1.013

Page 1

Motorway Bjergby Hirtshals DENMARK – 2002

Roads (01-013-A)


01-013-A – pag 2/2

Problem Complete rebuilding of a stretch of motorway on bad subsoil.

Composition

Cubic Area: 3,800 m3. Load: ADT = 60,000 vehicles/day. ADTT = 6,000 vehicles/day (ca. 10%).

Road bed 21 cm asphalt layer; 20 cm base course; 20 cm anti-frost layer. Base Geotextile, 400 g/m2, laid crossways to the road, overlaps min. 50 cm; Leca® 8-20 mm, thickness: ~1.80m wrapped in geotextile, min. 1.0 m overlaps. Subsoil Soft subsoil to a depth of 10 m.

Road surface in good condition, view towards Hirtshals, Hjørring section still under pre-load .

Construction No data available.

Building method Soil replacement for load compensation, with pre-load.

Quality control No data.

Performance Measurements No data. Flaws/damage Type: none. Time: -Visual appraisal as of 06.06.2004 Deformations: - none detectable. Transitional/contact areas: - no problems. Road surface: - impeccable condition.

Maintenance work Normal.

Appraisal/Experiences Use of Leca® has been successful to date, too early for long-term observations.

www.maxit-group.com maxitGroup AB, Box 415, SE-191 24 Sollentuna, Sweden Tel.: +46 (0)8 858 70 64 00, E-mail: info@maxit-group.com

construction is


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.