Architecture Design and Renovation Process

Page 1

BERIKA S PA C E S .

R E N O V AT I O N P L A N C L I E N T: 130 Rangituhi Cres. Poriua Budget: 1.6 Million


GANTT Chart of Renovation

Feb 20

March 20

April 20

May 20

June 20

July 20

Aug 20

Sep 20

Oct 20

Nov 20

Dec 20

Jan 21

Feb 21

March 21

April 21

Design (Pre Construction)

Phase 1 – Predesign Phase 2- Concept Design Phase 3 Developed Design Phase 4 Detail design Phase 5- Procurement

1

Phase 1 - Construction Phase 2 - Construction Phase 3- Construction Phase 4- Construction Phase 5- Construction Phase 6- Construction Phase 7- Construction Phase 8- Construction Phase 9- Construction Phase 10- Construction Phase 11- Construction Phase 12- Construction Phase 13- Construction Phase 14- Construction Phase 15- Construction Phase 16- Construction Closing Phase Marketing

Percentage % of fee per Phase

2 3 4 5

Construction 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Marketing

Closing

May 20


TIMELINE FOR RENOVATION PAGE 1 - 2 : DESIGN PHASES

PHASE:

TA S K S : For a smooth running project we break it down in stages. Each phase have different taks and a level of expectation. In general the phases are sequential and you will sign off on the completion of each task, permitting the project to move forward based on the decisions made up to that point.

PHASE 1 PRE DESIGN

TIME: The time frame to complete each phase varies depending on the complexity of your project.

GOAL: To research and determine the criteria for the project.

2 weeks

FEE: Our percentage fee varies on the complexity and value of the construction work. We invoice based upon Quantity Surveyor estimates of the amount until such time as a Contract Sum is fixed.

1% of Total Costs $16,000 $16,000 Total

Redesign property in order to run a business on the ground floor (resturant), family home of 4 upstairs. This insists of establishing and documenting the requirements for your project: • • • • • • •

PHASE 2 CONCEPT DESIGN

Brief - desired outcomes and objectives Preliminary Space planning (main entrace, desired rooms, spaces for restaurant/ house) Planning and costing - Budget Analysis - 1.6million Feasibility study Zoning & Town information Drainage plans Site analysis

GOAL: To explore a range of solutions to fit your given brief, we will present concept and narrow them down. Commencing design: We start off with sketches then progress into floor plans and 3D model walkthroughs. During the concept design stage, you will receive a number of different alternative ideas for your project. Several meetings will take place during this phase to make decisions and determine a direction for the design. At the end of this phase these documentations will be produced: •

Site Plan

Floor Plans

Elevations

Sections

Area Analysis

Renders + 3D Modelling

Preliminary Cost

2 weeks 5 weeks total

1% of Total Costs $16,000 $32,000 Total


TIMELINE FOR RENOVATION TA S K S :

TIME:

FEE:

PHASE 3 DEVELOPED DESIGN

Refine and develop design with preliminary structural systems defined. When the concept is agreed upon, we will refine in detail and shape the final design. We will make recommendations for the design of detail and the use of materials that reinforce the vision previously developed in the concept design stage.

PHASE 4 DETAIL DESIGN + DOCUMENTATION

Outline Specification: Preliminary written description of the project’s major systems and materials.

Key Interior Elevations: Drawings depicting the relationship and material choices of the project’s interior rooms.

Interior Schedules: A preliminary list of the type and location of interior finishes.

Key Details: Preliminary Large scale drawings of specific elements within the project.

Systems Consultant Drawings: May include structural, civil, and mechanical drawings.

Revised Cost Estimate: A revised estimate by a contractor of the cost of construction based on the current building design.

GOAL: Get pricing and engage with contractor for the projct This will include: •

Detailed Design Drawings- based on approved developed design.

Specifications- Prepare Preliminaries and General Sections

Materials and Finishes Schedule- Update against specification and mon-

1 Week 6 weeks total

2 weeks 8 weeks total

1% of Total Costs $16,000 $48,000 Total

4% of Total Costs $64,000 $112,000 Total

etary allowances. •

New Zealand Building Code and relevant NZ standards

Building Consent – Prepare and lodge application.

Consultants: Obtain detailed design input from other consultants – Review and evaluate against architectural design.

PHASE 5

Cost Advice – Obtain Pre-tender Estimate of Cost from Quantity Surveyor.

PHASE 4 & 5 DESIGN MAY OVERLAP

PROCUREMENT

GOAL: To get pricing and engage with a contractor for the project The tendering processes is inclusive of the following; • Preparation of contract documentation • Preparation of tender documents • Assessing suitable contractors • Answering queries from the various contractors and sub-contractors • Make document revisions and issue any notices to tenders • • •

Receiving tenders Analysing the received tenders including checking tender compliance Recommending a main contractor and letting the tender Prepare/ present tender report

1 week 9 weeks total

1.5% of Total Costs $24,000 $136,000 Total


TIMELINE FOR RENOVATION PHASES

FEE FEE

TIME

PHASE 1 PRE CONSTRUCTION

• Meeting: discuss workforce, Contractor Established

1 Week

• Site organization • Delivery plans defined - schedule to make sure everything is going to be on time

10 weeks Total

0.8 % of Total Costs $12,800 $148,800 Total

• For this project we will be having a Temporary construction office on the site (Digram 1) • In the beginning of the construction the family will need to relocate to Floor 1. As seen in Digram 2, the parents will be in bedroom one and the kids in bedroom two. • Perimeter & fencing established around the site • Access - As seen in Digram 3 there will be a temporary clip on stair on the Southern side of the balcony for access to top floor for builders. • Underground plumbing, where pipes are place, prepare the earth, remove any vegetation that is needed • The main Foundation for this project will remain the same

DIGRAM 1 - Site Plan

130 Rangituhi Cres. Porirua

Construction Office (container)

DIGRAM 2

Level 1

Level 1

DIGRAM 3 Level 2

Level 2

Preperation for construction zone

Bedroom 1 for Parents

Bedroom 2 for two kids

Stair Acess


TIMELINE FOR RENOVATION CONSTRUCTION

TA S K :

TIME:

FEE:

PHASE 2 CONSTRUCTION

3 Weeks

4 % of Total Costs $64,000

13 weeks Total

$212,800 Total

• Clients moved all furniture and living needs to level 1, extra furniture stored in garage • Interior wall demolition Level 2 (Digram 4) • First interior framing in place Level 2 • Filling in the void: On Level 2 there is a void that needs to be filled in (Digram 5), during the hours of 8am – 4pm the family will need to remain outside of the dining/ kitchen area where the void is over. There will be a temporary kitchen unit set up in the garage for cooking if needed.

DIGRAM 4

DIGRAM 5

Level 2

Level 1

Construction Zone ( Void)

Construction Zone

Stair Acess

PHASE 3

PHASE 2 & 3 CONSTRUCTION WILL OVERLAP

CONSTRUCTION

3 Week

• Interior framing for Level 2 (Digram 6)

16 weeks Total

• Remove / Relocation of staircase

6. 2% Total Costs $99,200 $312,000 Total

• Doors and windows, frames need to be in place • The entire roof structure in place, tiling to be completed in later stages

Level 2

DIGRAM 6

Ensuite Bedroom 2

Master Bedroom

Kitchen

Dining

Wardrobe

Study/ Bedroom 3

Bedroom 1

Bathroom

Laundry/ Storage

Lounge


TIMELINE FOR RENOVATION TA S K : PHASE 4 CONSTRUCTION

• Electrical wiring • Internal plumbing • HVAC Ducts are placed in attic

TIME:

FEE:

2 Weeks

2% Total Costs $ 32,000

Weeks 18 Total

$344,000 Total

2 Weeks

1.5% Total Costs $24,000

• Heating installed throughout level 2

PHASE 5 CONSTRUCTION

• Finishing off internal walls • Inspect quaility of framing • Electrical , plumbing & heating inspections and finishing off

20 weeks Total

$368,000 Total

1 Week

0.5% Total Costs $8,000

• Prepare for dry wall

PHASE 6

PHASE 5 & 6 CONSTRUCTION MAY OVERLAP

CONSTRUCTION

• Dry walls complete, apply textured if needed in design • Heavy Cleaning, remove big bulky leftovers for preparation of furniture to be moved in

21 weeks Total

$376,000 Total

PHASE 7 CONSTRUCTION

• Fixed furniture

4 Weeks

• Bathroom fixtures - toilet, bath, shower, sink • Cabinets

25 weeks Total

8% Total Costs $128,000 $504,000 Total

• Floor tiles

PHASE 8 CONSTRUCTION

• Counter tops • Bathroom Walls • Electrical plugs, lighting

5 Weeks

7% Total Costs $112,000

Weeks 24 Total

$ 616,000 Total

2 Weeks

5 % Total Costs $80,000

• Plumbing and HAVC trim outs • Preperation for family to move back upstairs

PHASE 9 CONSTRUCTION

PHASE 8 & 9 CONSTRUCTION MAY OVERLAP

• All other appliances installed • Carpet • Electrical connection to grid • Final Cleaning • Final building inspection with the client • Clients move in upstairs

Weeks 28 Total

$ 696,000 Total


TIMELINE FOR RENOVATION

PHASE 10 CONSTRUCTION

FEE FEE:

MEE: TTIIM

TA S K :

• Client moved upstairs • Delivery plans for restaurant, defined schedule to make sure everything is going to be on time • Clean up, preparation for construction

2 Weeks

2% Total Costs $32,000

30 Weeks Total

$728,000 Total

• Site Acess (Digram 7) • Demolishing walls Level 1 • First interior walls go in place DIGRAM 7

Level 1

Level 1

New Construction Zone

Acess through garage door in beginning, new doors will soon be in place

PHASE 11 CONSTRUCTION

• Interior framing / timber interior walls for Level 2 (Digram 8) • Doors and windows, frames need to be in places • Electrical wiring

4 Weeks 34 Weeks Total

5.5% Total Costs $88,000 $816,000 Total

• Internal plumbing • HVAC Ducts installed • Heating installed throughout level 1 DIGRAM 8 Level 1

Level 1

Outside Courtyard Office/ Back entrance

Bathrooms Bar Table / Eating area Counter

Commerical Kitchen Bar/ takeaway food pick up

Entrance


TIMELINE FOR RENOVATION TA S K :

TIME:

FEE:

PHASE 12 CONSTRUCTION

• Finishing off walls

3 Weeks

• Framing inspection

39 Weeks Total

• Electrical and plumbing inspections

3% Total Costs $48,000 $864,000 Total

• Prepare for dry wall

PHASE 13 CONSTRUCTION

• Dry walls complete, apply textured if needed in design • Heavy Cleaning, remove big bulky leftovers • Commercial kitchen large items installed (freezer + fridge)

6 Weeks 45 Weeks Total

14% Total Costs $224,000 $1,088,000 Total

• Landscaping planting • Driveway concreted for restaurant carpark 20 parking lots Residential parking for family round the back (Digram 9) • Paint the exterior DIGRAM 9 - Landscape plan Car parking for restaurant

Private Residential parking

PHASE 14

PHASE 13 & 14 CONSTRUCTION MAY OVERLAP

CONSTRUCTION

3 Weeks • Fixed furniture: Window seats, large wooden bench seating. • Cabinets • Flooring: tiling for restaurant/ bathrooms + commercial kitchen flooring • Residential Carport installed

48 Weeks Total

14% Total Costs $224,000 $1.312 Million Total


TIMELINE FOR RENOVATION TA S K :

TIME:

FEE:

PHASE 15 CONSTRUCTION

• Counter tops • Bathroom Walls • Electrical plugs, internal / external lighting

5 Weeks

8.5% Total Costs $136,000

53 Weeks Total

$1.448 Million Total

5 Weeks

8% Total Costs $128,000

• Plumbing and HAVC trim outs • Minor cosmetic corrections and external areas

PHASE 16 CONSTRUCTION

• All other appliances installed – commercial kitchen items • Furniture – tables, chairs, menu board

58 Weeks Total

$1.576 Million Total

• Electrical connection to grid • Final Cleaning • Final building inspection with the client, resolve any issues

MAKRETING PHASE WILL OVERLAP WITH ALL OTHER PHASES MARKETING PHASE

This project is a commercial build and we help with the marketing side of things. We do this constantly throughout the build, from design phase to end of construction.

Throughout project

0.4% Total Costs $6,400 $1,582,400 Million

During the construction of downstairs to get the business up and running the family will have a food cart and be selling their food at markets around Wellington. There will be a grand opening for the Restaurant, when everything is complete and tidy around the site. Things we can do to promote your new Restaurant: • Website development • Content creation for social media - Instagram, Facebook posts with images of food, menu board, interior finishes, logo and upcoming deals.

CLOSING PHASE • Deliver the final building with client • Builder user orientation, how to use devices/ spaces • Check everything is under the warranty in the house • We will do a quarterly checkup to make sure everything is going well with your final restaurant and residential home.

2 Weeks 60 Weeks Total 1 year 2 months

1.1% Total Costs $17,600 $1.6 Million Total


References: The design Process – https://www.nzia.co.nz/connect/working-with-an-architect/the-designprocess https://www.pearsonhighered.com/assets/samplechapter/0/1/3/4/0134454170.pdf https://pattersons.com/wp-content/uploads/2018/05/NZIA-AAS-2018.pdf https://hmhai.com/design-phases/ http://www.buildingguide.co.nz/resources-regulations/budgetcalculator/?fbclid=IwAR3M7a4FsZVdAon3whWmeJUVf6eyeq2epI61AjY0jLbvWN1EpGo d4OY5xhM https://www.homeloanexperts.com.au/home-loan-articles/stages-ofconstruction/?fbclid=IwAR1P8WNbU3dA2dQwhiMqsXHUoapQu0zR3a3lqQkVIUjWDX4qZTHCn_9KZQ