PROPOSAL FOR ESTABLISHING MODERN ABATTOIR IN KALADY GRAMA PANCHAYAT, ERNAKULAM DISTRICT, KERALA
Submitted to
RURAL INFRASTRUCTURE DEVELOPMENT FUND NATIONAL BANK FOR AGRICULTURE AND RURAL DEVELOPMENT By
KALADY GRAMA PANCHAYAT Through
ENVIRONMENT MANAGEMENT AGENCY KERALA DEPARTMENT OF ENVIRONMENT, GOVERNMENT OF KERALA
Prepared By
CENTRE FOR ENVIRONMENT AND DEVELOPMENT THIRUVANANTHAPURAM JULY 2010
RIDF PROPOSAL FOR ESTABLISHING MORDERN ABATTOIR IN KALADY GRAMA PANCHAYAT, ERNAKULAM DISTRICT, KERALA
Submitted to
NATIONAL BANK FOR AGRICULTURE AND RURAL DEVELOPMENT
Through
ENVIRONMENT MANAGEMENT AGENCY KERALA DEPARTMENT OF ENVIRONMENT, GOVERNMENT OF KERALA
Prepared By
CENTRE FOR ENVIRONMENT AND DEVELOPMENT THIRUVANANTHAPURAM JULY 2010
CONTENTS
INTRODUCTION
1
BACKGROUND
1
PROJECT OBJECTIVES
2
PROJECT LOCATION - KALADY PANCHAYAT
2
PROJECT JUSTIFICATION
3
FACILITIES REQUIRED IN A MODERN ABATTOIR
4
Reception area and resting grounds
4
Lairage
4
Slaughter Hall
5
Office & Rest room
5
Compound Wall and Gate
6
Green Belt
6
Water Requirement
6
Accessibility for Cleaning and Maintenance
7
Non acceptable material
7
Waste Management
8
DETAILED ESTIMATE
9
ESTIMATE REPORT
9
GENERAL ABSTRACT OF ESTIMATE
9
COMPONENT WISE ABSTRACTS OF ESTIMATE
10
Slaughter house, Lairage etc.
10
Soak Pit
15
Overhead Tank
16
Anaerobic Tank
18
Compound Wall and Gate
19
Road and Parking lot
20
DETAILED ESTIMATE FOR MODERN ABATTOIR FOR KALADY PANCHAYAT
21
Slaughter house, Lairage, Administrative Building and Watchman Shed
21
Soak Pit
37
Overhead Tank and Pump House
37
Anaerobic Tank
40
Compound Wall and Gate
41
Road and Parking lot
42
RATE ANALYSIS AS PER 2010 SoR OF KERALA PWD
ECONOMIC ANALYSIS
43
74
OPERATION AND MAINTENANCE
74
ECONOMIC ANALYSIS
75
Expenditure
75
Income
76
CONCLUSION
77
WORK SCHEDULE
78
ANNEXURE I: CHECK LIST OF DPR
79
ANNEXURE II: DETAILED DRAWINGS
1.0 INTRODUCTION 1.1 BACKGROUND India is endowed with the largest resource of livestock population in the world. The Indian Meat Industry is currently on the track of a remarkable leap forward. The global demand for Indian meat and meat products is increasing considerably during the past few years. We also have one of the largest domestic markets for our meat and meat products. More than 65% of the Indian population consumes meat and meat products. About 40 million people are engaged in meat sector, namely, trade of live animals, hides, bones, casings, horns and hooves etc.. However, the global competency of our products has not improved considerably in terms of quality and quantity. One of the major lacunae in this regard is lack of modern infrastructure for production of hygienic meat and for value addition. More scientific organization of this sector will generate more employment in rearing of animals on scientific lines and processing of slaughter-house by-products for allied industries. Kerala is the most ideal State in India for development of the meat sector. Kerala State is endowed with a highly literate population having basic knowledge on the nutritive requirements for growth and development. Around 95% of the Keralites consume meat and meat products. The state has practically slaughter slabs, and slaughter houses in all Panchayats, Municipalities and Corporations. However, it is most disgusting that large majority of such slaughter houses does not have the basic infrastructure essential for clean meat production . All most all the so called slaughter houses in the state are service-oriented and, as such, perform only the killing and dressing of animals. In most cases, the animals are slaughtered in open space by crude method in unhygienic environment and are selling the meat to the public. The overall responsibility of management of the slaughterhouse in the state is vested with the respective local bodies. Accordingly the slaughtering of animals should be done inside the slaughter house with required facilities, otherwise it is an offence. There are 44 licensed slaughter houses working in the LSGIs which are in most cases not meeting the basic facilities required for a modern slaughter house. As such, it is an established fact that the meat produced in such slaughter houses is highly contaminated, poor in quality and the operations create environmental pollution too. One reason for the spread of certain diseases among the public may be due to slaughtering the animals in unhygienic environment and distributing the meat. One major concern on the small and medium sized slaughter houses, not hitherto regarded seriously, is the magnitude of environmental pollution they are creating from the waste generated during slaughtering operations. The slaughter house wastes are enormously polluting our drinking water sources, the rivers and wetlands. A recent study
conducted
by
Centre
for
Environment
and
Development on behalf of the Environmental Management Agency, Kerala (EMAK) in the Periyar River Basin (PRB),
Slaughterhouse in River Bank: Cheruthoni
has revealed that one major source of pollution in Periyar River is slaughterhouse waste (CED, 2010). In many places, the slaughter houses are functioning very close to the river. The number of cattles slaughtered per day in the PRB area is around 500. Almost the same number of sheep/lamps/pigs is also slaughtered every day. The study suggested establishing modern abattoirs in the selected local bodies of PRB. The present project is prepared for NABARD assistance under RIDF scheme is aimed at establishing a modern abattoir in Kalady Panchayat, located in the midland basin of the PRB. The facility can also be used by at least
two more Panchayats (Malayattur-Neeliswaram & Kanjoor), lying on either sides of the Kalady Panchayat in the same Block (Angamaly).
1.2 PROJECT OBJECTIVES The objectives of the project are: i.
To establish a modern abattoir in Kalady Panchayat in Kerala and to ensure that the meat supplied to the publics are clean and hygienic
ii. To ensure that the slaughter house wastes generated in the Panchayat are processed scientifically iii. To ensure that the water bodies in the local bodies are not contaminated with slaughter house wastes
1.3 PROJECT LOCATION - KALADY PANCHAYAT Kalady Grama Panchayat is situated on the banks of the Periyar River, in Angamaly Block of Ernakulam District. The boundaries of the Panchayat are: Malayattoor-Neeliswram Panchayat on the east; Koovapady, Okkal and Kanjoor Panchayat towards south, Angamaly Municipality on the west
and
Thuravoor
Panchayat
towards north. The Panchayat was formed in 1956. The total area of the Panchayat is 16.68 sq.km. and the population as per 2001 census is 27021. Kalady is a famous pilgrim center cum tourist
destination.
It
gained
importance after Adi Sankaracharya, the great Indian philosopher of the 8th century
AD,
who
preached
the
monistic or 'advaita' philosophy, was born
there.
Kalady in
Malayalam
means ‘feet imprint’, took its name after Adi Sankara’s feet imprints on the spot where the river changed course so that it flowed nearer to Adi Sankara’s home. Kalady is also famous for the presence of large number of modern rice mills, the largest nutmeg market in India and its large vegetable market. The major land uses in the Panchayat are homestead planting, built-up areas and paddy cultivated area. The Periyar main river flows through the southern boundary of the Panchayat for a distance of about 5 km. The tributaries of Periyar flowing through the Panchayat are: Udumpuzha thodu, Kottamom thodu, Kaitha thodu, Arratu thodu, Ooman thodu, Mukkadai thodu, Palathodu, Kuzhiyampadom and Piraroor thura thodu. The two major water bodies in the Panchayat are: Manikkamangalam thura and Piraroor thura. The major sectors of employment are Agriculture, Cattle Rearing and Small Scale industries.
The Sree
Sankaracharya Sanskrit University and Sree Sankara Arts and Science College are the two major prestigious institutions in the Panchayat.
The main town in the Panchayat is Kalady with a vegetable/fish/meat market, many hospitals, schools, restaurants, hotels and public institutions. Major issues faced by the Panchayat in the environmental and health sector are the absence of a full proof solid and liquid waste management facility and facilities for proper supply of hygienic meat.
1.4 PROJECT JUSTIFICATION Hygiene of slaughter house is very important to prevent contamination of meat. Meat is easily perishable and contamination of meat can lead to serious health issues. The contamination of food will lead to various diseases, many even causing death. In a hamburger case, the Escherichia coli inside the meat survived due to short period heating which caused illness and death in children. All conditions and measures necessary to ensure the safety and suitability of meat at all stages of the food chain are needed. Ensuring hygiene is the shared responsibility of the farmers, manufactures and consumers. Slaughtering of animals also generates wastes consisting of non edible offal like lungs, large intestines, various glands, animal tissues, organs, various body parts, etc.; stomach/intestinal contents; dung; bones etc. Large quantity of waste water is also generated during washing. The average quantity of unusable wet solid waste produced by slaughtering (excluding dung) is estimated as12 kg per cattle/buffalo, 4 kg per pig, 2.5 kg per goat, and 0.6 kg per poultry. The present practices in most of the slaughter sheds and chicken stalls are to dispose the wastes to the rivers, streams or water bodies. The study initiated by EMAK in PRB clearly showed the Waste from Slaughterhouse
magnitude of pollution caused by slaughter house wastes in Periyar River, the longest and largest among the 44 rivers of Kerala, popularly known as the lifeline of Kerala. Almost all the bridges and culverts in the Periyar River Basin are the potential sites for throwing slaughter house and poultry waste. Construction and maintenance of modern slaughter house with Waste Management Facility is inevitable for maintaining societal hygiene in all urban and rural local bodies.
There are guidelines/ stipulations in the
legislations such as the Prevention of Cruelty to Animal Rules 2001, the Municipality Act 1994, the Kerala Panchayat Raj Act 1994 and Water (Prevention and Control of Pollution) Act 1974 etc., insisting minimum facilities to be provided in a modern slaughter house. Considering the special nature of the State, it may not be necessary to provide fully automated with highly sophisticated machineries for slaughter houses that is to be established for Grama Panchayats and Small Municipalities. In Kerala, slaughtering is being done by meat vendors, which are intended for sale, themselves through meat stalls. If the local body (LSGI) provides a common abattoir that can be made use by those meat vendors, which will ensure hygienic meat production and proper waste management at lowest cost. In Kalady Panchayat, at an average, 25 cattles and 15 goats are slaughtered every day.. About the same number of cattles and goats are slaughtered in the nearby two Panchayats (Malayattur-Neeliswaram & Kanjoor) together. The meat consumption in the restaurants and houses are steadily increasing. At present, the slaughtering is done in the market and other open areas in the Panchayat. The wastes are deposited mainly in the water bodies and open areas which ultimately reaches the Periyar River and contaminates the water which is used by the public for drinking and other purposes. There are no facilities for anti and post mortem inspection to ensure that the meat supplied to the public is clean and hygienic.
The public in this area is looking for meat processed in neat and clean environment without any dirt and safe for consumption. It is also the duty of the local bodies to protect and promote human health by providing hygienic meat to the consumers and ensure proper living environment for the public. Thus a modern abattoir with facilities for hygienic meat production and waste disposal is an urgently needed in the Panchayat.
1.5 FACILITIES REQUIRED IN A MODERN ABATTOIR The Prevention of Cruelty to Animals (Slaughter House) Rules, 2001 notified by the Government of India insists the following basic facilities in a modern abattoir:
1.5.1
1.
Reception area for animals
2.
Lairage (Resting place for animals)
3.
Room for Veterinary Doctor for performing anti-mortem and post– mortem examination.
4.
Place for isolated resting place for diseased animals.
5.
Stunning place / Halal slaughtering place
6.
Bleeding place (for removal of blood)
7.
Removal of skin and washing place
8.
Evisceration place (removal of contents from stomach)
9.
Meat removal and examination place.
10.
Storage facilities for skin, bones, blood, fat etc.
11.
Proper drainage and facilities for liquid and solid waste management.
Reception area or resting grounds The slaughter house shall have a reception area of adequate size sufficient for livestock subject to veterinary inspection. The reception area of slaughter house shall have proper ramps for direct unloading of animals from vehicles or railway wagons and the said reception area shall have adequate facility sufficient for feeding and watering of animals. Separate isolation pens shall be provided in slaughter house with watering and feeding arrangements for animals suspected to be suffering from contagious and infectious diseases, and fractious animals, in order to segregate them from the remaining animals. The resting grounds in slaughter house shall have overhead protective shelters.
1.5.2
Lairage
Lairage is for keeping the animals indented for slaughter, well in advance for observation and convenience. For providing water and feed to the animals, arrangement shall be there in the lairage. The lairage should have anti mortem facility to check each animal for physical disease or pregnancy. 1.5.3
Slaughter Hall
Separate provision shall be made for slaughtering large and small animals. Separate space shall be provided for stunning, bleeding and dressing of carcass. Animals shall not be slaughtered in sight of other animals. Dirty area consists of bleeding & dressing section and clean area for meat cutting inspection and dispatch. Pedal operated water taps and wash basin shall be provided in the slaughter hall. At the bleeding area, the bl ood is to be collected in stainless steel basin for further processing/ disposal. The collected blood is to be stored in tank for heating and drying. Stainless steel wheel barrow is to be provided in the slaughter hall to collect and remove
waste items like large bones, tail, intestine etc into the stripery outside and dispose the same on completing the slaughter of the day. Stunning Area: As per PCA Rules a stunning area is to be provided for large animals. Floor level of stunning box need be in an elevated plane than that of the bleeding area. One side of the stunning box shall be with hinged plate. Immediately after stunning, the animal falls on the side wall of the stunning box, and the hinged plate will open and the animal slips on to the bleeding area. The bleeding area need be positioned in such a way that, an animal in the stunning box will not see the bleeding animal. In the case of halal slaughtering, separate cubicles made up of RCC wall and with ceramic tile in walls shall be utilised. Sufficient drains and floor slope shall be provided for easy drainage of blood from the cubicles. Bleeding is done by hoisting the animal to a height of 5 m rail system and blood collection vessel with funnel shall be used for collection of blood. Continuous rail arrangement in the slaughter hall: A continuous rail arrangement should be provided on the top of the large animal slaughter hall. The rail arrangement covers the bleeding area and hanging area for the smooth and convenient movement of the carcass for processing. Dressing: Dressing is carried out in rails fitted at a height of 3 m. Adequate means and tools for dehiding or belting of the animals should be provided. Hides or skins should be transported either in a closed wheel barrow or by a chute provided with a self - closing door. Means for immediate disposal of legs, horns, hooves etc. should be provided through spring load floor chutes or side wall doors or closed wheel barrows. Evisceration: Adequate space and suitable and properly located facilities shall be provided for inspection of the viscera of the various types of animals slaughtered. This area shall have adequate facilities for hand washing, tool sterilization and floor washing and contrivances for immediate separation and disposal of condemned material. Adequate arrangements may be made for identification, inspection and correlation of carcass, viscera and head. Waste Grinder: The waste generated is to be grinded / shredded before putting in to the biogas plant. For this a motorized waste grinder is needed. This is given as an optional item in the project proposal. It is an optional item.
1.5.4
Office & Rest room
An office for the veterinary doctor and health inspector and rest room for the workers are included in the project. Toilets are to be provided in the project. It is for the use of workers and for office in the slaughter house. It is provided with flush, wash basin, floor with tiles, light fittings etc. A green belt of sufficient width with suitable species of trees shall be developed around the compound. Electrification: Electrification of the slaughter house shall be done in order to get sufficient light in the slaughter hall and inspection area. Sufficient number of electric lamp inside and out side the house is considered. Plumbing work: The slaughter house is to be provided with sufficient number of water taps, wash basin, pedal operated water taps etc. Also flexible hose arrangement is there for easy cleaning of the slaughter hall.
1.5.5
Compound Wall and Gate
The area shall be protected with a compound wall and gate to avoid unwanted persons to enter into the compound.
1.5.6
Green Belt
In order to provide an aesthetic appearance to the abattoir, the boundaries and open areas shall be planted with trees like Chempakam (Michelia chempaka), Neem (Azaridca indica), Pongilliam (Pongamia glabra), Poomaruth (Lagerstromia flos-reginae) etc. 1.5.7
Water Requirement
The process flow chart of activities for a modern abattoir as given in figure 1 shows that, water is required in the slaughter house at all stages of operation. RECEPTION
Water . . . . . . . . . . . . . . . . . . . . . . . . . . . .
washwater
LAIRAGE
ANTIMORTOM
STUNNING / HALAL SLAUGHTER
blood
blood
BLEEDING
HORN & HOOVES REMOVAL
BLEEDING washwater
EVISCERATION
REMOVAL HORN &HEAD HOOVES REMOVAL DEHIDING
EVISCERATION CARCASS WASHING
washwater
RED OFFAL REMOVAL
HEAD REMOVAL CARCASS SPLITTING
CARCASS WASHING DEHIDING
washwater
POST MORTEM
CARCASS WASHING DESPATCH/ FREEZER
Fig. 1 Process flow chart for Modern Slaughter House The major water uses are: Safe, potable and constant supply of fresh water at adequate pressure Floor washing with water jet of 200 to 330 kPa pressure Carcasses washing 1000 to 1700 kPa pressure A constant supply of clean hot water shall be available in the slaughter hall and work rooms during the working hours

0
Hot water not less than 82 C for sterilizing of equipment and secondary floor washing Suitable facilities for washing of hands (including adequate supplies of hot and cold running water, nail brushes, soap or other detergents) Non-potable water for fire fighting purpose
The main emphasis of the process is to segregate waste at different stages and to recover resources from it and use minimum quantity of water. For this, the slaughter house requires sufficient good quality water round the year. This is for consumption of animals, its washing before slaughtering, washing the meat, human consumption, washing the floor and other areas etc. If water supply is available connection can be taken and over head PVC water tanks can be provided for this purpose. Otherwise a bore well can be constructed, and shall be provided with pump. A solar water heater shall be installed for the purpose of hot water. Hot water shall be used for washing slaughter hall and for sterilising tools. 1.5.8
Accessibility for Cleaning and Maintenance All parts of the product zone shall be readily accessible to sight and reach for cleaning and inspection Where necessary for proper cleaning and inspection, equipment shall be easily demountable. To facilitate this dismantling, quick opening devices that require no tools or, such simple tools as a mallet and an open – end wrench shall be provided. Bayonet joints, butterfly clamps, spring bolts, and other similar devices are desirable for connecting or closing parts of equipment. Where parts should be retained by nuts and bolts, the design shall provide for fixed studs with wing nuts, rather than bolts to a tapped hole All bearing shall be located outside the product zone and if adjacent thereto, shall be constructed with a readily removable seal at the entrance of the shafts, into the product zone Interior corners of equipment shall be provided with radii (minimum 6mm), except where greater radii are required to facilitate drainage and cleaning. All welding within the product zone shall be continuous, smooth, even and relatively flush with the adjacent surfaces All parts of the product zone shall be free of recesses, open seams and gaps, crevices, protruding ledges, inside threads, inside shoulders, inside bolts or rivets and deal ends. Where necessary for sanitary maintenance, equipment shall be constructed and installed so as to be completely self-draining Care shall be taken to prevent contaminating product by lubricants used in overhead motors, gears, and similar devices. If drip pans are necessary, they should be easily accessible for inspection and removable for cleaning. All safety or gear guards shall be readily removable for cleaning and inspection All external surfaces that do not contact with food products shall be free of pen seams, gaps, crevices and inaccessible recesses.
1.5.9
Non acceptable material Copper and its alloys in equipment used for edible products Cadmium in any form in equipment handling edible products Equipment with painted surface in product zone Enamel containers or equipment is not desirable Lead
For elimination of fatigue and comfortable working for labourers the working table should be at waist height of the worker to work in standing position. If the table is at more height (that is 800 mm to 860 mm) it should have a platform incorporated for the balance height above 860mm. Working platform for on-the rail operations should be of such height that the slaughter man has neither to stoop too low or stretch himself to his operation zone, and he should be able to reach operation zone in his natural standing position. 1.5.10
Waste Management
Effective waste management can reduce environmental problems associated with slaughter house. The strategy followed is to reduce waste by segregating resources from different types of wastes generated in the slaughter houses. Solid waste is the main waste product from a slaughter house. Solid waste from slaughter house can be divided into two main groups, namely edible & inedible. Organs such as brain, liver, heart are the examples of edible by-products. Hooves, horns, hair, gall bladder, ears, skin, bones etc. are the inedible byproducts. The components left unrecovered forms are the solid wastes. In a modern slaughter house most of the solid wastes can be recovered as by-products. Success of material recovery depends on how slaughtering is done and how the facilities are provided in the slaughter house. Biogas Plant for Solid Waste Treatment: Dung from lairage and other wastes in slurry form can be treated in biogas plant. Slaughter house having a capacity to slaughter 30-40 large and 40 small animals generates about 750 kg of solid waste per day. This can be treated in a biogas plant with 40m
3
capacity. For getting more
efficiency, and considering the increase in number of animals, in the future two biogas plants with 25 m
3
is
envisaged in the present project. Facility for utilizing biogas for generating electricity for operating equipments in the plant /lighting the plant area is also envisaged in the project. Liquid Waste Treatment: Wastewater mainly wash water from slaughter house is to be collected and to be conveyed to a common collection cum equilisation tank. About 8m
3
per day of effluent is generated from a
slaughter house with capacity to slaughter 30 - 40 large animals. The strategy adopted is to reduce pollution load by by-product recovery and use of less quantity of water for washing purpose. Wastewater mainly consists of wash water can be treated in an effluent treatment plant established in the site of slaughter house. The process for effluent treatment suggested is anaerobic treatment followed by dispersion trench.
2.0 DETAILED ESTIMATE
2.1 ESTIMATE REPORT Sub : Construction of a modern Abattoir at Kalady for Kalady Panchayath Ref:
EMAK / 7 / 2008 dt. 29/05/2010 of the Director, EMAK, Trivandrum.
The proposal is to construct a Modern Abattoir at Kalady for Kalady Panchayat. An extent of 0.40 ha of land comprising in Sy. No 295/2 and 394 of Kalady Village under their possession is set apart for the above purpose. The components envisaged in this estimate are: i.
Slaughter House Building.
ii.
Administrative Building, Refrigeration room, Lairage, Watchman shed and toilet block.
iii.
Overhead water tank with bore well and pump set.
iv.
Boundary wall and gate.
v.
Bio gas plant and bio conversion generator kit.
vi.
Anaerobic tank.
vii.
Soak pit
viii.
Internal road and parking lot.
ix.
Water Supply and drainage system.
x.
Electrification works
xi.
Hot water generation and supply
xii.
Stainless steel ladder, bench, wheel barrow, pressure washer, chopper, mixer grinder and hooks.
All the RCC works are proposed as 1:1.5:3 mix. The floor of the slaughter area is proposed to be finished with white superior quality marble and the remaining area of floor of the slaughter house is proposed to be finished with fully vitrified tiles. Doors are proposed to be made with Anjili wood and windows are with glazed stee l works. Roof of the slaughter area is proposed with powder coated GI tile profile roofing sheet. Facilities for refrigeration room are also provided. Provisions for washing and changing room are also included in the slaughter house. The estimate is prepared based on 2010 SoR of PWD. The conveyance of materials is taken as actual as provided by Panchayat. The estimate amount comes to Rs.94,00,000/- including 10% contractor’s profit. 2.2 GENERAL ABSTRACT OF ESTIMATE No.
Details of work
Amount (Rs.)
1
Slaughter house, Lairage etc
2
Soak pit
60,63,915.00
3
Over head Tank
6,42,541.00
4
Anaerobic Tank
2,23,714.00
5
Compound wall and gate
9,40,142.00
6
Road and parking lot
4,91,935.00
7
Electrification works
3,00,000.00
8 9
Preparation of Design and detailed estimate 2% Technical supervision 4%
1,71,630.00 3,43,260.00
10
Unforseen Expenses
2,07,625.00
15,238.00
Total
Grand Total
86,77,485.00
94,00,000.00 Ninety Four Lakhs Only
2.3 COMPONENT WISE ABSTRACTS OF ESTIMATE 2.3.1 Slaughter house, Lairage etc. Sl No 1 2
3
4
5
6
7
8
9
10
Ref: to Rate analysis
Description
Site clearance Earth work excavation in hard soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking Cement Concrete 1:4:8 using 40mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete RCC 1:11/2:3 using 20mm nominal size broken stone in columns footing including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm nominal size broken stone in columns including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm nominal size broken stone for Plinth beam including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm nominal size broken stone for sunshade, Lintal and beam, including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm nominal size broken stone for slab including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm broken stone for base and side wall of drain including cost and conveyance of all materials, labour charges, hire for formwork, watering, curing, etc. complete but excluding cost of reinforcement. Reinforced Cement Concrete 1:11/2:3 using 20mm (nominal size) broken stone for covering pre-cast slab / perforated precast slab including cost and conveyance of materials, labour charges and watering, curing , fixing charge, etc complete
Unit
Quantity
10
LS 3 m
1
m
10
dm
10
Rate
Amount
365.00
m
3
1501.50
25000.00 54804.75
42.00
m
3
3373.98
141707.13
3
47000.00
m
3
63.01
296154.99
dm
3
17000.00
dm
3
120.78
205329.17
10
dm
3
26000.00
dm
3
94.18
244868.95
10
dm
3
23000.00
dm
3
3
239515.74 104.14
10
dm
3
21000.00
dm
3
207673.74 98.89
10
dm
3
12000.00
dm
3
64.64
77572.52
10
dm
3
11000.00
dm
3
77.89
85681.42
Sl No 11
12
13
14
15
16
17
18
19
20
Ref: to Rate analysis
Description
Unit
Quantity
RCC 1:11/2:3 using 20mm nominal size broken stone for Vertical Drop slab including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. Providing Reinforcement for RCC work,bent, tied and placed in position using TMT steel Filling and forming the basement with contractor's own good quality clean earth and conveyed from available sources with all lead and lift including all for consolidation Brick work in Cement mortar 1:5 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete Cement Concrete 1:2:4 using 20mm (nominal size) broken stone for storm water drain including cost and conveyance of materials, labour charges and watering, curing etc complete but excluding all form work and reinforcement Flooring with cement concrete 1:4:8, using 40mm nominal size broken stone including cost and conveyance for materials and labour charges and watering Cement Concrete 1:11/2:3 using 20mm nominal size broken stone for levelling course Plastering with Cement mortar 1:4 ,12mm thick one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete Plastering with Cement mortar 1:3 ,12mm thick to surface one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete
10
dm
1
Qtl
Plastering with cement mortar 1:3 12 mm thick with neat cement flushing coat over including cost and conveyance for materials and labour charges and watering, curing etc. complete
3
1000.00
Rate
dm
3
Amount
90.99
9098.97
Qtl
5727.81
1174201.05
205.00 10
m
3
106.00
m
3
2612.5
27692.50
1
m
3
120.00
m
3
2840.66
340878.91
10
dm
41000.00
dm
57.48
235650.58
1
m
29.00
m
3
3
3
3
97845.40 3,373.98
10
dm
3
15000.00
dm
3
82277.05 54.85
10
m
2
1300.00
m2
1365.25
177482.45
10
m
2
220.00
m
2
1409.39
31006.59
10
m
2
713.00
m
2
1707.54
121747.83
Sl No 21
22
23 24
25
26 26 27 28
29
30
31
Ref: to Rate analysis
Description
Steel works welded or fitted in built up section, truss and framed work with M.S angle or GI pipes etc. straightening, cutting welding, fabricating and hoisting, including applying a coat of iron primer. For slaughter house Steel works welded or fitted in built up section, truss and framed work with M.S angle or GI pipes etc. straightening, cutting welding, fabricating and hoisting, including applying a coat of iron primer. for Lairage 3m length tress Purlin 32mm GI Pipe, cutting, laying etc complete Steel work in R.S Joist (in single section) cutting, hoisting and fixing in position including applying a coat iron primer etc., complete(Supply Channel section for providing pulley block) Roofing with powder coated GI tile profile sheets with bolts and nuts and bitumen washer including necessary overlap of 150mm at ends etc. complete Powder coated sheet Ridge coping for sheet roofing Welding by electric plant Supplying and fixing stainless steel grating to internal drains Marble slab flooring to slaughter floor and dressing area using 16mm thick white super quality marble slab in cement mortar 1:3 Supplying and paving good quality Vitrified tiles 60x60 cm size white colour over 12mm thick cement mortar 1:3 one coat including cost and conveyance of materials and labour charges, watering, curing, etc. complete Dadoing wall with best glazed white or coloured tiles 7.5mm thick or nearest in 12mm cement mortar 1:3 and pointing with coloured cement Providing fabricating and fixing Aluminium Single Door shutter using Aluminium powder coated hollow section of size 100x44.5x1.5mm (9245) for bottom, end vertical and top horizontal section of size 50x44.50x1.2mm (9258) and middle horizontal section of size 50x50x2mm (9286) and fixing 12mm thick pre laminated
Unit
Quantity
Rate
Amount
1
No
5
No
8119.20
40596.02
1
m
83.00
m
1862.95
154625.08
1
m
220.00
m
185.01
40701.27
1
T
1.50
T
55069.93
82604.90
10
m2
225.00
m2
4789.40
107761.50
1
m
13.00
m
215.88
2806.38
1 1
m m2
17.00 22.00
m m2
79.74 4019.40
1355.59 88426.80
10
m2
110.00
m2
16,468.3 9
181152.29
10
m2
185.00
m2
8,339.39
154278.72
10
m2
475.00
m2
983.27
46705.33
1
m2
19.00
m2
4275.53
81234.99
Sl No
32
33
34
35
36 37
37
38
39
Ref: to Rate analysis
Description
particle board at bottom and 5.5mm thick olaine glass at top including hinges, handle, glazing clips, rubber beading, Door closer, Locking arrangements. etc. Anjili wood planed and framed work for frames for doors, windows, ventilators etc. Supplying and fixing Anjili wood fully panelled shutters( as per standard drawings) to suit the door frames already fixed, inclusive of labour charges, for fixing all fittings but exclusive of cost of fittings etc complete Supplying And Fixing steel window of standard size using 20X90X3 mm thick 'Z' section for outer frames and shutter frames weighing 1.4 Kg/m providing 2 central vertical frame using J section weighing 1.6 Kg/m, providing window sahes 2 Nos for each shutter Supplying And Fixing Rolling shutter of approved make and painted with a priming coat of iron primer, made of 80x1.25 mm M.S laths interlocked together through their entire length and jointed together at he end by the end locks mounted on specially, designed pipe shaft, with brackets, side guides and arrangements for inside and outside locking with push and pull operation etc complete Supplying and fixing Top cover for Rolling shutter White Cement washing one coat including cost and conveyance for materials and labour charges and watering, curing etc. complete Finishing new cement plastered walls with Plastic Emulsion water proof paint, two coats including cost and conveyance for materials and labour charges and watering, curing etc. complete Painting with synthetic enamel paint approved qulity one coat including a priming coat to new wood works including cost and conveyance for materials and labour charges, etc. complete Painting with synthetic enamel paint approved quality two coat including a priming coat to new iron work ,including cost and conveyance for materials and labour charges, etc. complete
Unit
Quantity
Rate
Amount
10
dm3
120.00
dm3
746.78
8961.42
10
dm2
500.00
dm2
340.35
17017.60
1
m2
37.00
m2
3333.38
123335.03
10
dm2
1800.00
dm2
187.06
33669.90
9.00
m
528.06
4752.50
1
m
10
m2
1291.00
m2
85.74
11069.16
10
m2
1037.00
m2
574.75
59601.58
10
m2
13.00
m2
746.41
970.33
10
m2
37.00
m2
737.06
2727.10
Sl No 40
41
42
43
44
45
46
Ref: to Rate analysis
Description
Painting with synthetic enamel paint two coat on Rolling shutter using approved quality paint as specified, one coat Supplying and Fixing Europian type, water closet (Earthern ware white best quality) with p or S trap, using duro-plastic seat and cover and C.P brass hinges with rubber buffers,1.5 liter white enamelled PVC low level flushing cistern with fittings and brackets, including cutting and making good the walls and floors etc. Supplying and fitting 550x400mm or nearest size wash hand basin of white glazed earthenware (Indian make- best quality) with C.I brackets, a pair of 15mm C.P. brass pillar taps and 2 nos. 15mm lead and brass connections with brass unions, using 15mm lead pipe weighing not less than 1.60Kg per m, 2 nos. 15mm GM wheel valves, rubber plug and CP brass chains, 32mm CP brass waste of standard pattern, 32mm lead trap with access cap, soldering the joints complete, including cutting making good the walls, painting the brackets, waste connections, etc., with suitable paint two coats (Indian fitting –best qulty.) Supplying, threading, laying and jointing 110mm diameter PVC pipe 4kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including trenching to a minimum depth of 50cm and refilling, etc, complete(External work) Supplying, threading, laying and jointing 50mm diameter PVC pipe 6kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including trenching to a minimum depth of 50cm and refilling, etc, complete(External work) Supplying, laying and jointing 20mm nominal diameter PVC pipe 10kgf/cm2 (ISI marked) and specials such as tees, bends, elbows, etc, with clamp and solvent cement for jointing pipe including cutting and making good the walls, painting exposed face, etc, (Internal work) Constructing Inspection Chamber of size 40x40cm or 40x60cm inside the sewer line
Unit
Quantity
Rate
Amount
10
m2
40.00
m2
737.06
2948.22
1
No
3.00
No
2739.88
8219.64
1
No
3.00
No
2572.79
7718.37
1
m
25.00
m
192.23
4805.63
1
m
30.00
m
80.74
2422.20
1
m
25.00
m
34.08
852.04
3
No.
1635.11
4905.33
1
Sl No
Ref: to Rate analysis
Description
Unit
up to a depth not exceeding 60cms with brick masonry in cement mortar 1:6, 23cm thick wall forming channels inside with cement concrete 1:3:6 using 40mm broken stone, plastering the inside and channels with cement mortar 1:3, 12mm thick with neat cement flushing coat including all earth work and foundation concrete 20cm thick, etc. complete Supplying stainless steel ladder 3m height Supplying stainless steel bench up to 1.50m height Supplying stainless steel wheel barrow
47 48 49
1
Quantity
Rate
1
Amount
7000.00
7000.00
1
E
4
E
10000.00
40000.00
1
E
3
E
10000.00
30000.00
50
Supplying pressure washer 200330 KPA
150000.00
51
Dispersion trench 500x150x200cm. Solar water heater 500 ltr Chopper Mixer grinder Biogas plant Biogas Conversion generator Stainless steel Hooks Total Say
22000.00
52 53 54 55 56 57
1
E
1
E
NA 15.00
1
90000.00
500.00
90000.00 25000.00 40000.00 500000.00 0.00 7500.00 60,63,914.67 60,63,915.00
2.3.2 Soak Pit Sl No 1
2
3
4
Ref: to Rate analysis
Description
Unit
Quantity
Rate
Amount
Earth work excavation in hard soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking Brick work in Cement mortar 1:6 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete RCC 1:11/2:3 using 20mm broken stone for pre-cast circular cover slab of soak pit including all for formwork, watering, curing, fixing charge, etc complete but excluding cost and labour for reinforcement.
10
m3
9.00
1501.50
1,351.35
1
m3
4.00
2717.21
10,868.84
10
dm3
230.00
Reinforcement for RCC work, bent, tied and placed in position using TMT steel Total Say
1
qtl
1.00
dm3
56.50
1,299.50
qtl
5727.81
5,727.81
15,238.04 15,238.00
2.3.3 Overhead Tank Sl No 1
2
3
4
5
6
7
8
9
10
11
Ref: to Rate analysis
Description
Unit
Quantity
Rate
Amount
Earth work excavation in hard soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking Cement Concrete 1:4:8 using 40mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete RCC 1:11/2:3 using 20mm nominal size broken stone in columns footing including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm nominal size broken stone in columns including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm nominal size broken stone for beam including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm nominal size broken stone for Bottom slab of Tank including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm nominal size broken stone for Side wall of Tank including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm nominal size broken stone for Cover slab of Tank including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. Providing Reinforcement for RCC work,bent, tied and placed in position using TMT steel
10
m3
22.00
m3
1501.50
3,303.30
1
m3
3.00
m3
3373.98
1
q
25
Q
5727.81
Supplying, laying and jointing 32mm nominal diameter PVC pipe 10kgf/cm2 (ISI marked) and specials such as tees, bends, elbows, etc, with clamp and solvent cement for jointing pipe including cutting and making good the walls, painting exposed face, etc, (External work) Supplying, laying and jointing 32mm nominal diameter PVC pipe 10kgf/cm2 (ISI marked) and specials such as tees, bends, elbows, etc, with clamp and solvent cement for jointing pipe including cutting and making good the walls, painting exposed face, etc, (Internal work)
1
m
80.00
m
74.64
5970.8
1
m
20.00
m
73.57
1471.43
10,121.94
10
dm3
4000.00
dm3
63.01 25,204.68
10
dm3
2500
dm3
120.78 30,195.47
10
10
10
dm3
dm3
dm3
4500
2500
5000.00
dm3 104.14
46,861.78
98.89
24,723.06
dm3
dm3
64.64 32,321.88
10
dm3
6000
dm3
77.89 46,735.32
143195.25
Sl No 12
13
14
15
16
17
18
19
20
21
Ref: to Rate analysis
Description
Unit
Quantity
Rate
Amount
Supplying, laying and jointing 25mm nominal diameter PVC pipe 10kgf/cm2 (ISI marked) and specials such as tees, bends, elbows, etc, with clamp and solvent cement for jointing pipe including cutting and making good the walls, painting exposed face, etc, (Extrnal work) Supplying, threading, laying and jointing 20mm diameter PVC pipe 10kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including trenching to a minimum depth of 50cm and refilling, etc, complete(External work) Brick work in Cement mortar 1:5 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete Anjili wood planed and framed work for frames for doors, windows, ventilators etc.
1
m
60.00
m
52.23
3133.63
1
m
45.00
m
45.02
2025.79
1
m3
7.00
m3
2840.66
19884.60
10
d3
1000.00
dm3
746.78
74678.46
Supplying and fixing Anjili wood fully panelled shutters( as per standard drawings) to suit the door frames already fixed, inclusive of labour charges, for fixing all fittings but exclusive of cost of fittings etc complete Supplying And Fixing steel window of standard size using 20X90X3 mm thick 'Z' section for outer frames and shutter frames weighing 1.4 Kg/m providing 2 central vertical frame using J section weighing 1.6 Kg/m, providing window sahes 2 Nos for each shutter Plastering with Cement mortar 1:4 ,12mm thick one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete Painting with synthetic enamel paint approved qulity two coat including a priming coat to new wood works after rubbing with sand paper and cleaning surface including cost and conveyance for materials and labour charges, etc. complete Painting with synthetic enamel paint approved quality two coat including a priming coat to new iron work ,including cost and conveyance for materials and labour charges, etc. complete White Cement washing one coat including cost and conveyance for materials and labour charges and watering, curing etc. complete
10
dm2
200.00
340.35
6807.04
1
m2
0.5
m2
3333.38
1666.69
10
m2
67.00
m2
1365.25
9147.17
10
m2
4.50
m2
746.41
335.88
10
m2
4.50
m2
737.06
331.67
10
m2
67.00
m2
85.74
574.46
Sl No
Ref: to Rate analysis
22
Description
Unit
Finishing new cement plastered walls with Emulsion water proof paint, two coats including cost and conveyance for materials and labour charges and watering, curing etc. complete Provide Bore well with submerged Pumb and accessaries
23
10
m2
Quantity
67.00
m2
Rate
574.75
Amount
3850.83
1,50,000.00
Total Say
6,42,541 .14 6,42,541.00
2.3.4 Anaerobic Tank Sl No
Ref: to Rate analysis
Description
Unit
Quantity
Rate
Amount
1
Earth work excavation in hard soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking
10
m3
140.00
m3
1501.50
21,021.00
2
Cement Concrete 1:4:8 using 40mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete
1
m3
4.00
m3
3373.98
13,495.92
3
RCC 1:11/2:3 using 20mm nominal size broken stone in columns footing including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement.
10
dm3
4000.00
dm3
63.01
25,204.68
4
RCC 1:11/2:3 using 20mm broken stone for base and side wall of Tank including cost and conveyance of all materials, labour charges, hire for formwork, watering, curing, etc. complete but excluding cost of reinforcement.
10
dm3
14000.00
dm3
64.64
90,501.27
5
Reinforced Cement Concrete 1:11/2:3 using 20mm (nominal size) broken stone for covering pre-cast slab / perforated pre-cast slab including cost and conveyance of materials, labour charges and watering, curing , fixing charge, etc complete but excluding an
10
dm3
3000
dm3
77.89
23,367.66
6
Providing Reinforcement for RCC work
1
Q
2.50
Qtl
5727.81
14,319.53
7
Cast iron heavy dutyman hole cover with frame size 60x60cm
1
E
3.00
E
4019.40
12,058.20
8
Providing stainless steel screen inside
1
m2
1.70
m3
4019.40
6,832.98
Sl No
Ref: to Rate analysis
9
Description
Unit
Plastering with Cement mortar 1:3 ,12mm thick to surface one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete
10
m2
Quantity
120.00
m2
Rate
1409.39
Amount
16,912.68
Total
2,23,713.92
Say
2,23,714.00
2.3.5 Compound Wall and Gate Sl No
Ref: to Rate analysis
Description
Unit
Quantity
Rate
Amount
1
Earth work excavation in hard soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking
10
m3
94.00
m3
1501.50
21,021.00
2
Random rubble masonry in cement mortar 1:6 for foundation and basement including pointing simultaneously with same mortar and providing necessary weep holes including cost and conveyance of materials and labour charges, watering, curing etc complete
1
m3
147.00
m3
2115.46
3,10,973.03
3
Brick work in Cement mortar 1:5 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete
1
m3
130.00
2840.66
3,69,285.49
4
Plastering with Cement mortar 1:4 ,12mm thick one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete
10
m2
1120.00
m2
1365.25
1,52,907.96
5
White Cement washing one coat including cost and conveyance for materials and labour charges and watering, curing etc. complete
10
m2
1120.00
m2
85.74
9,602.99
6
Finishing new cement plastered walls with cement water proof paint, two coats including cost and conveyance for materials and labour charges and watering, curing etc. complete
10
m2
1120.00
m2
574.75
64,372.00
7
Supplying and fixing M.S gate with 32mm GI pipe outer frame and 12mm Sq.rod vertical at 10 cm c/c and horizontal at 15cm c/c ,including all fittings like clamp and locking arrangment.
1
m2
8.00
m2
2360.86
18,886.91
Total
9,40,142.47
Say
9,40,142.00
2.3.6 Road and Parking lot Sl No 1 2
3
4
5
6
7
Ref: to Rate analysis
Description
Unit
Sectioning upto 150mm on the surface of new road Supplying 60mm graded metal (Proportion of 7:3 of 60mm and 36mm by volume) and stacking in standard heap for measurements including cost, conveyance, etc Supplying and stacking 36mm hard granite broken stone in standard uniform heap for measurements Supplying and stacking good hard gravely red earth for blinding for measurements Supplying hard blue granite broken stone 12mm size and stacking in standard uniform heap for measurements including cost, conveyance, etc, complete Supplying hard blue granite broken stone 6mm size and stacking in standard uniform heap for measurements including cost, conveyance, etc, complete Metalling the roadway 100mm spread thickness compacted to 75mm using departmental broken stone (graded in the ratio of 7:3 of 60mmand 36mm sizes)1m3/10m2 and departmental blinding materials (0.20m3/10m2 ), bed rolling, spreading broken stones to template, rolling dry to compaction from sides to central until the movement of broken stones cease, watering profusely and rolling until the fines cream up and fill the voids of the stones, then spreading the gravelly earth and sweeping in to the joints, watering and rerolling until the gravelly earth has worked in to all the crevises and only a thin coat of slurry remains, then take off the roller and allow to set to harden for 24 hours and rerolling next day until any deformity is rectified, including fencing, lighting, watching and maintaining the surface free of ruts for 15 days after completion as per IRC.2-1-2
10
m2
370.00
m2
132.00
4,884.00
1
m3
83.60
m3
851.40
71,177.04
1
m3
83.60
m3
928.40
77,614.24
1
m3
18.66
m3
311.30
5,807.30
1
m3
83.60
m3
1461.19
1,22,155.07
1
m3
4.80
m3
939.40
4,506.30
526.47
44,012.98
10
Quantity
836.00
Rate
Amount
Sl No
Ref: to Rate analysis
8
9
Description
Unit
Quantity
Rate
Metalling the roadway 100mm spread thickness compacted to 75mm using 36mm departmental broken stone (1m3/10m2) and departmental blinding materials (0.15m3/10m2 ), spreading broken stones to template, rolling dry to compaction, watering profusely, and rolling until the fines cream up and fill the voids of the stones, then spreading the gravelly earth and sweeping in to the joints, watering and rerolling until the gravelly earth has worked in to all the crevises and only a thin coat of slurry remains, then take off the roller and allow to set to harden for 24 hours and rerolling next day until any deformity is rectified, including fencing, lighting, watching and maintaining the surface free of ruts for 15 days after completion as per IRC.2-1-2 Providing 20mm Pre-mix chipping carpet over W.B.M. surface with departmental broken stone after thoroughly cleaning the base with wire brushes, bass brooms and applying a priming coat of 7.50Kg of bitumen 10m2 and spreading the hot pre-mix (formed of 0.27m3 of departmental 12mm metal and 12.96Kg of bitumen per 10m2) rolling to dense surface, then spreading the seal coat (comprising of a hot pre-mix of 0.09m3 of 6mm departmental metal and 8.64Kg of bitumen per 10m2) again rolling including the cost of bitumen, oils and fuel, hire of bsss brooms, camber board, roller and other machines, watching, lighting and other charges, etc complete (Total usage of bitumen is 29.10Kg per 10m2) as per IRC.3-2-2
10
836.00
526.47
10
m2
836.00
m2
1408.67
Total Say
Amount
44,012.98
1,17,764.87
4,91,934.77 4,91,935.00
2.4 DETAILED ESTIMATE FOR MODERN ABATTOIR 2.4.1 Slaughter house, Lairage, Administrative Building and Watchman Shed Sl.No
Description of Items
No
Length
Breadth
Height
Quantity
Unit
1
Site clearance
2
Earth work excavation in hard soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking
LS
Slaughter house Building Column footing
17
2.20
2.20
2.50
205.70
Ground beam
2
10.92
0.45
0.40
3.93
Sl.No
Description of Items
No
Length
Breadth
Height
Quantity
2
18.65
0.45
0.40
6.71
3
10.66
0.45
0.40
5.76
6
3.5
0.45
0.45
4.25
Column footing
8
1.7
1.7
2.5
57.80
Ground beam
2
9.38
0.45
0.4
3.38
4
3.5
0.45
0.4
2.52
Column footing
16
1.4
1.4
2.1
65.86
Ground beam
2
20.4
0.45
0.4
7.34
5
3.5
0.45
0.4
3.15
Column footing
4
1.7
1.7
2.1
24.28
Ground beam
4
3
0.45
0.4
2.16
Unit
Admin Building
Lairage
Watch man shed
Total
392.84
M
3
Deduction
3
Column footing
17X2
2.2
0.45
0.4
13.46
Ground beam
8x2
1.7
0.45
0.4
4.90
16x2
1.4
0.45
0.4
8.06
4x2
1.7
0.45
0.4
2.45
Total Deduction
28.87
M
3
Total
363.96
M
3
Say
365.00
M
3
Cement Concrete 1:4:8 using 40mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete Slaughter house Building Column footing
17
2.20
2.20
0.15
12.34
Ground beam
2
10.92
0.45
0.10
0.98
2
18.65
0.45
0.10
1.68
3
10.66
0.45
0.10
1.44
6
3.5
0.45
0.10
0.95
Column footing
8
1.7
1.7
0.15
3.47
Ground beam
2
9.38
0.45
0.1
0.84
4
3.5
0.45
0.1
0.63
Column footing
16
1.4
1.4
0.15
4.70
Ground beam
2
20.4
0.45
0.1
1.84
5
3.5
0.45
0.1
0.79
Column footing
4
1.7
1.7
0.15
1.73
Ground beam
4
3
0.45
0.1
0.54
Storm water drain
1
180
0.6
0.1
10.8
Admin Building
Lairage
Watchman shed
Sl.No
Description of Items
No
Length
Breadth
Height
Total
Quantity
Unit
42.73
Deduction Column footing Ground beam
4
0.4
0.23
0.1
0.31
8
0.4
0.23
0.1
0.31
16
0.23
0.23
0.1
0.08
4
0.23
0.23
0.1
0.17
Total Deduction
0.88
Total Less Deduction
41.85
Say
42.00
3
1
Slaughter house Building
17
2.00
17
Admin building
2.00
0.25
17.00
(2x2)+(0.5x0.5)/2
0.25
9.03
8
1.50
0.20
3.60
8
(1.5x1.5)+(0.5x0.5)/2
0.20
3.80
4
1.50
0.20
1.80
4
(1.5x1.5)+(0.5x0.5)/2
0.20
1.90
16
1.2
0.20
4.61
16
(1.2x1.2)+(0.5x0.5)/2
1.50 1.50
5.01 3
Total
46.75
M
Say
47000.00
dm
3
1
RCC 1:1 /2:3 using 20mm nominal size broken stone in columns including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. Slaughter house Building
8
0.40
0.23
6.50
4.78
9
0.40
0.23
4.50
3.73
Admin building
8
0.40
0.23
5.00
3.68
Lairage
8
0.23
0.23
4.50
1.90
8
0.23
0.23
4.00
1.69
4
0.23
0.23
4.50
0.95
Watchman shed Total Say 6
M
RCC 1:1 /2:3 using 20mm nominal size broken stone in columns footing including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement.
Watch man shed
5
17
M
17000.00
dm3
1
RCC 1:1 /2:3 using 20mm nominal size broken stone for Plinth beam including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. Slaughter house Building Ground beam
2
10.92
0.23
0.40
2.01
2
18.65
0.23
0.40
3.43
3
10.66
0.23
0.40
2.94
6
3.5
0.23
0.40
1.93
2
9.38
0.23
0.4
1.73
4
3.5
0.23
0.4
1.29
2
20.4
0.45
0.4
7.34
Admin Building Ground beam
Lairage Ground beam
3
16.74
Sl.No
Description of Items
No
Length
Breadth
Height
Quantity
5
3.5
0.45
0.4
3.15
4
3
0.45
0.4
2.16
Unit
Watchman shed Ground beam Total
25.98
Deduction Columns
17
0.4
0.23
0.4
Total Say 7
0.63 3
25.36
M
26000.00
dm3
1
RCC 1:1 /2:3 using 20mm nominal size broken stone for sunshade, Lintal and beam, including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. Slaughter house Building Ground beam
2
10.92
0.23
0.40
2.01
2
18.65
0.23
0.40
3.43
3
10.66
0.23
0.40
2.94
3
3.5
0.23
0.40
0.97
15
3.5
0.23
0.15
1.81
10
10.23
0.23
0.15
3.53
2
18.65
0.6
0.05
1.12
2
12.12
0.6
0.05
0.73
2
9.38
0.23
0.4
1.73
4
3.5
0.23
0.4
1.29
4
1.2
0.23
0.4
0.44
2
3
0.23
0.15
0.21
2
4
0.23
0.15
0.28
2
1.5
0.23
0.15
0.10
4
3.5
0.23
0.15
0.48
1
9.38
0.6
0.05
0.28
Beam
4
3
0.23
0.4
1.10
Ground beam
4
3.00
0.23
0.15
0.41
2
4.66
0.6
0.05
0.28
2
3.46
0.6
0.05
0.21
Lintel
Sunshade
Admin Building Ground beam
Lintel
Watchman shed
Total
23.35
Deduction for column
8
17
0.4
0.23
0.4
0.63
8
0.4
0.23
0.4
0.29
M
3
Total deduction
0.92
Total Less deduction
22.43
M
Say
23000.00
dm3
1
RCC 1:1 /2:3 using 20mm nominal size broken stone for slab including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement.
3
Sl.No
9
10
Description of Items
No
Length
Breadth
Height
Quantity
For Slaughter house Building
1
10.92
3.96
0.10
4.32
1
10.92
7.69
0.10
8.40
Slaughter slab
1
3.00
4.00
0.15
1.80
Counter
1
3.00
1.00
0.10
0.30
Admin Building
1
9.38
5.15
0.10
4.83
Watch man shed
1
3.46
3.46
0.10
1.20
Total
20.85
Say
21000.00
For Slaughter house Floor
1
55
1
0.10
5.50
1
21
1
0.10
2.10
Leading drain to Biogas plant
1
35
1
0.10
3.50
Total
11.10
Say
12000.00
dm
10.75
m3
11000.00
dm3
Reinforced Cement 1 Concrete 1:1 /2:3 using 20mm (nominal size) broken stone for covering pre-cast slab / perforated pre-cast slab including cost and conveyance of materials, labour charges and watering, curing , fixing charge, etc complete but excluding an
358
0.6
0.5
0.10
3
1
RCC 1:1 /2:3 using 20mm nominal size broken stone for Vertical Drop slab including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. Admin building
1
12.78
Say 12
dm3
RCC 1:11/2:3 using 20mm broken stone for base and side wall of drain including cost and conveyance of all materials, labour charges, hire for formwork, watering, curing, etc. complete but excluding cost of reinforcement.
Say 11
Unit
0.1
0.6
0.77
m3
1000.00
dm3
Providing Reinforcement for RCC work,bent, tied and placed in position using TMT steel Column footing – 46.75 m3 @ 70 Kg/m3
272.31
RCC column– 16.74 m3 @ 140 Kg/m3
2343.52
Ground Beam – 25.36 m3 @ 130 Kg/m3
3296.46
Beam – 22.43 m3 @ 140Kg/m3
3139.84
Slab – 20.85 m3 @ 90 Kg/m3
1876.47
Storm water drain – 51.60 m3 @ 100 Kg/m3
5160.00
Precast slab – 10.75 m3 @ 120 Kg/m3
1290.00
Drop slab – 0.77 m3 @ 70 Kg/m3
53.90
Total
20432.49
Kg
Sl.No
Description of Items
No
Length
Breadth
Height
Say 13
14
Quantity 205.00
Unit Qtl
Filling and forming the basement with contractor's own good quality clean earth and conveyed from available sources with all lead and lift including all for consolidation Slaughter house
1
18.00
10.00
0.45
81.00
Admin building
1
9.00
5.00
0.45
20.25
Watchman Shed
1
3.00
3.00
0.45
4.05
Total
105.30
Say
106.00
m3
Brick work in Cement mortar 1:5 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete Slaughter house
Admin Building
Watch man shed
2
18.65
0.23
3.00
25.74
5
10.12
0.23
3.00
34.91
6
3.5
0.23
3.00
14.49
1
2.5
0.23
3.00
1.73
2
2
0.23
3.00
2.76
1
2.45
0.23
3.00
1.69
2
10.12
0.23
1.50
6.98
2
10.12/2
0.23
1.50
3.49
2
9.38
0.23
3.00
12.94
4
3.5
0.23
3.00
9.66
1
22.96
0.23
0.80
4.22
1
20.44
0.23
1.00
4.70
3
3.5
0.23
2.00
4.83
4
3
0.23
3.00
8.28
1
13.84
0.12
0.80
1.33
Total
137.76
M3
Deduction Door
Window
9
0.9
0.23
2.1
3.91
2
0.9
0.23
2.1
0.87
1
0.9
0.23
2.1
0.43
3
0.75
0.23
2.1
1.09
1
1.5
0.23
2.1
0.72
2
2
0.23
2.1
1.93
1
2
0.23
1.5
0.69
15
1.5
0.23
1.5
7.76
5
1
0.5
0.23
0.58
Total deduction
17.99
Total Less deduction
119.77
Say
120.00
M3
Sl.No
Description of Items
No
Length
Breadth
Height
Quantity
15
Cement Concrete 1:2:4 using 20mm (nominal size) broken stone for storm water drain including cost and conveyance of materials, labour charges and watering, curing etc complete but excluding all form work and reinforcement
1
180
1.5
0.15
40.50
Say 16
dM3
Flooring with cement concrete 1:4:8, using 40mm nominal size broken stone including cost and conveyance for materials and labour charges and watering Slaughter house
Admin Building
17
41000.00
Unit
2
3.00
3.5
0.10
2.10
1
4.00
3.5
0.10
1.40
1
3.50
3.5
0.10
1.23
1
2.47
3.5
0.10
0.86
1
1.80
3.5
0.10
0.63
1
2.00
3.5
0.10
0.70
1
10.46
3.5
0.10
3.66
1
4.00
3.5
0.10
1.40
1
6.23
3.5
0.10
2.18
1
3.00
3.5
0.075
0.79
1
4.00
3.5
0.075
1.05
1
1.50
3.5
0.075
0.39
1
9.38
1.2
0.075
0.84
1
19.77
3.5
0.1
6.92
1
21.00
1.00
(0.3+0.1)/2
4.2
Total
28.36
Say
29.00
M3
Cement Concrete 1 1:1 /2:3 using 20mm nominal size broken stone for levalling course Slught floor
1
10.46
7
0.10
7.32
1
2
3.5
0.10
0.70
1
19.77
3.5
0.10
6.92 14.94 15000.00
18
dM3
Plastering with Cement mortar 1:4 ,12mm thick one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete Slaughter house (outside)
2
18.65
3.45
128.69
2
10.92
3.45
75.35
2
7.46
2.00
29.84
Sl.No
Description of Items
No
Length
Breadth
2
10.92/2
1.50
16.38
2
3.73
2.00
14.92
1
2.46
2.00
4.92
1
13.0
3.00
39.00
1
13.0
3.00
39.00
1
4.40
2.50
11.00
1
4.70
2.50
11.75
1
2.90
2.50
7.25
Preparation room
1
15.00
3.00
45.00
Ramp
1
11.00
5.00
55.00
Freezer room
1
10.60
3.00
31.80
1
11.94
3.00
35.82
Delivery Area
1
14.00
3.00
42.00
Dressing Room
1
34.92
3.00
104.76
2
7.00
2.00
28.00
2
10.46/2
1.50
15.69
store
1
15
3.00
45.00
Waste deposit
1
19.56
3.00
58.68
Parapet
1
26.3
1.72
45.24
1
18.38
1.72
31.61
Out side
1
26.64
3.45
91.91
Parapet
1
29.00
1.85
53.65
Inside dadoing
1
13.00
3.00
39.00
1
15.00
3.00
45.00
Toilet
1
8.00
3.00
24.00
Lairage
3x2
3.50
2.00
42.00
3
3.50
0.23
2.42
2
20.44
0.23
9.40
1
20.44
0.23
4.70
9
0.92
1.00
8.28
9
0.92
2.50
20.70
Slaughter house (inside)
Height
Quantity
Admin building
column
watch man
0.00
out side
1
13.84
3.45
47.75
inside
1
12
3
36.00
Parapet
1
13.84
1.85
25.60
Total
1367.10
Deduction Door
12
0.9
2.1
22.68
3
0.75
2.1
4.725
Unit
Sl.No
19
Description of Items
No
Length
Breadth
Height
Quantity
Opening
1
1.5
2.1
3.15
2
2
2.1
8.4
1
2
1.5
3
Window
15
1.5
1.5
33.75
Ventilator
5
1
0.5
2.5
Total deduction
78.21
Total Less deduction
1288.90
Say
1300.00
Unit
m2
Plastering with Cement mortar 1:3 ,12mm thick to surface one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete Under of Slabs Slaughter house Office
1
3.00
3.50
10.50
1
3.00
3.50
10.50
Preparation
1
4.00
3.50
14.00
Cold
1
1.80
3.50
6.30
Dressing
1
2.47
3.50
8.65
Delivery
1
3.50
3.50
12.25
store
1
4.00
3.50
14.00
Waste room
1
6.23
3.50
21.81
shade
2
11.68
0.70
16.35
2
12.12
0.70
16.97
1
3.00
3.50
10.50
1
4.00
3.50
14.00
1
1.50
3.50
5.25
1
9.38
1.20
11.26
1
1.73
1.00
1.73
drop
1
12.78
1.30
16.61
Sun shade
1
9.38
0.70
6.57
Room
1
3.00
3.00
9.00
Sun shade
2
4.66
0.70
6.52
2
3.46
0.70
4.84
Admin Bldg. Office room
Varandha
Watchman Shed
20
Total
217.60
Say
220.00
m2
Plastering with cement mortar 1:3 12 mm thick with neat cement flushing coat over the slab including cost and conveyance for materials and labour charges and watering, curing etc. complete Slaughter house Slaughter house
1
10.92
7.69
83.97
1
10.92
3.96
43.24
Sl.No
Description of Items
No
Length
Breadth
Height
Quantity
Sun shade
2
18.65
0.70
26.11
2
12.22
0.70
17.11
Admin building
1
9.38
5.14
48.21
Admin bldg. – sun shade
1
9.38
0.70
6.57
Watch man Shed
1
3.46
3.46
11.97
Watchman bldg. – sun shade
2
3.66
0.70
5.12
2
3.46
0.70
4.84
In side of external drain
1
56
1.10
61.60
1
180
1.70
306.00
Lairage
1
20.5
3.73
76.47
Ramp
1
21
1.00
21.00
Total
712.22
Say
713.00
m2
5
Nos
21
Steel works welded or bolted in built-up section, truss and framed work with M.S angle or GI pipes etc. straightening, cutting welding, fabricating and hoisting, including applying a coat of iron primer for slaughter house
5
22
Steel works welded or fitted in built-up section, truss and framed work with M.S angle or GI pipes etc. straightening,cutting welding, fabricating and hoisting, including applying a coat of iron primer. for Lairage 3m length tress
2
21.00
42.00
9
4.50
40.50
23
Total
82.50
Say
83.00
Purlin 32mm GI Pipe, cutting, laying etc complete
2x9
12.00
m
216.00
Say 24
Unit
220.00
m
Steel work in R.S Joist (in single section) cutting, hoisting and fixing in position including applying a coat iron primer etc., complete(Supply Channel section for providing pulley block) ISMB 225x110
3
7.5
31.2
702.00
ISMB 100x50
1x2
32
9.2
588.80
Support for beam
6x2
0.5
9.2
55.2
RSJ for holding pulley and hooks 1x32 = 32m
Sl.No
Description of Items
No
Length
Breadth
Height
Quantity
Unit
ISMB 100x50
25
5% wastage
67.3
Total
1.413.30
kg
Say
1.5
T
Roofing with powder coated GI tile profile sheets with bolts and nuts and bitumen washer including necessary overlap of 150mm at ends etc. complete Slaughter building
2
12.50
4.50
112.50
Lairage
1
22.00
5.00
110.00
Total
222.50
Say
225.00
m2 m
26
Powder coated sheet Ridge coping for sheet roofing
1
13.00
13.00
27
Welding by electric plant
3x2
0.75
4.50
10
0.35
3.50
2x12
0.35
8.40
Total
16.40
Say
17.00
m
22.00
m2
28
Supplying and fixing stainless steel gratings to internal drains
29
Marble slab flooring to slaughter floor and dressing area using 16mm thick white superior quality marble slab in cement mortar 1:3 etc. complete
30
1
55.00
0.40
Dressing area
1
10.46
7.00
73.22
Side of slaughter floor
2
4.00
0.50
4.00
Cold storage
1
1.80
3.50
6.30
1
2.47
1.00
2.47
Top of counter
1
3.50
1.00
3.50
Preparation room
1
4.00
3.50
14.00
Step
2
3.50
0.45
3.15
1
3.50
0.15
0.53
Total
107.17
Say
110.00
m2
Supplying and paving good quality Vitrified tiles 60x60 cm size white colour over 12mm thick cement mortar 1:3 one coat including cost and conveyance of materials and labour charges, watering, curing, etc. complete Slaughter house Office
1
3.00
3.50
10.50
Delivery area
1
3.50
3.50
12.25
Toilet
1
3.00
3.50
10.50
Changing
1
2.47
2.50
6.18
Store
1
4.00
3.50
14.00
Waste depositing
1
6.23
3.50
21.81
Sl.No
Description of Items
No
Length
Breadth
Height
Quantity
Inside room
1
55.00
0.90
49.50
1
3.00
3.50
10.50
1
4.00
3.50
14.00
1
1.50
2.50
3.75
1
9.38
1.20
11.26
1
1.73
1.00
1.73
1
13.00
0.10
1.30
1
15.00
0.10
1.50
1
7.00
0.10
0.70
1
3.00
3.00
9.00
1
12.00
0.10
1.20
2
2.50
0.45
2.25
1
2.50
0.45
1.13
2
1.20
0.45
1.08
1
1.20
0.15
0.18
Unit
Admin building Floor
Skirting
Watchman Shed Floor
Store
31
Total
184.30
Say
185.00
m2
Dadoing wall with best glazed white or coloured tiles 7.5mm thick or nearest in 12mm cement mortar 1:3 and pointing with coloured cement Slought house
1
36.84
3.50
128.94
Dressing area
2
3.50
3.50
24.50
Preparation
1
15.00
3.00
45.00
Cold storage
1
10.00
3.00
30.00
Toilet
1
13.00
3.00
39.00
1
4.40
2.50
11.00
1
4.70
2.50
11.75
1
2.90
2.50
7.25
Changing room
1
9.94
3.00
29.82
Delivery area
1
10.50
3.00
31.50
Store
1
15.00
3.00
45.00
Waste
1
19.46
3.00
58.38
1
13.00
1.50
19.50
1
8.00
2.10
16.80
Toilet
498.44 Deduction Door
Window
7
0.9
2.1
13.23
1
0.9
1.5
1.35
3
0.75/2
2.1
2.3625
10
1.5/2
1.5
11.25
Sl.No
32
33
Description of Items
Breadth
Height
Quantity 28.19
Total Less deduction
470.25
Say
475.00
Providing fabricating and fixing Aluminium Single Door shutter using Aluminium powder coated holow section of size 100x44.5x1.5mm (9245) for bottom, end vertical and top horizontal section of size 50x44.50x1.2mm (9258) and middle horizontal section of size 50x50x2mm (9286) and fixing 12mm thick prelaminated particle board at bottom and 5.5mm thick olaine glass at top including hinges,handle, glazing clips, rubber beading, Door closser,Locking arrangements. etc.
8
0.9
2.1
15.12
1
1.5
2.1
3.15
Total
18.27
Say
19.00
Unit
m2
m2
Anjili wood planed and framed work for frames for doors, windows, ventilators etc.
Watchman shed
35
Length
Total deduction
Admin building
34
No
2x2
2.15
0.1
0.075
0.06
2x1
1.05
0.1
0.075
0.02
1x2
2.15
0.1
0.075
0.03
1x1
1.05
0.1
0.075
0.01
Total
0.12
Say
120.00
Supplying and fixing Anjili wood fully panelled shutters( as per standard drawings) to suit the door frames already fixed, inclusive of labour charges, for fixing all fittings but exclusive of cost of fittings etc complete
3
0.8
2.05
Supplying And Fixing steel window of standard size using 20X90X3 mm thick 'Z' section for outer frames and shutter frames weighing 1.4 Kg/m providing 2 central vertical frame using J section weighing 1.6 Kg/m, providing window sashes 2 nos. for each shutter
15
1.50
1.50
33.75
5
1.00
0.50
2.5
Say
dm3
4.92
500.00
Total
36.25
Say
37.00
dm2
m2
Sl.No
Description of Items
36
Supplying And Fixing Rolling shutter of approved make and painted with a priming coat of iron primer, made of 80x1.25 mm M.S laths interlocked together through their entire length and jointed together at he end by the end locks mounted on speciallly, designed pipe shaft, with brackets, side guides and arrangements for inside and outside locking with push and pull operation etc complete
37
No
Length
Breadth
39
40
1
3.50
2.50
8.75
Delivery counter
1
2.50
1.50
3.75
Cattle entry
1
2.00
2.50
5.00 17.5
M2
Say
1800.00
dm2
Supplying and fixing Top cover for Rolling shutter Delivery entrance
1
4.0
4.00
Delivery counter
1
3.00
3.00
Cattle entry
1
2.00
2.00 9.00
m
White Cement washing one coat including cost and conveyance for materials and labour charges and watering, curing etc. complete Qty. vide item 18
1288.9
Qty. vide item 19
217.6
Total
1506.50
Deduction for Dadoing area
470.25
Total less deduction
1036.26
m2
Say
1037
m2
Finishing new cement plastered walls with Plastic Emulsion water proof paint, two coats including cost and conveyance for materials and labour charges and watering, curing etc. complete Qty. vide item 18
1288.9
Qty. vide item 19
217.60
Total
1506.50
Deduction for Dadoing area
470.25
Total less deduction
1036.26
Say
1037.00
m2
Painting with synthetic enamel paint of approved quality two coats over a priming coat to new wood works including cost and conveyance for materials and labour charges, etc. complete -
Say
3
0.9
2.1
12.76 13.00
m2
Painting with synthetic enamel paint of approved quality two coats over a priming coat to new iron work, including cost and conveyance for materials and labour charges, etc. complete 2x0.50x37.00 m2
42
Unit
Total
2x1.125
41
Quantity
Delivery entrance
Total 38
Height
37.00
m2
Painting with synthetic enamel paint two coat on Rolling shutter using approved quality paint as specified, one coats 2x1.14x17.2 m2
39.90
Say
40.00
m2
Sl.No
Description of Items
No
43
Supplying and Fixing Europian type, water closet (Earthern ware white best quality) with p or S trap, using duroplastic seat and cover and C.P brass hinges with rubber buffers,1.5 liter white enamelled PVC low level flushing cistern with fittings and brackets, including cutting and making good the walls and floors etc.
44
Length
Breadth
Height
Quantity
Unit
3
3.00
Nos
Supplying and fitting 550x400mm or nearest size wash hand basin of white glazed earthenware (Indian make- best quality) with C.I brackets, a pair of 15mm C.P. brass pillar taps and 2 nos. 15mm lead and brass connections with brass unions, using 15mm lead pipe weighing not less than 1.60Kg per m, 2 nos. 15mm GM wheel valves, rubber plug and CP brass chains, 32mm CP brass waste of standard pattern, 32mm lead trap with access cap, soldering the joints complete, including cutting making good the walls, painting the brackets, waste connections, etc., with suitable paint two coats (Indian fitting –best quality)
3
3.00
Nos
45
Supplying, threading, laying and jointing 110mm diameter PVC pipe 4kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including trenching to a minimum depth of 50cm and refilling, etc, complete(External work)
1
25.00
25.00
m
46
Supplying, threading, laying and jointing 50mm diameter PVC pipe 6kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including
1
30.00
30.00
m
Sl.No
Description of Items
No
Length
25.00
Breadth
Height
Quantity
Unit
25.00
m
trenching to a minimum depth of 50cm and refilling, etc, complete(External work) 47
Supplying, laying and jointing 20mm nominal diameter PVC pipe 10kgf/cm2 (ISI marked) and specials such as tees, bends, elbows, etc, with clamp and solvent cement for jointing pipe including cutting and making good the walls, painting exposed face, etc, (Internal work)
1
48
Constructing Inspection Chamber of size 40x40cm or 40x60cm inside the sewer line up to a depth not exceeding 60cms with brick masonry in cement mortar 1:6, 23cm thick wall forming channels inside with cement concrete 1:3:6 using 40mm broken stone, plastering the inside and channels with cement mortar 1:3, 12mm thick with neat cement flushing coat including all earth work and foundation concrete 20cm thick, etc. complete
3
3.00
Nos
49
Supplying stainless steel ladder 3m height
1
1.00
No
50
Supplying stainless steel bench up to 1.50m height
4
4.00
No
51
Supplying stainless steel wheel barrow
3
3.00
No
52
Supplying pressure washer 200-330 KPA
1
1.00
No
53
Generator 10KV
1
1.00
No
54
Solar water heater 500 ltr
1
1.00
No
55
Chopper
1
1.00
No
56
Mixer grinder
1
1.00
No
57
Biogas plant
1
1.00
No
58
Biogas Conversion generator
59
Stainless steel Hooks
NA 15
15.00
2.4.2 Soak Pit Sl. No 1
Details of work
No
Length Breadth Height Quantity Unit (m) (m) (m) Earth work excavation in all classes of soil except hard rock and depositing on bank with initial lead up to 50 m and lift up to 1.5m including breaking, clods, watering, ramming and sectioning of spoil bank, etc complete. Foundation of pit 1.1 1.1 0.23 0.87 Pit
2
3
4
1.1
1.1
2.1
7.98
Total
8.85
Say
9.00
m3
Brick work in Cement mortar 1:6 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete For foundation
1.73
0.35
0.23
0.44
Above Foundation
1.73
0.23
2.1
2.62
Total
3.06
Say
4.00
RCC 1:11/2:3 using 20mm broken stone for pre-cast circular cover slab of soak pit including all for formwork, watering, curing,fixing charge, etc complete but excluding cost and labour for reinforcement. Total
0.98
0.98
0.075
m3
0.23
230.00
dm3
Reinforcement for RCC work, bent, tied and placed in position using TMT steel 8mm dia bar @12cm c/c 2bars for 1 slab
2
1.91
3.82
4 bars for 1 slab
4
1.79
7.16
4
1.67
6.68
4
1.55
6.2
4
1.42
5.68
4
1.3
5.2
4
1.18
4.72
4
1.05
4.2
4
0.9
3.6
4
0.8
3.2
4
0.65
2.6
4
0.5
2
3.1
1.91
6.00
Total weight
61.06
Total weight = 61.06m x 0.395kg/m
24.12
Add wastage and lap, 5%
1.21
Total
25.32
Kg
Say
0.30
qtl
Unit
Kg
2.4.3 Overhead Tank and Pump House Sl. No 1
Description of Items
No
Length
Breadth
Height
Quantity
Earth work excavation in hard soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking
1
3.8
3.8
1.5
21.66
Say
22.00
m3
Sl. No 2
3
4
5
6
7
8
9
10
11
Description of Items
No
Length
Breadth
Height
Quantity
Unit
Cement Concrete 1:4:8 using 40mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete
1
3.8
3.8
0.2
2.888
m3
3.00
m3
1
RCC 1:1 /2:3 using 20mm nominal size broken stone in columns footing including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. 1 RCC 1:1 /2:3 using 20mm nominal size broken stone in columns including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. 1 RCC 1:1 /2:3 using 20mm nominal size broken stone for beam including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. 1 RCC 1:1 /2:3 using 20mm nominal size broken stone for Bottom slab of Tank including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. 1 RCC 1:1 /2:3 using 20mm nominal size broken stone for Side wall of Tank including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement.
Say 1
3.6
3.6
0.25
Say 4
4000.00 0.3
0.3
6
Say 4x4
3
0.3
0.3
3.4
0.2
Say
2 2 Total Say
0.2 0.2
1.8 1.8
dm3
2.312 2500
3.4 3
dm3
4.32 4500
3.4
dm3
2.16 2500
Say 1
3.24
dm3
2.45 2.16 4.61 5000.00
dm3
1
RCC 1:1 /2:3 using 20mm nominal size 3 3.4 3.4 0.15 5.202 broken stone for Cover slab of Tank including Say 6000 all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. Providing Reinforcement for RCC work, bent, tied and placed in position using TMT steel Column footing – 3.24 m3 @ 70 Kg/m3 226.80
dm3
RCC column – 2.16 m3 @ 140 Kg/m3
302.40
Beam – 4.32 m3 @ 140Kg/m3
604.80
Bottom Slab – 2.31m3 @ 90 Kg/m3
207.90
Tank side wall – 4.61 m3 @ 100 Kg/m3
461.00
Cover slab – 5.2 m3 @ 120 Kg/m3
624.24
Total
2427.14
Kg
Say
25.00
Qtl.
Supplying, laying and jointing 32mm nominal diameter PVC pipe 10kgf/cm2 (ISI marked) and specials such as tees, bends, elbows, etc, with clamp and solvent cement for jointing pipe including cutting and making good the walls, painting exposed face, etc, (External work) Supplying, laying and jointing 32mm nominal diameter PVC pipe 10kgf/cm2 (ISI marked) and specials such as tees, bends, elbows, etc, with clamp and solvent cement for jointing pipe including cutting and making good the walls, painting exposed face, etc, (Internal work)
m
m
1
50
80.00
1
20
20.00
Sl. No 12
13
14
15
Description of Items
No
Supplying, laying and jointing 25mm nominal diameter PVC pipe 10kgf/cm2 (ISI marked) and specials such as tees, bends, elbows, etc, with clamp and solvent cement for jointing pipe including cutting and making good the walls, painting exposed face, etc, (External work) Supplying, threading, laying and jointing 20mm diameter PVC pipe 10kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including trenching to a minimum depth of 50cm and refilling, etc, complete(External work) Brick work in Cement mortar 1:5 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete - Pump house Anjili wood planed and framed work for frames for doors, windows, ventilators etc.
Quantity
Unit
1
60.00
m
1
45.00
m
4
Length
3
Breadth
0.23
Height
2.5
Say
6.90 7.00
2
2.15
0.1
0.075
0.03
1
1
0.1
0.075
0.01
m3
0.04 say 16
17
18
Supplying and fixing Anjili wood fully paneled shutters( as per standard drawings) to suit the door frames already fixed, inclusive of labour charges, for fixing all fittings but exclusive of cost of fittings etc complete Supplying And Fixing steel window of standard size using 20X90X3 mm thick 'Z' section for outer frames and shutter frames weighing 1.4 Kg/m providing 2 central vertical frame using J section weighing 1.6 Kg/m, providing window sashes 2 Nos for each shutter Plastering with Cement mortar 1:4 ,12mm thick one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete Deduction
1
1000.00 0.8
2.05
Say 0.5
20
21
Painting with synthetic enamel paint approved quality two coat including a priming coat to new wood works after rubbing with sand paper and cleaning surface including cost and conveyance for materials and labour charges, etc. complete - 2x1.125 Painting with synthetic enamel paint approved quality two coat including a priming coat to new iron work ,including cost and conveyance for materials and labour charges, etc. complete - 2x0.5 Say White Cement washing one coat including cost and conveyance for materials and labour charges and watering, curing etc. complete Qty. as per item no.18
dm2
0.45 0.5
m2
0.9
1
14.4
2.5
36.00
1
12.8
2.5
32.00
Total
68.00 0.9
2.1
1.89
Total Less deduction Say 19
200.00
1 Say
1
1
0.9
2.1
Say 1
m3
1.64
0.9
0.5
66.11 67.00
m2
4.25
m2
4.50
m2
0.45
4.50
m2
67.00
m2
Sl. No 22
23
Description of Items
No
Finishing new cement plastered walls with Emulsion water proof paint, two coats including cost and conveyance for materials and labour charges and watering, curing etc. complete - Qty. as per item no.18 Provide Bore well with submerged Pump and accessories
Length
Breadth
Height
1
Quantity
Unit
67.00
m2
1
No.
2.4.4 Anaerobic Tank Sl. No 1
Description of Items
No
Length
Breadth
Height
Quantity
Earth work excavation in hard soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking
1
9
5.4
2.85
138.51
2
Cement Concrete 1:4:8 using 40mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete
1
5.9
3.4
0.15
3.01
1
1.45
1.7
0.15
0.37
3
4
5
6
1
RCC 1:1 /2:3 using 20mm nominal size broken stone in columns footing including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. RCC 1:11/2:3 using 20mm broken stone for base and side wall of Tank including cost and conveyance of all materials, labour charges, hire for formwork, watering, curing, etc. complete but excluding cost of reinforcement.
1
Reinforced Cement Concrete 1:1 /2:3 using 20mm (nominal size) broken stone for covering pre-cast slab / perforated pre-cast slab including cost and conveyance of materials, labour charges and watering, curing , fixing charge, etc complete but excluding cost and labour for reinforcement.
Say
140.00
Total
3.38
Say
4.00
1
5.6
3.1
0.2
3.47
1
1.5
1.6
0.2
0.48
m3
m3
Total
3.95
m3
Say
4000.00
dm3
2
5.4
0.2
2.5
5.40
3
2.5
0.2
2.5
3.75
2
1.4
0.2
1.5
0.84
1
1.2
0.2
1.5
0.36
5
2.6
0.15
1.7
3.32
Total
13.67
m3
Say
14000.00
dm3
1
5.4
2.9
0.15
2.35
1
1.4
1.6
0.15
0.34
Total
2.69
m3
Say
3000
dm3
Providing Reinforcement for RCC work bent, tied and place in position using TMT steel Base slab – 4m3 @ 110 kg/m3
440.00
Side wall – 14m3 @ 120 kg/m3
1680.00
Covering slab – 3m3 @ 110 kg/m3
330.00
Total
2450.00
kg
Say
2.50
Qt
3
No.
7
Supplying and providing cast iron heavy duty man hole cover with frame size 60x60cm
3
8
Providing stainless steel screen inside
1
1.2
1.4
say 9
Unit
Plastering with Cement mortar 1:3 ,12mm thick to surface one coat floated hard and
1.68 1.7
1
5
2.5
12.5
1
15
2.5
37.5
m2
Sl. No
Description of Items
No
Length
trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete
2
Breadth
Height
Quantity
2.5
2.5
12.5
5
2.5
3.7
46.25
1
1.2
1.2
1.44
1
4.8
1.5
7.2
Total
117.39
Say
120.00
Unit
m2
2.4.5 Compound Wall and Gate Sl. No
Description of Items
No
Length
Breadth
Height
Quantity
1
Earth work excavation in hard soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking
1
260
0.6
0.6
93.6
2
3
4
5
6
7
Say
94.0
Random rubble masonry in cement mortar 1 260 0.6 0.6 93.6 1:6 for foundation and basement including 1 260 0.45 0.45 52.65 pointing simultaneously with same mortar and Total 146.25 providing necessary weep holes including cost and conveyance of materials and labour Say 147.00 charges, watering, curing etc complete Brick work in Cement mortar 1:5 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete Wall
1
260
0.23
2.00
119.60
Extra for pillar
90
0.35
0.12
2.00
7.56
Gate pillar
2
0.6
0.6
2.50
1.80
Total
128.96
Say
130.00
Plastering with Cement mortar 1:4 ,12mm thick one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete
2
260
2
1040
1
260
0.23
59.8
90x2
0.12
2
4.32
2
2.4
2.5
12
2
0.6
0.6
0.72
Unit
m3
m3
m3
Total
1116.84
Say
1120.00
m2
White Cement washing one coat including cost and conveyance for materials and labour charges and watering, curing etc. complete Same as item no.4 Finishing new cement plastered walls with cement water proof paint, two coats including cost and conveyance for materials and labour charges and watering, curing etc. complete Same as item no.4 Supplying and fixing M.S gate with 32mm GI pipe outer frame and 12mm Sq.rod vertical at 10 cm c/c and horizontal at 15cm c/c ,including all fittings like clamp and locking arrangement.
1120.00
m2
1120.00
m2
8.00
m2
1
4
2
2.4.6
Road and Parking Lot
Sl. No
Description of Items
No
Length
Breadth
Height
1
Sectioning upto 150mm on the surface of new road
1
14.00
5.00
70.00
1
30.00
10.00
300.00
Total 2
Quantity
370.00
Supplying 60mm graded metal (Proportion of 7:3 of 60mm and 36mm by volume) and stacking in standard heap for measurements including cost, conveyance, etc
1
130.00
4.10
0.10
53.30
1
30.00
10.10
0.10
30.30
Supplying and stacking 36mm hard granite broken stone in standard uniform heap for measurements
1
130.00
4.10
0.10
53.30
1
30.00
10.10
0.10
30.30
4
Supplying and stacking good hard gravelly red earth for blinding for measurements
1
130
4.1
5
Supplying hard blue granite broken stone 12mm size and stacking in standard uniform heap for measurements including cost, conveyance, etc, complete
1
130.00
1
30.00
6
Supplying hard blue granite broken stone 6mm size and stacking in standard uniform heap for measurements including cost, conveyance, etc, complete
1
130.00
4.10
7
Metalling the roadway 100mm spread thickness compacted to 75mm using departmental broken stone (graded in the ratio of 7:3 of 60mmand 36mm sizes)1m3/10m2 and departmental blinding materials (0.20m3/10m2 ), bed rolling, spreading broken stones to template, rolling dry to compaction from sides to central until the movement of broken stones cease, watering profusely and rolling until the fines cream up and fill the voids of the stones, then spreading the gravelly earth and sweeping in to the joints, watering and rerolling until the gravelly earth has worked in to all the crevices and only a thin coat of slurry remains, then take off the roller and allow to set to harden for 24 hours and rerolling next day until any deformity is rectified, including fencing, lighting, watching and maintaining the surface free of ruts for 15 days after completion as per IRC.2-1-2
1
130.00
4.10
533.00
1
30.00
10.10
303.00
Metalling the roadway 100mm spread thickness compacted to 75mm using 36mm departmental broken stone (1m3/10m2) and departmental blinding materials (0.15m3/10m2 ), spreading broken stones to template, rolling dry to compaction, watering profusely, and rolling until the fines cream up and fill the voids of the stones, then spreading the gravelly earth and sweeping in to the joints, watering and rerolling until the gravelly earth has worked in to all the crevices and only a thin coat of slurry remains, then take off the roller and allow to set to harden for 24 hours and rerolling next day until any deformity is rectified, including fencing, lighting, watching and maintaining the surface free of ruts for 15 days after completion as per IRC.2-1-2
1
130.00
4.10
533.00
1
30.00
10.10
303.00
3
8
Total
83.60
Total
m2
m3
83.60
m3
0.035
18.66
m3
4.10
0.10
53.30
10.10
0.10
30.30
Total
Total
Total
Unit
0.009
83.60
m3
4.80
m3
836.00
836.00
m2
m2
9
2.5
Providing 20mm Pre-mix chipping carpet over W.B.M. surface with departmental broken stone after thoroughly cleaning the base with wire brushes, bass brooms and applying a 2 priming coat of 7.50Kg of bitumen 10m and 3 spreading the hot pre-mix (formed of 0.27m of departmental 12mm metal and 12.96Kg of 2 bitumen per 10m ) rolling to dense surface, then spreading the seal coat (comprising of a 3 hot pre-mix of 0.09m of 6mm departmental 2 metal and 8.64Kg of bitumen per 10m ) again rolling including the cost of bitumen, oils and fuel, hire of bass brooms, camber board, roller and other machines, watching, lighting and other charges, etc complete (Total usage 2 of bitumen is 29.10Kg per 10m ) as per IRC.3-2-2
1
130.00
4.10
533.00
1
30.00
10.10
303.00
Total
836.00
RATE ANALYSIS AS PER 2010 SOR OF KERALA PWD Description of Items
Unit
1
Site clearance
LS
2
Earth work excavation in hard soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Labour 4.000
Man
Each
240.00
2.250
Man( 1 Boy= 0.75 man)
Each
180.00
960.00 405.00 1,365.00
3
111
Cement Concrete 1:4:8 using 40mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete Materials
m
0.95m3
40mm (nominal size) broken stone
m3
490.00
465.50
0.48m3
Sand
m3
1750.00
840.00
171kg
Cement
ton
4700.00
803.70
40mm (nominal size) broken stone
m3
246.00
33.70
0.48m
Sand
m
3
158.00
75.84
171kg
Cement
ton
234.00
40.01
32.50
0.95m3 3
-
-
Labour
-
0.100
Mason
Each
325.00
1.000
Man
Each
240.00
40.00
1.400
Woman
Each
240.00
336.00
Total RCC 1:11/2:3 using 20mm nominal size broken stone in columns footing including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement.
1501.50
3
Conveyance
4
m2
3,067.25
3373.98
Sl. No
Ref: to PWD/ PHED Data item
Quantity
0.02m2
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Cement Concrete 1:11/2:3 using 20mm (nominal size) broken stone
10dm3
49.86
49.86
Formwork for reinforced cement concrete in slab including wooden planks, joists, bamboo posts and labour for taking down after completion of work (hire and labour charge only)
10m2
3709.24
7.42
Total 5
RCC 1:11/2:3 using 20mm nominal size broken stone in columns including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement.
57.28
Amount with CP (Rs)
63.01
10dm3
Main data
0.14m2
Cement Concrete 1:11/2:3 using 20mm (nominal size) broken stone
10dm3
49.86
49.86
Formwork for reinforced cement concrete in slab including wooden planks, joists, bamboo posts and labour for taking down after completion of work (hire and labour charge only)
10m2
3709.24
51.93
8.01
Add 20% over the rate for items no. 132 for column Total 6
RCC 1:11/2:3 using 20mm nominal size broken stone for Plinth beam including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement.
109.80
120.78
3
10dm
Conside 1 m length of work Concrete = 1.00X0.23X0.23 = 52.9 dm3 Formwork = 2X1.00X.23 = 0.46 m2 Formwork required for 10 dm3 = 0.46 *10 /52.9 = 0.087 Main data 10 dm3
Cement Concrete 1:11/2:3
10dm3
52.14188
49.86
0.087 m2
Formwork
10 m2
3709.24
32.27 3.48
Add 10% over the rate for items no. 132 for beam
85.62 7
RCC 1:11/2:3 using 20mm nominal size broken stone for sunshade, Lintal and beam, including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement.
10dm3
Main data
0.11m2
Cement Concrete 1:11/2:3 using 20mm
10dm3
Formwork for reinforced cement concrete in slab including wooden planks, joists, bamboo posts and labour for taking down after completion of work (hire and labour charge only)
10m2
49.86 49.86 3709.24
40.80
94.18
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
4.00
Add 10% over the rate for items no. 132 for beam
104.14 94.67 8
RCC 1:11/2:3 using 20mm nominal size broken stone for slab including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. Sub data Consider 10mX10m area of slab Qty of CC Slab= 1x10.00x10.00x0.10=10m3 Total= 10m3= 10000dm3 Area of Formwork Slab= 1x10.00x10.00=100.00m2 Total = 100.00m2 Formwork for 10dm3 of CC =100.00x10/10000 =0.10m2 Main data 10dm3
Cement Concrete 1:1.5:3 using 20mm (nominal size) broken stone
10dm3
47.1092
0.10m2
Formwork for reinforced cement concrete in slab including wooden planks, joists, bamboo posts and labour for taking down after completion of work (hire and labour charge only)
10m2
3709.24
49.86 40.04
89.90 9
RCC 1:11/2:3 using 20mm broken stone for base and side wall of drain including cost and conveyance of all materials, labour charges, hire for formwork, watering, curing, etc. complete but excluding cost of reinforcement. Consider 60cmx50cm size of RCC drain with 15cm wall thickness
Consider 10m length of drain Sub data Consider 10m length of side drain Qty of CC Base of SD= 1x10.00x0.80x0.15=1.2m3 Side wall of SD=2x10.00x0.15x0.50=1.50 Total= 2.70m3= 2700dm3 Area of Formwork Side wall of SD=2x10.00x0.75=15.00m2
10dm3
98.89
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Side wall of SD=2x10.00x0.50=10.00m2 Total = 25.00m2 Formwork for 10dm3 of CC =25.00x10/2700 =0.096m2 Main data 10dm3
Cement Concrete 1:11/2:3 as per Sub data 4
10dm3
49.86
49.86
0.096m2
Formwork for reinforced cement concrete in slab as per Sub data 3(Consider 25%)
10m2
3709.24
8.90
58.77 10
Reinforced Cement Concrete 1:11/2:3 using 20mm (nominal size) broken stone for covering pre-cast slab / perforated pre-cast slab including cost and conveyance of materials, labour charges and watering, curing , fixing charge, etc complete but excluding an
64.64
10dm3
Consider RCC pre-cast slab 100cmx100cmx10cm Quanty of concrete = 3 1x1.00x1.00x0.10 = 0.1m Total = 100dm3 Area of form work = 3x1.00x0.1 = 2 0.3m Total = 0.30m2 Formwork for 10dm3 concrete=0.3x10/150= 0.02m2 Main data 3
10dm
0.02m2
3
Cement Concrete 1:11/2:3 as per Sub data No.2
10dm
Formworkas per Sub data No.3 (Consider 25%)
10m2
49.86 49.86 3709.24 18.55
Labour 0.010
Heavy load mazdoor for conveying and providing the slab in line and level (0.010HLM/10dm3)
Each
240.00
2.40
70.81 11
RCC 1:11/2:3 using 20mm nominal size broken stone for Vertical Drop slab including all for formwork, watering, curing, etc complete but excluding cost and labour for reinforcement. Consider 10m length of slab Sub data Consider 10m length of side slab Qty of CC Side wall of S=2x10.00x0.10x0.60=1.20
77.89
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Total= 1.2m3= 1200dm3 Area of Formwork Side wall of S=2x10.00x0.60=12.00m2 Total = 12.00m2 Formwork for 10dm3 of CC =12.00x10/1200 =0.10m2 Main data 10dm3
Cement Concrete 1:11/2:3 as per Sub data 4
10dm3
47.11
47.11
0.10m2
Formwork for reinforced cement concrete in slab as per Sub data
10m2
3709.24
35.61 82.72
12
90.99
Providing Reinforcement for RCC work, bent, tied and placed in position using TMT steel Materials
-
1q
TMT steel
q
4472.00
0.45kg
Iron wire for tying Grill(22g)
kg
70.00
472.00 31.50
Conveyance 1q
Tor steel
ton
234.00
23.40
Labour
-
1.000
Blacksmith for bending steel
Each
325.00
325.00
1.480
Men for tying steel and placing in position
Each
240.00
355.20 207.10
13
Filling and forming the basement with contractor's own good quality clean earth and conveyed from available sources with all lead and lift including all for consolidation
5727.81
10m3
Sub data for earthwork 56
Earth work excavation in ordinary soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking
10m3
711
Sub data for consolidation
0.35
Consolidation
10m3
Man
Each
240
84
10m3
711
711
1m3
158
10m3
84
Main data 10m3
Earth work excavation in ordinary soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking Conveyance
10m3
Good quality gravelly earth
10m3
Extra lead, if any
10m3
Consolidation
0 1580 0 84 2375
2612.5
Sl. No
Ref: to PWD/ PHED Data item
Quantity
14
Description of Items
Unit
Brick work in Cement mortar 1:5 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete
m3
Rate (Rs)
Amount without CP (Rs)
Materials 460Nos
Amount with CP (Rs)
-
Country Burnt bricks
1000 nos.
2500.00
1,150.00
0.24m
Dry sand
m3
1750.00
420.00
69kg
Cement
ton
4700.00
324.30
3
Conveyance
-
460Nos
Country Burnt bricks
1000 nos.
210.00
96.60
0.24m3
Dry sand
m3
158.00
37.92
69kg
Cement
ton
234.00
16.15
Labour
-
0.700
Brick Mason
Each
325.00
27.50
0.350
Man
Each
240.00
84.00
0.700
Woman
Each
240.00
168.00
10% extra labour LS
47.95
Hire charge for scaffolding
10.00 2,582.42
15
Cement Concrete 1:2:4 using 20mm (nominal size) broken stone for storm water drain including cost and conveyance of materials, labour charges and watering, curing etc complete but excluding all form work and reinforcement Consider 40cmx40cm size of CC drain with 15cm wall thickness Consider 10m length of drain Sub data for formwork Consider 10m length of side drain Qty of CC Base of SD= 1x10.00x0.70x0.15=1.05m3 Side wall of SD=2x10.00x0.15x0.40=1.20 Total= 2.25m3= 2250dm3 Area of Formwork Side wall of SD=2x10.00x0.55=11.00m2 Side wall of SD=2x10.00x0.40=8.00m2 Total = 19.00m2 Formwork for 10dm3 of CC =19.00x10/2250 =0.08m2 Sub data cc 1:2:4 Materials
-
2840.66
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
20mm (nominal size) broken stone
m
0..0045m
Sand
3.3kg
Cement
3
0.009m
3
Rate (Rs)
Amount without CP (Rs)
3
700.00
6.30
m
3
1750.00
7.88
ton
4700.00
15.51
Conveyance 3
0.009m
20mm (nominal size) broken stone 3
Amount with CP (Rs)
0.00 3
246.00
2.21
3
m
0..0045m
Sand
m
158.00
0.71
3.3kg
Cement
ton
234.00
0.77
Labour
0.00
0.00
Mason
Each
325.00
0.65
0.01
Man
Each
240.00
2.40
0.04
Woman
Each
240.00
8.40 44.83
Main data 10dm3
Cement Concrete 1:2:4 using 20mm (nominal size) broken stone for storm water drain
10dm3
44.83
44.83
0.08m2
Formwork for reinforced cement concrete in slab as per Sub data 3(Consider 25%)
10m2
3709.24
7.42
52.25 16
57.48
Flooring with cement concrete 1:4:8, using 40mm nominal size broken stone including cost and conveyance for materials and labour charges and watering Same as item no.3
17
Cement Concrete 1:11/2:3 using 20mm nominal size broken stone for leveling course
3,373.98 10dm3
Materials
-
0.009m3
20mm (nominal size) broken stone
m3
700.00
6.30
0..0045m3
Sand
m3
1750.00
7.88
4.32kg
Cement
ton
4700.00 20.30
Conveyance 0.009m3
20mm (nominal size) broken stone
m3
246.00 2.21
3
0..0045m
Sand
3
m
158.00 0.71
4.32kg
Cement
ton
234.00 1.01
Labour 0.002
Mason
Each
325.00
0.010
Man
Each
240.00
0.65 2.40 0.035
Woman
Each
240.00 8.40 49.86
54.85
Sl. No
Ref: to PWD/ PHED Data item
Quantity
18
Description of Items
Unit
Plastering with Cement mortar 1:4 ,12mm thick one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete
10m2
Rate (Rs)
Amount without CP (Rs)
Materials 0.15m3
Dry sand
Amount with CP (Rs)
m3
1750.00 262.50
54kg
Cement
ton
4700.00 253.80
Conveyance 3
0.15m
Dry sand
3
m
158.00 23.70
54kg
Cement
ton
234.00
12.64
Labour
-
0.900
Brick mason
Each
325.00
292.50
0.550
Man
Each
240.00
132.00
1.100
Woman
Each
240.00
64.00
Plastering with Cement mortar 1:3 ,12mm thick to surface one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete
10m2
1,241.14 19
Materials 3
3
0.14m
Dry sand
m
1750.00
245.00
66kg
Cement
ton
4700.00
310.20
Conveyance
-
0.14m3
Dry sand
m3
158.00
22.12
66kg
Cement
ton
234.00
15.44
Labour
-
0.900
Brick mason
Each
325.00
292.50
0.550
Man
Each
240.00
132.00
1.100
Woman
Each
240.00
264.00 1,281.26
20
10m2
Plastering with cement mortar 1:3 12 mm thick with neat cement flushing coat over including cost and conveyance for materials and labour charges and watering, curing etc. complete
10m2
Plastering with Cement mortar 1:3 ,12mm thick
10m2
1281.26
Materials
22kg
Cement
1365.25
1409.39
1,281.26 -
ton
4700.00
103.40
ton
234.00
5.15
Each
325.00
162.50
Conveyance 22kg
Cement Labour
0.500
Brick mason
-
1,552.31
1707.54
Sl. No
Ref: to PWD/ PHED Data item
21
754
Quantity
Description of Items
Unit
Steel works welded or fitted in built up section, truss and framed work with M.S angle or GI pipes etc. straightening, cutting welding, fabricating and hoisting, including applying a coat of iron primer. For slaughter house
Each
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Weight of one tabular frame = 105 kg=1.05qtl Calculation Length of 40mm dia (1x7.50)+(2x5.00) = 17.50 x 3.43 kg/m = 60. 00 kg
60.00
32mm dia (1x1.50)+ (2x1.00) = 3.50 x 2.74 kg/m = 9.59 kg
9.59
25mm dia (2x2.80)+ (2x1.40) = 8.40 x 1.50 kg/m = 12.60 kg
12.60
Guzate plate 18.06
(3x0.2x0.15)+ (6x0.15x0.15) = 0.23x 78.50 kg/m = 18.06 kg 5% wastage
5.01 105.05Kg
18.38m
40mm dia GI pipe (including 5% wastage)
m
154.00
2,830.52
3.68m
32mm dia GI pipe
m
128.00
471.04
8.82m
25mm dia GI pipe
m
110.00
970.20
18.96kg
10 mm thick M.S plate
Qtl
3600.00
682.56
LS
Conveyance of material
LS
50.00
50.00
3m2
Applying Iron primer
10m2
181.75
54.53
Labour for leveling 0.50
Blacksmith
Each
325.00
162.50
0.20
Heavy load mazdoor
Each
270.00
54.00
0.30
Fitter
Each
300.00
90.00
0.10
Head load
Each
270.00
27.00
Cutting pipe and plate
22
1.25
Blacksmith
Each
325.00
406.25
1.50
Heavy load mazdoor
Each
270.00
405.00
1.50
Welder for welding
Each
325.00
487.50
1.00
Heavy load mazdoor for assisting the welder
Each
270.00
270.00
LS
Hire charge for welding plant
100.00
100.00
LS
Current charges and welding road
50.00
50.00
1.00
Heavy load mazdoor for hoisting and placing
270.00
270.00
Total
7,381.10
Each
8119.20
Steel works welded or fitted in built up section, truss and framed work with M.S angle or GI pipes etc. straightening, cutting welding, fabricating and hoisting, including applying a coat of iron primer. for Lairage 3m length tress - Length for 3m
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
6.3m
25mm dia GI pipe, including 5% wastage
m
110.00
693.00
0.93kg
M.S Rod,12mm dia
Qtl
3250.00
3,022.50
LS
Conveyance
LS
25.00
25.00
0.38m2
Priming coat
10m2
181.75
6.91
1.05 Qtl
333.50
42.50
1.05 Qtl
811.25
103.38
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
{(2x3.00)+ 5% wastage}=6.30, 6.3m 25 dia GI pipe 1.5kg/m=9.45kg (12x0.35)+5% wastage=4.41, 4.41 kg MS rod 0.89kg/m =3.93 9.45+3.93=13.38 kg Labour charge Leveling 13.38kg
previous item no.20 Cutting
13.38kg
previous item no.20 Welding
1.50
Welder for welding
E
325.00
487.50
1.00
Heavy load mazdoor for assisting the welder
E
270.00
270.00
LS
Hire charge for welding plant
100.00
100.00
LS
Current charges and welding road
50.00
50.00
1.00
Heavy load mazdoor for hoisting and placing
270.00
270.00
LS
Hire charge for pulling rope
10.00
10.00
23
Each
For 3m
5,080.78
Say for 1m
1,693.59
1862.95
Purloin 32mm GI Pipe, cutting, laying etc complete for 30m 31.5m
32mm dia GI pipe
m
128.00
4,032.00
3.5m2
priming coat
10m2
181.75
63.61
LS
Conveyance
LS
30.00
30.00
Labour 2.0
Blacksmith
E
325.00
650.00
1.0
Heavy load mazdoor
E
270.00
270.00
Total
5,045.61
For 1m 24
168.19
Steel work in R.S Joist (in single section) cutting, hoisting and fixing in position including applying a coat iron primer etc., complete(Supply Channel section for providing pulley block)
T
1.05 T
R.S Joist including 5% wastage
Qtl
9m2
Iron primer one coat
10m2
4200.00
44,100.00
181.75
163.58
185.01
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Labour
25
1.00
Blacksmith
E
325.00
1.00
Fitter
E
300.00
300.00
10.00
Heavy load mazdoor
E
270.00
2,700.00
10.00
Man mazdoor
E
240.00
2,400.00
LS
Hire charge for chain and pulley block, etc
LS
75.00
75.00
Total
50,063.58
SR453
Roofing with powder coated GI tile profile sheets with bolts and nuts and bitumen washer including necessary overlap of 150mm at ends etc. complete
325.00
55069.93
10m2
Materials 11.5m2
Powder coated sheet
m2
280.00
3,220.00
LS
conveyance from Ernakulam
LS
50.00
50.00
36Nos
Stud with washer
E
5.00
180.00
520.00
Labour 1.60
Carpenter
E
325.00
1.60
Man mazdoor
E
240.00
384.00 4,354.00
26
4789.40
Powder coated sheet Ridge coping for sheet roofing for 30m 15.75
Powder coated sheet
1m2
LS
conveyance
LS
280.00
4,410.00
30.00
30.00
120.00
Stud with washer
1.50
Carpenter
E
5.00
600.00
E
325.00
1.50
Man mazdoor
487.50
E
240.00
360.00
Total
5,887.50
For 1m
27
196.25
215.88
Welding by electric plant Details for 30m 180Nos
Welding Rods 8g
100 Nos
420.00
756.00
3.75
Welder
LS
Current charges and hire for welding plant
E
325
1,218.75
LS
200
200.00
Total
2,174.75
For 1m
m
Supplying and fixing stainless steel grating to internal drains
1m2
1m2
Cost for grating
1m2
3600.00
3,600.00
0.20
mazdoor
Each
270.00
54.00
28
72.49
3,654.00 29
Marble slab flooring to slaughter floor and dressing area using 16mm thick white super quality marble slab in cement mortar 1:3
79.74
4019.40
Sl. No
Ref: to PWD/ PHED Data item
Quantity
506
Description of Items
Unit
Plastering with Cement mortar 1:3 ,12mm thick
10m
Rate (Rs)
2
1281.26
2
1281.26
Amount without CP (Rs)
Amount with CP (Rs)
1,281.26
Main data Materials 2
10m
Cement plastering using cement mortar 1:3, 12mm thick
10m
10m2
Marble slab
m2
0.33kg
White cement
kg
15.00
15.00
1.00
Carborandom stone
E
120.00
120.00
0.25kg
Oxalic acid
kg
80.00
20.00
0.10kg
Mansion polish
kg
200.00
20.00
50.00
50.00
1,281.26 1100.00
conveyance for marble
11,000.00
Labour 1.00
Brick mason
E
325.00
325.00
0.88
Man mazdoor
E
240.00
10.00
Polishing 4.00
Polisher (special mazdoor)
E
255.00
1,020.00
2.00
Men
E
240.00
480.00
2day
Hire charge for Polishing machine
day
200.00
400.00
LS
Sundries
LS
30.00 14,971.26
30
506
16,468.39
2
Supplying and paving good quality Vitrified tiles 60x60 cm size white colour over 12mm thick cement mortar 1:3 one coat including cost and conveyance of materials and labour charges, watering, curing, etc. complete
10m
Plastering with Cement mortar 1:3 ,12mm thick
10m2
1281.26
1,281.26
1281.26
1,281.26
Main data Materials 10m2
Cement plastering using cement mortar 1:3, 12mm thick
10m2
10m2
Vitrified tiles
m2
570.00
5,700.00
0.33kg
White cement
kg
15.00
15.00
50.00
50.00
325.00
Conveyance Labour 1.000
Brick mason
325.00
0.875
Man mazdoor
240.00
210.00 7,581.26
31
Dadoing wall with best glazed white or coloured tiles 7.5mm thick or nearest in 12mm cement mortar 1:3 and pointing with coloured cement
1m2
Main data Materials 1m2
Ceramic tiles Add extra 5% for cornices, angle etc
1m2
320.00
320.00
16.00
16.00
8,339.39
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
0.48kg
cement
T
Conveyance
Rate (Rs)
Amount without CP (Rs)
4700.00
2.26
10.00
10.00
Amount with CP (Rs)
Labour 0.900
Brick mason
325.00
292.50
0.500
Man mazdoor
240.00
120.00
LS 1m2
LS Plastering with Cement mortar 1:3 ,12mm thick
10m2
5.00
5.00
1281.26
128.13 893.88
32
Providing fabricating and fixing Aluminium Single Door shutter using Aluminium powder coated hollow section of size 100x44.5x1.5mm (9245) for bottom, end vertical and top horizontal section of size 50x44.50x1.2mm (9258) and middle horizontal section of size 50x50x2mm (9286) and fixing 12mm thick prelaminated particle board at bottom and 5.5mm thick olaine glass at top including hinges, handle, glazing clips, rubber beading, Door closer, Locking arrangements. etc. Area= 1x0.80x2.10 =1.68m2 100x44.5x1.2 section (9246) Bottom - 1x0.80 =0.80 5% wastage = 0.04 =0.84 x 1.504kg/m =1.263 kg
1.263
50x50x1.2mm (9286) Middle - 1x0.70 = 0.70 5% wastage = 0.04 0.888kg/m = 0.657kg
0.657 =0.74 x 4.868
50x50x1.2mm (9258) Top and Side - 1x0.80 = 0.80 2 x2.05 =4.10 5% wastage = 0.24 =5.14 x 0.947kg/m = 4.868 kg Glazing clip 2x3.60 = 7.20 2x3.10 = 6.20 wastage =0.67 x 0.176 kg/m = 2.476kg
2.476 5% =14.07m
2mm thick angle 12 x 0.05 = 0.60 wastage=0.03 0.30 = 0.19kg
0.189
5% 0.63 x
9.453 9.453kg
Powder coated Aluminium
kg
215.00
2,032.40
0.81m2
12mm particle board
m2
712.00
576.72
0.63m2
5.5mm thick plain glass
m2
360.00
226.80
LS
Rubber beading
LS
20.00
20.00
2.0
Hinges
E
50.00
100.00
2.0
Door handle
E
69.00
138.00
1.0
Door closser
E
1100.00
1,100.00
1.0
Door lock
E
625.00
625.00
983.27
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
50.0
25mm steel screws
10
7.50
375.00
LS
Conveyance
LS
30.00
30.00
Rate (Rs)
Amount without CP (Rs)
25% fabrication charge
Amount with CP (Rs)
1,305.98 6,529.89
Say 33
7182.88 / 1.68
Anjili wood planed and framed work for frames for doors, windows, ventilators etc.
m2
7182.88 4275.53
3
10dm
Materials 3
10.5dm
Anjili wood scantlings allowing 5% wastage
3
10dm
555.61
583.40
Labour 0.220
Carpenter
Each
325.00
0.100
Man
Each
240.00
71.50 24.00 678.90
34
Supplying and fixing Anjili wood fully panelled shutters( as per standard drawings) to suit the door frames already fixed, inclusive of labour charges, for fixing all fittings but exclusive of cost of fittings etc complete
746.78
10dm2
Materials 3
3.19dm
Anjili wood scantiling with 5% wastage
10dm3
555.61
177.24
125.45
Labour 0.386
Carpenter
Each
325.00
0.028
Man
Each
240.00
6.72 309.41
35
Supplying And Fixing steel window of standard size using 20X90X3 mm thick 'Z' section for outer frames and shutter frames weighing 1.4 Kg/m providing 2 central vertical frame using J section weighing 1.6 Kg/m, providing window sahes 2 Nos for each shutter Main Data Material Charges 35.560
MS Section @ Rs 40.84 (as per Sub data 2)
Kg
40.48
1,439.47
23.140
MS Rod kg @ Rs 38.90 (as per Sub data 2)
Kg
38.90
900.15
17.400
Aluminium channel @ Rs 20 / m
m
20.00
348.00
375.00
795.00
25.00
75.00
2
2.120
Plane Glass 3 mm
m
3.000
Window handles @ Rs25/no.
Nos
LS Cost for Screws
15.00
Labour Charges 58.700
Conveyance @ Rs 187.20 / ton
Kg
187.20
10.99
340.35
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
55.910
Fabrication Charges
Qtl
0.750
Carpenters for fixing 0.37
2.100
Rate (Rs)
Amount without CP (Rs)
3686.11
2,060.90
Each
325.00
243.75
Each
240.00
88.80
0.75
Each
325.00
243.75
0.37
Each
240.00
88.80
138.65
29.12
Painting Primer (as per Sub data 3)
2
10 m
LS for Glass conveyance
Amount with CP (Rs)
25.00 6,363.72
2
For 1 m
36
SR763
10dm2
3,030.34
Supplying And Fixing Rolling shutter of approved make and painted with a priming coat of iron primer, made of 80x1.25 mm M.S laths interlocked together through their entire length and jointed together at he end by the end locks mounted on speciallly, designed pipe shaft, with brackets, side guides and arrangements for inside and outside locking with push and pull operation etc complete
10dm2
Rolling shutter
m2
Conveyance
Ls
1400.00
140.00
5.00
5.00
3333.38
Labour 0.030
Fitter
E
270.00
8.10
0.030
man mazdoor
E
240.00
7.20
0.030
Mason
E
325.00
9.75 170.05
37 1m
Supplying and fixing Top cover for Rolling shutter
1m
Cost of top cover
m
conveyance
LS
450.00
450.00
5.00
5.00
187.06
Labour 0.030
Fitter
E
270.00
8.10
0.030
man mazdoor
E
240.00
7.20
0.030
Mason
E
325.00
9.75 480.05
38
White Cement washing one coat including cost and conveyance for materials and labour charges and watering, curing etc. complete
10m2
Materials 1.48kg
White Cement
kg
15.00
22.20
LS
Sundries including brush, etc
LS
5.00
5.00
ton
234.00
0.35
Each
240.00
28.80
Conveyance 1.48kg
White Cement Labour
0.120
Special man mazdoor
528.06
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
0.090
Man(1 Boy= 0.75 Man)
Each
Rate (Rs)
Amount without CP (Rs)
240.00
21.60 77.95
39
Finishing new cement plastered walls with Plastic Emulsion water proof paint, two coats including cost and conveyance for materials and labour charges and watering, curing etc. complete
Amount with CP (Rs)
85.74
10m2
Materials 1.15kg
Plastic Emulsion paint
kg
180.00
207.00
LS
Brushes and sundries,etc.
LS
5.00
5.00
270.00
310.50
Labour 1.15
Painter
Each
Painting with synthetic enamel paint approved quality one coat including a priming coat to new wood works including cost and conveyance for materials and labour charges, etc. complete
10m2
Painting priming coat on new wood works after rubbing with sand paper and cleaning surface including cost and conveyance for materials and labour charges, etc. complete
10m2
190.25
190.25
162.00
86.30
5.00
5.00
270.00
297.00
522.50 40
SR612
10m2
574.75
Materials 1.15L
Synthetic enamel paint
L
LS
Brushes and sundries,etc.
LS
Labour 1.100
Painter
Each
678.55 41
746.41
Painting with synthetic enamel paint approved quality two coat including a priming coat to new iron work ,including cost and conveyance for materials and labour charges, etc. complete Painting priming coat on new iron work after rubbing with emery paper and cleaning the surface including cost and conveyance for materials and labour charges, etc. complete
10m2
181.75
181.75
162.00
186.30
5.00
5.00
270.00
297.00
Materials 1.15L
Synthetic enamel paint
litres
LS
Sundries including brush, etc
LS
Labour 1.100
Painter
Each
670.05 42
737.06
Painting with synthetic enamel paint two coat on Rolling shutter using approved quality paint as specified, one coat Same as Item No.38
737.06
Sl. No
Ref: to PWD/ PHED Data item
Quantity
43
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Supplying and Fixing Europian type, water closet (Earthern ware white best quality) with p or S trap, using duro-plastic seat and cover and C.P brass hinges with rubber buffers,1.5 liter white enamelled PVC low level flushing cistern with fittings and brackets, including cutting and making good the walls and floors etc. 1.0
White glazed earthernware European type W.C pan
E
634.00
634.00
1.0
Duroplastic seat and lid with CP brass hinges and rubber buffers
E
311.00
311.00
1.0
PVC flushing cistern with fitting
E
753.00
753.00
1.0
15mm PVC connecter
E
44.00
44.00
1.0
Wheel GM valve
E
155.00
155.00
LS
Sundries etc
LS
10.00
10.00
4.0kg
Cement
T
4700.00
18.80
0.50
Plumber
E
325.00
162.50
0.50
Mason
E
325.00
162.50
1.00
Man
E
240.00
240.00 2,490.80
44
Supplying and fitting 550x400mm or nearest size wash hand basin of white glazed earthenware (Indian make- best quality) with C.I brackets, a pair of 15mm C.P. brass pillar taps and 2 nos. 15mm lead and brass connections with brass unions, using 15mm lead pipe weighing not less than 1.60Kg per m, 2 nos. 15mm GM wheel valves, rubber plug and CP brass chains, 32mm CP brass waste of standard pattern, 32mm lead trap with access cap, soldering the joints complete, including cutting making good the walls, painting the brackets, waste connections, etc., with suitable paint two coats (Indian fitting –best quality) Materials 1No
550x400mm basin
1No
480.00
480.00
2Nos
15mm CP pillar tap
1No
242.00
484.00
2Nos
15mm GM wheel valve
1No
188.00
376.00
2Nos
15mm lead and brass connections with brass unions
1No
97.00
194.00
1No
32mm CP brass waste with chain and plug
1No
6.00
6.00
1No
32mm dia. CP lead trap with unions
1No
165.00 165.00
1No
CI brackets
LS
Sundries such as T.W. plugs, screws, red lead, etc.
2.00Kg
cement
1No
T
55.00
55.00
4.50
4.50
4700.00
9.40
2739.88
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Labour 0.500
Plumber / Fitter
Each
325.00
162.50
0.500
Mason
Each
325.00
162.50
1.000
Man mazdoor
Each
240.00
240.00 2,338.90
45
2572.79
Supplying, threading, laying and jointing 110mm diameter PVC pipe 4kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including trenching to a minimum depth of 50cm and refilling, etc, complete(External work) Consider 30m Materials 30m
110mm PVC pipe (4kgf/cm2-ISI marked)
m
130.00
Add PVC specials 5% LS
Solvent cement, etc
3,900.00 195.00
LS
30.00
Labour Labour 50% of GI pipe 0.750
Fitter
Each
270.00
202.50
0.750
Man
Each
240.00
180.00
3.000
Man for trenching and refilling
Each
240.00
720.00
LS
Conveyance of pipe
LS
15.00 5,242.50
Cost for 1m 46
174.75
192.23
Supplying, threading, laying and jointing 50mm diameter PVC pipe 6kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including trenching to a minimum depth of 50cm and refilling, etc, complete(External work) Consider 30m Materials 30m
50mm PVC pipe (6kgf/cm2-ISI marked)
m
38.00
Add PVC specials 5% LS
Solvent cement, etc
1,140.00 57.00
LS
20.00
Labour Labour 50% of GI pipe 0.500
Fitter
Each
270.00
135.00
0.500
Man
Each
240.00
120.00
3.000
Man for trenching and refilling
Each
240.00
720.00
LS
Conveyance of pipe
LS
10.00 2,202.00
Cost for 1m
73.40
80.74
Sl. No
Ref: to PWD/ PHED Data item
Quantity
47
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Supplying, laying and jointing 20mm nominal diameter PVC pipe 10kgf/cm2 (ISI marked) and specials such as tees, bends, elbows, etc, with clamp and solvent cement for jointing pipe including cutting and making good the walls, painting exposed face, etc, (Internal work) Consider 30m Materials 30m
20mm PVC pipe (10kgf/cm2-ISI marked)
m
11.00
LS
30.00
30.00
Add PVC specials 15% LS
Clamps, solvent cement cement, cement, sand, paint, etc
330.00 49.50
1.00
Labour 1.000
Fitter
Each
210.00
270.00
1.000
Man
Each
168.00
240.00
LS
Conveyance of pipe
LS
10.00 929.50
Cost for 1m
30.98
48
Supplying stainless steel lader 3m height
Each
7000.00
49
Supplying stainless steel bench up to 1.50m height
Each
10000.00
50
Supplying stainless steel wheel barow
Each
10000.00
51
Supplying pressure washer 200-330 KPA
Each
150000.00
52
Dispersion Trench
Each
22000.00
53
Solar water heater 500 ltr
54
Chopper
55
Mixer grinder
40000.00
56
Biogas plant
5000000.0 0
57
Biogas Conversion generator
58
Supplying and fixing M.S gate with 32mm GI pipe outer frame and 12mm Sq.rod vertical at 10 cm c/c and horizontal at 15cm c/c ,including all fittings like clamp and locking arrangement.
90000.00 25000.00
NA
32mm GI pipe16m+5% wastage 16.8x2.74kg/m=46.03 12mm Sq rod 2x19x2.0=76.00 2x13x2.00 =52.00 add 5% wastahe =6.00 Total =134.00 x 1.13 kg/m =151.42 kg Total 197.45kg Sub data for grill work 100Nos
welding rod 8g
34.08
100
420.00
420.00
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
3.5m2
Iron primer
10m2
Rate (Rs)
Amount without CP (Rs)
181.75
63.61
Amount with CP (Rs)
Labour 2.500
Blacksmith for leveling
E
325
812.50
1.500
Blacksmith for cutting
E
325
487.50
1.000
Head load mazdoor
E
270
270.00
1.000
welder
E
325
325.00
1.000
Heavy load mazdoor
E
270
270.00
2.500
Blaksmith
E
325
812.50
LS
Conveyance
LS
75
75.00
LS
Hire charge for welding plant
LS
100
100.00
LS
Sundries
LS
50
50.00 3686.11
Main data 16.8m
32mm GI pipe
m
128
2150.40
151.42kg
12mm Sq rod
Qtl
3250
4921.15
197.45kg
steel conveyance
T
324
63.97
197.45kg
Grill work
Qtl
3686.11
7278.23
4.000
M.S clamp
E
100
400.00
LS
Locking arrangement
LS
500
500.00
288dm3
CC 1:2:4 for fixing clamp
10dm3
44.83
1291.17
1.000
mason
E
325
325.00
1.000
Man
E
240
240.00
For 8m2
17169.92
Hence for 1m2 59
2146.24
Brick work in Cement mortar 1:6 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete Materials 460Nos 3
Country Burnt bricks
1000n os. 3
2500.00 1,150.00
0.24m
Dry sand
m
1750.00
58kg
Cement
ton
4700.00
420.00 272.60 Conveyance 460Nos
Country Burnt bricks
1000n os.
210.00
0.24m3
Dry sand
m3
158.00
58kg
Cement
ton
234.00
96.60 37.92 13.57
Labour 0.700
Brick Mason
Each
325.00
227.50
0.350
Man
Each
240.00
84.00
0.700
Woman
Each
240.00
168.00
2360.86
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
RCC 1:11/2:3 using 20mm broken stone for pre-cast circular cover slab of soak pit including all for formwork, watering, curing, fixing charge, etc complete but excluding cost and labour for reinforcement.
10dm
Rate (Rs)
Amount without CP (Rs)
2,470.19 60
Amount with CP (Rs)
2717.21
3
Consider RCC slab of diameter 196cm and thickness 7.50cm Sub data Qty of CC Qty of CC = 3.14x0.98x0.98x0.075 = 3 3 0.226m = 226dm Area of Formwork Area of Formwork=2x3.14x0.98x0.075=0.46 2 2m Formwork for 10dm3 =0.462m2 x10/226=0.020m2 Sub data for formwork 132
Formwork for reinforced cement concrete in slab including wooden planks, joists, bamboo posts and labour for taking down after completion of work (hire and labour charge only)
10m2
3709.24
Sub data for CC Cement Concrete 1:11/2:3 using 20mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete but excluding all form work and reinforcement
122
10dm3
47.11
47.11
47.11
1.85
Main data 3
10dm
Cement Concrete 1:11/2:3 using 20mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete but excluding all form work and reinforcement
10dm3
0.02m2
Formwork for reinforced cement concrete in slab including wooden planks, joists, bamboo posts and labour for taking down after completion of work (hire and labour charge only) (Consider 25%)
10m2
3709.24
0.010
Man for fixing the slab in line and level
Each
168.00 2.40 51.36
61
Supplying, threading, laying and jointing 32mm diameter PVC pipe 10kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including trenching to a minimum depth of 50cm and refilling, etc, complete(External work) Consider 30m
1m
56.50
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Materials 30m
32mm PVC pipe (10kgf/cm2-ISI marked)
m
32.00
LS
15.00
15.00
162.50
Add PVC specials 5% LS
Solvent cement, etc
960.00 48.00
Labour Labour 50% of GI pipe 0.500
Fitter
Each
325.00
0.500
Man
Each
240.00
120.00
3.000
Man for trenching and refilling
Each
240.00
720.00
LS
Conveyance of pipe
LS
10.00 2,035.50
Cost for 1m 62
Supplying, laying and jointing 32mm nominal diameter PVC pipe 10kgf/cm2 (ISI marked) and specials such as tees, bends, elbows, etc, with clamp and solvent cement for jointing pipe including cutting and making good the walls, painting exposed face, etc, complete.(Internal work)
67.85
74.64
1m
Consider 30m Materials 30m
32mm PVC pipe (10kgf/cm2-ISI marked)
m
32.00
LS
45.00
45.00
Add PVC specials 15% LS
Clamps, solvent cement cement, cement, sand, paint, etc
960.00 144.00
Labour Labour 50% of GI pipe 1.500
Fitter
Each
325.00
487.50
1.500
Man
Each
240.00
360.00
LS
Conveyance of pipe
LS
10.00 2,006.50
Cost for 1m 63
Supplying, threading, laying and jointing 25mm diameter PVC pipe 10kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including trenching to a minimum depth of 50cm and refilling, etc, complete(External work)
66.88 1m
Consider 30m Materials 30m
25mm PVC pipe (10kgf/cm2-ISI marked)
m
15.00
LS
10.00
10.00
325.00
121.88
Add PVC specials 5% LS
Solvent cement, etc
450.00 22.50
Labour Labour 50% of GI pipe 0.375
Fitter
Each
73.57
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
0.375
Man
Each
240.00
90.00
3.000
Man for trenching and refilling
Each
240.00
720.00
LS
Conveyance of pipe
Rate (Rs)
Amount without CP (Rs)
LS
Amount with CP (Rs)
10.00 1,424.38
Cost for 1m 64
Supplying, threading, laying and jointing 20mm diameter PVC pipe 10kgf/cm2 (ISI marked) with fittings such as tees, bends, elbows, etc, including trenching to a minimum depth of 50cm and refilling, etc, complete(External work)
47.48
52.23
1m
Consider 30m Materials 30m
20mm PVC pipe (10kgf/cm2-ISI marked)
m
11.00
LS
10.00
10.00
81.25
Add PVC specials 5% LS
Solvent cement, etc
330.00 16.50
Labour Labour 50% of GI pipe 0.250
Fitter
Each
325.00
0.250
Man
Each
240.00
60.00
3.000
Man for trenching and refilling
Each
240.00
720.00
LS
Conveyance of pipe
LS
10.00 1,227.75
Cost for 1m 65
507
Plastering with Cement mortar 1:4 ,12mm thick one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete
40.93
45.02
2
10m
Materials 0.15m3
Dry sand
m3
1750.00
262.50
54kg
Cement
ton
4700.00
253.80
Conveyance 0.15m3
Dry sand
m3
158.00
23.70
54kg
Cement
ton
234.00
12.64
Labour 0.900
Brick mason
Each
325.00
292.50
0.550
Man
Each
240.00
132.00
1.100
Woman
Each
240.00
264.00 1,241.14
1365.25
Sub Data 1
51
Earth work excavation in ordinary soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including breaking. clods, watering, ramming and sectioning of spoil bank, etc complete.
3
10m
Labour 1.100
Man
Each
240.00
264.00
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
2.250
Man( 1 Boy= 0.75 man)
Each
Rate (Rs)
Amount without CP (Rs)
180.00
Amount with CP (Rs)
405.00 669.00
2
122(a)
Cement Concrete 1:1.5:3 using 20mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete but excluding all form work and reinforcement
10dm3
-
Materials 3
0.009m
3
700.00
6.30
m
3
1750.00
7.88
ton
4700.00
20.30
20mm (nominal size) broken stone
m
0..0045m
Sand
4.32kg
Cement
3
Conveyance 3
0.009m
3
246.00
2.21
3
20mm (nominal size) broken stone
m
0..0045m
Sand
m
158.00
0.71
4.32kg
Cement
ton
234.00
1.01
Each
325.00
3
Labour 0.002
Mason
0.65
0.010
Man
Each
240.00
0.035
Woman
Each
240.00
2.40 8.40 49.86 3
132
Formwork for reinforced cement concrete in slab including wooden planks, joists, bamboo posts and labour for taking down after completion of work(hire and labour charge only)
10m2
Materials 30mm thick mango or jungle wood planks and jungle wood joists 100mmx17mm at 60cm intervals 320dm3/4
Mango or Jungle wood planks(Taking that the materials can be used 4 times)
10dm3
228dm3/8
Mango wood joists and cleat etc.(Taking that the materials can be used 8 times)
10dm3
146.88
418.61
9Nos/6
Bamboos(Taking that the materials can be used 6 times)
Each
105.00
157.50
[
Spike and wire nails
kg
55.00
55.00
LS
Coir
LS
3.10
3.10
146.88
Labour
1,175.04
-
4.000
Carpenters for fitting up forms and taking downafter completion
Each
325.00
1,300.00
2.500
Man
do
240.00
600.00
Anjili wood scantiling
10dm3
3,709.24 4
301(a)
735.90
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Materials 3
14.4dm
Anjili log
3
m
36000.00
Conveyance 3
14.4dm
Anjili log
518.40 -
3
m
126.00
1.81
Labour
-
0.020
Man to put log in position and to assist Sawers
Each
240.00
4.80
0.330
sawing (@ 4.3 sawers/ 10m2 sawing)
10m
2
1290.00
42.57 567.58
Deduct 3
3.8dm
3
Cost of outer slabs at 25% log value
10dm
Mango wood scantiling
10dm
31.50
11.97 555.61
5
301(b)
3
Materials 3
14.4dm
m
3
7200.00
103.68
m3
126.00
1.81
Man to put log in position and to assist Sawers
Each
240.00
4.80
sawing (@ 4.3 sawers/ 10m2 sawing)
10m
2
1290.00
42.57
Mango log Conveyance
14.4dm3
Mango log Labour
0.020 2
0.33m
152.86 Deduct 3
3.8dm
3
Cost of outer slabs at 25% log value
10dm
Painting priming coat on new wood works after rubbing with sand paper and cleaning surface including cost and conveyance for materials and labour charges, etc. complete
10m
15.75
5.99 146.88
6
603
2
Materials 0.850
Wood primer
litre
85.00
72.25
LS
Sundries including brushes, sand paper, soap and putty etc
LS
10.00
10.00
Labour 0.400
Painter
Each
270.00
108.00 190.25
7
604
Painting priming coat on new iron work after rubbing with emery paper and cleaning the surface including cost and conveyance for materials and labour charges, etc. complete
2
10m
Materials 0.75L
Iron primer
litre
85.00
63.75
LS
Sundries including brushes, emery paper, soap etc
LS
10.00
10.0
Labour
-
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
0.400
Painter
Each
Rate (Rs)
270.00
Amount without CP (Rs)
Amount with CP (Rs)
108.00 181.75
8
123
Cement Concrete 1:3:6 using 20mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete
10dm3
Materials 3
0.009m
20mm (nominal size) broken stone
m3
700.00
6.30
0..0045m
Sand
m3
1750.00
7.88
2.16kg
Cement
ton
4700.00
10.15
20mm (nominal size) broken stone
m3
246.00
2.21
0..0045m
Sand
m3
158.00
0.71
2.16kg
Cement
ton
234.00
0.51
3
Conveyance 3
0.009m
3
-
Labour
-
0.002
Mason
Each
325.00
0.65
0.010
Man
Each
240.00
2.40
0.035
Woman
Each
240.00
8.40 39.21
9
274
Random rubble masonry in cement mortar 1:6 for foundation and basement including pointing simultaneously with same mortar and providing necessary weep holes including cost and conveyance of materials and labour charges, watering, curing etc complete
43.13
m3
Materials 3
1m
Blasted rubble 3
3
270.00
270.00
3
m
0.3m
Dry sand
m
1750.00
525.00
72kg
Cement
ton
4700.00
338.40
m3
246.00
246.00
3
Conveyance 1m3
Blasted rubble 3
0.3m
Dry sand
m
158.00
47.40
72kg
Cement
ton
234.00
16.85
227.50
Labour 0.700
Rubble Mason
Each
325.00
0.350
Man
Each
240.00
84.00
0.700
Woman
Each
240.00
168.00
Constructing Inspection Chamber of size 40x40cm or 40x60cm inside the sewer line up to a depth not exceeding 60cms with brick masonry in cement mortar 1:6, 23cm thick wall forming channels inside with cement concrete 1:3:6 using 40mm broken stone, plastering the inside and channels with cement mortar 1:3, 12mm thick with neat cement flushing coat including all earth work and foundation concrete 20cm thick, etc. complete
Each
1,923.15 10
2115.46
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Qty of earth work in all classes of 3 soil = 1x0.50x0.40x0.80 = 0.16m Qty of CC 1:3:6= 1x0.50x0.40x0.20= 0.04m3 Qty of CC 1:3:6 for channels = 3 1x0.50x0.15x0.15 = 0.011m Qty of CC total = 0.04+0.011= 3 3 0.051m =51dm Qty of brick work in CM 1:6 = 1x2.60x0.20x0.60 = 0.31m3 Qty of plastering with cement mortar 1:3, 12mm one coat inside= 2 1x0.50x0.40= 0.20m 2
= 1x1.80x0.60=1.08m
2
= 1x2.60x0.20= 0.52m 2
= 1.80m
Qty of flushing coat inside = 1x0.50x0.40= 0.20m2 = 1x1.80x0.60=1.08m2 = 1x2.60x0.20= 0.52m2 = 1.80m2 Sub data 3
56
Earth work excavation in ordinary soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking
10m
669.00
110
Cement Concrete 1:3:6 using 20mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete
10dm3
39.21
159(a)
Brick work in Cement mortar 1:6 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete
1m
2470.19
506
Plastering with Cement mortar 1:3 ,12mm thick one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete
10m2
1281.26
514
Add to cement plastering items for plastering with neat cement flushing coat including cost and conveyance for materials and labour charges and watering, curing etc. complete
10m2
1552.31
3
Main data 0.16m3
Earth work excavation in ordinary soil and depositing on bank with initial lead upto 50 m and lift upto 1.5m including neat banking
10m3
804.00
12.86
51dm3
Cement Concrete 1:3:6 using 20mm (nominal size) broken stone including cost and conveyance of materials, labour charges and watering, curing etc complete
10dm3
39.21
199.96
Amount with CP (Rs)
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
3
Brick work in Cement mortar 1:6 with country burnt bricks 22.9cmx11.2cmx7cm including cost and conveyance of materials, labour charges and curing etc complete
1m
2
Plastering with Cement mortar 1:3 ,12mm thick one coat floated hard and trowelled to smooth including cost and conveyance for materials and labour charges and watering, curing etc. complete
10m
2
Add to cement plastering items for plastering with neat cement flushing coat including cost and conveyance for materials and labour charges and watering, curing etc. complete
10m
0.31m
1.80m
1.80m
Rate (Rs)
Amount without CP (Rs)
2470.19
765.76
2
1281.26
230.63
2
1552.31
279.42
3
Amount with CP (Rs)
1486.47
1635.11
DATA FOR ROAD 1
651
Sectioning upto 150mm on the surface of new road
10m2
-
Labour 0.500
-
man mazdoor
Each
Supplying 60mm graded metal (Proportion of 7:3 of 60mm and 36mm by volume) and stacking in standard heap for measurements including cost, conveyance, etc
1m
0.700
60mm broken stone
1m3
0.300
36mm broken stone
240.00
2
120.00 120.00
410.00
287.00
510.00
153.00
334.00
334.00
Conveyance 1.000
3
Broken stone
1m
Supplying and stacking 36mm hard granite broken stone in standard uniform heap for measurements
1m3
36mm broken stone
1m3
510.00
510.00
36mm broken stone
1m3
334.00
334.00
Supplying and stacking good hard gravelly red earth for blinding for measurements
1m3
Red earth
1m3
125.00
125.00
Red earth
1m3
158.00
158.00
Supplying hard blue granite broken stone 12mm size and stacking in standard uniform heap for measurements including cost, conveyance, etc, complete
1m3
12mm broken stone
1m3
774.00 3
1m3
132.00
3
851.40
-
Conveyance 1m3
844.00 4
1m3
928.40
-
Conveyance 1m3
283.00 5
1m3
-
740.00
740.00
311.30
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
Unit
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
Conveyance 3
1m
12mm broken stone
3
1m
334.00
588.35 1,328.35
6
Supplying hard blue granite broken stone 6mm size and stacking in standard uniform heap for measurements including cost, conveyance, etc, complete
1m
3
6mm broken stone
1m
3
Conveyance
3
6mm broken stone
1m 1m 1m
-
3
520.00
520.00
3
334.00
334.00
1m
854.00 7
655
Metalling the roadway 100mm spread thickness compacted to 75mm using departmental broken stone (graded in the ratio of 7:3 of 60mmand 36mm sizes)1m3/10m2 and departmental blinding materials (0.20m3/10m2 ), bed rolling, spreading broken stones to template, rolling dry to compaction from sides to central until the movement of broken stones cease, watering profusely and rolling until the fines cream up and fill the voids of the stones, then spreading the gravelly earth and sweeping in to the joints, watering and rerolling until the gravelly earth has worked in to all the crevices and only a thin coat of slurry remains, then take off the roller and allow to set to harden for 24 hours and rerolling next day until any deformity is rectified, including fencing, lighting, watching and maintaining the surface free of ruts for 15 days after completion as per IRC.2-1-2
1461.19
3
939.40
2
10m
Detailed for 10 m2
-
0.670
man mazdoor
Each
240.00
160.80
0.670
woman
Each
240.00
160.80
0.503
Man(1 Boy=0.75 man)
Each
240.00
120.60
0.012
hire of roller
1 day
2060.00
24.72
0.220
diesel oil for roller
1L
39.50
8.69
LS
sundries
LS
3.00
3.00 78.61
526.47
Sl. No
Ref: to PWD/ PHED Data item
8
655
Quantity
Description of Items
Unit
Metalling the roadway 100mm spread thickness compacted to 75mm using 36mm departmental broken stone (1m3/10m2) and departmental blinding materials (0.15m3/10m2 ), spreading broken stones to template, rolling dry to compaction, watering profusely, and rolling until the fines cream up and fill the voids of the stones, then spreading the gravelly earth and sweeping in to the joints, watering and rerolling until the gravelly earth has worked in to all the crevises and only a thin coat of slurry remains, then take off the roller and allow to set to harden for 24 hours and rerolling next day until any deformity is rectified, including fencing, lighting, watching and maintaining the surface free of ruts for 15 days after completion as per IRC.2-1-2
10m
Rate (Rs)
Amount without CP (Rs)
Amount with CP (Rs)
2
-
Detailed for 10 m2
-
0.670
man mazdoor
Each
240.00
160.80
0.670
woman
Each
240.00
160.80
0.503
Man(1 Boy=0.75 man)
Each
240.00
120.60
0.012
hire of roller
1 day
2060.00
24.72
0.220
diesel oil for roller
1L
39.50
8.69
LS
sundries
LS
3.00
3.00 478.61
9
674
Providing 20mm Pre-mix chipping carpet over W.B.M. surface with departmental broken stone after thoroughly cleaning the base with wire brushes, bass brooms and applying a priming coat of 7.50Kg of 2 bitumen 10m and spreading the hot pre-mix (formed of 0.27m3 of departmental 12mm metal and 12.96Kg of bitumen per 10m2 ) rolling to dense surface, then spreading the seal coat (comprising of a hot pre3 mix of 0.09m of 6mm departmental metal and 8.64Kg of bitumen per 10m2) again rolling including the cost of bitumen, oils and fuel, hire of bsss brooms, camber board, roller and other machines, watching, lighting and other charges, etc complete (Total usage of bitumen is 29.10Kg per 10m2 ) as per IRC.3-2-2
2
10m
Data for 100m2 0.12day
Hire for boiler
1 day
36.00
4.32
0.12day
Hire of roller
1day
2060.00
247.20
0.12day
Hire of HM Plant
1day
830.00
99.60
0.36day
Hire of Wheel bara
1day
3.50
1.26
2.20L
Diesel Oil
L
39.00
85.80
4.00L
Diesel oil for Plant
L
39.00
156.00
10.80L
Kerozene oil
L
26.00
280.80
11.60L
Kerozene oil for Plant
L
26.00
301.60
526.47
Sl. No
Ref: to PWD/ PHED Data item
Quantity
Description of Items
LS
Sundries
291kg
Bitumen (60/70 grade) (Packed)
Unit
T
Rate (Rs)
Amount without CP (Rs)
LS
5.00
30903.00
8,992.77
Conveyance 291kg
Bitumen
Amount with CP (Rs)
T
384.00
111.74
1,800.00
Labour
-
7.500
special man
Each
240.00
3.000
woman
Each
240.00
720.00 12,806.10
Cost for 10m2
1,280.61
1408.67
3.0
ECONOMIC ANALYSIS
The overall objective of the project to establish a modern abattoir in Kalady Panchayat is to ensure the supply of clean and hygienic meat to the public and to ensure that the water bodies in the area are not contaminated with slaughter house wastes. The activities envisaged in the abattoir are shown in the diagram below:
Slaughter House Lairage
Hygienic killing of animals Dressing (dehiding, removal of legs, horns, hooves etc) Evisceration (removal of contents from stomach) Slicing the Carcass into large pieces, washing Washing Carcass Post-mortem Examination
Animals brought in by registered meat vendors Ante-mortem Examination
Waste Treatment / Disposal Lairage Slaughter house
Meat Stalls Transporting Carcass from SH to retail shop and sale by registered vendors
The animals brought in by the registered vendors will be examined by qualified veterinary doctors and slaughtered in the slaughter house, dressed, sliced in large pieces, washed and will be handed over to the vendors for transportation to their meat shop and for retail sales.
3.1
OPERATION AND MAINTENANCE
Operation and maintenance of the slaughter house is proposed to be by engaging qualified butchers on piece rate and sanitation workers on daily wage basis. The activities will be supervised by a health inspector and the veterinary doctor in the panchayat will carryout the anti-mortem and post-mortem inspections. Appropriate fees for the slaughtering and waste treatment services will be levied from the meat vendors so as to meet the O&M costs and for payback of the capital cost. The proposed slaughter house in Kalady Panchayat can handle upto 60 large animals (cattle) and 40 small animals (Goats) per day. The estimated average slaughtering in Kalady and neighboring Panchayats is 50 cattle and 30sheep /day. The expected minimum number of animals in the abattoir is 40 large and 20 small animals per day.
3.2 ECONOMIC ANALYSIS 3.2.1
Expenditure
The costs involved in the functioning of the Abattoir are mainly related to: 1.
Butcher charges
2.
Wages to Sanitation workers and security staff
3.
Supervision and Veterinary Doctor charges
4.
Electricity Charges
5.
Water charges
6.
Pollution Control Board Certificate/Renewal etc.
7.
Annual maintenance
8.
Miscellaneous expenditure
The economics of the abattoir is worked out considering the following basic details; Average number of large animals slaughtered per day
: 40
Average number of small animals slaughtered per day
: 20
Number slaughter days/year excluding national and state holidays
: 350
Number of large animals slaughtered per year (50x350)
: 14,000
Number of small animals slaughtered per year (30x350)
: 7,000
The abstract of expenditure for running the plant is given below:
Sl. No.
Item
1 Butcher charges
1.
Amount (`) 3010000.00
2 Wages to Sanitation workers and security staff
505000.00
3 Supervision and Veterinary Doctor Charges
224000.00
4 Electricity Charges
14000.00
5 Water charges
12100.00
6 Pollution Control Board Certificate/Renewal
10000.00
7 Annual maintenance
50000.00
8 Miscellaneous expenditure
40000.00
Total
38,65,100.00
Expenses excluding butcher charges
8,55,100.00
Butcher charges
The butchers are expected to do the following activities in the abattoir: Hygienic killing of animals Dressing (dehiding, removal of legs, horns, hooves etc) Evisceration (removal of contents from stomach)
Slicing the Carcass into large pieces, washing Washing Carcass Qualified butchers will be engaged for undertaking this activity. The present rate ` 200/- for large animal and ` 30/- for small animal. The cost for this activity will be ` 30,14,000/- (40x350x200+20x350x30) 2.
Wages to Sanitation workers and security staff
Two security staff and 5 sanitation workers are required for proper functioning of the abattoir. The security staff shall be engaged from licensed agencies and the prevailing rate is ` 5,000/month. The sanitation workers shall be appointed as daily workers at a rate of Rs. 220/day including all allowances. Thus the total coast for wages will be ` 5,05,000/- (5000x12x2+220x350x5) 3.
Supervision and Veterinary Doctor Charges
It is the responsibility of the local bodies to ensure the supply of hygienic meat to public and to protect the environment for which the local bodies have veterinary doctors and health inspectors. They have other duties also to perform. However, a part of their salary shall be levied under this activity. The amount will be around `20,000/month and the total for one year is ` 2,24,000 (4x350x10). 4.
Electricity Charges
Electricity is required for pumping water, operating high pressure water jet, aerator motor, lighting lamps etc. The total power required /day is estimated as 8 units per day of which about 4 units used for lighting lamps will be obtained from the biogas plant. The amount required for paying the electricity charges per year at the rate of ` 10/unit will be ` 14,000. 5.
Water charges
Water is required for washing the carcass, floor cleaning, lairage cleaning, toilet use, gardening etc. The average quantity of water required per large animal is around 150 liter and for small animal is 30 liter. The total quantity of water per day is thus estimated at around 6.5 KLD (kilo liter/day) and 2275 kilo liter/year. About 50% of this (1175 kilo liter) will be met from the bore well present in the compound and balance from the public water supply. The amount required per year for this at the prevailing rate of ` 11/kilo liter, ` 12,100. 6.
Pollution Control Board Certificate/Renewal
Pollution control certificate is required for operating the unit. The license fee to be paid for two years will be ` 20,000/- for units establishing coast between 1 crore to 5 crore (including land value). Thus `10,000/year is required for this purpose. 7.
Annual maintenance
Annual maintenance include maintenance of the building and equipment. The cost estimated is ` 50,000/year 8.
Miscellaneous expenditure
The miscellaneous cost is for meeting the unforeseen expenses during daily operations. The cost estimated is `40,000/year 3.2.2
Income
The Panchayat shall fix a service charge for using the facilities. The butcher charges have to be paid extra. The suggested service charges excluding the butcher charges is ` 60/- for large animal and ` 20/- for small animal. The income expected from this is ` 9,80,000/year (14,000x60+7000x20). 3.3
CONCLUSION
The Central and State legislations like Prevention of Cruelty to Animals Rules 2001, the Municipality Act 1994, the Kerala Panchayat Raj Act 1994 and Water (Prevention & Control of Pollution) Act 1974 etc., insists establishment of modern slaughter houses and has to be monitored by the local bodies. However, this is not happening now and most of the slaughter activities are carried out in open places. This is largely due to the absence of a locally centralized slaughter house with appropriate facilities. This results in unhygienic slaughtering activity and unscientific dumping of slaughter wastes in the streams and water bodies which finally pollutes the Periyar River. The Panchayat has the responsibility of ensuring sanitary facilities for ensuring public health. Thus, they are supposed to run the abattoir in a no-loss no-profit basis. The major benefit of the plant will be related to the public health and environmental aspects, which cannot be counted on monitory basis. The excess of income over expenditure as per the present economic analysis is ` 1,24,900/year. This shall be deposited in a corpus fund and can be used for establishing additional facilities in future. Thus, project shall be operated in a self sustainable manner.
4.0 WORK SCHEDULE
4.
CHECK LIST OF DPR Check list for preparation of Detailed Project Report to be submitted for loans under Rural Infrastructure Development Fund (RIDF)
Project Sector i. ii. iii.
Environment
Name of Project Districts Covered Project Outlay ( Rs. In crores.)
Sl.
Construction of Modern Abattoir Kalady Panchayat in Ernakulam District 0.94 crores
Item
Remarks
No:
Furnished (Yes/No)
1
General
i.
Whether the project is prioritized by the State Government
Yes GO(Rt) No:4907/10/Findated18-062010
ii
Whether the project submitted through the Nodal Department
Yes (Environment Department)
iii.
Whether the project included in the State Plan
Yes EAE-015-River Action Plan-2010-11 HOA-5425-00-208-98 Part of the action plan for protection of Periyar river.
2
Clearances from (wherever applicable)
i.
Ministry of Environment & Forests
ii.
Administrative approval with details
iii.
Technical Sanction with details
iv.
Land acquisition-Extent, status and time frame
3
General
i.
Whether the present project is part of Government of India programme. If yes, furnish details of support and conditions of Government of India
ii.
Justification of the project with reference to National and Human Development Index
NA
Clearance from State Pollution Control Board for waste management facilities has to be during construction
To be obtained after getting approval from NABARD -DoOwn Land available with Kumili and Kalady Panchayaths
Consent letter attached
No
The project aims at ensuring the supply of clean and hygienic meat to the public and protecting water resources
Detailed justification given in introductory part (1.4)
4
Technical Aspects
i.
Whether projects are based on detailed site specific plans or based on replicable model
ii.
Approved drawings/details to be furnished
Yes
Drawings enclosed as annexure 3
iii.
Whether all components have been included in the project. If not, the arrangements for the same by State Government may be specified.
Yes
Detailed estimate attached as annexure 2
5
Financial Aspects
i.
Schedule of rates adopted(specify the year of SoR)
ii.
If not, whether cost proposed will be sufficient to create the assets
iii.
Cost Estimate
2010 NA Rs. 94,000,00/-
a
Item wise cost of project
Yes
b
Item wise expenditure incurred
NA
c
Item wise cost of balance works
NA
d
Item wise RIDF loan
e
Item wise State Government contribution
NIL
f
Year-wise phasing of RIDF loan and State and Government contribution
RIDF(2010-11) Rs. 0.94 crores
g
Bar/PERT/CPM chart for project execution
To be completed in 12 months
h
Share of Government of India, if any, to be specified
NIL
Specific justification for high cost of development
NA
i 6
Site specific designs prepared based on a replicable model developed for a level terrain
Rs. 94,000,00/- for one modern abattoir in Kalady Panchayat
Benefits and Justification Overall impact of the project intangible and non-intangible terms to be assessed and detailed
7
Execution, Operation and Maintenance
i.
Arrangements for execution of projects to be specified
Abstract of estimate attached
There is no proper mechanism for ensuring supply of clean meat to the public and the disposal of wastes. The wastes are ultimately polluting the Periyar river. On commissioning the facility, hygienic meat supply shall be ensured and the waste can be scientifically disposed thus arresting the pollution to the Periyar river.
The Panchayat Engineering wing attached to the Local Self Government Department . One Assistant Engineer and Two Overseers are attached with the Panchayat supervised by one AEE at Block level and one EE at the District level- reporting to CE (LSGD) through regional SE’s.
Bar chart of work schedule enclosed as annexure 4
ii.
Role of community in execution and operation and maintenance of projects after completion
8
Infrastructure facilities
i.
Organizational Structure of the implementing department (co-ordination mechanism, where project to be executed by other than implementing department)
The project will be implemented by the Panchayat engineering wing. Technical guidance & periodic monitoring will be done by the Environment Management Agency Kerala (EMAK) under the Environment Department. A project monitoring committee including the Local Panchayat representatives will be constituted.
ii.
Capacity and preparedness of the implementing department and status of implementation of earlier sanctioned projects
This is the first project of its kind to be funded by NABARD
iii.
Quality control infrastructure and mechanism
The engineering wing attached with the Panchayat is qualified enough for construction quality control. Random checking of samples of construction materials can be arranged through the nearest technical institutes.
iv.
Availability of labour
Locally available
v.
Budget provision
Under RIDF in 2010-11
a
For contribution to State share
NIL
b
For subsequent operation and maintenance
Self sustaining
c
For repayment of loans-Principal and interest
-
The Panchayat will take up operation and maintenance of the facility on a self sustaining basis from the revenue to be collected from the beneficiaries
9
Project Risks
i.
Land acquisition
NIL- Land available with panchayat
ii.
Forest clearance
NA
iii.
Rail way/road crossings
NA
iv.
Construction hazards
Nil
v.
Any other risk (specify)
NIL
10
Convergence with any other programme of Government of India
NA
Details to be furnished about the mechanism of implementation
NA
Name, Designation and Signature (with date) of the Head of the Implementing Department