X 9%) + ((1.25(.5) + .67(.5) + R(6)) X 92%) = 20

BATT INSULATION = R-VALUE 3.3 (1) LAYER OF 6" ROCKWOOL INSULATION WILL PROVIDE R-VALUE OF 19.8. (6.44 X 9%) + ((.625 + .335 + 19.8) X 92%) = .58 + (20.76 X 92%) = .58 + 22.56 = R-VALUE 23.14

BATT INSULATION 24" OC

W1 W2 W1 W1 = 2" WOOD STUD 2" / 24" = 9% W2 = 22" OF BATT INS. 22" / 24" = 92%

RIGID INS.

R-49 REQUIRED ((9.375+i(2)) X 9%) + ((2.096 + R(8) = i(2)) X 92%) = 49

BATT INSULATION = R-VALUE 3.3 (1) LAYER OF 8" ROCKWOOL INSULATION WILL PROVIDE RVALUE OF 26.4.

W2 = 22" OF BATT INS. 22" / 24" = 92%-1.01 1.25(.5) .91(8") ? ? 0.0 .91(.5)

POLYISOCTANURATE RIGID INSULATION 7.2 PER INCH WILL PROVIDE 14.4 R-VALUE @2" ((9.375+7.2(2)) X 9%) + ((2.096 + 3.3(8) + 7.2(2)) X 92%) = 49 (23.775 X 9%) + (42.896 X 92%) = (2.14) + (43.8) = 45.956 R-VALUE

LAYERED WALL SYSTEM

12/06/2021

PK ARKITEKTAR, HOLIDAY COTTAGES

FINAL COURSE BOOKLET
TSM2006
GREG BAKER
A-1C.1.8
ASSIGNMENT 1C

ASSIGNMENT 1D

CONTINUE TO DEVELOP ENLARGED DETAILS FOR SELECTED CASE STUDY.

DEMONSTRATE COMPLETE UNDERSTANDING OF CONSTRUCTION SHOWN IN DETAILS. PROVIDE DESCRIPTIONS FOR EACH MATERIAL/ELEMENT FOR HOW IT CONTRIBUTES TO THE SYSTEM.

ASSIGNMENT 1D

12/06/2021 A-1D

FINAL COURSE BOOKLET
TSM2006
GREG BAKER
ASSIGNMENT 1D

GREEN ROOF

AIDS IN THERMAL CONTROL, AESTHETIC AND ENVIRONMENTAL BUILDING SYSTEM

MINERAL WOOL INSULATION

THERMAL CONTROL BETWEEN WOOD JOISTS

WATERPROOF MEMBRANE

PREVENTS MOISTURE FROM GREEN ROOF TO PERMEATE TO INTERIOR STRUCTURE

AIR BARRIER

ALLOWS MOISTURE TO DRY PRIOR TO CONTACT WITH STRUCTURE

GRAVEL WATER FILTRATION FROM GREEN ROOF

STEEL ANGLE CONTAINS SOIL AT GREEN ROOF

PLYWOOD SHEET

LATERAL SUPPORT TO ROOF SYSTEM

SEALANT AND BACKER RODS

ROLLER BLIND CONTROLS NATURAL LIGHT AT WINDOW TO INTERIOR

WOOD JOIST

PROVIDE CONTINUOUS SEAL AT WINDOW PERIMETER CARRIES STRUCTURAL LOADS OF ROOF

EXTRUDED POLYSTYRENE CLOTH COVER WOOD CLAD CEILING

AIDS IN THERMAL CONTROL AT CEILING AND ROOF

PROVIDES AESTHETIC CONTROL AT SEAMS IN WOOD CLAD CEILING INTERIOR FINISH SYSTEM AT CEILING

FINAL COURSE BOOKLET
BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-1D.1.1 ASSIGNMENT 1D LAYERED WALL SYSTEM 3" = 1'-0" 1 01 SECTION DETAIL -WALL TO ROOF (1.2) (1.6) PLAN CALLOUT, NTS, (1.1) SECTION
GREG
CALLOUT, NTS, (1.2)

WELDED WIRE FABRIC REINFORCEMENT

PROVIDES TENSILE SUPPORT TO CONCRETE SLAB INTERIOR FINISH TREATMENT TO CONCRETE SLAB

POLISHED CONCRETE FINISH

CONCRETE SLAB FOUNDATION

FLOOT STRUCTURAL COMPONENT, 4" MIN

FLASHING

BENT METAL, PROVIDES MOISTURE CONTROL AT BASE OF WALL

EXTRUDED POLYSTYRENE INSULATION

THERMAL AND MOISTURE PROTECTION BELOW SLAB MOISTURE CONTROL, BRIDGES NONSTRUCTURAL SEAMS

WATERPROOFING MEMBRANE

SECTION CALLOUT, NTS, (1.2)

DRAINAGE MAT

DIRECTS MOISTURE DOWN TO DRAINAGE SYSTEM

MOISTURE CONTROL

FILTER FABRIC COARSE GRAVEL

DRAINAGE CONTROL BELOW SLAB

EXTRUDED POLYSTYRENE BELOW GRADE

THERMAL CONTROL AT STRUCTURAL CONCRETE WALL

PLAN CALLOUT, NTS, (1.1)

FINAL COURSE BOOKLET
BAKER TSM2006
A-1D.1.2 ASSIGNMENT 1D LAYERED WALL SYSTEM 3" = 1'-0" 1 01 SECTION DETAIL -FLOOR TO WALL (1.2) (1.6)
GREG
PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021

STEEL DOWEL ANCHORS

ANCHOR FOUNDATION WALL TO FOOTING

THERMAL AND MOISTURE PROTECTION BELOW SLAB

COMPACT SOIL

SUPPORTS LOADS FROM STRUCTURE TO GROUND

WATER PROOFING MEMBRANE

MOISTURE CONTROL, BRIDGES NONSTRUCTURAL SEAMS

CONCRETE FOUNDATION WALL

STRUCTURAL COMPONENT TO SUPPORT CONCRETE SLAB

EXTRUDED POLYSTYRENE BELOW GRADE 2" MIN

DIRECTS WATER AWAY FROM CONCRETE CONNECTION TOWARDS DRAINAGE SYSTEM DIRECTS WATER TOWARDS DRAINAGE SYSTEM

6" MIN GRAVEL COVER

DRAINAGE PIPE

COLLECTS WATER TO DIRECT AWAY FROM STRUCTURE

SLOPE WITH MORTAR FILTER FABRIC OVER PIPE

PROTECTION OF DRAINAGE PIPE STRUCTURAL COMPONENT TO DISTRIBUTE LOADS LATERALLY

CONCRETE FOOTING

COMPACTED GRAVEL (4") PACKED GRAVEL TO CARRY VERTICAL LOAD FROM FOOTER TO EARTH

FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-1D.1.3 ASSIGNMENT 1D LAYERED WALL SYSTEM 3" = 1'-0" 1 01 SECTION DETAIL -FOOTING TO FOUNDATION (1.2) (1.6) PLAN CALLOUT, NTS, (1.1) SECTION CALLOUT, NTS, (1.2)

GREG

FURRING STRIP

SUPPORT FOR WOOD PANEL SYSTEM VENTILATION GAP AIR SPACE ALLOWS FOR MOISTURE CONTROL

PROVIDES LATERAL SUPPORT TO WALL SYSTEM

WOOD STUD

2X6 STRUCTURAL SUPPORT

WINDPAPER PLYWOOD SHEET GYP WALL BOARD

VAPOR BARRIER IMPEDES VAPOR INTO INTERIOR. LOCATED ON INTERIOR OF INSULATION IN COLD CLIMATES THERMAL CONTROL AT EXTERIOR WALL 2 LAYERS OF 5/8" INTERIO FINISH MATERIAL

VERTICAL EXTERIOR CLADDING SYSTEM SEALANT AND BACKER RODS PROVIDE CONTINUOUS SEAL AROUND WINDOW FRAME DOUBLE GLAZED WINDOW PROVIDE NATURAL LIGHT AND EXTERIOR VIEWS WHILE MAINTAINING THERMAL CONTROL

MINERAL WOOL INSULATION

TREATED WOOD
PANEL FACADE
FINAL COURSE BOOKLET
BAKER TSM2006
A-1D.1.4 ASSIGNMENT 1D LAYERED
3"
WIND CONTROL AND AESTHETIC MATERIAL IN PANEL GAPS 1 01 PLAN DETAIL -WINDOW JAMB (1.2) (1.6)
PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021
WALL SYSTEM
= 1'-0"
PLAN CALLOUT, NTS, (1.1) SECTION CALLOUT, NTS, (1.2)

ASSIGNMENT 2A

USING CASE STUDY, CHANGE THE BUILDING CONSTRUCTION SYSTEM FOR THE FOUNDATION, FLOOR, WALL OR ROOF.

DEVELOP DETAILS TO SHOW NEW CONSTRUCION METHOD SELECTED AND HOW THE NEW SYSTEM CONNECTS TO THE OTHER BUILDING SYSTEMS.

IDENTIFY BUILDING MATERIALS FOR EACH OF THE FOUR BUILIDNG SYSTEMS AND CATEGORIZE INTO CONSTRUCTION DIVISIONS.

ASSIGNMENT 2A

12/06/2021 A-2A

FINAL COURSE BOOKLET
TSM2006
GREG BAKER
ASSIGNMENT 2A

CURTAIN WALL MULLION

ALUMINUM PARAPET CAP

METAL PANEL FACE

CURTAIN WALL MULLIONS

DOUBLE PANE INSULATED GLASS

GLASS CURTAIN WALL FRAMING

BENT METAL FLASHING

GREEN ROOF BEYOND GROUND

HOLIDAY

2' - 0"
FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR,
COTTAGES 12/06/2021 A-2A.1.1 ASSIGNMENT
CURTAIN
SYSTEM PLAN CALLOUT, NTS,
SECTION CALLOUT, NTS,
3/4"
1 01 ELEVATION DETAIL 2
CURTAIN WALL FRAME DOUBLE PANE INSULATED GLASS 2 01 PLAN
2A
WALL
(1.1)
(1.2) (1.2) (1.6)
= 1'-0"
3/4" = 1'-0"
VIEW 3 (1.2) (1.6)

SOIL

WATERPROOF MEMBRANE

STEEL ANGLE

GREEN ROOF AIR BARRIER

ALUMINUM PARAPET CAP PARAPET FRAMING METAL PANEL FACE

PLYWOOD SHEET MINERAL WOOL INSULATION

NOTCHED WOOD BEAM

RIGID INSULATION

STEEL BEAM

WOOD JOIST THERMAL INSULATION

CLOTH COVER WOOD CLAD CEILING

CURTAIN WALL MULLION

CURTAIN WALL FRAME DOUBLE PANE INSULATED GLASS

MULL-IT-OVER TRANSITION

INTERIOR WOOD STUD FRAMING

INTERIOR INSULATION

DOUBLE PANE INSULATED GLASS

CURTAIN WALL FRAMING

RIGID INSULATION CONCRETE CURB

FLASHING

FINAL COURSE BOOKLET GREG BAKER TSM2006
A-2A.1.2 ASSIGNMENT
CURTAIN
PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 3/4" = 1'-0" 1 01 WALL SECTION 3
2A
WALL SYSTEM PLAN CALLOUT, NTS, (1.1) SECTION CALLOUT, NTS, (1.2) (1.2) (1.6) 3/4" = 1'-0" 2 01 EXT WALL TO INT WALL (1.2) (1.6)

I.

FOUNDATION

DIVISION 03

03 FOUNDATION WALL, CAST-IN-PLACE

STRUCTURAL WALL BELOW GRADE TO SUPPORT LATERAL LOADS AND STRUCTURE ABOVE 03 CONCRETE FOOTING

DISTRIBUTES STRUCTURAL LOAD FROM FOUNDATION WALL DIVISION 07

07 THERMAL INSULATION

PREVENTS THERMAL HEAT LOSS FROM FOUNATION WALL INTO SOIL

07 THERMAL INSULATION

SYSTEM--

PREVENTS THERMAL HEAT LOSS FROM FOUNATION WALL INTO SOIL DIVISION 22

22 DRAINAGE PIPE

HELPS TO COLLECT WATER AND TO REDISTRIBUTE AWAY FROM STRUCTURE DIVISION 31

31 DRAINAGE ROCK COLLECTS MOISTURE AT GROUND AND DIRECTS AWAT FROM STRUCTURE AND TOWARDS DRAINAGE PIPE SYSTEM

31 SUPPORTING SOIL SOIL OUTSIDE OF FOUNDATION WALL PROVIDES LATERAL SUPPORT FOR STRUCTURE COMPACTED SOIL HELPS TO PROVIDE SUPPORT TO FOUNDATION SOIL BELOW FLOOR AND INSIDE OF FOUNDATION WALL PROVIDES SUPPORT FOR STRUCTURE

(1.1)(1.2)(1.6) (1.1)(1.2)(1.6)

DVISION 03

03 POLISHED CONCRETE SLAB ON GRADE FINISHED FLOOR, POURED ON SITE

03 CONCRETE CURB RAISED EDGE AT CONCRETE SLAB DIVISION 07

07 THERMAL INSULATION

PREVENTS THERMAL HEAT LOSS FROM CONCRETE SLAB INTO SOIL DIVISION 31

31 FROST-FREE GROUND FILLER (GRAVEL)

PREVENTS CAPILLARY GROUNDWATER RISE AND CONCRETE CRACKING FROM FREEZING

31 SUPPORTING SOIL

SOIL BELOW FLOOR AND INSIDE OF FOUNDATION WALL PROVIDES SUPPORT FOR STRUCTURE

FINAL COURSE BOOKLET
TSM2006
A-2A.1.3
GREG BAKER
PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021
II. FLOOR SYSTEM-ASSIGNMENT 2A CURTAIN WALL SYSTEM

III. WALL SYSTEM-IV. ROOF SYSTEM--

DIVISION 05 05 CURTAIN WALL ALUMINUM FRAMING PLANTING ON GREEN ROOF, ENHANCES ENVIRONMENT DIVISION 07 07 METAL FLASHING MOISTURE CONTROL AT BASE OF CURTAIN WALL DIVISION 08 08 EXTERIOR DOUBLE PANE GLASS CURTAIN WALL GLASS FOR CURTAIN WALL SYSTEM

(1.1)(1.2)(1.6) (1.1)(1.2)(1.6)

DIVISION 05 05 STEEL ANGLE SUPPORTS SOIL AND ALLOWS FOR DRAINAGE 05 ALUMINUM PARAPET CAP COVER FOR PROTECTION AND MOISTURE CONTROL AT PARAPET 05 METAL PANEL FINISH FACE OF EXTERIOR WALL DIVISION 06 06 PLYWOOD SHEET PROVIDES SUPPORT FOR GREEN ROOF 06 WOOD JOIST ROOF STRUCTURE SYSTEM 06 WOOD FRAMING SUPPORTS STRUCTURE OF PARAPET 06 NOTCHED WOOD BEAM TRANSFERS LOAD FROM ROOF TO STEEL BEAM 06 WOOD CLAD CEILING

DECORATIVE INTERIOR FINISH DIVISION 07 07 GREEN ROOF PLANTING PLANTING ON GREEN ROOF, ENHANCES ENVIRONMENT 07 SOIL PROVIDES FIILTRATION OF WATER FROM GREEN ROOF 07 WATER PROOF MEMBRANE BARRIER OF RAINWATER FROM GREEN ROOF TO WOOD STRUCTURE 07 AIR BARRIER

ALLOWS FOR AIR FLOW AND FOR MOISTURE PREVENTION 07 MINERAL WOOL INSULATION

THERMAL INSULATION IN ROOF SYSTEM 07 RIGID INSULATION

THERMAL INSULATION IN ROOF SYSTEM DIVISION 12 12 CLOTH COVER DECORATIVE COVER BEHIND CLAD CEILING

FINAL COURSE BOOKLET GREG BAKER TSM2006
A-2A.1.4
PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021
ASSIGNMENT 2A
CURTAIN WALL SYSTEM

ASSIGNMENT 2B

CONTINUE TO RESEARCH AND DEVELOP NEW CONSTRUCTION METHOD FOR SELECTED CASE STUDY.

PROVIDE ENLARGED DETAILS FOR FOUNDATION, FLOOR TO WALL, WALL TO ROOF, AND PARTITION PLAN DETAIL.

IDENTIFY ALL BUILDING MATERIALS/ELEMENTS AND DESCRIBE THEIR CONTRIBUTION TO THE OVERALL BUILDING STRUCTURE.

MODIFIED BUILDING SYSTEM SHOULD BE LOGICAL AND SHOULD CONNECT PROPERLY TO ADJACENT BUILDING SYSTEMS TO CREATE PROPER ENCLOSURE.

ASSIGNMENT 2B

12/06/2021 A-2B

FINAL COURSE BOOKLET
TSM2006
GREG BAKER
ASSIGNMENT 2B

GREEN ROOF

AIDS IN THERMAL CONTROL, AESTHETIC AND ENVIRONMENTAL BUILDING SYSTEM

SOIL (4" DEPTH)

SHALLOW FOR GREEN ROOF SOIL FOR LOW GROWING PLANTS, FILTERS WATER

THERMAL CONTROL BETWEEN WOOD JOISTS, THROUGHOUT ROOF AS SHOWN

WATERPROOF MEMBRANE

PREVENTS MOISTURE FROM GREEN ROOF TO PERMEATE TO INTERIOR STRUCTURE

TIE BAR

ADHESIVE STRIP AT PARAPET TO SECURE WATERPROOF MEMBRANE

ALLOWS MOISTURE TO DRY PRIOR TO CONTACT WITH STRUCTURE

PARAPET WOOD FRAMING (2X4)

PROVIDE STRUCTURE TO PARAPET

ALUMINUM PARAPET FLASHING

AIR BARRIER WRAP PLYWOOD SHEET (1/2", 2 LAYERS)

CONTROLS MOISTURE AT PARAPET CAP, ALLOWS FOR WATER DRAINAGE

LATERAL SUPPORT TO ROOF SYSTEM

METAL PANEL FACE

EXTERIOR PANEL SYSTEM

GRAVEL WATER FILTRATION FOR GREEN ROOF NOTCHED WOOD BEAM

TRANSFERS LOAD FROM WOOD ROOF TO STEEL BEAM

STEEL BEAM

MINERAL WOOL INSULATION WOOD JOIST (2X8) EXTRUDED POLYSTYRENE

CARRIES STRUCTURAL LOADS OF ROOF

AIDS IN THERMAL CONTROL AT CEILING AND ROOF

SEALANT AND BACKER RODS

PROVIDE CONTINUOUS SEAL AT WINDOW PERIMETER CURTAIN WALL ALUMINUM FRAMING

STRUCTURAL SUPPORT TO ROOF SYSTEM HOUSES GLAZING IN WATERPROFF SYSTEM

DOUBLE PANE INSULATION GLASS

THERMAL INSULATION AT CURTAINWALL

CLOTH COVER

PROVIDES AESTHETIC CONTROL AT SEAMS IN WOOD CLAD CEILING

WOOD CLAD CEILING

INTERIOR FINISH SYSTEM AT CEILING

FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR,
COTTAGES 12/06/2021 A-2B.1.1 ASSIGNMENT 2B CURTAIN WALL SYSTEM PLAN CALLOUT, NTS, (1.1) 3" = 1'-0" 1 01 SECTION DETAIL -WALL TO ROOF 2 (1.1)(1.2)(1.6)
HOLIDAY
SECTION CALLOUT, NTS, (1.2)

CURTAIN WALL MULLION (BEYOND) VERTICAL SUPPORT AND FRAME FOR GLAZING AT CURTAIN WALL

DOUBLE PANE INSULATION GLASS

THERMAL INSULATION AT CURTAIN WALL

WELDED WIRE FABRIC REINFORCEMENT

PROVIDES TENSILE SUPPORT TO CONCRETE SLAB

POLISHED CONCRETE FINISH

INTERIOR FINISH TREATMENT TO CONCRETE SLAB

ALUMINUM CURTAIN WALL FRAME

HOUSES GLAZING IN WATER PROOF SYSTEM

CONCRETE SLAB FOUNDATION

FLOOT STRUCTURAL COMPONENT, 4" MIN

MESH WITH SKIMMED CONCRETE

PROTECTION AT EXPOSED RIGID INSULATION

FLASHING

BENT METAL, PROVIDES MOISTURE CONTROL AT BASE OF WALL

EXTRUDED POLYSTYRENE INSULATION

THERMAL AND MOISTURE PROTECTION BELOW SLAB, VAPOR BARRIER AT FACE MOISTURE CONTROL, BRIDGES NONSTRUCTURAL SEAMS

WATERPROOFING MEMBRANE

DRAINAGE MAT

DIRECTS MOISTURE DOWN TO DRAINAGE SYSTEM

FILTER FABRIC COARSE GRAVEL

MOISTURE CONTROL DRAINAGE CONTROL BELOW SLAB

EXTRUDED POLYSTYRENE BELOW GRADE

THERMAL CONTROL AT STRUCTURAL CONCRETE WALL

FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-2B.1.2 ASSIGNMENT 2B CURTAIN WALL SYSTEM PLAN CALLOUT, NTS, (1.1) 3" = 1'-0" 1 01 SECTION DETAIL -FLOOR TO WALL 2 (1.1)(1.2)(1.6) SECTION CALLOUT, NTS, (1.2)

2" MIN

STEEL DOWEL ANCHORS

ANCHOR FOUNDATION WALL TO FOOTING

EXTRUDED POLYSTYRENE BELOW GRADE

THERMAL AND MOISTURE PROTECTION BELOW SLAB

SUPPORTS LOADS FROM STRUCTURE TO GROUND

WATER PROOFING MEMBRANE

MOISTURE CONTROL, BRIDGES NONSTRUCTURAL SEAMS

CONCRETE FOUNDATION WALL

STRUCTURAL COMPONENT TO SUPPORT CONCRETE SLAB

COMPACT SOIL DIRECTS WATER AWAY FROM CONCRETE CONNECTION TOWARDS DRAINAGE SYSTEM

6" MIN GRAVEL COVER

DIRECTS WATER TOWARDS DRAINAGE SYSTEM

PERFORATED DRAINAGE PIPE

COLLECTS WATER TO DIRECT AWAY FROM STRUCTURE

SLOPE WITH MORTAR FILTER FABRIC OVER PIPE

PROTECTION OF DRAINAGE PIPE

CONCRETE FOOTING

STRUCTURAL COMPONENT TO DISTRIBUTE LOADS LATERALLY

COMPACTED GRAVEL (4") PACKED GRAVEL TO CARRY VERTICAL LOAD FROM FOOTER TO EARTH

FINAL COURSE BOOKLET
BAKER TSM2006 PK ARKITEKTAR,
COTTAGES 12/06/2021 A-2B.1.3 ASSIGNMENT 2B CURTAIN WALL SYSTEM PLAN CALLOUT, NTS, (1.1) 3" = 1'-0" 1 01 SECTION DETAIL -FOOTING TO FOUNDATION 2 (1.1)(1.2)(1.6)
GREG
HOLIDAY
SECTION CALLOUT, NTS, (1.2)

ALUMINUMCURTAIN WALL FRAME

HOUSES GLAZING IN WATER PROOF SYSTEM

ALUMINUM CURTAIN WALL MULLION

VERTICAL SUPPORT AND FRAME FOR GLAZING AT CURTAIN WALL

DOUBLE PANE INSULATED GLASS

THERMAL INSULATION AT CURTAIN WALL

FOAM GASKET

PROVIDES CONNECTION SURFACE FROM MULL-IT-OVER TO GLAZING

ACOUSTICAL FOAM (STC 60) PROVIDES SOUND CONTROL BETWEEN ROOMS ALONG CURTAIN WALL

MULL-IT-OVER TRANSITION (6")

PROVIDES AESTHETIC AND ACOUSTIC TRANSITION FROM CURTAIN WALL SYSTEM TO INTERIOR METAL STUD

SECTION CALLOUT, NTS, (1.2)

INTERIOR WOOD STUD FRAMING (2X8)

PROVIDES VERTICAL SUPPORT TO INTERIOR PARTITION WALL

GYPSUM BOARD (1/2")

INTERIOR WALL FINISH MATERIAL, SKIM COAT PLASTER, 2 COATS OF WHITE LATEX PAINT

MINERAL WOOL INSULATION

THERMAL AND ACOUSTIC CONTROL BETWEEN INTERIOR WOOD STUDS, THROUGHOUT INTERIOR WALLS THAT MEET EXTERIOR CURTAIN WALL

FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-2B.1.4 ASSIGNMENT 2B CURTAIN WALL SYSTEM PLAN CALLOUT, NTS, (1.1) 3" = 1'-0" 1 01 EXT WALL TO INT WALL 2 (1.1)(1.2)(1.6)(1.7)

ASSIGNMENT 2C

DEVELOP AXONOMETRIC DRAWINGS FOR AN 8 FT WIDE SPAN OF MODIFIED CASE STUDY (INTERIOR AND EXTERIOR).

SHOW ALL BUILDING MATERIALS/ELEMENTS WITH SCALE FIGURE. IDENTIFY ALL COMPONENTS AND DESCRIBE CONTRIBUTION TO BUILDING SYSTEM.

ASSIGNMENT 2C

12/06/2021 A-2C

FINAL COURSE BOOKLET
TSM2006
GREG BAKER
ASSIGNMENT 2C
FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-2C.1.1 ASSIGNMENT 2C CURTAIN WALL SYSTEM 1 INTERIOR AXONOMETRIC 2 EXTERIOR AXONOMETRIC
3/8" = 1'-0" (1.1)(1.2)(1.6)(1.7) 3/8" = 1'-0" (1.1)(1.2)(1.6)(1.7)

GYPSUM WALL BOARD ON 2X8 WOOD STUD SKIM COATED AND PAINTED WHITE INTERIOR FINISH

DOUBLE PANE INSULATION GLASS

THERMAL INSULATION AT CURTAIN WALL

ALUMINUM CURTAIN WALL FRAME

INTERIOR FINISH TREATMENT TO CONCRETE SLAB

CONCRETE SLAB FOUNDATION

FLOOT STRUCTURAL COMPONENT, 4" MIN, CURB AT PERIMETER

HOUSES GLAZING IN WATER PROOF SYSTEM PROTECTION AT EXPOSED RIGID INSULATION

MESH WITH SKIMMED CONCRETE

EXTRUDED POLYSTYRENE BELOW GRADE

THERMAL CONTROL AT STRUCTURAL CONCRETE WALL

WATERPROOFING MEMBRANE

MOISTURE CONTROL, BRIDGES NONSTRUCTURAL SEAMS

EXTRUDED POLYSTYRENE INSULATION

THERMAL AND MOISTURE PROTECTION BELOW SLAB, VAPOR BARRIER AT FACE

POLISHED CONCRETE FINISH DRAINAGE MAT

DIRECTS MOISTURE DOWN TO DRAINAGE SYSTEM MOISTURE CONTROL

FILTER FABRIC

PERFORATED DRAINAGE PIPE

DIRECTS WATER TOWARDS DRAINAGE SYSTEM COLLECTS WATER TO DIRECT AWAY FROM STRUCTURE

CONCRETE FOUNDATION WALL

STRUCTURAL COMPONENT TO SUPPORT CONCRETE SLAB

CONCRETE FOOTING

STRUCTURAL COMPONENT TO DISTRIBUTE LOADS LATERALLY

COMPACTED GRAVEL (4") PACKED GRAVEL TO CARRY VERTICAL LOAD FROM FOOTER TO EARTH

COARSE GRAVEL

DRAINAGE CONTROL BELOW SLAB

6" MIN GRAVEL COVER COMPACT SOIL

SUPPORTS LOADS FROM STRUCTURE TO GROUND

FINAL COURSE BOOKLET
BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-2C.1.2 ASSIGNMENT 2C CURTAIN WALL SYSTEM 1 INTERIOR AXONOMETRIC_01 BOTTOM (1.1)(1.2)(1.6)(1.7) 3/4" = 1'-0"
GREG

GREEN ROOF

AIDS IN THERMAL CONTROL, AESTHETIC AND ENVIRONMENTAL BUILDING SYSTEM

SOIL (4" DEPTH)

SHALLOW FOR GREEN ROOF SOIL FOR LOW GROWING PLANTS, FILTERS WATER

GRAVEL WATER FILTRATION FOR GREEN ROOF

ALUMINUM PARAPET FLASHING

CONTROLS MOISTURE AT PARAPET CAP, ALLOWS FOR WATER DRAINAGE

WATERPROOF MEMBRANE

PROVIDE STRUCTURE TO PARAPET

PARAPET WOOD FRAMING (2X4)

PREVENTS MOISTURE FROM GREEN ROOF TO PERMEATE TO INTERIOR STRUCTURE

AIR BARRIER WRAP

ALLOWS MOISTURE TO DRY PRIOR TO CONTACT WITH STRUCTURE

METAL PANEL FACE

EXTERIOR PANEL SYSTEM

EXTRUDED POLYSTYRENE

AIDS IN THERMAL CONTROL AT CEILING AND ROOF

STEEL BEAM

STRUCTURAL SUPPORT TO ROOF SYSTEM

SEALANT AND BACKER RODS

PROVIDE CONTINUOUS SEAL AT WINDOW PERIMETER

PLYWOOD SHEET (1/2", 2 LAYERS)

LATERAL SUPPORT TO ROOF SYSTEM

MINERAL WOOL INSULATION

THERMAL CONTROL BETWEEN WOOD JOISTS, THROUGHOUT ROOF AS SHOWN

WOOD JOIST (2X8)

CARRIES STRUCTURAL LOADS OF ROOF

WOOD CLAD CEILING

INTERIOR FINISH SYSTEM AT CEILING

DOUBLE PANE INSULATION GLASS

THERMAL INSULATION AT CURTAINWALL

CURTAIN WALL ALUMINUM FRAMING

HOUSES GLAZING IN WATERPROFF SYSTEM

NOTCHED WOOD BEAM

TRANSFERS LOAD FROM WOOD ROOF TO STEEL BEAM

FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-2C.1.3 ASSIGNMENT 2C CURTAIN WALL SYSTEM 1 INTERIOR AXONOMETRIC_02 TOP (1.1)(1.2)(1.6)(1.7)3/4" = 1'-0"

GYPSUM WALL BOARD ON 2X8 WOOD STUD SKIM COATED AND PAINTED WHITE INTERIOR FINISH MULL-IT-OVER TRIM ACOUSTIC AND AESTHETIC TRANSITION FROM INTERIOR WALL TO MULLION

DOUBLE PANE INSULATION GLASS

ALUMINUM CURTAIN WALL FRAME

INTERIOR FINISH TREATMENT TO CONCRETE SLAB

CONCRETE SLAB FOUNDATION

FLOOT STRUCTURAL COMPONENT, 4" MIN, CURB AT PERIMETER

THERMAL INSULATION AT CURTAIN WALL HOUSES GLAZING IN WATER PROOF SYSTEM PROTECTION AT EXPOSED RIGID INSULATION

MESH WITH SKIMMED CONCRETE

FLASHING

BENT METAL, PROVIDES MOISTURE CONTROL AT BASE OF WALL

WATERPROOFING MEMBRANE

MOISTURE CONTROL, BRIDGES NONSTRUCTURAL SEAMS

EXTRUDED POLYSTYRENE BELOW GRADE

THERMAL CONTROL AT STRUCTURAL CONCRETE WALL

POLISHED CONCRETE FINISH DRAINAGE MAT

DIRECTS MOISTURE DOWN TO DRAINAGE SYSTEM

CONCRETE FOUNDATION WALL

STRUCTURAL COMPONENT TO SUPPORT CONCRETE SLAB

FILTER FABRIC

MOISTURE CONTROL

PERFORATED DRAINAGE PIPE

COLLECTS WATER TO DIRECT AWAY FROM STRUCTURE

CONCRETE FOOTING

STRUCTURAL COMPONENT TO DISTRIBUTE LOADS LATERALLY

COMPACTED GRAVEL (4") PACKED GRAVEL TO CARRY VERTICAL LOAD FROM FOOTER TO EARTH

COMPACT SOIL

SUPPORTS LOADS FROM STRUCTURE TO GROUND

FINAL COURSE BOOKLET
BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-2C.1.4 ASSIGNMENT 2C CURTAIN WALL SYSTEM 1 EXTERIOR AXONOMETRIC_01 BOTTOM (1.1)(1.2)(1.6)(1.7)3/4" = 1'-0"
GREG

GREEN ROOF

AIDS IN THERMAL CONTROL, AESTHETIC AND ENVIRONMENTAL BUILDING SYSTEM

SOIL (4" DEPTH)

SHALLOW FOR GREEN ROOF SOIL FOR LOW GROWING PLANTS, FILTERS WATER

WATERPROOF MEMBRANE

AIR BARRIER WRAP

ALLOWS MOISTURE TO DRY PRIOR TO CONTACT WITH STRUCTURE

PLYWOOD SHEET (1/2", 2 LAYERS)

LATERAL SUPPORT TO ROOF SYSTEM

MINERAL WOOL INSULATION

THERMAL CONTROL BETWEEN WOOD JOISTS, THROUGHOUT ROOF AS SHOWN CARRIES STRUCTURAL LOADS OF ROOF

WOOD JOIST (2X8) EXTRUDED POLYSTYRENE

AIDS IN THERMAL CONTROL AT CEILING AND ROOF

WOOD CLAD CEILING

INTERIOR FINISH SYSTEM AT CEILING WATER FILTRATION FOR GREEN ROOF

GRAVEL

ALUMINUM PARAPET FLASHING PARAPET WOOD FRAMING (2X4)

PREVENTS MOISTURE FROM GREEN ROOF TO PERMEATE TO INTERIOR STRUCTURE

METAL PANEL FACE

PROVIDE STRUCTURE TO PARAPET CONTROLS MOISTURE AT PARAPET CAP, ALLOWS FOR WATER DRAINAGE EXTERIOR PANEL SYSTEM

STEEL BEAM

STRUCTURAL SUPPORT TO ROOF SYSTEM

SEALANT AND BACKER RODS

DOUBLE PANE INSULATION GLASS

THERMAL INSULATION AT CURTAINWALL

PROVIDE CONTINUOUS SEAL AT WINDOW PERIMETER CURTAIN WALL ALUMINUM FRAMING

HOUSES GLAZING IN WATERPROFF SYSTEM

FINAL COURSE BOOKLET GREG BAKER TSM2006 PK ARKITEKTAR, HOLIDAY COTTAGES 12/06/2021 A-2C.1.5 ASSIGNMENT 2C CURTAIN WALL SYSTEM 1 EXTERIOR AXONOMETRIC_02 TOP (1.1)(1.2)(1.6)(1.7)3/4" = 1'-0"

SOURCES:

(1.1) "Vacation Cottages / PK Arkitektar" 18 Jan 2020. ArchDaily. Accessed 30 Aug 2021. <https://www.archdaily.com/778709/vacation-cottages-pk-arkitektar> ISSN 0719-8884

(1.2) Arkitektar, PK. “PK Arkitektar - BHM.” The Plan. The Plan, March 31, 2016. <https://www.theplan.it/eng/award-2016-house/bhm-2>

(1.3) “| Building Energy Codes Program.” Building Envelope Insulation R-Value Compliance Requirements by Climate Zone. Accessed September 28, 2021. <https://www.energycodes.gov/>

(1.4) Marteinsson, Björn, and Gudni Gudnason. “Drivers for Sustainable Renovation in Residential Buildings after Adoption of Thermal Insulation Requirements.” Rannís Icelandic National Research Fund. Accessed September 27, 2021. https://www.irbnet.de/daten/iconda/CIB21289.pdf.

(1.5) WorldClim. Accessed September 28, 2021. https://worldclim.org/data/index.html.

(1.6) Ching, Frank. Building Construction Illustrated. Hoboken, NJ: John Wiley and Sons, 2020.

(1.7) “People in Glass Buildings Should Not Hear Their&nbsp;Neighbors.” Mull. Accessed November 16, 2021. <https://www.mullitoverproducts.com/.>

(2.1) "Clyfford Still Museum / Allied Works Architecture" 31 Jan 2012. ArchDaily. Accessed 30 Aug 2021. <https://www.archdaily.com/203388/clyfford-still-museum-allied-works-architecture-2> ISSN 0719-8884

(2.2) “Clyfford Still Museum - Allied Works Architecture.” The Plan. Accessed September 21, 2021. <https://www.theplan.it/eng/architecture/clyfford-still-museum>

(3.1) "Wood Innovation Design Centre / Michael Green Architecture" 19 Jul 2020. ArchDaily. Accessed 30 Aug 2021.

<https://www.archdaily.com/630264/wood-innovation-design-centre-michael-green-architecture> ISSN 0719-8884

(3.2) Hooper, Emily. “Innovative Detail: Wood Innovation and Design Centre.” Architect Magazine, March 24, 2015.

<https://www.architectmagazine.com/technology/detail/innovative-detail-wood-innovation-and-design-centre_o>

(3.3) “Governor General's Medal Winner: Wood Innovation and Design Centre.” Canadian Architect, June 22, 2019.

<https://www.canadianarchitect.com/governor-generals-wood/>

(3.4) “Wood Innovation and Design Centre.” Michael Green Architecture. Accessed September 6, 2021. <http://mg-architecture.ca/work/wood-innovation-design-centre/>

12/06/2021

FINAL COURSE BOOKLET
TSM2006 BIBLIOGRAPHY
B-1.1
GREG BAKER

FINAL COURSE BOOKLET

TSM2006: DETAIL AND CONSTRUCTION DOCUMENTS

TERM: FALL 2021

INSTRUCTOR: MARY POLITES SUBMISSION BY: GREG BAKER DATE: DECEMBER 6, 2021

FINAL
BOOKLET GREG
TSM2006
A-0.0
COURSE
BAKER
COVER SHEET 12/06/2021